Entergy Nuclear Holding Company, No. 1, Inc., et al.; Electric 
Rate and Corporate Regulation Filings

July 29, 1999.
    Take notice that the following filings have been made with the 
Commission:

1. Entergy Nuclear Holding Company No. 1, Inc.

[Docket No. EG99-187-000]

    Take notice that on July 13, 1999, Entergy Nuclear Holding Company 
No. 1, Inc. amended its Application for Determination of Exempt 
Wholesale Generator Status filed on July 9, 1999.

[[Page 42936]]

    Comment date: August 18, 1999, in accordance with Standard 
Paragraph E at the end of this notice. The Commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

2. Commonwealth Edison Company, Unicom Investment Inc., Edison 
Mission Energy

[Docket Nos. EC99-96-000 and ER99-3691-000]

    Take notice that on July 22, 1999, Commonwealth Edison Company 
(ComEd), Unicom Investment Inc. (UII), and Edison Mission Energy 
(Mission) (collectively, the Parties), filed an application under 
Section 203 of the Federal Power Act for authorization for the sale by 
ComEd of its fossil generating facilities to a special purpose 
subsidiary of Mission. On the same date, the Parties filed under 
Section 205 of the Federal Power Act forms of Facilities Agreements 
that ComEd and Mission will enter into to govern interconnection and 
operations subsequent to the sale by ComEd to Mission.
    ComEd, UII, and Mission, request the Commission to allow the 
Facilities Agreements to become effective upon closing of the sale 
transaction, which the parties expect to occur on or shortly after 
September 30, 1999.
    Comment date: August 23, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

3. Jersey Central Power & Light Company, Metropolitan Edison 
Company, Pennsylvania Electric Company, Sithe Energies, Inc., Sithe 
Pennsylvania Holdings LLC, Sithe New Jersey Holdings LLC, Sithe 
Maryland Holdings LLC, York Haven Power Company

[Docket No. EC99-97-000]

    Take notice that on July 22, 1999, Jersey Central Power & Light 
Company, Metropolitan Edison Company and Pennsylvania Electric Company 
(doing business as and collectively referred to as GPU Energy), Sithe 
Energies, Inc. (Sithe), and Sithe affiliates Sithe Pennsylvania 
Holdings LLC, Sithe New Jersey Holdings LLC, Sithe Maryland Holdings 
LLC and York Haven Power Company submitted for filing an application 
pursuant to Section 203 of the Federal Power Act (FPA) concerning both 
the sale of substantially all of GPU Energy's non-nuclear generating 
facilities to the above-mentioned Sithe affiliates and the related 
corporate reorganization of entities within the Sithe corporate family 
that are subject to the Commission's jurisdiction under Section 205 of 
the FPA.
    Comment date: August 23, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

4. Niagara Mohawk Power Corporation, New York State Electric & Gas 
Corporation, AmerGen Energy Company L.L.C.

[Docket Nos. EC99-98-000 and ER99-3804-000]

    Take notice that on July 23, 1999, Niagara Mohawk Power Corporation 
(Niagara Mohawk), New York State Electric 7 Gas Corporation (NYSEG) and 
AmerGen Energy Company, LLC (collectively, the Applicants) tendered for 
filing an application under Section 203 of the Federal Power Act for 
approval to transfer certain limited jurisdictional facilities 
associated with the sale of Niagara Mohawk and NYSEG of their interests 
in the Nine Mile Point Unit Nos. 1 and 2 nuclear gathering facilities 
located in the Town of Scriba, Oswego County, New York.
    The Applicants have served copies of this filing on the New York 
Public Service Commission.
    Comment date: August 23, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

5. Illinova Corporation, Dynegy Inc.

[Docket No. EC99-99-000]

    Take notice that on July 23, 1999, Illinova Corporation (Illinova) 
and Dynegy Inc. (Dynegy), tendered for filing with the Federal Energy 
Regulatory Commission (Commission) pursuant to Section 203 of the 
Federal Power Act, 16 U.S.C. Sec. 824b (1994 & Supp. 1998) and Part 33 
of the Commission's Regulations, 18 CFR 33.1, a Joint Application for 
Approval of Merger and Request for Expedited Consideration.
    Comment date: September 21, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

