DEPARTMENT OF ENERGY
[Docket No. ER97-1615-000]


Portland General Electric Company; Notice of Filing

February 25, 1997.
    Take notice that on February 7, 1997, Portland General Electric 
Company (PGE), tendered for filing under PGE's Final Rule pro forma 
tariff (FERC Electric Tariff Original Volume No. 8, Docket No. OA96-
137-000), an executed Service Agreement for Non-firm Point-to-Point 
Transmission Service with Puget Sound Power & Light Company.
    Pursuant to 18 CFR 35.11, and the Commission's Order in Docket No. 
PL93-2-002 issued July 30, 1993, PGE respectfully requests that the 
Commission grant a waiver of the notice requirements of 18 CFR 35.3 to 
allow the Service Agreement to become effective January 24, 1997.
    A copy of this filing was caused to be served upon Puget Sound 
Power & Light Company as noted in the filing letter.
    Any person desiring to be heard or to protest said application, 
should file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
motions or protests should be filed on or before March 10, 1997. 
Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of this filing are on file with the 
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.