[Federal Register Volume 63, Number 17 (Tuesday, January 27, 1998)]
[Notices]
[Page 3888]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-1872]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. CP98-185-000]


NorAm Gas Transmission Company; Notice of Request Under Blanket 
Authorization

January 21, 1998.
    Take notice that on January 14, 1998, NorAm Gas Transmission 
Company (NorAm), 1600 Smith Street, Houston, Texas 77002, filed in 
Docket No. CP98-185-000 a request pursuant to Sections 157.205 and 
157.211 of the Commission's regulations under the Natural Gas Act (18 
CFR 157.205 and 157.211) under NorAm's blanket certificate issued in 
Docket Nos. CP82-384-000 and CP82-384-001 for authorization to operate 
certain facilities in Arkansas, Louisiana, Oklahoma and Texas, all as 
more fully set forth in the request which is on file with the 
Commission and open to public inspection.
    NorAm specifically requests authority at the request of ARKLA, a 
distribution division of NorAm Energy Corporation (ARKLA), to operate 
existing taps for delivery of natural gas to ARKLA for resale to 
consumers other than the right-of-way grantors from whom the taps were 
originally installed. NorAm states that the volumes through these taps 
range from 1 MMBtu to 200 MMBtu per day. The location and size of each 
tap for certification is shown in Exhibit Z of the application. NorAm 
further states that there will be no new construction.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Section 157.205 of 
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
the request. If no protest is filed within the time allowed therefor, 
the proposed activity shall be deemed to be authorized effective the 
day after the time allowed for filing a protest. If a protest is filed 
and not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to Section 7 of the Natural Gas Act.
David P. Boergers,
Acting Secretary.
[FR Doc. 98-1872 Filed 1-26-98; 8:45 am]
BILLING CODE 6717-01-M