6. Sierra Pacific Power Company, Nevada Power Company

[Docket No. EC99-100-000]

    Take notice that on July 23, 1999, Sierra Pacific Power Company 
(Sierra) and Nevada Power Company (Nevada Power) tendered for filing 
pursuant to Section 203 of the Federal Power Act, a Joint Application 
for Authorization of Transfer of Control Over Transmission Facilities. 
This application intended to transfer control over the Applicants' 
transmission facilities to the Mountain West Independent System 
Administrator (Mountain West) as contemplated in the related filing in 
Docket No. ER99-3719-000.
    Comment date: August 23, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

7. Energy Alternatives, Inc.

[Docket No. EG99-200-000]

    Take notice that on July 21, 1999, Energy Alternatives, Inc. 
(Energy Alternatives) filed with the Federal Energy Regulatory 
Commission an application for determination of exempt wholesale 
generator status pursuant to Part 365 of the Commission's regulations.
    Energy Alternatives, a Minnesota corporation, is a wholly-owned 
subsidiary of Midwest Energy Services, Inc., a Minnesota corporation, 
which is a wholly-owned subsidiary of Dakota Electric Association, a 
Minnesota cooperative corporation, which owns and operates an electric 
distribution system.
    Energy Alternatives will own and operate generating facilities with 
a nominal capacity of 20 MW located in distribution substations near 
the cities of Lakeville, Miesville, and Hastings, Minnesota and in the 
townships of Byllesby and Castle Rock in Dakota County, Minnesota, 
consisting of ten 2 MW Caterpillar diesel reciprocating engine 
generator sets, five 480 volt/12,470 volt step up transformers, and 
associated circuit breakers. The facilities will be interconnected with 
the distribution system of Dakota Electric Association.
    Comment date: August 19, 1999, in accordance with Standard 
Paragraph E at the end of this notice. The Commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

8. COSI Coldwater, Inc.

[Docket No. EG99-204-000]

    Take notice that on July 27, 1999, COSI Coldwater, Inc. 
(Applicant), with its principal office at 111 Market Place, Suite 200, 
Baltimore, Maryland 21202, filed with the Federal Energy Regulatory 
Commission (Commission) an application for determination of exempt 
wholesale generator status pursuant to Part 365 of the Commission's 
regulations.
    The Facilities are located on more than 20 rivers and streams 
throughout upstate New York and consist of 72 hydroelectric generating 
plants that have a combined capacity of approximately 660 MW. Electric 
energy produced by the Facilities is sold exclusively at wholesale.
    Comment date: August 19, 1999, in accordance with Standard 
Paragraph E at the end of this notice. The

[[Page 42937]]

Commission will limit its consideration of comments to those that 
concern the adequacy or accuracy of the application.

9. COSI Carr St., Inc.

[Docket No. EG99-205-000]

    Take notice that on July 27, 1999, COSI Carr St., Inc. (Applicant), 
with its principal office at 111 Market Place, Suite 200, Baltimore, 
Maryland 21202, filed with the Federal Energy Regulatory Commission 
(Commission) an application for determination of exempt wholesale 
generator status pursuant to Part 365 of the Commission's regulations.
    Applicant states that it will provide operation and maintenance 
services to the East Syracuse Station (the Facility) an approximately 
101 MW natural gas-fired combined-cycle cogeneration facility, located 
in East Syracuse, New York. Electric energy produced by the Facility is 
sold exclusively at wholesale.
    Comment date: August 19, 1999, in accordance with Standard 
Paragraph E at the end of this notice. The Commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

10. Nordic Electric, L.L.C., Con Edison Solutions, Inc., AC Power 
Corporation, Sparc, L.L.C., Agway Energy Services, Inc., Total Gas 
& Electric, Inc., Metro Energy Group, LLC, Shell Energy Services 
Company, L.L.C.

