[Federal Register Volume 66, Number 139 (Thursday, July 19, 2001)]
[Notices]
[Page 37667]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 01-18025]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP00-40-000, -001, and -002]
Florida Gas Transmission Company; Notice of Availability of the
Final Environmental Impact Statement for the Proposed FGT Phase V
Expansion Project
July 13, 2001.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared a final environmental impact statement (EIS)
to assess the environmental impact associated with the construction of
facilities proposed by Florida Gas Transmission Company (FGT) and
referred to in this final EIS as the FGT Phase V Expansion Project in
the above-referenced docket.
The final EIS was prepared to satisfy the requirements of the
National Environmental Policy Act. The staff concludes that approval of
the FGT Phase V Expansion Project, with appropriate mitigating measures
as recommended, would have limited adverse environmental impact. The
final EIS evaluates alternatives to the proposal, including system
alternatives, route alternatives, and route variations.
The final EIS assesses the potential environmental effects of the
construction and operation of the proposed facilities in Mississippi,
Alabama, and Florida.
The purpose of the FGT Phase V Expansion Project is to transport up
to 112,487 million cubic feet per day of natural gas on an annual basis
to seven electric generation customers and others in Florida. Three of
these customers, representing 94 percent of proposed transportation
capacity, are in the process of developing and constructing additional
gas-fired electric generating capacity to serve the growing market for
electricity in Florida. FGT estimates the total cost of its Phase V
Expansion Project at $452 million.
FGT proposes to construct and operate an interstate natural gas
pipeline and associated aboveground facilities under Section 7(c) of
the Natural Gas Act (NGA) and Title 18, CFR, Part 157. FGT proposes to
expand its existing 5,225-mile-long natural gas pipeline transmission
system by the construction of approximately 165.8 miles of pipeline
loops and laterals, 132,615 horsepower of additional compression at
nine existing and three new compressor stations, and other associated
auxiliary facilities in various locations in Mississippi, Alabama, and
Florida.
In addition, FGT proposes to acquire from Koch Gateway Pipeline
Company (KGPC) an interest in KGPC's Mobile Bay Lateral that would give
FGT the rights to about 50 percent of the available capacity on that
system. Concurrent with FGT's filing, KGPC filed an application in
Docket No. CP00-39-000 for approval to abandon by sale to FGT the
interest in its Mobile Bay Lateral. However, the environmental analysis
of this action qualifies as a categorical exclusion and is not included
in the EIS.
The final EIS has been placed in the public files of the FERC and
is available for public inspection at:
Federal Energy Regulatory Commission, Public Reference and Files
Maintenance Branch, 888 First Street, NE., Room 2A, Washington, DC
20426, (202) 208-1371.
Copies of the final EIS have been mailed to Federal, state and
local agencies, public interest groups, individuals who have requested
the final EIS, newspapers, and parties to this proceeding.
In accordance with the Council on Environmental Quality's (CEQ)
regulations implementing the National Environmental Policy Act, no
agency decision on a proposed action may be made until 30 days after
the U.S. Environmental Protection Agency publishes a notice of
availability of an final EIS. However, the CEQ regulations provide an
exception to this rule when an agency decision is subject to a formal
internal appeal process which allows other agencies or the public to
make their views known. In such cases, the agency decision may be made
at the same time the notice of the final EIS is published, allowing
both periods to run concurrently. The Commission decision for this
proposed action is subject to a 30-day rehearing period.
Additional information about the proposed project is available from
the Commission's Office of External Affairs, at (202) 208-1088 or on
the FERC Internet website (www.ferc.gov) using the ``RIMS'' link to
information in this docket number. Click on the ``RIMS'' link, select
``Docket #'' from the RIMS Menu, and follow the instructions. For
assistance with access to RIMS, the RIMS helpline can be reached at
(202) 208-2222.
Similarly, the ``CIPS'' link on the FERC Internet website provides
access to the texts of formal documents issued by the Commission, such
as orders, notices, and rulemakings. From the FERC Internet website,
click on the ``CIPS'' link, select ``Docket #'' from the CIPS menu, and
follow the instructions. For assistance with access to CIPS, the CIPS
helpline can be reached at (202) 208-2474.
David P. Boergers,
Secretary.
[FR Doc. 01-18025 Filed 7-18-01; 8:45 am]
BILLING CODE 6717-01-P