[Federal Register Volume 64, Number 67 (Thursday, April 8, 1999)]
[Notices]
[Pages 17148-17149]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-8765]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army Corps of Engineers
Intent to Prepare an Integrated Feasibility Report/Environmental
Impact Statement for Environmental Restoration and Flood Control in the
Sand Creek Watershed near Wahoo, Nebraska
AGENCY: U.S. Army Corps of Engineers, DoD.
ACTION: Notice of intent.
-----------------------------------------------------------------------
SUMMARY: Congress authorized the U.S. Army Corps of Engineers (COE) to
conduct a reconnaissance study along the Lower Platte River and
Tributaries, Nebraska in the interest of flood control, environmental
restoration, and other purposes. The COE has conducted a reconnaissance
study pursuant to this authority, and has determined that further study
in the Sand Creek Watershed in the nature of a Feasibility-Phase Study
is required to fulfill the intent of the study authority and to assess
the extent of the Federal interest.
The goal of the integrated Feasibility Study/EIS will be to
determine the alternative that provides a desired combination of
environmental restoration, reduction of sedimentation and water quality
improvement, while also providing flood damage reduction and recreation
benefits.
Alternatives proposed for consideration are (1) a 637-surface acre
multipurpose impoundment one mile north of Wahoo, Nebraska on Sand
Creek locally known as the Lake Wanahoo proposal, (2) seven smaller
impoundments upstream from the Lake Wanahoo site proposed by the
Natural Resources Conservation Service (NRCS) in 1998, (3) two smaller
impoundments upstream that were proposed by the COE back in 1960, (4) a
combination of Lake Wanahoo and one of the old COE damsites, (5) a
combination of Lake Wanahoo and the seven smaller upstream
impoundments, and (6) one or more stream channel grade control
structures starting at the Lake Wanahoo location and sized to provide
wetlands without creating a structure needing a dam classification. The
no COE action alternative will also be considered.
[[Page 17149]]
A single scoping meeting will be held in Wahoo, Nebraska in the
Lower Platte North Natural Resources District (NRD) conference room
from 7:00-9:00 pm on May 4, 1999. Scoping comments will be accepted by
phone or mail at any time during the preparation of the Draft
Feasibility Report/Draft EIS.
FOR FURTHER INFORMATION CONTACT: Questions about the proposed action
and Draft EIS should be directed to Candace M. Thomas, Chief,
Environmental and Economics Section, Water Resources Branch, U.S. Army
Corps of Engineers, 215 North 17th Street, Omaha, Nebraska 68102-4978,
phone (402) 221-4575, email: Candice.M.T[email protected]
SUPPLEMENTARY INFORMATION: The Lower Platte North NRD is a cost-sharing
sponsor in the preparation of the feasibility study/EIS, and would also
be required to cost-share on any project that results from the study.
The feasibility report and EIS will be integrated to reduce paperwork
and redundancy, and to consolidate planning documentation into one
consistent report.
A watershed planning approach has been taken in the Sand Creek
watershed. A 1998 watershed plan prepared by the Lower Platte North NRD
and the NRCS consists of 7 dams that will reduce rural and urban flood
damages, reduce sedimentation and scour, enhance fish and wildlife
habitat, enhance water quality, improve economic conditions, and
provide recreational opportunities. That planning process was extended
nearly three years for additional studies and consultation with the
USFWS on the timing and flows of the Platte River and potential impacts
on the endangered pallid sturgeon.
During the delay period, the Lower Platte North NRD also began
pursuing a Lake Wanahoo project that would address some of the same
flooding problems. The opportunity for building Lake Wanahoo stems from
the redesign of U.S. Highway 77 from a two-lane highway to a four-lane
expressway. This construction is scheduled to begin in 2002. The Lake
Wanahoo dam embankment could also serve as the expressway crossing of
Sand Creek.
Gregory D. Showalter,
Army Federal Register Liaison Officer.
[FR Doc. 99-8765 Filed 4-7-99; 8:45 am]
BILLING CODE 3710-62-M