[Federal Register Volume 61, Number 166 (Monday, August 26, 1996)]
[Notices]
[Pages 43754-43756]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 96-21611]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY
[Docket No. ER96-2664-000, et al.]


Entergy Services, Inc., et al.; Electric Rate and Corporate 
Regulation Filings

August 19, 1996.
    Take notice that the following filings have been made with the 
Commission:

1. Entergy Services, Inc.

[Docket No. ER96-2664-000]

    Take notice that on August 8, 1996, Entergy Services, Inc. (Entergy 
Services), submitted for filing the Interchange Agreement between 
Entergy Arkansas, Inc.; Entergy Gulf States, Inc.; Entergy Louisiana, 
Inc.; Entergy Mississippi, Inc.; Entergy New Orleans, Inc.; and Entergy 
Services, Inc., and the Sam Rayburn Municipal Power Agency (SRMPA). To 
the extent necessary, Entergy Services requests a waiver of notice 
requirements of the Federal Power Act and the Commission's Regulations.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

2. Northeast Utilities Service Company

[Docket No. ER96-2666-000]

    Take notice that on August 8, 1996, Northeast Utilities Service 
Company (NUSCO), tendered for filing an unexecuted Service Agreement to 
provide Network Integration Transmission Service to Unitil Power 
Corporation (UNITIL) under the terms and conditions of the NU System 
Companies' Open Access Transmission Service Tariff No. 8.
    NUSCO states that a copy of this filing has been mailed to UNITIL.
    NUSCO requests that the Service Agreement become effective July 9, 
1996.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

3. Florida Power & Light Company

[Docket No. ER96-2667-000]

    Take notice that on August 9, 1996, Florida Power & Light Company 
(FPL), tendered for filing (i) Amendment Number Eleven to the Agreement 
to Provide Specified Transmission Service between Florida Power & Light 
Company and City of Starke, Florida; (ii) Short-Term Firm Umbrella 
Service Agreement between Florida Power & Light Company and City of 
Starke, Florida; and (iii) Non-Firm Umbrella Service Agreement between 
Florida Power & Light Company and City of Starke, Florida. FPL asks 
that the filing be made effective July 9, 1996.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

4. Pennsylvania-New Jersey-Maryland Interconnection Restructuring

[Docket No. ER96-2668-000]

    Take notice that on August 8, 1996, PECO Energy Company (PECO) 
filed the following documents as part of PECO's restructuring plan for 
the Pennsylvania-New Jersey-Maryland (PJM) Interconnection (the Open 
Market Plan):
    1. PJM Regional Open Access Transmission Tariff, including a black-
lined comparison to the Commission's pro forma tariff
    2. PJM Regional Transmission Owners' Agreement
    3. PJM Wholesale Power Exchange Agreement
    4. PJM Regional Reserve Planning Agreement
    5. Independent System Operator Agreement
    6. Exchange Service Agreement
    7. Independent System Planner Agreement
    As part of the Open Market Plan, PECO filed revisions to certain 
other existing agreements concerning the PJM Interconnection. PECO also 
filed with the Commission an application pursuant to Sec. 202 of the 
Federal Power Act (FPA), 16 U.S.C. 824b, to be separately noticed.
    Copies of the filing were served on the Regulatory Commission of 
Delaware, the District of Columbia, Maryland, New Jersey, Pennsylvania, 
and Virginia.
    PECO states that a copy of the filing may be downloaded from its 
OASIS on the internet at http/oasis peco.com.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

5. Florida Power & Light Company

[Docket No. ER96-2669-000]

    Take notice that on August 9, 1996, Florida Power & Light Company 
(FPL), tendered for filing (i) Amendment Number Twenty-Five to Revised 
Agreement to Provide Specified Transmission Service between Florida 
Power & Light Company and Utilities Commission, City of New Smyrna 
Beach, Florida; (ii) Short-Term Firm Umbrella Service Agreement between 
Florida Power & Light Company and Utilities Commission, City of New 
Smyrna Beach, Florida; and (iii) Non-Firm Umbrella Service Agreement 
between Florida Power & Light Company and Utilities Commission, City of 
New Smyrna Beach, Florida. FPL asks that the filing be made effective 
July 9, 1996.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

