[Federal Register Volume 63, Number 110 (Tuesday, June 9, 1998)]
[Notices]
[Pages 31451-31452]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-15239]


-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

GENERAL SERVICES ADMINISTRATION

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

[OMB Control No. 9000-0078]


Proposed Collection; Comment Request Entitled Make-or-Buy Program

AGENCIES: Department of Defense (DOD), General Services Administration 
(GSA), and National Aeronautics and Space Administration (NASA).

ACTION: Notice of request for comments regarding an extension to an 
existing OMB clearance (9000-0078).

-----------------------------------------------------------------------

SUMMARY: Under the provisions of the Paperwork Reduction Act of 1995 
(44 U.S.C. Chapter 35), the Federal Acquisition Regulation (FAR) 
Secretariat will be submitting to the Office of Management and Budget 
(OMB) a request to review and approve an extension of a currently 
approved information collection requirement concerning Make-or-Buy 
Program. The clearance currently expires on September 30, 1998.

DATES: Comments may be submitted August 10, 1998.


[[Page 31452]]


FOR FURTHER INFORMATION CONTACT: Ralph DeStefano, Federal Acquisition 
Policy Division, GSA (202) 501-1758.

ADDRESSES: Send comments regarding this burden estimate or any other 
aspect of this collection of information, including suggestions for 
reducing this burden, to: FAR Desk Officer, OMB, Room 10102, NEOB, 
Washington, DC 20503, and a copy to the General Services 
Administration, FAR Secretariat (MVRS), 1800 F Street, NW, Room 4035, 
Washington, DC 20405.

SUPPLEMENTARY INFORMATION:

A. Purpose

    Price, performance, and/or implementation of socio-economic 
policies may be affected by make-or-buy decisions under certain 
Government prime contracts. Accordingly, Section 15.407-2, Make-or-Buy 
Programs, of the FAR--
    (i) Sets forth circumstances under which a Government contractor 
must submit for approval by the contracting officer a make-or-buy 
program, i.e., a written plan identifying major items to be produced or 
work efforts to be performed in the prime contractor's facilities and 
those to be subcontracted;
    (ii) Provides guidance to contracting officers concerning the 
review and approval of the make-or-buy programs; and
    (iii) Prescribes the contract clause at FAR 52.215-9, Changes or 
Additions to Make-or-Buy Programs, which specifies the circumstances 
under which the contractor is required to submit for the contracting 
officer's advance approval a notification and justification of any 
proposed change in the approved make-or-buy program.
    The information is used to assure the lowest overall cost to the 
Government for required supplies and services.

B. Annual Reporting Burden

    Public reporting burden for this collection of information is 
estimated to average 8 hours per termination, including the time for 
reviewing instructions, searching existing data sources, gathering and 
maintaining the data needed, and completing and reviewing the 
collection of information.
    The annual reporting burden is estimated as follows: Respondents, 
150; responses per respondent, 3; total annual responses, 450; 
preparation hours per response, 8; and total response burden hours, 
3,600.

Obtaining Copies of Proposals

    Requester may obtain a copy of the justification from the General 
Services Administration, FAR Secretariat (MVRS), Room 4035, Washington, 
DC 20405, telephone (202) 501-4755. Please cite OMB Control No. 9000-
0078, Make-or-Buy Program, in all correspondence.

    Dated: June 3, 1998.
Sharon A. Kiser,
FAR Secretariat.
[FR Doc. 98-15239 Filed 6-8-98; 8:45 am]