DEPARTMENT OF ENERGY
[Docket No. EG97-37-000, et al.]


CNG Kauai, Inc., et al.; Electric Rate and Corporate Regulation 
Filings

March 7, 1997.
    Take notice that the following filings have been made with the 
Commission:

1. CNG Kauai, Inc.

[Docket No. EG97-37-000]

    On February 28, 1997, CNG Kauai, Inc. (CNG Kauai), with its 
principal office located at One Park Ridge Center, P.O. Box 15746, 
Pittsburgh, PA 15244-0746, filed with the Federal Energy Regulatory 
Commission an application for determination of exempt wholesale 
generator status pursuant to Part 365 of the Commission's Regulations.
    CNG Kauai will be a Delaware limited partnership which will own a 
one percent general partner interest and a ninety-eight percent limited 
partner interest in Kauai Power Partners, Inc., L.P., a Delaware 
limited partnership which will own an advanced steam-injected gas 
turbine electric generating facility in Kauai, Hawaii and will sell 
energy at wholesale from that facility to Kauai Electric.
    Comment date: March 27, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The Commission will limits its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

2. Kauai Power Partners, L.P.

[Docket No. EG97-38-000]

    On February 28, 1997, Kauai Power Partners, L.P. (KPP), with its 
principal office located at One Park Ridge Center, P.O. Box 15746, 
Pittsburgh, PA 15244-0746, filed with the Federal Energy Regulatory 
Commission an application for determination of exempt wholesale 
generator status pursuant to Part 365 of the Commission's Regulations.
    KPP will be a Delaware limited partnership which will own an 
advanced steam-injected gas turbine electric generating facility in 
Kauai, Hawaii and which will sell energy at wholesale from that 
facility to Kauai Electric.
    Comment date: March 27, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The Commission will limit its 
consideration of comments to those concern the adequacy or accuracy of 
the application.

3. Kazak Power Partners Limited

[Docket No. EG97-39-000]

    On February 28, 1997, Kazak Power Partners Limited (Applicant), 6th 
Floor, No. 1 Minster Court, Mincing Lane, London EC3R 7AA, England, 
filed with the Federal Energy Regulatory Commission an application for 
determination of exempt wholesale generator status pursuant to Part 365 
of the Commission's Regulations.
    Applicant, formed under the laws of the United Kingdom, is owned by 
E Prime Projects International, Inc. (which has a 25% interest), 
Independent Power Corporation PLC (which has a 50% interest), and 
Samsung Deutschland GmbH (which has a 25% interest). Applicant intends 
to own or operate, or both own and operate, all or part of the 
Karaganda Steam Power Station GRES 2. This facility is a 608 MW oil and 
coal-fired electric generating station consisting of eight generating 
units, and associated equipment, buildings, and land.
    Comment date: March 27, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The Commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

4. E Prime Projects International, Inc.

[Docket No. EG97-40-000]

    On February 28, 1997, E Prime Projects International, Inc. 
(Applicant), 1331 17th Street, Suite 601, Denver, Colorado 80202, filed 
with the Federal Energy Regulatory Commission an application for 
determination of exempt wholesale generator status pursuant to Part 365 
of the Commission's Regulations.
    Applicant, a Delaware corporation, is a wholly-owned subsidiary of 
E Prime, Inc., a Colorado corporation. Applicant owns a 25% interest in 
Kazak Power Partners Limited. Kazak Power Partners Limited will wholly 
own the Karaganda Steam Power Station GRES 2. Applicant intends to 
indirectly through an affiliate own or operate, or both own and 
operate, all or part of the Karaganda Steam Power Station GRES 2. This 
facility is a 608 MW oil and coal-fired electric generating station 
consisting of eight generating units, and associated equipment, 
buildings, and land.
    Comment date: March 27, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The Commission will limits its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

5. E Prime Operating, Inc.

[Docket No. EG97-41-000]

    On February 28, 1997, E Prime Operating, Inc. (Applicant), 1331 
17th Street, Suite 601, Denver, Colorado 80202, filed with the Federal 
Energy Regulatory Commission an application for determination of exempt 
wholesale generator status pursuant to Part 365 of the Commission's 
Regulations.
    Applicant, a Delaware corporation, is wholly owned by E Prime 
Projects International, Inc. Applicant intends to operate all or part 
of the Karaganda Steam Power Station GRES 2. This facility is a 608 MW 
oil and coal-fired electric generating station consisting of eight 
generating units, and associated equipment, buildings, and land.
    Comment date: March 27, 1997, in accordance with Standard Paragraph 
E at the end of this notice. The Commission will limits its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

6. PanEnergy Power Services, Inc.

[Docket No. ER95-7-013]

    Take notice that on February 7, 1997, PanEnergy Power Services, 
Inc. tendered for filing its revised FERC Electric Rate Schedule No. 1 
in the above-referenced docket.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

7. Washington Water Power Company

[Docket No. ER97-289-000]

    Take notice that on February 24, 1997, Washington Water Power 
Company tendered for filing an amendment in the above-referenced 
docket.