[Docket No. ER96-127-008, ER97-705-009, ER97-2867-008, ER98-2671-002, 
ER97-4186-007, ER97-4202-008, ER99-801-001 and ER99-2109-001]

    Take notice that on July 23, 1999, the above-mentioned power 
marketers filed quarterly reports with the Commission in the above-
mentioned proceedings for information only. These filings are available 
for public inspection and copying in the Public Reference Room or on 
the web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

11. CoEnergy Trading Company, MAC Power Marketing, L.L.C., New 
Millennium Energy Corporation, Spokane Energy, L.L.C.

[Docket No. ER96-1040-015, ER98-575-004, ER97-2681-006 and ER98-4336-
003]

    Take notice that on July 22, 1999, the above-mentioned power 
marketers filed quarterly reports with the Commission in the above-
mentioned proceedings for information only. These filings are available 
for public inspection and copying in the Public Reference Room or on 
the web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

12. DukeSolutions

[Docket No. ER98-3813-004]

    Take notice that on July 21, 1999, the above-mentioned power 
marketer filed a quarterly report with the Commission in the above-
mentioned proceeding for information only. This filing is available for 
public inspection and copying in the Public Reference Room or on the 
web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

13. Wisconsin Electric Power Company

[Docket No. ER99-2900-000]

    Take notice that on July 23, 1999, Wisconsin Electric Power Company 
(Wisconsin Electric), tendered for filing revisions to its Coordination 
Sales Tariff (FERC Electric Tariff, First Revised Volume No. 2) as 
directed in the July 2, 1999 letter order in this docket.
    Wisconsin Electric respectfully requests an effective date June 1, 
1999. Wisconsin Electric requests waiver of the Commission's advance 
notice requirements.
    Copies of the filing have been served on all current customers 
under the Coordination Sales Tariff, the Michigan Public Service 
Commission, and the Public Service Commission of Wisconsin.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

14. Dayton Power and Light Company

[Docket No. ER99-3684-000]

    Take notice that on July 22, 1999, Dayton Power and Light Company 
(Dayton), tendered for filing service agreements establishing TXU 
Energy Trading Company as a customer under the terms of Dayton's 
Market-Based Sales Tariff.
    Dayton requests an effective date of one day subsequent to this 
filing for the service agreements. Accordingly, Dayton requests waiver 
of the Commission's notice requirements.
    Copies of this filing were served upon TXU Energy Trading Company 
and the Public Utilities Commission of Ohio.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

15. Allegheny Power Service Corporation on Behalf of Monongahela 
Power Company, the Potomac Edison Company and West Penn Power 
Company (Allegheny Power)

[Docket No. ER99-3685-000]

    Take notice that on July 22, 1999, Allegheny Power Service 
Corporation on behalf of Monongahela Power Company, The Potomac Edison 
Company and West Penn Power Company (Allegheny Power), tendered for 
filing Supplement No. 25 to add Ameren Energy, Inc., (Customer) to the 
Market Rate Tariff under which Allegheny Power offers generation 
services.
    Allegheny Power requests a waiver of notice requirements to make 
service available as of June 21, 1999, to Ameren Energy, Inc..
    Copies of the filing have been provided to the Public Utilities 
Commission of Ohio, the Pennsylvania Public Utility Commission, the 
Maryland Public Service Commission, the Virginia State Corporation 
Commission, the West Virginia Public Service Commission, and all 
parties of record.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

16. The United Illuminating Company

[Docket No. ER99-3686-000]

    Take notice that on July 22, 1999, The United Illuminating Company 
(UI), tendered for filing for informational purposes all individual 
Purchase Agreements and Supplements to Purchase Agreements executed 
under UI's Wholesale Electric Sales Tariff, FERC Electric Tariff, 
Original Volume No. 2, as amended, during the six-month period November 
1, 1998, through April 30, 1999.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

17. Southern Indiana Gas and Electric Company

[Docket No. ER99-3687-0000]

    Take notice that on July 22, 1999, Southern Indiana Gas and 
Electric Company (SIGECO), tendered for filing the following agreement 
concerning the provision of electric service to Allegheny Power Service 
Corporation, as a umbrella-term service agreement under its market-
based Wholesale Power Sales Tariff.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

18. Arizona Public Service Company

[Docket No. ER99-3688-000]