6. The Dayton Power and Light Company

[Docket No. ER96-2670-000]

    Take notice that on August 9, 1996, The Dayton Power and Light 
Company (Dayton), tendered for filing an executed Master Electric 
Interchange Agreement between Dayton and PanEnergy Power Services, Inc. 
(PanEnergy).
    Pursuant to the rate schedules attached as Exhibit B to the 
Agreement, Dayton will provide to PanEnergy power and/or energy for 
resale.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

7. Puget Sound Power & Light Company

[Docket No. ER96-2671-000]

    Take notice that on August 9, 1996, Puget Sound Power & Light 
Company (Puget), tendered for filing the 1996-97 Operating Procedures 
under the Pacific Northwest Coordination Agreement (PNCA).
    Puget states that the 1996-97 Operating Procedures relate to 
service under the PNCA. A copy of the filing was served upon the 
parties to the PNCA.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

8. Wisconsin Power and Light Company

[Docket No. ER96-2672-000]

    Take notice that on August 9, 1996, Wisconsin Power and Light 
Company (WP&L), tendered for filing Agreements dated July 11, 1996, 
establishing Dairyland Power Cooperative as a point-to-point 
transmission customer under the terms of WP&L's Transmission Tariff.
    WP&L requests an effective date of July 11, 1996 and accordingly 
seeks waiver of the Commission's notice

[[Page 43755]]

requirements. A copy of this filing has been served upon the Public 
Service Commission of Wisconsin.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

9. AYP Energy Inc.

[Docket No. ER96-2673-000]

    Take notice that on August 9, 1996, AYP Energy Inc. (Applicant), 
filed with the Federal Energy Regulatory Commission a petition for 
authority to sell power at market-based rates, and request for blanket 
authorization and for certain waivers of the Commission's Regulations. 
Applicant has also filed its FERC Electric Rate Schedule No. 1.
    Applicant has requested that its rate schedule be accepted for 
filing and allowed to become effective immediately upon acceptance. 
Applicant intends to engage in transactions in which it will sell 
electric power at rates and on terms and conditions that are negotiated 
with the purchaser.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

10. The Dayton Power and Light Company

[Docket No. ER96-2674-000]

    Take notice that on August 9, 1996, The Dayton Power and Light 
Company (Dayton), tendered for filing an executed Master Electric 
Interchange Agreement between Dayton and Sonat Power Marketing, Inc. 
(Sonat).
    Pursuant to the rate schedules attached as Exhibit B to the 
Agreement, Dayton will provide to Sonat power and/or energy for resale.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

11. The Dayton Power and Light Company

[Docket No. ER96-2675-000]

    Take notice that on August 9, 1996, The Dayton Power and Light 
Company (Dayton), tendered for filing an executed Master Electric 
Interchange Agreement between Dayton and Citizens Lehman Power Sales 
(CLPS).
    Pursuant to the rate schedules attached as Exhibit B to the 
Agreement, Dayton will provide to CLPS power and/or energy for resale.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

12. Illinois Power Company

[Docket No. ER96-2676-000]

    Take notice that on August 9, 1996, Illinois Power Company 
(Illinois Power), 500 South 27th Street, Decatur, Illinois 62526, 
tendered for filing a Power Sales Tariff, Service Agreement under which 
Sonat Power Marketing, Inc. will take service under Illinois Power 
Company's Power Sales Tariff. The agreements are based on the Form of 
Service Agreement in Illinois Power's tariff.
    Illinois Power has requested an effective date of August 1, 1996.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

13. Central Louisiana Electric Company, Inc.

[Docket No. ER96-2677-000]

    Take notice that on August 9, 1996, Central Louisiana Electric 
Company, Inc. (CLECO), tendered for filing an initial MR-1 Tariff for 
Power Sales at Negotiated Rates.
    CLECO has served a copy of the filing on the Louisiana Public 
Service Commission and a copy of the filing is available for public 
inspection at CLECO's offices during normal business hours.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

14. Commonwealth Edison Company

[Docket No. ER96-2678-000]

