[Federal Register Volume 63, Number 225 (Monday, November 23, 1998)]
[Notices]
[Pages 64694-64698]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-31110]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. EL99-3-999, et al.]


MidAmerican Energy Company, et al.; Electric Rate and Corporate 
Regulation Filings

November 10, 1998.
    Take notice that the following filings have been made with the 
Commission:

1. MidAmerican Energy Company

[Docket No. EL99-3-000]

    Take notice that on November 3, 1998, MidAmerican Energy Company 
filed an Amendment to Petition for Enforcement and Declaratory Order in 
the above-captioned proceeding.
    Comment date: December 3, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

2. Storm Lake Power Partners I LLC, Storm Lake Power Partners II 
LLC, and Lake Benton Power Partners II LLC

[Docket No. EC99-8-000]

    Take notice that on November 4, 1998, Storm Lake Power Partners I, 
LLC, Storm Lake Power Partners II LLC, and Lake Benton Power Partners 
II (Applicants), each of 13000 Jameson Road, Tehachapi, California 
93561, submitted for filing an application for approval under Section 
203 of the Federal Power Act of a corporate reorganization in which the 
Applicants' indirect parent Enron Development Corp. will transfer its 
interests in the Applicants to a new entity, Midwest Power Funding LLC 
and will then transfer its interest in Midwest Power Funding LLC to 
another new entity, Enron Wind Midwest LLC, which will be unduly owned 
by Enron Wind Development Corp. No determination has been made that the 
submittal constitutes a complete filing.
    The Applicants are constructing wind power generation facilities in 
Iowa and Minnesota. The purpose of the reorganization is to permit the 
issuance of a consolidated debt offering for construction and term debt 
financing for the facilities. The reorganization will not change the 
ultimate ownership or control of the facilities.
    Comment date: December 4, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

3. Old Dominion Electric Cooperative v. PJM Interconnection, L.L.C.

[Docket No. EL99-9-000]

    Take notice that on November 4, 1998, Old Dominion Electric 
Cooperative (Old Dominion) tendered for filing a complaint against PJM 
Interconnection, L.L.C., for modification of the PJM Open Access Tariff 
and Attendant PJM Market Structure Agreement and request for 
investigation of the cause of a persistent run-up in energy market 
prices within PJM since Locational Marginal Pricing (LMP) was 
implemented by it. Old Dominion requests that the Commission direct a 
modification of the PJM Open Access Tariff and the necessary associated 
agreement to grant the PJM Office of the Interconnection the authority 
that it has previously requested to recall Capacity Resources planned 
for bilateral sales outside the PJM control area--in order to serve PJM 
internal loads prior to scheduling external generation bid at market 
prices. In addition, Old Dominion requests that the Commission initiate 
an investigation pursuant to Section 206 of the Federal Power Act to 
determine the cause of a dramatic and persistent increase in Energy 
Market prices to consumers within the PJM control area since the LMP 
proposal of the PJM Companies, excluding PECO Energy, was implemented 
on April 1, 1998. Old Dominion maintains that such an investigation is 
necessary in the

[[Page 64695]]

absence of operation of a market power policing Market Monitoring Plan 
and implementing Market Monitoring Unit by PJM.
    Copies of Old Dominion's complaint filing were served upon PJM 
Interconnection, L.L.C., and state regulatory authorities in Virginia, 
Delaware, Maryland, Pennsylvania and New Jersey.
    Comment date: December 4, 1998, in accordance with Standard 
Paragraph E at the end of this notice. Answers to the Complaint are 
also due on or before December 4, 1998.

4. Tenaska Power Services Company, Entergy Power marketing Corp., 
CoAgra Energy Services, Inc., e prime, inc., Energy Services, Inc., 
Colonial Energy, Inc., and Niagara Mohawk Energy Marketing, Inc.