[[Page 11861]]

    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

8. American Electric Power Service Corporation

[Docket No. ER97-906-000]

    Take notice that on February 20, 1997, American Electric Power 
Service Corporation (AEPSC), submitted for filing with the Commission, 
an amendment to the AEP Companies' Power Sales Tariff, proposing minor 
clarifications, made at the request of the Commission's Staff. The 
Power Sales Tariff has previously been accepted and designated as AEP 
companies' FERC Electric Tariff First Revised Volume No. 2.
    A copy of the filing was served upon all customers and affected 
State Utility Regulatory Commissions.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

9. Texas Utilities Electric Company; Texas Utilities Electric Company 
v. Central Power and Light Company, West Texas Utilities Company, 
Public Service Company of Oklahoma and Southwestern Electric Power 
Company

[Docket No. ER97-1056-000]

    Take notice that on February 27, 1997, Central Power and Light 
Company (CPL) and West Texas Utilities Company (WTU) withdrew the 
December 31, 1996, filing in the above-referenced docket.
    CPL and WTU state that copies of the filing were served on Texas 
Utilities Electric Company, Houston Lighting & Power Company and the 
Public Utility Commission of Texas.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

10. Columbia Energy Services Corporation

[Docket No. ER97-1621-000]

    Take notice that on February 26, 1997, Columbia Energy Services 
Corporation (CES) tendered for filing with the Federal Energy 
Regulatory Commission an amendment to CES's February 10, 1997, filing 
of Rate Schedule No. 1. The amendment clarifies the relationship 
between CES and its parent and affiliates.
    Comment date: March 20, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

11. Strategic Power Management, Inc.

[Docket No. ER97-1781-000]

    Take notice that on February 10, 1997, Strategic Power Management, 
Inc. tendered for filing a Notice of Name Change stating that Strategic 
Energy Management, Inc. has changed its name to Strategic Power 
Management, Inc.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

12. Black Hills Power and Light Company

[Docket No. ER97-1782-000]

    Take notice that on February 4, 1997, Black Hills Power and Light 
Company tendered for filing a Notice of Cancellation of the supplement 
to its Executed Form of Service Agreement with Illinova Power 
Marketing, Inc.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

13. Pacific Northwest Generating Cooperative

[Docket No. ER97-1802-000]

    Take notice that on February 20, 1997, Pacific Northwest Generating 
Cooperative (PNGC), filed service agreements for six (6) short-term 
power sale transactions with Alberta Power. The service agreements 
incorporated terms and conditions of the Western Systems Power Pool 
Agreement and the sales were made on price terms conforming to PNGC's 
Rate Schedule FERC No. 3 (market-based rate schedule).
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

14. Peabody POWERTRADE, Inc.

[Docket No. ER97-1826-000]

    Take notice that on February 20, 1997, Peabody POWERTRADE, Inc. 
(Powertrade) filed a request for the cancellation of its FERC Electric 
Rate Schedule No. 1, to be effective immediately.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

15. Illinois Power Company

[Docket No. ER97-1827-000]

    Take notice that on February 21, 1997, Illinois Power Company (IP) 
and with Soyland Power Cooperative, Inc.'s (Soyland) statement of 
concurrence, tendered for filing an Amended and Restated Power 
Coordination Agreement, Amendment No. 6, between Illinois Power and 
Soyland Power Cooperative, Inc. Illinois Power and Soyland are 
requesting an effective date of September 1, 1996.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

16. Jersey Central Power & Light Company, Metropolitan Edison Company, 
and Pennsylvania Electric Company

[Docket No. ER97-1828-000]

    Take notice that on February 21, 1997, Jersey Central Power & Light 
Company, Metropolitan Edison Company and Pennsylvania Electric Company, 
each doing business as and collectively referred to herein as ``GPU 
Energy'', filed a Service Agreement between GPU Energy and Cenerprise, 
Inc., (Cenerprise) dated January 23, 1997. This Service Agreement 
specifies that Cenerprise has agreed to the rates, terms and conditions 
of the GPU Energy open access transmission tariff filed on July 9, 1996 
in Docket No. OA96-114-000.
    GPU Energy requests a waiver of the Commission's notice 
requirements for good cause shown and an effective date of January 23, 
1997, for the Service Agreement. GPU Energy has served copies of the 
filing on regulatory agencies in New Jersey and Pennsylvania and 
Cenerprise.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

