[Federal Register Volume 63, Number 29 (Thursday, February 12, 1998)]
[Notices]
[Pages 7154-7155]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-3522]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Application Ready for Environmental Analysis

February 6, 1998.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Minor License.
    b. Project No.: 11060-000.
    c. Date Filed: December 13, 1993.
    d. Applicant: J.M. Miller Enterprises.
    e. Name of Project: Sahko Hydroelectric Project.
    f. Location: On the Kastelu Drain, Twin Falls County, Idaho.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: D.W. ``Bill'' Block, P.E., J-U-B Engineers, 
Inc., 800 Falls Ave., Twin Falls, Idaho 83301, (208) 622-7215.
    i. FERC Contact: Nan S. Allen, 202-219-2938, or E-mail at 
[email protected].
    j. Deadline for comments, recommendations, terms and conditions, 
and prescriptions: See attached paragraph.
    k. Status of Environmental Analysis: The application is now ready 
for environmental analysis--see attached paragraph D10.
    l. Brief Description of Project: The proposed project would consist 
of: (1) an 11-foot-long, 13.5-foot-high, earth-fill embankment, 
impounding a 3-acre-foot forebay; (2) an 8.0-foot-wide, 10.0-foot-long, 
10.5-foot-deep concrete intake structure with protective trash racks; 
(3) an 80-foot-long, 9.5-foot-high, earth-fill embankment, impounding a 
4-acre-foot sediment collection pond; (4) a 24-inch-diameter 1,950-
foot-long, steel penstock; (5) a 25-foot-wide, 50 foot-long, masonry-
block powerhouse, with an installed capacity of 500 kilowatts; (6) a 6-
foot-wide, 30-foot-long, 3-foot deep, rock-lined tailrace; (7) a 34.5-
kilovolt, 2,000-foot-long transmission line; and (8) related 
appurtenances.
    m. This notice also consists of the following standard paragraphs: 
A4 and D10.
    n. A copy of the application is available for inspection and 
reproduction at the Commission's Public Reference Room, located at: 888 
First St., N.E., Room 2A, Washington, D.C. 20426, or by calling (202) 
208-1371.
    A4. Development Application--Public notice of the filing of the 
initial development application, which has already been given, 
established the due date for filing competing applications or notices 
of intent. Under the Commission's regulations, any competing 
development application must be filed in response to and in compliance 
with public notice of the initial development application. No competing 
applications or notices of intent may be filed in response to this 
notice.
    D10. Filing and Service of Responsive Documents--The application is 
ready for environmental analysis at this time, and the Commission is 
requesting comments, reply comments, recommendations, terms and 
conditions, and prescriptions.
    The Commission directs, pursuant to Section 4.34(b) of the 
Regulations (see Order No. 533 issued May 8, 1991, 56 FR 23108, May 20, 
1991) that all comments, recommendations, terms and conditions and 
prescriptions concerning the application be filed with the

[[Page 7155]]

Commission within 60 days from the issuance date of this notice. All 
reply comments must be filed with the Commission within 105 days from 
the date of this notice.
    Anyone may obtain an extension of time for these deadlines from the 
Commission only upon a showing of good cause or extraordinary 
circumstances in accordance with 18 CFR 385.2008.
    All filings must (1) bear in all capital letters the title 
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person submitting the filing; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicants. Any of these documents must 
be filed by providing the original and the number of copies required by 
the Commission's regulations to: The Secretary, Federal Energy 
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426. 
An additional copy must be sent to Director, Division of Project 
Review, Office of Hydropower Licensing, Federal Energy Regulatory 
Commission at the above address. Each filing must be accompanied by 
proof of service on all persons listed on the service list prepared by 
the Commission in this proceeding, in accordance with 18 CFR 4.34(b), 
and 385.2010.
David P. Boergers,
Acting Secretary.
[FR Doc. 98-3522 Filed 2-11-98; 8:45 am]
BILLING CODE 6717-01-M