    Take notice that on July 22, 1999, Arizona Public Service Company 
(APS), tendered for filing revised Exhibits A and C to APS-FERC Rate 
Schedule No. 225 between APS and Citizens Utilities Company (Citizens).
    Current rate levels are unaffected, revenue levels are unchanged 
from

[[Page 42938]]

those currently on file with the Commission, and no other significant 
change in service to these or any other customer results from the 
revisions proposed herein. No new or modifications to existing 
facilities are required as a result of these revisions.
    Copies of this filing have been served on Citizens and the Arizona 
Corporation Commission.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

19. Cinergy Services, Inc.

[Docket No. ER99-3689-000]

    Take notice that on July 22, 1999, Cinergy Services, Inc. 
(Cinergy), acting as agent for and on behalf of The Cincinnati Gas & 
Electric Company (CG&E) and PSI Energy, Inc., and Cleveland Public 
Power (CPP), tendered for filing an executed Letter Amendment to the 
Third Party Limited Term Agreement. This Agreement has been designated 
by Federal Energy Regulatory Commission (FERC) as CG&E Rate Schedule 
FERC No. 47.
    The Letter Amendment provides that CG&E will only use firm 
transmission service through the American Power System and CPP will 
reimburse CG&E for the additional cost.
    Cinergy and CPP are requesting an effective date of one day after 
this filing.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

20. Alliance Energy Services Partnership

[Docket No. ER99-3690-000]

    Take notice that on July 22, 1999, Alliance Energy Services 
Partnership (AESP), pursuant to section 35.15 of the Commission's 
Regulations, tendered for filing a notice of cancellation of its Rate 
Schedule FERC No. 1.
    AESP has requested an effective date for the proposed rate schedule 
cancellation of July 23, 1999. Accordingly, AESP requests waiver of the 
60-day prior notice requirement.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

21. Sithe New Jersey Holdings LLC, Sithe Pennsylvania Holdings LLC, 
Sithe Maryland Holdings LLC, Sithe Power Marketing, L.P. Sithe 
Energies, Inc.

[Docket No. ER99-3692-000]

    Take notice that on July 22, 1999, Sithe New Jersey Holdings LLC 
and Sithe Pennsylvania Holdings LLC (together Applicants), tendered for 
filing a petition for Commission acceptance of proposed rate schedules. 
Applicants request authority to make wholesale power sales, including 
energy and capacity, at market-based rates, requests certain blanket 
authorizations, and waiver of certain of the Commission's Regulations.
    The Applicants intend to engage in wholesale power sales. The 
Applicants do not own or control and are not affiliated with any entity 
that owns or controls electric transmission or distribution facilities 
in the United States. Applicants further state that it is not 
affiliated with any franchised electric utility in the Untied States. 
Applicants conclude that any interests that its affiliates have in 
domestic electric generation facilities do not raise any generation 
market power concerns.
    Applicants request that the tendered rate schedules become 
effective as of closing of a divestiture transaction with Jersey 
Central Power & Light Company, Metropolitan Edison Company and 
Pennsylvania Electric Company. The closing is anticipated for September 
of 1999.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

22. Midwest Generation, LLC

[Docket No. ER99-3693-000]

    Take notice that on July 22, 1999, Midwest Generation, LLC 
(Seller), a limited liability company organized under the laws of the 
State of Delaware, petitioned the Commission for an order: (1) 
Accepting Seller's proposed market-based rate tariff; (2) granting 
waiver of certain requirements under Subparts B and C of Part 35 of the 
regulations, and (3) granting the blanket approvals normally accorded 
sellers permitted to sell at market-based rates. Seller is an indirect 
subsidiary of Edison International.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

23. Southwest Power Pool

[Docket No. ER99-3694-000]

    Take notice that on July 22, 1999, Southwest Power Pool (SPP), 
tendered for filing four service agreements for point-to-point 
transmission service and loss compensation service under the SPP Tariff 
with Western Resources Generation Services (Western Resources) and 
Public Service Company of Colorado (PSCo).
    SPP requests an effective date of July 1, 1999, for these 
agreements.
    Copies of this filing were served upon Western Resources and PSCo.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

24. Puget Sound Energy, Inc.

[Docket No. ER99-3695-000]

