DEPARTMENT OF EDUCATION
DEPARTMENT OF ENERGY
[Docket No. ER94-1246-007, et al.]
Ashton Energy Corporation, et al.; Electric Rate and Corporate
Regulation Filings
April 10, 1996.
Take notice that the following filings have been made with the
Commission:
1. Ashton Energy Corporation, Texpar Energy, Inc., Industrial Gas &
Electric, Service Company Mock Resources, Inc.
[Docket No. ER94-1246-007 Docket No. ER95-62-004 Docket No. ER95-257-
005 Docket No. ER95-300-006 (not consolidated)]
Take notice the following informational filings have been made with
the Commission and are on file and available for inspection and copying
in the Commission's Public Reference Room:
On April 8, 1996, Ashton Energy Corporation filed certain
information as required by the Commission's August 10, 1994 order in
Docket No. ER94-1246-000.
On March 18, 1996, Texpar Energy, Inc. filed certain information as
required by the Commission's December 27, 1994 order in Docket No.
ER95-62-000.
On April 1, 1996, Industrial Gas & Electric Service Company filed
certain information as required by the Commission's February 1, 1995
order in Docket No. ER95-257-000.
On April 8, 1996, Mock Resources, Inc. filed certain information as
required by the Commission's March 16, 1995 order in Docket No. ER95-
300-000.
2. Illinois Power Company
[Docket No. ER96-1074-000]
Take notice that on April 2, 1996, Illinois Power Company tendered
for filing an amendment in the above-referenced docket.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
3. Ohio Edison Company
[Docket No. ER96-1234-000]
Take notice that on March 28, 1996, Ohio Edison Company tendered
for filing an amendment in the above-referenced docket.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
4. Northeast Utilities Service Company
[Docket No. ER96-1385-000]
Take notice that Northeast Utilities Service Company (NUSCO) on
March 25, 1996, tendered for filing, a Service Agreement with Koch
Power Services, Inc. (Koch) under the NU System Companies' System Power
Sales/Exchange Tariff No. 6.
Koch also filed a Certificate of Concurrence as it relates to
exchange transactions under the Tariff.
NUSCO states that a copy of this filing has been mailed to Koch.
NUSCO requests that the Service Agreement become effective sixty
(60) days following the Commission's receipt of the filing.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
5. Union Electric Company
[Docket No. ER96-1386-000]
Take notice that on March 25, 1996, Union Electric Company tendered
for filing, a Transmission Service Agreement dated March 26, 1996
between Tennessee Power Company (TPC) and UE. UE asserts that the
purpose of the Agreement is to set out specific rates, terms, and
conditions for transmission service transactions from UE to TPC.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
6. Northeast Utilities Service Company
[Docket No. ER96-1388-000]
Take notice that Northeast Utilities Service Company (NUSCO) on
March 25, 1996, tendered for filing, a Service Agreement and a
Certificate of Concurrence with Commonwealth Electric Company (Com
Electric) and under the NU System Companies' System Power Sales/
Exchange Tariff No. 6.
NUSCO states that a copy of this filing has been mailed to Com
Electric.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
7. Cook Inlet Energy Supply, L.P.
[Docket No. ER96-1410-000]
Take notice that on March 27, 1996, Cook Inlet Energy Supply, L.P.
tendered for filing an application requesting approval of rate
schedule, clarification of jurisdiction, and petition for waivers, and
blanket approvals.
Comment date: April 25, 1996, in accordance with Standard Paragraph
E at the end of this notice.
8. Exeter & Hampton Electric Company
[Docket No. ER96-1430-000]
Take notice that on March 28, 1996, Exeter & Hampton Electric
Company (E&H) tendered for filing transmission rates contained in its
Schedule PP, New Hampshire Retail Competition Pilot Program Service,
Exeter & Hampton Electric Company, FERC Electric Tariff, Original
Volume ______ (Schedule PP). E&H states that the transmission rates in
Schedule PP are proposed to become effective May 28, 1996.
Comment date: April 23, 1996, in accordance with Standard Paragraph
E at the end of this notice.
[[Page 16769]]
9. Portland General Electric Company
[Docket No. ER96-1434-000]
Take notice that on March 27, 1996, Portland General Electric
Company tendered for filing a letter requesting the Commission issue a
supplement to FERC Electric Tariff 1st Revised Volume No. 2 (Rate
schedule FERC No. 4) to reflect the name change from National Electric
Associates L.P. to National Gas & Electric L.P.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
10. KC United Corp.
[Docket No. ER96-1446-000]
Take notice that on April 5, 1996, KC United Corp. tendered for
filing an amendment in the above-referenced docket.
Comment date: April 25, 1996, in accordance with Standard Paragraph
E at the end of this notice.
11. Allegheny Power Service Corporation on Behalf of Monongahela Power
Company, The Potomac Edison Company, and West Penn Power Company
(Allegheny Power)
[Docket No. ER96-1460-000]
Take notice that on March 29, 1996, Allegheny Power Service
Corporation on behalf of Monongahela Power Company, The Potomac Edison
Company and West Penn Power Company (Allegheny Power), filed a Service
Agreement to add CINergy Services, Inc. as a Customer under Allegheny
Power's Point-to-Point Transmission Service Tariff which has been
accepted for filing by the Federal Energy Regulatory Commission.