[Docket Nos. ER94-389-017, ER95-1615-013, ER95-1751-012, ER95-1269-012, 
ER95-1021-013, ER97-1968-006, and ER96-2525-009]

    Take notice that the following informational filings have been made 
with the Commission and are available for public inspection in the 
Commission's Office of Public Information:
    On October 30, 1998, Tenaska Power Services Company filed certain 
information as required by a Commission order issued in Docket No. 
ER94-389-000.
    On October 30, 1998, Entergy Power Marketing Corporation filed 
certain information as required by a Commission order issued in Docket 
No. ER95-1615-000.
    On October 30, 1998, ConAgra Energy Services, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER95-1751-000.
    On October 30, 1998, e prime, inc. filed certain information as 
required by a Commission order issued in Docket No. ER95-1269-000.
    On October 30, 1998, Energy Services, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER95-1021-000.
    On October 30, 1998, Colonial Energy, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER97-1968-000.
    On October 30, 1998, Niagara Mohawk Energy Marketing, Inc. filed 
certain information as required by a Commission order issued in Docket 
No. ER96-2525-000.

5. Southwest Power Pool Inc.

[Docket No. ER98-1163-003]

    Take notice that on November 4, 1998, Southwest Power Pool Inc., 
tendered for filing its compliance filing in response to the Federal 
Energy Regulatory Commission's October 5, 1998, order in the captioned 
proceeding.
    Copy of this filing is being served on all parties on the 
Commission's service list.
    Comment date: November 24, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

6. CinCap V, LLC, Southern Energy Retail Trading and Marketing, 
Inc., Southern Energy Trading and Marketing Inc., Enron Energy 
Services, Inc., Constellation Power Source, Enron Power Marketing, 
Inc., Equitable Power Services Company, Tosco Power, Inc., 
Competitive Utility Services Corporation, Sithe Power Marketing 
Inc., North American Energy, Inc., Kamps Propane, Inc., Medical 
Area Total Energy Plant, Inc., Energy International Power Marketing 
Corporation, Automated Power Exchange, Inc., and CL Power Sales 
Six. L.L.C.

[Docket Nos. ER98-4055-001, ER98-1149-001, ER95-976-015, ER98-13-007, 
ER97-2261-007, ER94-24-027, ER94-1539-018, ER96-2635-007, ER97-1932-
007, ER98-107-004, ER98-242-002, ER98-1148-001, ER98-1992-002, ER98-
2059-002, ER98-1033-000, and ER96-2652-016]

    Take notice that the following informational filings have been 
filed with the Commission and are available for public inspection and 
copying in the Commission's Office of Public Information:
    On October 30, 1998, CinCap V, LLC filed certain information as 
required by a Commission order issued in Docket No. ER98-4055-000.
    On October 30, 1998, Southern Energy Retail Trading and Marketing, 
Inc. filed certain information as required by a Commission order issued 
in Docket No. ER98-1149-000.
    On October 30, 1998, Southern Energy Trading and Marketing Inc. 
filed certain information as required by a Commission order issued in 
Docket No. ER95-976-000.
    On October 30, 1998, Enron Energy Services, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER98-13-000.
    On October 30, 1998, Constellation Power Source, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER97-2261-000.
    On October 30, 1998, Enron Power Marketing, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER94-24-000.
    On October 30, 1998, Equitable Power Services Company filed certain 
information as required by a Commission order issued in Docket No. 
ER94-1539-000.
    On October 30, 1998, Tosco Power Inc. filed certain information as 
required by a Commission order issued in Docket No. ER96-2635-000.
    On October 30, 1998, Competitive Utility Services Corporation filed 
certain information as required by a Commission order issued in Docket 
No. ER97-1932-000.
    On October 30, 1998, Sithe Power Marketing Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER98-107-000.
    On October 30, 1998, North American Energy, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER98-242-000.
    On October 30, 1998, Kamps Propane, Inc. filed certain information 
as required by a Commission order issued in Docket No. ER98-1148-000.
    On October 30, 1998, Medical Area Total Energy, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER98-1992-000.
    On October 30, 1998, Automated Power Exchange, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER98-1033-000.
    On October 30, 1998, CL Power Sales Six, L.L.C. filed certain 
information as required by a Commission order issued in Docket No. 
ER96-2652-000.

