[Federal Register Volume 62, Number 74 (Thursday, April 17, 1997)] [Notices] [Page 18770] From the Federal Register Online via the Government Publishing Office [www.gpo.gov] [FR Doc No: 97-9895] ----------------------------------------------------------------------- DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP97-307-000] Transcontinental Gas Pipe Line Corporation; Notice of Request Under Blanket Authorization April 11, 1997. Take notice that on March 26, 1997, Transcontinental Gas Pipe Line Company (Transco), 2800 Post Oak Boulevard, P.O. Box 1396, Houston, Texas 77251-1396, filed in Docket No. CP97-307-000 a request pursuant to Sections 157.205, 157.212, and 157.216 of the Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 157.212, 157.216) for authorization to expand an existing delivery point to South Carolina Pipeline Corporation (SCPC) and to remove pipeline at the Grover Meter Station, located in Cleveland County, North Carolina, under Transco's blanket certificate issued in Docket No. CP82-426-000, pursuant to Section 7(c) of the Natural Gas Act, all as more fully set forth in the request that is on file with the Commission and open to public inspection. Transco proposes to expand the Grove Meter Station, an existing delivery point to SCPC, by (1) Installing a 16-inch main line tap and approximately 800 feet of new 16-inch pipe to the Grove Meter Station and retiring 800 feet of 10-inch pipe, (2) retiring, replacing, and expanding the Grove Meter Station piping, odorization system, and other appurtenances, and (3) constructing 1,791 feet of 16-inch pipeline loop from the Grove Meter Station outlet to a tie-in with SCPC's pipeline at the North Carolina/South Carolina state border, all located in Cleveland County, North Carolina, to be referred to as the Grove Meter Station Expansion. Transco states it currently delivers up to 70,000 Dth per day to SCPC at the Grove Meter Station. As a result of the expansion proposed herein, Transco declares the capacity of the Grove Meter Station will be increased to 200,000 Dth per day. Transco asserts it has sufficient delivery flexibility to accomplish such additional deliveries without detriment or disadvantage to its other customers. Transco states the estimated cost to construct the Grove Meter Expansion to be $1,056,736, with SCPC reimbursing Transco for all costs associated with the project. Any person or the Commission's staff may, within 45 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to Section 157.205 of the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the request. If no protest is filed within the time allowed therefor, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to Section 7 of the Natural Gas Act. Linwood A. Watson, Jr., Acting Secretary. [FR Doc. 97-9895 Filed 4-16-97; 8:45 am] BILLING CODE 6717-01-M