[Federal Register Volume 61, Number 87 (Friday, May 3, 1996)]
[Notices]
[Pages 19926-19927]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 96-11059]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Notice of Application for Major New License
April 29, 1996.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Major New License.
b. Project No.: 1984-056.
c. Date filed: January 25, 1996.
d. Applicant: Wisconsin River Power Company.
e. Name of Project: Petenwell-Castle Rock Project.
f. Location: On the Wisconsin River in Adams, Juneau, and Wood
Counties, Wisconsin.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. Secs. 791(a)-
825(r).
h. Applicant Contact: Mr. Richard L. Hilliker, President, Wisconsin
River Power Company, P.O. Box 8050, Wisconsin Rapids, WI 54495, (715)
422-3722.
i. FERC Contact: Robert Bell (202) 219-2806.
j. Comment Date: July 1, 1996.
k. Status of Environmental Analysis: This application is accepted
for filing but is not ready for environmental analysis at this time--
see attached standard paragraph E1.
l. Description of Project: The constructed project consists of the
following developments:
Petenwell Development
(1) the Petenwell Dam consists of a series of dams and dikes 15,505
feet long and approximately 38 feet high; (2) an impoundment having a
surface area of 25,180 acres, with a storage capacity of 495,000 acre-
feet at normal water surface elevation of 923.9 feet msl; (3) an intake
structure; (4) a powerhouse having 4 generating units having a total
installed capacity of 20-MW; (5) a transmission line; and (6)
appurtenant facilities.
Castle Rock Development
(1) the Castle Rock Dam consist of a series of dams and dikes
19,374 feet long and approximately 30 feet high; (2) an impoundment
having a surface area of 14,900 acres and storage capacity of 136,000
acre-feet at normal water surface elevation of 881.9 feet msl; (3) an
intake structure; (4) a powerhouse having 5 generating units having a
total installed capacity of 15-MW; (5) a transmission line; and (6)
appurtenant facilities.
No additional capacity is being proposed for this project under
this new license.
m. Purpose of Project: Project power would be utilized for sale to
Wisconsin River Power Company's customers.
n. This notice also consists of the following standard paragraphs:
B1 and E1.
o. Available Location of Application: A copy of the application, as
amended and supplemented, is available for inspection and reproduction
at the Commission's Public Reference and Files Maintenance Branch,
located at 888 North Capitol Street, Washington, D.C., 20426, or by
calling (202) 208-1371. A copy is also available for inspection and
reproduction at Mr. Richard L. Hilliker, President, Wisconsin River
Power Company, P.O. Box 8050, Wisconsin Rapids, WI 54495, (715) 422-
3722.
B1. Protests or Motions to Intervene--Anyone may submit a protest
or a
[[Page 19927]]
motion to intervene in accordance with the requirements of Rules of
Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In
determining the appropriate action to take, the Commission will
consider all protests filed, but only those who file a motion to
intervene in accordance with the Commission's Rules may become a party
to the proceeding. Any protests or motions to intervene must be
received on or before the specified deadline date for the particular
application.
E1. Filing and Service of Responsive Documents--The application is
not ready for environmental analysis at this time; therefore, the
Commission is not now requesting comments, recommendations, terms and
conditions, or prescriptions.
When the application is ready for environmental analysis, the
Commission will issue a public notice requesting comments,
recommendations, terms and conditions, or prescriptions.
All filings must (1) bear in all capital letters the title
``PROTEST'' or ``MOTION TO INTERVENE;'' (2) set forth in the heading
the name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005.
Agencies may obtain copies of the application directly from the
applicant. Any of these documents must be filed by providing the
original and the number of copies required by the Commission's
regulations to: The Secretary, Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC 20426. An additional copy must be
sent to Director, Division of Project Review, Office of Hydropower
Licensing, Federal Energy Regulatory Commission, at the above address.
A copy of any protest or motion to intervene must be served upon each
representative of the applicant specified in the particular
application.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 96-11059 Filed 5-2-96; 8:45 am]
BILLING CODE 6717-01-M