[Federal Register Volume 62, Number 59 (Thursday, March 27, 1997)]
[Notices]
[Pages 14678-14679]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-7788]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP97-238-000]
Portland Natural Gas Transmission System and Maritimes &
Northeast Pipeline, L.L.C.; Notice of Application
March 21, 1997.
Take notice that on March 18, 1997, Portland Natural Gas
Transmission System (PNGTS), 300 Friberg Parkway, Westborough,
Massachusetts 01581-5039, and Maritimes & Northeast Pipeline, L.L.C.
(Maritimes), 1284 Soldiers Field Road, Boston, Massachusetts 02135,
(together as joint applicants), completed the filing of a joint
application in Docket No. CP97-238-000 for a certificate of public
convenience and necessity, pursuant to Section 7(c) of the Natural Gas
Act, to construct and operate jointly-owned pipeline facilities for the
transportation of natural gas, all as more fully set forth in the
application which is on file with the Commission and open to public
inspection.
The completion of the joint application, originally filed February
10, 1997, was preceded by two public conferences at the Commission and
four letters from the Office of Pipeline Regulation (OPR) requesting
the information required to complete the filing. The joint applicants
request that the Commission issue a preliminary determination on non-
environmental issues by May 31, 1997, and a certificate by August 31,
1997.
Specifically, joint applicants seek authorization to construct
about:
--99.8 miles of 30-inch pipeline and appurtenant facilities from
Dracut, Massachusetts to Westbrook, Maine;
--a 3.8 mile, 12-inch lateral at Westbrook, Maine (Westbrook Lateral);
--a 1.36 mile, 16-inch lateral near Newington, New Hampshire (Newington
Lateral);
--a 0.6 mile, 20-inch interconnecting line at Haverhill, Massachusetts
(Haverhill Lateral);
--eight meter and regulation stations, and other appurtenant facilities
The estimated cost of the joint pipeline proposal is $172.4 million.
PNGTS will be responsible for the engineering, design, and
construction management of the jointly-owned pipeline, and Maritimes
will be designated as the operator, including field operations and gas
dispatching. The cost and ownership of the joint pipeline facilities
will be based upon the ration of each owner's allocated capacity. The
total capacity of the joint pipeline is 631,860 Mcf per day, with
421,860 Mcf per day allocated to Maritimes and 210,000 Mcf per day
allocated to PNGTS. The proposed laterals off the joint pipeline will
be part of the jointly-owned facilities and will be sized according to
each owner's requirements. The cost allocation of the laterals will be
based on the ratio of each owner's capacity through the lateral. The
cost and ownership ratios are in the following table.
[[Page 14679]]
------------------------------------------------------------------------
Maritimes PNGTS
Facilities (percent) (percent)
------------------------------------------------------------------------
Mainline................................ 66.76 33.24
Westbrook Maritimes Meter............... 100.00 0.00
Westbrook PNGTS Meter................... 0.00 100.00
Dracut Meter and Modifications.......... 67.69 32.31
Wells Meter............................. 89.09 10.91
Westbrook Lateral....................... 63.35 36.65
Granite State Meter at Westbrook........ 41.10 58.90
Newington Lateral....................... 41.10 58.90
Granite State Meter at Newington........ 0.00 100.00
PSNH Meter at Newington................. 50.00 50.00
Haverhill Lateral....................... 1.42 98.58
Tennessee Meter at Haverhill............ 0.00 100.00
------------------------------------------------------------------------
Each owner will be responsible for recovering all of its share of
costs and expenses of the joint pipeline facilities through rates
proposed in its related filings in Docket Nos. CP96-178-000, et al.
(Maritimes), CP96-809-000 (Maritimes), and CP96-249-000, et al.
(PNGTS). The Joint Pipeline facilities will be operated in accordance
with each of the owner's separate tariffs proposed in their respective
filings listed above.
The joint applicants each amended their original proposals to
address the impacts of the joint application. Maritimes' amendments
were filed on February 24, 1997, and PNGTS' amendment was filed on
March 18, 1997. Separate notices of these amendments will be issued.
However, certain information which is needed to complete the processing
of this application remains to be filed.\1\ Complete and accurate
filing of that information on the schedule stated in the joint
applicants' March 18, 1997, filing is essential for the expeditious
processing of these applications.
---------------------------------------------------------------------------
\1\ See the March 21, 1997, OPR Director's letter to the joint
applicants.
---------------------------------------------------------------------------
Any person desiring to be heard or to make any protest with
reference to said application should on or before April 15, 1997 file
with the Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426, a motion to intervene or a protest in accordance
with the requirements of the Commission's Rules of Practice and
Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
Natural Gas Act (18 CFR 157.10). All protests filed with the Commission
will be considered by it in determining the appropriate action to be
taken but will not serve to make the protestants parties to the
proceeding. Any person wishing to become a party to a proceeding or to
participate as a party in any hearing therein must file a motion to
intervene in accordance with the Commission's Rules.
Take further notice that, pursuant to the authority contained in
and subject to jurisdiction conferred upon the Federal Energy
Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and
the Commission's Rules of Practice and Procedure, a hearing will be
held without further notice before the Commission or its designee on
this application if no motion to intervene is filed within the time
required herein, if the Commission on its own review of the matter
finds that a grant of the certificate is required by the public
convenience and necessity. If a motion for leave to intervene is timely
filed, or if the Commission on its own motion believes that a formal
hearing is required, further notice of such hearing will be duly given.
Under the procedure herein provided for, unless otherwise advised,
it will be unnecessary for the joint applicants to appear or be
represented at the hearing.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 97-7788 Filed 3-26-97; 8:45 am]
BILLING CODE 6717-01-M