[Federal Register Volume 61, Number 206 (Wednesday, October 23, 1996)]
[Notices]
[Pages 54991-54992]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 96-27100]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY
[Docket No. CP97-17-000]


ANR Pipeline Company; Notice of Request Under Blanket 
Authorization

October 17, 1996.
    Take notice that on October 8, 1996, ANR Pipeline Company (ANR), 
500 Renaissance Center, Detroit, Michigan 48243, filed in Docket No. 
CP97-17-000 a request pursuant to Sections 157.205 and 157.212 of the 
Commission's Regulations under the Natural Gas Act (18 CFR 157.205 and 
157.212) for authorization to construct and operate an interconnection 
between ANR and Wisconsin Fuel & Light Company (WF&L), in Marathon 
County, Wisconsin, to accommodate WF&L's continuing growth load. ANR 
makes such request under its blanket certificate issued in Docket No. 
CP82-480-000 pursuant to Section 7 of the Natural Gas Act, all as more 
fully set forth in the request on file with the Commission and open to 
public inspection.
    ANR is proposing to modify its existing Callon tap which is located 
on ANR's Wittenberg Lateral in Marathon County. ANR mentions that the 
Callon tap was originally installed as part of the Wittenberg Lateral 
in 1969, but that ANR never delivered gas at that tap. ANR states that 
WF&L submitted a request to ANR, in which WF&L requested to tie into 
the Callon tap in order to accommodate continuing load growth in WF&L's 
Wausau distribution area. It is indicated that the Callon tap currently 
consists of a 4-inch underground valve with a high head extension and a 
blind flange. ANR states that it is proposing to modify the Callon tap 
so that it would be above ground, making maintenance and repairs more 
convenient. ANR further states that it proposes to add a flange and an

[[Page 54992]]

insulated flange, a reducer, two piping elbows, and approximately eight 
feet of 2-inch piping at this interconnection, as part of the 
modification.
    ANR avers that approximately 240 Mcf of natural gas during a peak 
day, will be delivered to this interconnection, and that the delivery 
quantity will be within WF&L's certificated entitlements. It is 
estimated that the proposed modification will cost approximately 
$3,000.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Section 157.205 of 
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
the request. If no protest is filed within the time allowed therefor, 
the proposed activity shall be deemed to be authorized effective the 
day after the time allowed for filing a protest. If a protest is filed 
and not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 96-27100 Filed 10-22-96; 8:45 am]
BILLING CODE 6717-01-M