Allegheny Power proposes to make service available to CINergy Services,
Inc. as of March 1, 1996.
Copies of the filing have been provided to the Public Utilities
Commission of Ohio, the Pennsylvania Public Utility Commission, the
Maryland Public Service Commission, the Virginia State Corporation
Commission, the West Virginia Public Service Commission.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
12. Cambridge Electric Light Company
[Docket No. ER96-1461-000]
Take notice that on March 29, 1996, Cambridge Electric Light
Company (Cambridge), submitted for filing proposed FERC Electric
Tariffs for Point-to-Point Transmission Service (Point-to-Point Tariff)
and for Network Integration Service (Network Tariff, Collectively
Tariffs). The proposed Tariffs are modeled after the Commission's pro
forma Tariffs accompanying its notice of proposed rulemaking on open-
access transmission in Docket No. RM95-8-000. The Point-to-Point
Tariff, upon its effectiveness, will supersede the existing FERC
Electric Tariff for Firm Transmission Service, First Revised Volume 3
and the FERC Electric Tariff for Non-Firm Transmission Service, First
Revised Volume 4. Cambridge requests that the Commission accept these
proposed Tariffs and permit them to take effect without suspension,
condition or modification, as of May 28, 1996. In addition, Cambridge
requests waiver by the Commission of any requirements of the
Commission's rules and regulations, as well as any authorizations, as
may be necessary or required to permit these Tariffs to be accepted by
the Commission and made effective in the manner proposed herein.
As required by the Commission, once the final rule for the Open
Access NOPR is issued, Cambridge will modify these tariffs, as
necessary, to ensure that they are consistent with the substantive
requirements in the final rule.
Copies of the filing were served upon the Town of Belmont, the
Massachusetts Bay Transportation Authority and the Massachusetts
Department of Public Utilities.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
13. Public Service Company of New Mexico
[Docket No. ER96-1462-000]
Take notice that on April 1, 1996, Public Service Company of New
Mexico (PNM), tendered for filing pursuant to Sec. 205 of the Federal
Power Act, 15 U.S.C. 824d, and Sec. 35.13 of the regulations of the
Federal Energy Regulatory Commission (Commission), (18 CFR 35.13),
changes in rates for certain transmission services. PNM states that it
proposes amendments between PNM and the following parties: Western Area
Power Administration (Western), Plains Electric Generation and
Transmission Cooperative, Inc. (Plains), Incorporated County of Los
Alamos, New Mexico (IAC); Navajo Tribal Utility Authority (NTUA);
Southwestern Public Service Company (SPS); El Paso Electric Company
(EPE); City of Gallup, New Mexico (COG); and Kirtland Air Force Base
(KAFB).
PNM's filing includes the following amendments to rate schedules
for transmission services:
(1) Amendment Number Two to Contract No. 8-07-40-70695, Contract
between PNM and United States Department of Energy Western Area Power
Administration Salt Lake City Area Integrated Projects. (FERC Rate
Schedule No. 86.)
(2) Amendment Number One to Service Schedule F to the
Interconnection Agreement Between PNM and the Incorporated County of
Los Alamos, New Mexico. (FERC Rate Schedule No. 60.)
(3) Amendment Number Three to the Agreement for Wheeling Service
between PNM and the Navajo Tribal Utility Authority. (FERC Rate
Schedule No. 27.)
(4) Amendment Number Two to Agreement to Wheel Power between PNM
and Plains Electric Generation and Transmission Cooperative, Inc. (FERC
Rate Schedule No. 25.)
(5) Amendment Number Two to Service Schedule 1 to the
Interconnection Agreement between PNM and El Paso Electric Company.
(FERC Rate Schedule No. 9.) Amendment Number One to the PNM/EPE
Operating Procedure No. 9.
(6) Amendment Number One to Special Delivery Agreement for
Federally Allocated Salt Lake City Integrated Projects Power and Energy
between PNM and Southwestern Public Service Company. (FERC Rate
Schedule No. 83.)
PNM's filing also includes amendments to the following rate
schedules for firm network transmission service to Plains, to reflect
that Plains will be charged its load ratio share for service under such
agreements:
(1) Service Schedule G to the Master Interconnection Agreement
between PNM and Plains.
(2) Letter Agreement Implementing Certain Temporary Arrangements
between PNM and Plains Relating to Plains' Demands in Excess of 328 MW.
PNM's filing also includes the following amendments to rate
schedules for firm point-to-point transmission and ancillary services,
to charge customers under these rate schedules separate rates for such
services:
(1) Amendment Number One to Contract No. DE-AC04-89AL57511 between
PNM and the Department of Energy, on behalf of Kirtland Air Force Base.
(2) Amendment Number Two to the Contract for Electric Service
between PNM and the City of Gallup, New Mexico.
