[Federal Register Volume 64, Number 75 (Tuesday, April 20, 1999)] [Notices] [Page 19351] From the Federal Register Online via the Government Publishing Office [www.gpo.gov] [FR Doc No: 99-9812] ----------------------------------------------------------------------- DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP99-294-000] Panhandle Eastern Pipe Line Company; Notice of Request Under Blanket Authorization April 14, 1999. Take notice that on April 9, 1999, Panhandle Eastern Pipe Line Company (Panhandle) P.O. Box 1642, Houston, Texas 77251-1642, filed in Docket No. CP99-294-000 a request pursuant to Sections 157.205 and 157.212 of the Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 157.212). Panhandle filed for authorization to modify the Illinois Power Company Mt. Auburn M&R Station, an existing delivery point located in Christian County, Illinois, to permit increased deliveries, all as more fully set forth in the request that is on file with the Commission and open to public inspection. This filing may be viewed on the web at http://www.ferc.fed.us/online/rims.htm (please call (202) 208-2222 for assistance). Panhandle asserts that the upgrade is relatively minor and will increase the maximum design capacity of the Mt. Auburn meter station from approximately 7,000 Dt per day to approximately 12,000 Dt per day. Panhandle estimates the cost of the upgrade to be $130,700, of which amount, Illinois Power will reimburse Panhandle 100%. Any person or the Commission's staff may, within 45 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to Section 157.205 of the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to Section 7 of the Natural Gas Act. David P. Boergers, Secretary. [FR Doc. 99-9812 Filed 4-19-99; 8:45 am] BILLING CODE 6717-01-M