DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. CP00-58-000]


Columbia Gas Transmission Corporation; Notice of Application for 
Abandonment Authorization

January 7, 2000.
    Take notice that on December 22, 1999, Columbia Gas Transmission 
Corporation (Columbia), a Delaware corporation, whose main office is 
located at 12801 Fair Lakes Parkway, Fairfax, Virginia 22030-0146, 
filed in the referenced docket pursuant to Section 7(b) of the Natural 
Gas Act (NGA) and Part 157 of the Federal Energy Regulatory 
Commission's (the Commission) Regulations thereunder (18 CFR 157.7 and 
157.18), an application for authority to abandon by sale to Columbia 
Natural Resources (CNR), the Cleveland Storage Field (Cleveland 
Storage) located in Randolph, Upshur and Webster Counties, West 
Virginia, and all as more fully set forth in the Application on file 
with the Commission and open to public inspection. This filing may be 
viewed on the web at http://www.ferc.us/online/rims.htm (call 202-208-
2222).
    Specifically, Columbia proposes to abandon and sell to CNR its 
Cleveland Storage, consisting of 8.1 miles of storage pipeline, 9 
active storage wells, 8 observation wells and ancillary facilities for 
$525,000. CNR proposes to use the Cleveland Storage as a production 
facility.
    Columbia is seeking to abandon Cleveland Storage after having 
observed a significant deterioration in the performance and geologic 
integrity of the reservoir. Columbia states that it will rely upon its 
retained storage capacity to offset the reduction in working gas 
capacity and deliverability associated with the abandonment, which is 
expected to have only a 0.01% effect on Columbia's overall 4.4 Bcf 
design day deliverability from Columbia's other active storage fields.
    In addition, Columbia seeks authority to sell 830 MMcf of base gas 
that was previously withdrawn from Cleveland Storage between 1996 and 
1999 during Columbia's integrity and performance assessment of the 
field. The disposition of proceeds from the proposed sale of this base 
gas will be made pursuant to Section C, of Article IV, of Stipulation 
II of the Settlement in Docket No. RP95-408, Columbia Gas Transmission 
Corp., 79 FERC para.Sec. 61,044 (1997). Columbia states that this 
settlement defines future additional sales of base gas no longer needed 
by Columbia as a result of more efficient operation of its storage 
fields. Columbia will comply with the annual reporting requirements 
provided for in Section D of Article IV.
    Any person desiring to be heard or to make any protest with 
reference to said application should on or before January 28, 2000, 
file with the Federal Energy Regulatory Commission, 888 First Street, 
NE, Washington, DC 20426, a motion to intervene or a protest in 
accordance with the requirements of the Commission's Rules of Practice 
and Procedure (18 CFR 385.211 or 385-214) and the Regulations under the 
Natural Gas Act (18 CFR 157.10). All protests filed with the Commission 
will be considered by it in determining the appropriate action to be 
taken, but will not serve to make protestants parties to the 
proceedings. Any person wishing to become a party to a proceeding or to 
participate as a party in any hearing therein must file a motion to 
intervene in accordance with the Commission's Rules.
    Take further notice that, pursuant to the authority contained in 
and subject to the jurisdiction conferred upon the Federal Energy 
Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
Commission's Rules of Practice and Procedure, a hearing will be held 
without further notice before the Commission or its designee on this 
application if no motion to intervene is filed within the time required 
herein, if the Commission on its own review of the matter finds that a 
grant of the certificate is required by the public convenience and 
necessity. If a motion for leave to intervene is timely filed, or if 
the Commission on its own motion believes that a formal hearing is 
required, further notice of such hearing will be duly given.
    Under the procedure herein provided for, unless otherwise advised, 
it will be unnecessary for Columbia to appear or be represented at the 
hearing.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 00-786 Filed 1-12-00; 8:45 am]
BILLING CODE 6717-01-M