PNM requests an effective date of June 1, 1996, for the foregoing
amendments, with the exception of the amendment to the Agreement to
Wheel Power between PNM and Plains, for which PNM requests an effective
date of July 1, 1996.
[[Page 16770]]
Copies of the filing have been served on Western, Plains, LAC,
NTUA, SPS, EPE, COG, KAFB, and the New Mexico Public Utility
Commission. Copies of the filing are available for public inspection at
PNM's offices in Albuquerque, New Mexico.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
14. Louisville Gas and Electric Company
[Docket No. ER96-1463-000]
Take notice that on April 1, 1996, Louisville Gas and Electric
Company (LG&E), tendered for filing a service agreement between LG&E
and Michigan Public Power Agency (MPPA) under Rate PSS--Power Sales
Service.
A copy of the filing has been mailed to the Kentucky Public Service
Commission.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
15. Wisconsin Public Service Corporation
[Docket No. ER96-1464-000]
Take notice that on April 1, 1996, Wisconsin Public Service
Corporation, tendered for filing an executed service agreement with
Aquila Power Corporation under its CS-1 Coordination Sales Tariff.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
16. Florida Power Corporation
[Docket No. ER96-1465-000]
Take notice that on April 1, 1996, Florida Power Corporation,
tendered for filing a service agreement providing for service to Delhi
Energy Services, Inc. pursuant to Florida Power's power sales tariff.
Florida Power requests that the Commission waive its notice of filing
requirements and allow the Service Agreement to become effective on
April 2, 1996.
Florida Power requests that the Commission waive its notice of
filing requirements to allow the Service Agreement to become effective
on the date listed above.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
17. Kansas Gas and Electric Company
[Docket No. ER96-1466-000]
Take notice that on April 1, 1996, Kansas Gas and Electric Company
(KGE), tendered for filing a proposed new service schedule under the
Second Supplement to the Electric Interconnection Agreement (the
Operating Agreement) between KGE and Western Resources, Inc. (Western
Resources). KGE states that the proposed service schedule provides for
the sale of capacity under the Operating Agreement (Supplement No. 27
to FERC Rate Schedule No. 93) between KGE and Western Resources.
Copies of the filing were served upon Western Resources, Inc. and
the Kansas Corporation Commission.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
18. Western Resources, Inc.
[Docket No. ER96-1467-000]
Take notice that on April 1, 1996, Western Resources, Inc. (Western
Resources), tendered for filing a proposed change to its Federal Energy
Regulatory Commission Electric Rate Schedule No. 235. Western Resources
states the purpose of the change is to provide generation deferral
service to the City of Sabetha. The change is proposed to become
effective June 1, 1996. Copies of the filing were served upon the City
of Sabetha and the Kansas Corporation Commission.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
19. Western Resources, Inc.
[Docket No. ER96-1468-000]
Take notice that on April 1, 1996, Western Resources, Inc.,
tendered for filing a participation power agreement and a firm
transmission service agreement between Western Resources and the City
of Burlington, Kansas and an electric service agreement between Kansas
Gas and Electric Company and the City of Burlington, Kansas. The
agreements are proposed to become effective June 1, 1996.
A copy of this filing was served upon the City of Burlington,
Kansas and the Kansas Corporation Commission.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
20. Northeast Utilities Service Company
[Docket No. ER96-1469-000]
Take notice that on April 1, 1996, Northeast Utilities Service
Company (NUSCO), tendered for filing, a Service Agreement and a
Certificate of Concurrence with the Vermont Electric Cooperative, Inc.
(VEC) under the NU System Companies' System Power Sales/Exchange Tariff
No. 6.
NUSCO states that a copy of this filing has been mailed to VEC.
Comment date: April 24, 1996, in accordance with Standard Paragraph
E at the end of this notice.
21. David M. Wilks
[Docket No. ID-2954-000]
Take notice that on March 27, 1996, David M. Wilks (Applicant)
tendered for filing under section 305(b) of the Federal Power Act to
hold the following positions:
Director; President and Chief Operating Officer--Southwestern Public
Service Company
Director--Utility Engineering Corporation
Comment date: April 26, 1996, in accordance with Standard Paragraph
E at the end of this notice.
22. Robert H. Spilman
[Docket No. ID-2955-000]
Take notice that on March 28, 1996, Robert H. Spilman (Applicant)
tendered for filing an application under section 305(b) of the Federal
Power Act to hold the following positions:
Director--Virginia Electric and Power Company
Director--NationsBank Corporation
Comment date: April 26, 1996, in accordance with Standard Paragraph
E at the end of this notice.
Standard Paragraph
E. Any person desiring to be heard or to protest said filing should
file a motion to intervene or protest with the Federal Energy
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,
in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such
motions or protests should be filed on or before the comment date.
Protests will be considered by the Commission in determining the
appropriate action to be taken, but will not serve to make protestants
parties to the proceeding. Any person wishing to become a party must
file a motion to intervene. Copies of this filing are on file with the
Commission and are available for public inspection.
Lois D. Cashell,