DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. CP99-294-000]


Panhandle Eastern Pipe Line Company; Notice of Request Under 
Blanket Authorization

April 14, 1999.
    Take notice that on April 9, 1999, Panhandle Eastern Pipe Line 
Company (Panhandle) P.O. Box 1642, Houston, Texas 77251-1642, filed in 
Docket No. CP99-294-000 a request pursuant to Sections 157.205 and 
157.212 of the Commission's Regulations under the Natural Gas Act (18 
CFR 157.205, 157.212). Panhandle filed for authorization to modify the 
Illinois Power Company Mt. Auburn M&R Station, an existing delivery 
point located in Christian County, Illinois, to permit increased 
deliveries, all as more fully set forth in the request that is on file 
with the Commission and open to public inspection. This filing may be 
viewed on the web at http://www.ferc.fed.us/online/rims.htm (please 
call (202) 208-2222 for assistance).
    Panhandle asserts that the upgrade is relatively minor and will 
increase the maximum design capacity of the Mt. Auburn meter station 
from approximately 7,000 Dt per day to approximately 12,000 Dt per day. 
Panhandle estimates the cost of the upgrade to be $130,700, of which 
amount, Illinois Power will reimburse Panhandle 100%.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Section 157.205 of 
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
the request. If no protest is filed within the time allowed therefore, 
the proposed activity shall be deemed to be authorized effective the 
day after the time allowed for filing a protest. If a protest is filed 
and not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to Section 7 of the Natural Gas Act.
David P. Boergers,
Secretary.
[FR Doc. 99-9812 Filed 4-19-99; 8:45 am]
BILLING CODE 6717-01-M