17. Jersey Central Power & Light Company, Metropolitan Edison Company, 
Pennsylvania Electric Company

[Docket No. ER97-1829-000]

    Take notice that on February 21, 1997, Jersey Central Power & Light 
Company, Metropolitan Edison Company and Pennsylvania Electric Company, 
each doing business as and collectively referred to herein as ``GPU 
Energy'', filed a Service Agreement between GPU Energy and Vitol Gas & 
Electric LLC, (Vitol) dated January 23, 1997. This Service Agreement 
specifies that Vitol has agreed to the rates, terms and conditions of 
the GPU Energy open access transmission tariff filed on July 9, 1996 in 
Docket No. OA96-114-000.
    GPU Energy requests a waiver of the Commission's notice 
requirements for good cause shown and an effective date of January 23, 
1997 for the Service Agreement. GPU Energy has served copies of the 
filing on regulatory agencies in New Jersey and Pennsylvania and Vitol.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

[[Page 11862]]

18. Jersey Central Power & Light Company, Metropolitan Edison Company, 
Pennsylvania Electric Company

[Docket No. ER97-1830-000]

    Take notice that on February 21, 1997, Jersey Central Power & Light 
Company, Metropolitan Edison Company and Pennsylvania Electric Company, 
each doing business as and collectively referred to herein as ``GPU 
Energy'', filed a Service Agreement between GPU Energy and Southern 
Energy Marketing, Inc., (``Southern'') dated January 23, 1997. This 
Service Agreement specifies that Southern has agreed to the rates, 
terms and conditions of the GPU Energy open access transmission tariff 
filed on July 9, 1996 in Docket No. OA96-114-000.
    GPU Energy requests a waiver of the Commission's notice 
requirements for good cause shown and an effective date of January 23, 
1997 for the Service Agreement. GPU Energy has served copies of the 
filing on regulatory agencies in New Jersey and Pennsylvania and 
Southern.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

19. Jersey Central Power & Light Company, Metropolitan Edison Company, 
Pennsylvania Electric Company

[Docket No. ER97-1831-000]

    Take notice that on February 21, 1997, Jersey Central Power & Light 
Company, Metropolitan Edison Company and Pennsylvania Electric Company, 
each doing business as and collectively referred to herein as ``GPU 
Energy'', filed a Service Agreement between GPU Energy and Virginia 
Electric and Power Company, (``VEPCO'') dated January 23, 1997. This 
Service Agreement specifies that VEPCO has agreed to the rates, terms 
and conditions of the GPU Energy open access transmission tariff filed 
on July 9, 1996 in Docket No. OA96-114-000.
    GPU Energy requests a waiver of the Commission's notice 
requirements for good cause shown and an effective date of January 23, 
1997 for the Service Agreement. GPU Energy has served copies of the 
filing on regulatory agencies in New Jersey and Pennsylvania and VEPCO.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

20. Jersey Central Power & Light Company, Metropolitan Edison Company, 
Pennsylvania Electric Company

[Docket No. ER97-1832-000]

    Take notice that on February 21, 1997, Jersey Central Power & Light 
Company, Metropolitan Edison Company and Pennsylvania Electric Company, 
each doing business as and collectively referred to herein as ``GPU 
Energy'', filed a Service Agreement between GPU Energy and Plum Street 
Energy Marketing, Inc., (Plum Street) dated January 23, 1997. This 
Service Agreement specifies that Plum Street has agreed to the rates, 
terms and conditions of the GPU Energy open access transmission tariff 
filed on July 9, 1996 in Docket No. OA96-114-000.
    GPU Energy requests a waiver of the Commission's notice 
requirements for good cause shown and an effective date of January 23, 
1997, for the Service Agreement. GPU Energy has served copies of the 
filing on regulatory agencies in New Jersey and Pennsylvania and Plum 
Street.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

21. Jersey Central Power & Light Company, Metropolitan Edison Company, 
Pennsylvania Electric Company

[Docket No. ER97-1833-000]

    Take notice that on February 21, 1997, Jersey Central Power & Light 
Company, Metropolitan Edison Company and Pennsylvania Electric Company, 
each doing business as and collectively referred to herein as ``GPU 
Energy'', filed a Service Agreement between GPU Energy and Niagara 
Mohawk Power Company, (NiMo) dated January 23, 1997. This Service 
Agreement specifies that NiMo has agreed to the rates, terms and 
conditions of the GPU Energy open access transmission tariff filed on 
July 9, 1996 in Docket No. OA96-114-000.
    GPU Energy requests a waiver of the Commission's notice 
requirements for good cause shown and an effective date of January 23, 
1997, for the Service Agreement. GPU Energy has served copies of the 
filing on regulatory agencies in New Jersey and Pennsylvania and NiMo.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