7. Boston Edison Company

[Docket Nos. ER99-35-000, EL99-7-000, and EL99-8-000]

    Take notice that on October 22, 1998, Boston Edison Company (Boston 
Edison), tendered for filing Standstill Agreements with Braintree 
Electric Light Department and Reading Municipal Light Department in the 
above-captioned proceeding.
    Boston Edison states that copies of this filing have been posted 
and served upon the customers involved in Docket No. ER98-35-000 and 
the Massachusetts Department of Telecommunications and Energy.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

8. Commonwealth Electric Company and Cambridge Electric Light 
Company

[Docket No. ER99-275-000]

    Take notice that on November 5, 1998, Commonwealth Electric company 
(Commonwealth) and Cambridge Electric Light Company (Cambridge), 
tendered for filing a corrected Service Agreement between Southern 
Company Energy Marketing, L.P., replacing the Service Agreement 
inadvertently filed

[[Page 64696]]

on October 22, 1998, in the above-referenced docket.
    Comment date: November 25, 1998, in accordance with standard 
Paragraph E at the end of this notice.

9. NorAm Energy Services, Inc., CNG Power Services Corporation, El 
Paso Energy Marketing, CMS Marketing, Services and Company, Koch 
Energy Trading Company, CL Power Sales Two, L.L.C.

[Docket Nos. ER99-472-000, ER94-1554-018, ER95-428-016, ER96-2350-015, 
ER95-218-015, and ER95-892-029]

    Take notice that the following informational filings have been 
filed with the Commission and are available for public inspection and 
coping in the Commission's Office of Public Information:
    On October 30, 1998, NorAm Energy Services, Inc. filed certain 
information as required by a Commission order issued in Docket No. 
ER98-928-000.
    On October 30, 1998, CNG Power Services Corporation filed certain 
information as required by a Commission order issued in Docket No. 
ER94-1554-000.
    On October 30, 1998, El Paso Energy Marketing filed certain 
information as required by a Commission order issued in Docket No. 
ER95-428-000.
    On October 30, 1998, CMS Marketing, Services and Trading Company 
filed certain information as required by a Commission order issued in 
Docket No. ER96-2350-000.
    On October 30, 1998, Koch Energy Trading Company filed certain 
information as required by a Commission order issued in Docket No. 
ER95-218-000.
    On October 30, 1998, CL Power Sales Two, L.L.C. filed certain 
information as required by a Commission order issued in Docket No. 
ER95-892-000.

10. Duke Power, Williams Generation Company-Hazelton, CNG Retail 
Services Corp., CL Power Sales One, L.L.C., CL Power Sales Three, 
L.L.C., CL Power Sales Four, L.L.C., CL Power Sales Five, L.L.C., 
Citizens Power Sales, and Sempra Energy Trading Corp.

[Docket Nos. ER99-514-000, ER99-515-000, ER97-1845-005, ER95-892-028, 
ER95-892-030, ER95-892-031, ER95-892-032, ER94-1685-022, and ER94-1691-
020]

    Taken notice that the following informational filings have been 
made with the Commission and are available for public inspection and 
copying in the Commission's public reference room:
    On October 30, 1998, Duke Power filed certain information as 
required by a Commission order issued in Docket No. ER96-110-000.
    On October 30, 1998, Williams Generation Company-Hazelton filed 
certain information as required by a Commission order issued in Docket 
No. ER97-4587-000.
    On October 30, 1998, CNG Retail Services Corporation filed certain 
information as required by a Commission order issued in Docket No. 
ER97-1845-000.
    On October 30, 1998, CL Power Sales One, L.L.C., Cl Power Sales 
Three, L.L.C., CL Power Sales Four, L.L.C. and CL Power Sales Five, 
L.L.C. filed certain information as required by a Commission order 
issued in Docket No. ER95-892-000.
    On October 30, 1998, Citizens Power Sales filed certain information 
as required by a Commission order issued in Docket No. ER94-1685-000.
    On October 30, 1998, Sempra Energy Trading Company filed certain 
information as required by a Commission order issued in Docket No. 
ER94-1691-000.