    Take notice that on July 22, 1999, Puget Sound Energy, Inc. (PSE), 
tendered for filing a Service Agreement under the provisions of PSE's 
market-based rates tariff, FERC Electric Tariff, First Revised Volume 
No. 8, with Engelhard Power Marketing, Inc. (Engelhard).
    A copy of the filing was served upon Engelhard.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

25. Puget Sound Energy, Inc.

[Docket No. ER99-3696-000]

    Take notice that on July 22, 1999, Puget Sound Energy, Inc. (PSE), 
tendered for filing a Service Agreement under the provisions of PSE's 
market-based rates tariff, FERC Electric Tariff, First Revised Volume 
No. 8, with Enron Power Marketing, Inc. (EPMI).
    A copy of the filing was served upon EPMI.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

26. Puget Sound Energy, Inc.

[Docket No. ER99-3697-000]

    Take notice that on July 22, 1999, Puget Sound Energy, Inc. (PSE), 
tendered for filing a Service Agreement under the provisions of PSE's 
market-based rates tariff, FERC Electric Tariff, First Revised Volume 
No. 8, with Heartland Energy Services (Heartland).
    A copy of the filing was served upon Heartland.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

27. Puget Sound Energy, Inc.

[Docket No. ER99-3698-000]

    Take notice that on July 22, 1999, Puget Sound Energy, Inc. (PSE), 
tendered for filing a Service Agreement under the provisions of PSE's 
market-based rates tariff, FERC Electric Tariff, First Revised Volume 
No. 8, with Hetch-Hetchy Water & Power (Hetch-Hetchy).
    A copy of the filing was served upon Hetch-Hetchy.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

28. Puget Sound Energy, Inc.

[Docket No. ER99-3699-000]

    Take notice that on July 22, 1999, Puget Sound Energy, Inc. (PSE), 
tendered for filing a Service Agreement under the provisions of PSE's 
market-based rates tariff, FERC Electric Tariff,

[[Page 42939]]

First Revised Volume No. 8, with Illinova Energy Partners, Inc. 
(Illinova).
    A copy of the filing was served upon Illinova.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

29. Puget Sound Energy, Inc.

[Docket No. ER99-3700-000]

    Take notice that on July 22, 1999, Puget Sound Energy, Inc. (PSE), 
tendered for filing a Service Agreement under the provisions of PSE's 
market-based rates tariff, FERC Electric Tariff, First Revised Volume 
No. 8, with Entergy Electric System (Entergy).
    A copy of the filing was served upon Entergy.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

30. Puget Sound Energy, Inc.

[Docket No. ER99-3701-000]

    Take notice that on July 22, 1999, Puget Sound Energy, Inc. (PSE), 
tendered for filing a Service Agreement under the provisions of PSE's 
market-based rates tariff, FERC Electric Tariff, First Revised Volume 
No. 8, with Engage Energy US, L.P. (Engage).
    A copy of the filing was served upon Engage.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

31. Rochester Gas and Electric Corporation

[Docket No. ER99-3702-000]

    Take notice that on July 22, 1999, Rochester Gas and Electric 
Corporation (RG&E), tendered for filing a Market Based Service 
Agreement between RG&E and TransAlta Energy Marketing (U.S.) Inc., 
(Customer). This Service Agreement specifies that the Customer has 
agreed to the rates, terms and conditions of RG&E's FERC Electric Rate 
Schedule, Original Volume No. 3 (Power Sales Tariff) accepted by the 
Commission in Docket No. ER97-3553-000 (80 FERC para. 61,284) (1997)).
    RG&E requests waiver of the Commission's sixty (60) day notice 
requirements and an effective date of July 19, 1999, for TransAlta 
Energy Marketing (U.S.) Service Agreement.
    RG&E has served copies of the filing on the New York State Public 
Service Commission and on the Customer.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

32. Puget Sound Energy, Inc.

[Docket No. ER99-3703-000]

    Take notice that on July 22, 1999, Puget Sound Energy, Inc. (PSE), 
tendered for filing a Service Agreement under the provisions of PSE's 
market-based rates tariff, FERC Electric Tariff, First Revised Volume 
No. 8, with Idaho Power Company (IPC).
    A copy of the filing was served upon IPC.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