22. Wisconsin Electric Power Company

[Docket No. ER97-1834-000]

    Take notice that on February 24, 1997, Wisconsin Electric Power 
Company (Wisconsin Electric), tendered for filing a firm transmission 
service agreement with WPS Energy Services Inc. (WPS Energy) for 10 MW 
for a two week period commencing February 9, 1997. The power is 
received from Wisconsin Electric's interface with Commonwealth Edison 
Company (ComEd) and is delivered to Upper Peninsula Power Company 
(UPPCO).
    Wisconsin Electric respectfully requests an effective date of 
February 9, 1997 in order to effectuate the transaction. Wisconsin 
Electric is authorized to state that WPS Energy Services joins in the 
requested effective date.
    Copies of the filing have been served on WPS Energy, UPPCO, ComEd, 
the Michigan Public Service Commission, and the Public Service 
Commission of Wisconsin.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

23. Pacific Gas and Electric Company

[Docket No. ER97-1835-000]

    Take notice that on February 21, 1997, Pacific Gas and Electric 
Company (PG&E), tendered for filing; (1) the fourth Service Agreement 
under its Open Access Transmission Tariff (PG&E's OAT Tariff) dated 
January 28, 1997; and (2) a request for termination of the second and 
third Service Agreements between PG&E and the San Francisco Bay Area 
Rapid Transit District (BART), dated November 8, 1996 and November 27, 
1996 respectively, and the January 28--Service Agreement referred to 
above.
    The Service Agreements were entered into by and between PG&E and 
BART and entitled ``Service Agreements for Firm Point-to-Point 
Transmission Service.'' The three Service Agreements were entered into 
for the purpose of firm point-to-point transmission service for the 
same 5 MW of power delivered to BART at PG&E's Bayshore Substation. The 
effective dates of termination are either the requested dates shown 
below or such other date(s) the Commission deems appropriate for 
termination.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

24. The Detroit Edison Company

[Docket No. OA96-78-002]

    Take notice that on February 28, 1997, The Detroit Edison Company 
(``Detroit Edison'') tendered for filing revised pages of Detroit 
Edison's Open Access Transmission Tariff. The revisions were filed in 
accordance with the Commission's order in American Electric Power 
Service Corp., et al., 78 FERC para. 61,070 (1997).

[[Page 11863]]

    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

25. Niagara Mohawk Power Corporation

[Docket No. OA96-194-001]

    Take notice that on February 27, 1997, Niagara Mohawk Power 
Corporation (Niagara Mohawk) tendered for filing its compliance report 
pursuant to the Commission's order issued January 29, 1997. Copies of 
the filing have been served by Niagara Mohawk upon the other parties to 
the above-captioned proceeding.
    Comment date: March 21, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

26. Ohio Edison Company, Pennsylvania Power Company

[Docket No. OA97-556-000]

    Take notice that on February 28, 1997, Ohio Edison Company, on 
behalf of itself and Pennsylvania Power Company, tendered for filing an 
amendment to the rate schedules for power sales offered under an its 
Interchange Agreement with the Allegheny Power System. This amendment 
was made in compliance with Order No. 888 to unbundle the charges for 
generation and transmission services for transactions after March 1, 
1997. Copies of the filing have been provided to the Public Utilities 
Commission of Ohio, the Pennsylvania Public Utility Commission, the 
Maryland Public Service Commission, the Virginia State Corporation 
Commission, and the West Virginia Public Service Commission.
    Comment date: March 20, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

27. Ohio Edison Company

[Docket No. OA97-557-000]

    Take notice that on February 28, 1997, Ohio Edison Company tendered 
for filing an amendment to the provisions for bulk power sales offered 
under its Interconnection Agreement with Dayton Power & Light Company. 
This amendment is made in compliance with Order No. 888 to unbundle the 
charges for generation and transmission services for transactions after 
March 1, 1997. Copies of the filing have been provided to the Public 
Utilities Commissions of Ohio and Pennsylvania.
    Comment date: March 20, 1997, in accordance with Standard Paragraph 
E at the end of this notice.

Standard Paragraph

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
motions or protests should be filed on or before the comment date. 
Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of this filing are on file with the 
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 97-6364 Filed 3-12-97; 8:45 am]