[Federal Register Volume 65, Number 46 (Wednesday, March 8, 2000)]
[Rules and Regulations]
[Pages 12115-12116]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 00-5343]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Part 157
[Docket No. RM81-19-000]
Natural Gas Pipelines; Project Cost and Annual Limits
Issued February 7, 2000.
AGENCY: Federal Energy Regulatory Commission, DOE.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: Pursuant to the authority delegated by 18 CFR 375.308(x)(1),
the Director of the Office of Energy Projects (OEP) computes and
publishes the project cost and annual limits for natural gas pipelines
blanket construction certificates for each calendar year.
EFFECTIVE DATE: January 1, 2000.
FOR FURTHER INFORMATION CONTACT: Michael J. McGehee, Division of
Pipeline Certificates, (202) 208-2257.
Section 157.208(d) of the Commission's Regulations provides for
project cost limits applicable to construction, acquisition, operation
and miscellaneous rearrangement of facilities (Table I) authorized
under the blanket certificate procedure (Order No. 234, 19 FERC para.
61,216). Section 157.215(a) specifies the calendar year dollar limit
which may be expended on underground storage testing and development
(Table II) authorized under the blanket certificate. Section 157.208(d)
requires that the ``limits specified in Tables I and II shall be
adjusted each calendar year to reflect the `GDP implicit price
deflator' published by the Department of Commerce for the previous
calendar year.''
Pursuant to Sec. 375.308(x)(1) of the Commission's Regulations, the
authority for the publication of such cost limits, as adjusted for
inflation, is delegated to the Director of the Office of Energy
Projects. The cost limits for calendar year 1998, as published in Table
I of Sec. 157.208(d) and Table II of Sec. 157.215(a), are hereby
issued.
List of Subjects in 18 CFR Part 157
Administrative practice and procedure, Natural gas, Reporting and
recordkeeping requirements.
Daniel M. Adamson,
Director, Office of Energy Projects.
Accordingly, 18 CFR Part 157 is amended as follows:
PART 157--[AMENDED]
1. The authority citation for part 157 continues to read as
follows:
Authority: 15 U.S.C. 717-717w, 3301-3432; 42 U.S.C. 7101-7352.
2. Table I in Sec. 157.208(d) is revised to read as follows:
Sec. 157.208 Construction, acquisition, operation, and miscellaneous
rearrangement of facilities.
* * * * *
(d) * * *
------------------------------------------------------------------------
Limit
-------------------------------
Year Auto proj. Prior notice
cost limit proj. cost
(Col. 1) limit (Col. 2)
------------------------------------------------------------------------
1982.................................... $4,200,000 $12,000,000
1983.................................... 4,500,000 12,800,000
1984.................................... 4,700,000 13,300,000
1985.................................... 4,900,000 13,800,000
1986.................................... 5,100,000 14,300,000
1987.................................... 5,200,000 14,700,000
1988.................................... 5,400,000 15,100,000
1989.................................... 5,600,000 15,600,000
1990.................................... 5,800,000 16,000,000
1991.................................... 6,000,000 16,700,000
1992.................................... 6,200,000 17,300,000
1993.................................... 6,400,000 17,700,000
1994.................................... 6,600,000 18,100,000
1995.................................... 6,700,000 18,400,000
1996.................................... 6,900,000 18,800,000
1997.................................... 7,000,000 19,200,000
1998.................................... 7,100,000 19,600,000
1999.................................... 7,200,000 19,800,000
2000.................................... 7,300,000 20,200,000
------------------------------------------------------------------------
* * * * *
3. Table II in Sec. 157.215(a)(5) is revised to read as follows:
Sec. 157.215 Underground storage testing and development.
(a) * * *
(5) * * *
Table II
------------------------------------------------------------------------
Year Limit
------------------------------------------------------------------------
1982...................................................... $2,700,000
1983...................................................... 2,900,000
1984...................................................... 3,000,000
1985...................................................... 3,100,000
1986...................................................... 3,200,000
1987...................................................... 3,300,000
1988...................................................... 3,400,000
1989...................................................... 3,500,000
1990...................................................... 3,600,000
1991...................................................... 3,800,000
1992...................................................... 3,900,000
1993...................................................... 4,000,000
[[Page 12116]]
1994...................................................... 4,100,000
1995...................................................... 4,200,000
1996...................................................... 4,300,000
1997...................................................... 4,400,000
1998...................................................... 4,500,000
1999...................................................... 4,550,000
2000...................................................... 4,650,000
------------------------------------------------------------------------
* * * * *
[FR Doc. 00-5343 Filed 3-7-00; 8:45 am]