33. Rochester Gas and Electric Corporation

[Docket No. ER99-3704-000]

    Take notice that on July 22, 1999, Rochester Gas and Electric 
Corporation (RG&E), tendered for filing a Market Based Service 
Agreement between RG&E and American Electric Power Service Corporation. 
(Customer). This Service Agreement specifies that the Customer has 
agreed to the rates, terms and conditions of RG&E's FERC Electric Rate 
Schedule, Original Volume No. 3 (Power Sales Tariff) accepted by the 
Commission in Docket No. ER97-3553-000 (80 FERC para. 61,284) (1997)).
    RG&E requests waiver of the Commission's sixty (60) day notice 
requirements and an effective date of July 1, 1999, for American 
Electric Power Service Corporation's Service Agreement.
    RG&E has served copies of the filing on the New York State Public 
Service Commission and on the Customer.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

34. Metropolitan Chicago Healthcare Council--Shared Services, Inc.

[Docket No. ER99-3705-000]

    Take notice that on July 22, 1999, Metropolitan Chicago Healthcare 
Council--Shared Services, Inc. (MCHC--Shared Services, Inc.), tendered 
for filing its petition to the Commission for acceptance of MCHC--
Shared Services, Inc.'s Rate Schedule FERC Tariff No. 1; the granting 
of certain blanket approvals, including the authority to sell 
electricity at market based rates; and waiver of certain Commission 
Regulations.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

35. Cinergy Services, Inc.

[Docket No. ER99-3706-000]

    Take notice that on July 22, 1999, Cinergy Services, Inc., on 
behalf of its Operating Company affiliates, The Cincinnati Gas & 
Electric Company and PSI Energy, Inc. (COC), tendered for filing an 
executed service agreement between COC and OGE Energy Resources, Inc. 
(OERI), replacing the unexecuted service agreement filed on September 
4, 1998 under Docket No. ER99-170-000 per COC FERC Electric Power Sales 
Tariff, Original Volume No. 4, which has been replaced by the COC FERC 
Electric Cost-Based Power Sales Tariff, Original Volume No. 6-CB.
    COC and OERI are requesting an effective date of one day after the 
original filing in Docket No. ER99-170-000.
    Comment date: August 11, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

36. Northeast Utilities Service Company

[Docket No. ER99-3708-000]

    Take notice that on July 23, 1999, Northeast Utilities Service 
Company (NUSCO), tendered for filing, a Service Agreement with 
Consolidated Edison Energy, Inc. (CEEI) under the NU System Companies' 
Sale for Resale Tariff No. 7 Market Based Rates.
    NUSCO states that a copy of this filing has been mailed to CEEI.
    NUSCO requests that the Service Agreement become effective July 1, 
1999.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

37. Northeast Utilities Service Company

[Docket No. ER99-3709-000]

    Take notice that on July 23, 1999, Northeast Utilities Service 
Company (NUSCO), tendered for filing, a Service Agreement with Statoil 
Energy Trading, Inc. (Statoil) under the NU System Companies' Sale for 
Resale Tariff No. 7 Market Based Rates.
    NUSCO states that a copy of this filing has been mailed to Statoil.
    NUSCO requests that the Service Agreement become effective July 1, 
1999.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

38. Southwestern Public Service Company

[Docket No. ER99-3710-000]

    Take notice that on July 23, 1999, New Century Services, Inc., on 
behalf of Southwestern Public Service Company (Southwestern), tendered 
for filing an executed umbrella service agreement under Southwestern's 
market-based sales tariff with Tenaska Power Services Company 
(Tenaska). This umbrella service agreement provides for

[[Page 42940]]

Southwestern's sale and Tenaska's purchase of capacity and energy at 
market-based rates pursuant to Southwestern's market-based sales 
tariff.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

39. Pennsylvania Electric Company

[Docket No. ER99-3711-000]

    Take notice that on July 23, 1999, Pennsylvania Electric Company 
(doing business as and referred to as GPU Energy), tendered for filing 
the First Amended and Restated Interconnection Agreement by and between 
The Cleveland Electric Illuminating Company (CEI) and Pennsylvania 
Electric Company (Agreement). The Agreement is associated with the sale 
of GPU Energy's 20% interest in the Seneca Pumped Storage Generating 
Station (Seneca) to CEI.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

