DEPARTMENT OF ENERGY
[Docket No. RP97-239-000]


Northwest Pipeline Corporation; Notice of Proposed Changes in 
FERC Gas Tariff

January 31, 1997.
    Take notice that on January 29, 1997, Northwest Pipeline 
Corporation (Northwest) tendered for filing as part of its FERC Gas 
Tariff, Third Revised Volume No. 1, the following tariff sheets, to 
become effective March 1, 1997:

3rd Rev Third Revised Sheet No. 200
Second Revised Sheet No. 253
First Revised Sheet No. 254

[[Page 5624]]

Alternate First Revised Sheet No. 254
Second Revised Sheet No. 255
Alternate Second Revised Sheet No. 255
Second Revised Sheet No. 256
First Revised Sheet No. 311
Alternate First Revised Sheet No. 311
First Revised Sheet No. 322
Alternate First Revised Sheet No. 322
First Revised Sheet No. 357
Alternate First Revised Sheet No. 357

    Northwest states that the filing is submitted to revise the 
Facilities Reimbursement provision in Section 21 of the General Terms 
and Conditions of Northwest's Tariff. The preferred tariff sheets 
propose (1) to require customer reimbursement for requested receipt or 
delivery facilities, (2) to provide customers with greater flexibility 
in selecting methods of payment for such facilities and (3) to make 
other related changes as described in more detail in the filing. The 
alternate tariff sheets propose (1) to require customer reimbursement 
for requested receipt or delivery facilities in a lump sum and (2) to 
make other related changes as described in more detail in the filing.
    Northwest states that a copy of this filing has been served upon 
Northwest's customers and interested state regulatory commissions.
    Any person desiring to be heard or protest this filing should file 
a motion to intervene or protest with the Federal Energy Regulatory 
Commission, 888 First Street, N.E., Washington, DC 20426, in accordance 
with Sections 385.214 and 385.211 of the Commission's Rules and 
Regulations. All such motions or protests must be filed as provided in 
Section 154.210 of the Commission's Regulations. Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a motion to 
intervene. Copies of this filing are on file with the Commission and 
are available for public inspection in the Public Reference Room.
Lois D. Cashell,
Secretary.
[FR Doc. 97-2915 Filed 2-5-97; 8:45 am]
BILLING CODE 6717-01-M