    Take notice that on August 9, 1996, Commonwealth Edison Company 
(ComEd), submitted for filing four Service Agreements, establishing 
Calpine Power Services Company (Calpine), dated June 26, 1996, 
Pacificorp Power Marketing (Pacificorp), dated July 9, 1996, Entergy 
Power Inc. (EPI), dated July 15, 1996, and Entergy Power Marketing 
Corp. (EPMC), dated July 15, 1996, as customers under the terms of 
ComEd's Power Sales Tariff PS-1 (PS-1 Tariff). The Commission has 
previously designated the PS-1 Tariff as FERC Electric Tariff, Original 
Volume No. 2.
    ComEd requests an effective date of July 15, 1996 for the Service 
Agreements between ComEd and Calpine, Pacificorp and EPI, and an 
effective date of July 22, 1996 for the Service Agreement between ComEd 
and EPMC, and accordingly seeks waiver of the Commission's 
requirements. Copies of this filing were served upon Calpine, 
Pacificorp, EPI, EPMC and the Illinois Commerce Commission.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

15. Arizona Public Service Company

[Docket No. ER96-2679-000]

    Take notice that on August 12, 1996, Arizona Public Service Company 
(APS), tendered for filing a Service Agreement under APS-FERC Electric 
Tariff Original Volume No. 1 (APS Tariff) with the following entity: 
Koch Power Services, Inc.
    A copy of this filing has been served on the above listed party and 
the Arizona Corporation Commission.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

16. Virginia Electric and Power Company

[Docket No. ER96-2680-000]

    Take notice that on August 12, 1996, Virginia Electric and Power 
Company (the Company), tendered for filing a letter agreement 
implementing the rate schedules included in the Agreement for the 
Purchase of electricity for Resale between the Company and the Virginia 
Municipal Electric Association Number 1 (VMEA).
    Copies of the filing were served upon VMEA, the Virginia State 
Corporation Commission and the North Carolina Utilities Commission.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

17. Jersey Central Power & Light Co., Metropolitan Edison Company, 
Pennsylvania Electric Company.

[Docket No. ER96-2682-000]

    Take notice that on August 12, 1996, GPU Service Corporation (GPU), 
on behalf of Jersey Central Power & Light Company, Metropolitan Edison 
Company and Pennsylvania Electric Company (jointly referred to as the 
GPU Companies), filed a Service Agreement between GPU and Vastar Power 
Marketing, Inc. (VPM) dated July 25, 1996. This Service Agreement 
specifies that VPM has agreed to the rates, terms and conditions of the 
GPU Companies' Energy Transmission Service Tariff accepted by the 
Commission on September 28, 1995, in Docket No. ER5-791-000 and 
designated as FERC Electric Tariff, Original Volume No. 3.
    GPU requests a waiver of the Commission's notice requirements for 
good cause shown and an effective date July 25, 1996, for the Service 
Agreement. GPU has served copies of the filing on regulatory agencies 
in New Jersey and Pennsylvania and on VPM.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

[[Page 43756]]

18. Jersey Central Power & Light Co., Metropolitan Edison Company, 
Pennsylvania Electric Company.

[Docket No. ER96-2683-000]

    Take notice that on August 12, 1996, GPU Service Corporation (GPU), 
on behalf of Jersey Central Power & Light Company, Metropolitan Edison 
Company and Pennsylvania Electric Company (jointly referred to as the 
GPU Companies), filed a Service Agreement between GPU and Entergy Power 
Marketing Corporation (ENTERGY) dated July 25, 1996. This Service 
Agreement specifies that ENTERGY has agreed to the rates, terms and 
conditions of the GPU Companies' Energy Transmission Service Tariff 
accepted by the Commission on September 28, 1995, in Docket No. ER95-
791-000 and designated as FERC Electric Tariff, Original Volume No. 3.
    GPU requests a waiver of the Commission's notice requirements for 
good cause shown and an effective date July 25, 1996, for the Service 
Agreement. GPU has served copies of the filing on regulatory agencies 
in New Jersey and Pennsylvania and on ENTERGY.
    Comment date: September 3, 1996, in accordance with Standard 
Paragraph E at the end of this notice.

Standard Paragraph

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
motions or protests should be filed on or before the comment date. 
Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of this filing are on file with the 
Commission and are available for public inspection.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 96-21611 Filed 8-23-96; 8:45 am]