11. Entergy Services, Inc.

[Docket No. ER99-519-000]

    Take notice that on November 4, 1998, Entergy Services, Inc. 
(Entergy Services), on behalf of Entergy Arkansas, Inc., Entergy Gulf 
States, Inc., Entergy Louisiana, Inc., Entergy Mississippi, Inc., and 
Entergy New Orleans, Inc. (collectively, the Entergy Operating 
Companies), tendered for filing an Amendment (dated August 19, 1998), 
to the Capacity and Energy Letter Agreement between Entergy Services, 
Inc., and Sam Rayburn G&T Electric Cooperative, Inc.
    Entergy Services requests that the Letter Amendment be made 
effective as of August 1, 1998. Entergy Services also seeks waiver of 
the Commission's notice requirements.
    Comment date: November 24, 1998, in acordance with Standard 
Paragraph E at the end of this notice.

12. Entergy Services, Inc.

[Docket No. ER99-520-000]

    Take notice that on November 4, 1998, Entergy Services, Inc. 
(Entergy Services), on behalf of Entergy Arkansas, Inc., Entergy Gulf 
States, Inc., Entergy Louisiana, Inc., Entergy Mississippi, Inc., and 
Entergy New Orleans, Inc., tendered for filing the First Amendment to 
the Agreement for Special Requirements Wholesale Electric Service 
between Entergy Gulf States, Inc., and East Texas Electric Cooperative, 
Sam Rayburn G&T Electric Cooperative, Inc., and Tex-La Electric 
executed on August 21, 1988.
    Comment date: November 24, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

13. Western Resources, Inc.

[Docket No. ER99-522-000]

    Take notice that on November 4, 1998, Western Resources, Inc., 
(Western Resources), tendered for filing notice that effective the 
January 4, 1999, Service Agreement No. 44 to FERC Electric Tariff, 
Original Volume No. 5, the Non-Firm Point-to-Point Transmission Service 
Agreement between Western Resources, Inc., and Vastar Power Marketing, 
Inc., effective April 22, 1997 and filed with the Federal Energy 
Regulatory Commission by Western Resources, Inc., in docket No. ER97-
2990-000, is to be canceled.
    Notice of the proposed cancellation has been served upon southern 
Company Energy Marketing L.P., and the Kansas Corporation Commission.
    Comment date: November 24, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

14. New York State Electric & Gas Corporation

[Docket No. ER99-523-000]

    Take notice that on November 4, 1998, New York State Electric & Gas 
Corporation (NYSEG), tendered for filing an executed Network Service 
and Network Operating Agreements between NYSEG and Empire Natural Gas 
Corporation. These Agreements specify that the Transmission Customer 
has agreed to the rates, terms and conditions of NYSEG's currently 
effective open access transmission tariff and other revisions to the 
OATT applicable to all customers who take service under its retail 
access program.
    NYSEG requests waiver of the Commission's 60-day notice 
requirements and an effective date of October 23, 1998 for the 
Agreement.
    NYSEG has served copies of the filing on the New York State Public 
Service Commission and the Transmission Customer.
    Comment date: November 24, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

15. Carolina Power & Light Company

[Docket No. ER99-524-000]

    Take notice that on November 5, 1998, Carolina Power & Light 
Company (CP&L), tendered for filing an executed Service Agreement with 
Wabash Valley Power Association, Inc., under the provisions of CP&L's 
Market-Based Rates Tariff, FERC Electric Tariff No. 4. This Service 
Agreement supersedes the un-executed Agreement originally filed

[[Page 64697]]

in Docket No. ER 98-3385-000 and approved effective May 18, 1998.
    Copies of the filing were served upon the North Carolina Utilities 
Commission and the South Carolina Public Service Commission.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

16. Pacific Gas and Electric Company

[Docket No. ER99-525-000]

    Take notice that on November 5, 1998, Pacific Gas and Electric 
Company (PG&E), tendered for filing an amendment (First Amendment) to 
the Control Area and Transmission Service Agreement (Agreement) between 
PG&E and Power Exchange Corporation (PXC) which was accepted by the 
Commission on May 5, 1995 in FERC Docket No. ER95-769-000 as PG&E Rate 
Schedule FERC No. 186. The purpose of the First Amendment is to adopt 
new contract language resulting from the settlement of a dispute 
between the Parties.
    Copies of this filing were served upon PXC and California Public 
Utilities Commission.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

17. Commonwealth Edison Company

[Docket No. ER99-526-000]

