DEPARTMENT OF ENERGY

Notice of Proposed Power Rate--Robert D. Willis

AGENCY: Southwestern Power Administration (Southwestern), DOE.

ACTION: Notice for public review and comment.

-----------------------------------------------------------------------

SUMMARY: The Administrator, Southwestern, has prepared Current and 
Revised 1996 Power Repayment Studies for the Robert D. Willis (Willis) 
project which show the need for a decrease in annual revenues required 
to meet cost recovery criteria. The decrease in the revenues required 
will result from a change in the allocation of costs due to the remote 
operation of the Whitney Project from the Sam Rayburn (Rayburn) Project 
beginning in FY 1997. The existing power plant operators' costs will be 
allocated among three projects rather than just Willis and Rayburn. The 
Administrator has also developed a proposed rate schedule for the 
isolated Willis project to recover the required revenues. The proposed 
rate for the Willis project would decrease annual revenues 
approximately 9.3 percent from $294,312 to $266,928 beginning October 
1, 1996.

DATES: A Public Information Forum has been scheduled for July 16, 1996, 
in Tulsa Oklahoma. A Public Comment Forum will be held July 30, 1996, 
in Tulsa, Oklahoma. Written comments are due on or before (insert 30 
days from the date of Federal Register publication). Southwestern is 
conducting a 30 day public notice and comment period (10 CFR 
903.14(d)). This public participation period is for a minor rate 
adjustment which does not require any comment period to exceed 30 days. 
In addition, this project has a single hydroelectric power customer and 
that customer directly impacted has been informed of the proposed rate 
decrease. It is anticipated that any comments from the customer will be 
developed well within the 30 day period.

ADDRESSES: Written comments should be submitted to the Administrator, 
Southwestern Power Administration, U.S. Department of Energy, P.O. Box 
1619, Tulsa, Oklahoma 74101.

FOR FURTHER INFORMATION CONTACT: Mr. George C. Grisaffe, Assistant 
Administrator, Office of Administration and Rates, Southwestern Power 
Administration, U.S. Department of Energy, P.O. Box 1619, Tulsa, 
Oklahoma 74101, (918) 595-6628.

SUPPLEMENTARY INFORMATION: The U.S. Department of Energy was created by 
an Act of the U.S. Congress, Department of Energy Organization Act, P. 
L. 95-91, dated August 4, 1977, and Southwestern's power marketing 
activities were transferred from the Department of the Interior to the 
Department of Energy, effective October 1, 1977.
    Southwestern markets power from 24 multiple-purpose reservoir 
projects with power facilities constructed and operated by the U.S. 
Army Corps of Engineers. These projects are located in the States of 
Arkansas, Missouri, Oklahoma and Texas. Southwestern's marketing area 
includes these states plus Kansas and Louisiana. Of the total, 22 
projects comprise an Integrated System and are interconnected through 
Southwestern's transmission system and exchange agreements with other 
utilities. The Sam Rayburn Dam project, located in eastern Texas, is 
not interconnected with Southwestern's Integrated System hydraulically, 
electrically, or financially. Instead, the power produced by the Sam 
Rayburn Dam project is marketed by Southwestern as an isolated project 
under a contract through which the customer purchases the entire power 
output of the project at the dam. The Willis project, located on the 
Neches River downstream from the Sam Rayburn Dam, consists of two 4,000 
kilowatt hydroelectric generating units. It, like the Sam Rayburn Dam 
project, is

[[Page 35210]]

marketed as an isolated project under a contract through which the 
customer, Sam Rayburn Municipal Power Agency (SRMPA), receives the 
entire output of the project for a period of 50 years as a result of 
funding the construction of the hydroelectric facilities at the 
project. A separate power repayment study is prepared for each project 
which has a special rate based on its isolated project determination.
    Following Department of Energy Order Number RA 6120.2, the 
Administrator, Southwestern, prepared a current power repayment study 
for the Robert D. Willis project using the existing annual rate of 
$294,312. The study indicated that maintaining the current rate will 
create a revenue surplus for the project. This is primarily a result of 
adding the remote operation of the Whitney Project, beginning in FY 
1997, by the Corps of Engineers from the Sam Rayburn Project. The 
Revised Power Repayment Study for the isolated Willis project shows 
that a decrease of $27,384 (a 9.3 percent decrease) annually will 
satisfy repayment criteria. This decrease would change annual revenues 
produced by the Willis Project from $294,312 to $266,928 and satisfy 
the present financial criteria for repayment of the project.
    Opportunity is presented for customers and interested parties to 
receive copies of the studies and proposed rate schedule for the Willis 
project. If you desire a copy of the Repayment Study Data Package for 
the Willis project, please do not hesitate to submit your request to: 
Mr. George C. Grisaffe, Assistant Administrator, Office of 
Administration and Rates, P.O. Box 1619, Tulsa, OK 74101, (918) 595-
6628.
    A Public Information Forum is scheduled to be held at 4:30 p.m., 
central time (c.t.) Tuesday, July 16, 1996, in Southwestern's offices, 
room 1600, Williams Center Tower 1, One West Third Street, Tulsa, 
Oklahoma. The Forum is to explain to customers and interested parties 
the proposed rates and supporting studies. The Forum will be conducted 
by a chairman who will be responsible for orderly procedure. Questions 
concerning the rates, studies and information presented at the forum 
may be submitted from interested persons and will be answered, to the 
extent possible, at the forum. Questions not answered at the Forum will 
be answered in writing, except the questions involving voluminous data 
contained in Southwestern's records may best be answered by 
consultation and review of pertinent records at Southwestern's offices. 
Persons interested in attending the Public Information Forum should 
indicate in writing by 4:00 p.m., c.t., Friday, July 12, 1996, their 
intent to appear at such Forum. Accordingly, if no one so indicates 
their intent to attend, no such Forum will be held.
    A Public Comment Forum is scheduled to be held at 1:30 p.m., c.t., 
Tuesday, July 30, 1996, at the same location established for the Public 
Information Forum. At the Public Comment Forum interested persons may 
submit written comments or make oral presentations of their views and 
comments. This forum will also be conducted by a chairman who will be 
responsible for orderly procedure. Southwestern's representatives will 
be present, and they and the chairman may ask questions of speakers. 
The chairman may allow others to speak if time permits. Persons 
interested in attending or speaking at the Public Comment Forum should 
indicate in writing by 4:00 p.m., c.t., Friday, July 26, 1996, their 
intent to appear at such Forum. Accordingly, if no one so indicates 
their intent to attend, no such Forum will be held.
    A transcript of each Forum will be made. Copies of the transcripts 
may be obtained from the transcribing service. Copies of all documents 
introduced will be available from Southwestern upon request, for a fee. 
Written comments on the proposed rates for the project are due on or 
before 30 days from publication. Written comments should be submitted 
to the Administrator, Southwestern Power Administration, U.S. 
Department of Energy, P.O. Box 1619, Tulsa, Oklahoma 74101.
    Following review of the oral and written comments, the 
Administrator will submit the rate proposals and the Power Repayment 
Studies for the Willis project, in support of the proposed rates, to 
the Deputy Secretary of Energy for confirmation and approval on an 
interim basis and to the Federal Energy Regulatory Commission (FERC) 
for confirmation and approval on a final basis. The FERC will allow the 
public an opportunity to provide written comments on the proposed rate 
increases before making a final decision.

    Issued in Tulsa, Oklahoma, this 24th day of June, 1996.
Frances R. Gagan,
Acting Administrator.
[FR Doc. 96-17119 Filed 7-3-96; 8:45 am]