40. Pacific Gas and Electric Company

[Docket No. ER99-3713-000]

    Take notice that on July 23, 1999, Pacific Gas and Electric Company 
(PG&E), tendered for filing an Interconnection Agreement Between 
Pacific Gas and Electric Company and Fresno Irrigation District 
(Fresno), dated May 28, 1999. The Interconnection Agreement (IA or 
Agreement) establishes the terms and conditions under which PG&E will 
provide electric system interconnection between PG&E and Fresno. In its 
filing letter, PG&E has explained that the IA in this docket is 
identical to the Interconnection Agreement pending before the 
Commission in Laguna Irrigation District, Docket No. EL98-46-000 and 
related Docket No. ER99-3145-000, with the exception of the contents of 
Appendix A (specifying the points of interconnection) and the name of 
the Irrigation District. PG&E also has explained that the IA contains a 
reservation of rights with respect to disputes arising under the FPA.
    Copies of this filing have been served upon Fresno and the 
California Public Utilities Commission.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

41. Duquesne Light Company

[Docket No. ER99-3714-000]

    Take notice that on July 23, 1999, Duquesne Light Company 
(Duquesne), tendered for filing under Duquesne's pending Market-Based 
Rate Tariff, (Docket No. ER98-4159-000) an executed Service Agreement 
at Market-Based Rates with Aquila Energy Marketing Corporation 
(Customer).
    Duquesne has requested the Commission waive its notice requirements 
to allow the Service Agreement to become effective as of August 24, 
1998.
    Copies of this filing were served upon Customer.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

42. Allegheny Power Service Corporation on Behalf of Monongahela 
Power Company, The Potomac Edison Company and West Penn Power 
Company (Allegheny Power) and West Penn Power Company (Allegheny 
Energy)

[Docket No. ER99-3715-000]

    Take notice that on July 23, 1999, Allegheny Power Service 
Corporation on behalf of Monongahela Power Company, The Potomac Edison 
Company and West Penn Power Company (Allegheny Power) and West Penn 
Power Company (Allegheny Energy), tendered for filing Amendment No. 2 
to Supplement No. 8 to the Market Rate Tariff and Amendment No. 2 to 
Supplement No. 33 to the Standard Generation Service Tariff to 
incorporate Netting Agreements with New Energy Ventures, Inc. into the 
tariff provisions.
    Allegheny Power requests a waiver of notice requirements to make 
the Amendments effective as of the effective dates therein, May 28, 
1999 for Amendment No. 2 to Supplement No. 33 and June 2, 1999, for 
Amendment No. 2 to Supplement No. 8.
    Copies of the filing have been provided to the Public Utilities 
Commission of Ohio, the Pennsylvania Public Utility Commission, the 
Maryland Public Service Commission, the Virginia State Corporation 
Commission, the West Virginia Public Service Commission, and all 
parties of record.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

43. Allegheny Power Service Corporation on behalf of Monongahela 
Power Company, The Potomac Edison Company and West Penn Power 
Company (Allegheny Power) and West Penn Power Company (Allegheny 
Energy)

[Docket No. ER99-3716-000]

    Take notice that on July 23, 1999, Allegheny Power Service 
Corporation on behalf of Monongahela Power Company, The Potomac Edison 
Company and West Penn Power Company (Allegheny Power) and West Penn 
Power Company (Allegheny Energy), tendered for filing Amendment Nos. 1 
and 2 to Supplement No. 34 to the Standard Generation Service Tariff to 
incorporate Netting Agreements with Penn Power Energy into the tariff 
provisions.
    Allegheny Power and Allegheny Energy request a waiver of notice 
requirements to make the Amendments effective as of the effective dates 
therein, July 13, 1999.
    Copies of the filing have been provided to the Public Utilities 
Commission of Ohio, the Pennsylvania Public Utility Commission, the 
Maryland Public Service Commission, the Virginia State Corporation 
Commission, the West Virginia Public Service Commission, and all 
parties of record.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