    Take notice that on November 5, 1998, Commonwealth Edison Company 
(ComEd), tendered for filing one Service Agreement, establishing MBLP, 
as a customer under the terms of ComEd's Power Sales and Reassignment 
of Transmission Rights Tariff PSRT-1 (PSRT-1 Tariff). The Commission 
has previously designated the PSRT-1 Tariff as FERC Electric Tariff, 
First Revised Volume No. 2.
    ComEd requests an effective date of October 27, 1998, and 
accordingly seeks waiver of the Commission's notice requirements.
    Copies of this filing were served on MBLP and the Illinois Commerce 
Commission.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

18. Cinergy Services, Inc.

[Docket No. ER99-527-000]

    Take notice that on November 5, 1998, Cinergy Services, Inc. 
(Cinergy) and Duke Energy Trading and Marketing, L.L.C. (DETM), 
tendered for filing Notice of Assignment that DETM will replace Duke/
Louis Dreyfus, L.L.C. (d/LD) as a customer under the Interchange 
Agreement designated as Rate Schedule FERC No. 17.
    Cinergy is requesting an effective date of October 1, 1998.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

19. Niagara Mohawk Power Corporation

[Docket No. ER99-528-000]

    Take notice that on November 5, 1998, Niagara Mohawk Power 
Corporation (Niagara Mohawk), tendered for filing Notice of 
Cancellation effective December 2, 1998, Rate Schedule FERC No. 216, 
effective date March 24, 1995, and any supplements thereto, and filed 
with the Federal Energy Regulatory Commission by Niagara Mohawk Power 
Corporation is to be canceled.
    Notice of the proposed cancellation has been served upon North 
American Energy Conservation, Inc.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

20. Cinergy Services, Inc.

[Docket No. ER99-529-000]

    Take notice that on November 5, 1998, Cinergy Services, Inc. 
(Cinergy) and Duke Energy Trading and Marketing, L.L.C. (DETM) tendered 
for filing Consent of Assignment entered into between Cinergy and Duke 
Energy Trading and Marketing L.L.C. (DETM). Cinergy and DETM are 
requesting that DETM will replace Duke/Louis Dreyfus, L.L.C. (D/LD) of 
D/LD's rights and obligations under the Western Systems Power Pool 
Agreement designated as Rate Schedule FERC No. 1.
    Cinergy is requesting an effective date of October 1, 1998.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

21. Cinergy Services, Inc.

[Docket No. ER99-530-000]

    Take notice that on November 5, 1998, Cinergy Services, Inc. 
(Cinergy) and Duke Energy Trading and Marketing, L.L.C. (DETM) tendered 
for filing a Notice of Assignment that DETM will replace Duke/Louis 
Dreyfus, L.L.C. (D/LD) as a customer under the Cinergy Power Sales 
Standard Tariff, Volume No. 4.
    Cinergy is requesting an effective date of October 1, 1998.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

22. Ameren Services Company

[Docket No. ER99-535-000]

    Take notice that on November 6, 1998, Ameren services Company 
(ASC), tendered for filing a Service agreement for Firm Point-to-Point 
Transmission Service between ASC and Constellation Power Source, Inc., 
(CPS). ASC asserts that the purpose of the Agreement is to permit ASC 
to provide transmission service to CPS pursuant to Amerens's Open 
Access Transmission Tariff filed in Docket No. ER96-677-004.
    ASC requests that the Service Agreement be allowed to become 
effective October 8, 1998.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

23. Ameren Services Company

[Docket No. ER99-536-000]

    Take notice that on November 6, 1998, Ameren Services Company 
(ASC), tendered for filing a Service Agreement for Non-Firm Point-to-
Point Transmission Service between ASC and Constellation power Source, 
Inc., (CPS). ASC asserts that the purpose of the Agreement is to permit 
ASC to provide transmission service to CPS pursuant to Ameren's Open 
Access Transmission Tariff filed in Docket No. ER96-677-004.
    ASC requests that the Service Agreement be allowed to become 
effective on October 8, 1998.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

24. Allegheny Power Service Corp., on behalf of Monongahela Power 
Co., The Potomac Edison Company and West Penn Power Company 
(Allegheny Power)

