    Take notice that on October 9, 1998, Northern Natural Gas 
(Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed 
in Docket No. CP99-11-000, a request pursuant to Section 157.205 and 
157.212 of the Commission's Regulations under the Natural Gas Act (18 
CFR 157.205 and 157.212) for authorization to upgrade the Farley #1 TBS 
existing delivery point and appurtenant facilities located in Dubuque 
County, Iowa, to accommodate natural gas deliveries to UtiliCorp 
United, Inc. (UCU) under Northern's blanket certificate issued in 
Docket No. CP82-401-000, pursuant to 18 CFR Part 157, Subpart F of the 
Natural Gas Act, all as more fully set forth in the request which is on 
file with the Commission and open to public inspection.
    Northern states that it requests authorization to upgrade the 
existing delivery point to accommodate natural gas deliveries to UCU 
under currently effective throughput service agreement(s). Northern 
asserts that UCU has requested the proposed upgrade to provide 
additional natural gas service to the Farley #1#1 TBS for redelivery to 
a grain dryer. It is further stated that the estimated incremental 
volumes proposed to be delivered to UCU at this delivery point is 171 
MMBtu on a peak day and 19,276 MMBtu on an annual basis. Northern 
states that the estimated cost to upgrade the existing delivery point 
is $7,000. Northern further states that UCU would reimburse Northern 
for the total cost to upgrade the existing delivery point.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) motion to 
intervene or notice of intervention and pursuant to Section 157.205 of 
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
the request. If no protest is filed within the time allowed therefor, 
the proposed activity shall be deemed to be authorized effective the 
day after the time allowed for filing a protest. If a protest is filed 
and not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request be treated as an application for 
authorization pursuant to Section 7 of the Natural Gas Act.