44. Allegheny Power Service Corporation on behalf of Monongahela 
Power Company, The Potomac Edison Company and West Penn Power 
Company (Allegheny Power) and West Penn Power Company (Allegheny 
Energy)

[Docket No. ER99-3717-000]

    Take notice that on July 23, 1999, Allegheny Power Service 
Corporation on behalf of Monongahela Power Company, The Potomac Edison 
Company and West Penn Power Company (Allegheny Power) and West Penn 
Power Company (Allegheny Energy), tendered for filing Amendment Nos. 1 
and 2 to Supplement No. 3 to the Market Rate Tariff and Amendment Nos. 
1 and 2 to Supplement No. 32 to the Standard Generation Service Tariff 
to incorporate Netting Agreements with Strategic Energy, L.L.C., into 
the tariff provisions.
    Allegheny Power and Allegheny Energy request a waiver of notice 
requirements to make the Amendments effective as of the effective dates 
therein, July 13, 1999.
    Copies of the filing have been provided to the Public Utilities 
Commission of Ohio, the Pennsylvania Public Utility Commission, the 
Maryland Public Service Commission, the Virginia State Corporation 
Commission, the West Virginia Public Service Commission, and all 
parties of record.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

[[Page 42941]]

45. Allegheny Power Service Corporation on behalf of Monongahela 
Power Company, The Potomac Edison Company and West Penn Power 
Company (Allegheny Power) and West Penn Power Company (Allegheny 
Energy)

[Docket No. ER99-3718-000]

    Take notice that on July 23, 1999, Allegheny Power Service 
Corporation on behalf of Monongahela Power Company, The Potomac Edison 
Company and West Penn Power Company (Allegheny Power) and West Penn 
Power Company (Allegheny Energy), tendered for filing Amendment Nos. 1 
and 2 to Supplement No. 22 to the Standard Generation Service Tariff to 
incorporate Netting Agreements with American Energy Trading, Inc., into 
the tariff provisions.
    Allegheny Power and Allegheny Energy request a waiver of notice 
requirements to make the Amendments effective as of the effective dates 
therein, July 7, 1999.
    Copies of the filing have been provided to the Public Utilities 
Commission of Ohio, the Pennsylvania Public Utility Commission, the 
Maryland Public Service Commission, the Virginia State Corporation 
Commission, the West Virginia Public Service Commission, and all 
parties of record.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

46. Central Vermont Public Service Corporation

[Docket No. ER99-3723-000]

    Take notice that on July 23, 1999, Central Vermont Public Service 
Corporation (Central Vermont), tendered for filing a Service Agreement 
with Energy Atlantic, L.L.C., under its FERC Electric Tariff No. 8.
    Central Vermont requests waiver of the Commission's regulations to 
permit the service agreement to become effective on July 26, 1999.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

47. Bangor Hydro-Electric Company, Rochester Gas and Electric 
Corporation

[Docket No. ER99-3732-000 and ER99-3734-000]

    Take notice that on July 23, 1999, the above-mentioned affiliated 
power producers and/or public utilities filed their quarterly reports 
for the quarter ending, June 30, 1999.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

48. Cadillac Renewable Energy LLC

[Docket No. ER99-3733-000]

    Take notice that on July 23, 1999, Cadillac Renewable Energy LLC 
filed its quarterly report for the quarter ending March 31, 1999.
    Comment date: August 12, 1999, in accordance with Standard 
Paragraph E at the end of this notice.

Standard Paragraphs

    E. Any person desiring to be heard or to protest such filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, NE, Washington, DC 20426, in 
accordance with Rules 211 and 214 of the Commission's Rules of Practice 
and Procedure (18 CFR 385.211 and 385.214). All such motions or 
protests should be filed on or before the comment date. Protests will 
be considered by the Commission in determining the appropriate action 
to be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a motion to 
intervene. Copies of these filings are on file with the Commission and 
are available for public inspection. This filing may also be viewed on 
the Internet at http://www.ferc.fed.us/online/rims.htm (call 202-208-
2222 for assistance).
David P. Boergers,
Secretary.
[FR Doc. 99-20250 Filed 8-5-99; 8:45 am]