[Docket No. ER99-537-000]

    Take notice that on November 6, 1998, Allegheny Power Service 
Corporation on behalf of Monongahela Power Company, The Potomac Edison 
Company and West Penn Power Company (Allegheny Power) filed Supplement 
No. 8 to add one (1) new Customer to the Market Rate Tariff under which 
Allegheny Power officers generation services.
    Allegheny Power requests a waiver of notice requirements to make 
service available as of November 5, 1998, to new Energy Ventures, Inc.
    Copies of the filing have been provided to the Public Utilities 
Commission of Ohio, the Pennsylvania Public Utility Commission, the 
Maryland Public Service Commission, the Virginia State Corporation 
Commission, the West Virginia Public

[[Page 64698]]

Service Commission, and all parties of record.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

25. Peco Energy Company

[Docket No. ER99-538-000]

    Take notice that on November 6, 1998, PECO Energy Company (PECO), 
tendered for filing a Service Agreement dated June 2, 1997 with 
Kennebunk Light and Power District (KLPD) under PECO's FERC Electric 
Tariff Original Volume No. 1 (Tariff). The Service Agreement adds KLPD 
as a customer under the Tariff.
    PECO requests an effective date of October 8, 1998, for the Service 
Agreement.
    PECO states that copies of this filing have been supplied to KLPD 
and to the Pennsylvania Public Utility Commission.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

26. Montaup Electric Company

[Docket No. ER99-539-000]

    Take notice that on November 6, 1998, Montaup Electric Company 
(Montaup), tendered for filing Notice of Cancellation of its Rate 
Schedule FERC No. 123.
    Comment date: November 25, 1998, in accordance with Standard 
paragraph E at the of this notice.

27. Pacific Gas and Electric Company

[Docket No. ER99-540-000]

    Take notice that on November 6, 1998, Pacific Gas and Electric 
Company (PG&E), tendered for filing an agreement between PG&E, the 
United States of America, Department of Energy, Oakland Operations 
Office (DOE) (collectively Parties), entitled ``Settlement Agreement 
for Power Delivery to the United States Department of Energy 
Laboratories''.
    The Agreement is intended to, among other things, settle issues and 
implement procedures for PG&E's existing obligation to deliver power to 
DOE's Northern California Laboratories known as Lawrence Livermore 
National Laboratory (LLNL), Lawrence Livermore National Laboratory Site 
300 (Site 300), Stanford Linear Accelerator Center (SLAC), and Lawrence 
Berkeley National Laboratory (LBNL) under PG&E Rate Schedule FERC No. 
147.
    Copies of this filing have been served upon DOE, Western and the 
California Public Utilities Commission.
    Comment date: November 25, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

28. Western Systems Power Pool

[Docket No. ER99-541-000]

    Take notice that on November 6, 1998, the Western Systems Power 
Pool (WSPP), tendered for filing revisions to the WSPP Agreement, and 
for authorization to allow certain members of the WSPP to sell power 
under the WSPP Agreement at market-based rates.
    The WSPP states the revisions to the WSPP Agreement are necessary 
to update the terms of the WSPP Agreement and better ensure commercial 
enforceability of the agreements terms. In addition, the WSPP seeks 
authorization for WSPP members who have already received authorization 
from the Federal Energy Regulatory Commission (FERC) to sell power at 
market-based rates, and for WSPP members who are not subject to the 
FERC's jurisdiction under Section 201 of the Federal Power Act, to sell 
power under the WSPP Agreement at market-based rates.
    Comment date: November 26, 1998, in accordance with Standard 
Paragraph E at the end of this notice.

Standard Paragraphs

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission 888 First Street, NE., Washington, DC 20426, in 
accordance with Rules 211 and 214 of the Commission's Rules of Practice 
and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such motions or 
protests should be filed on or before the comment date. Protests will 
be considered by the Commission in determining the appropriate action 
to be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a motion to 
intervene. Copies of these filings are on file with the Commission and 
are available for public inspection.
David P. Boergers,
Secretary.
[FR Doc. 98-31110 Filed 11-20-98; 8:45 am]
BILLING CODE 6717-01-P