[Federal Register Volume 61, Number 75 (Wednesday, April 17, 1996)]
[Notices]
[Pages 16768-16770]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 96-9439]



-----------------------------------------------------------------------

DEPARTMENT OF EDUCATION
DEPARTMENT OF ENERGY
[Docket No. ER94-1246-007, et al.]


Ashton Energy Corporation, et al.; Electric Rate and Corporate 
Regulation Filings

April 10, 1996.
    Take notice that the following filings have been made with the 
Commission:

1. Ashton Energy Corporation, Texpar Energy, Inc., Industrial Gas & 
Electric, Service Company Mock Resources, Inc.

[Docket No. ER94-1246-007 Docket No. ER95-62-004 Docket No. ER95-257-
005 Docket No. ER95-300-006 (not consolidated)]

    Take notice the following informational filings have been made with 
the Commission and are on file and available for inspection and copying 
in the Commission's Public Reference Room:
    On April 8, 1996, Ashton Energy Corporation filed certain 
information as required by the Commission's August 10, 1994 order in 
Docket No. ER94-1246-000.
    On March 18, 1996, Texpar Energy, Inc. filed certain information as 
required by the Commission's December 27, 1994 order in Docket No. 
ER95-62-000.
    On April 1, 1996, Industrial Gas & Electric Service Company filed 
certain information as required by the Commission's February 1, 1995 
order in Docket No. ER95-257-000.
    On April 8, 1996, Mock Resources, Inc. filed certain information as 
required by the Commission's March 16, 1995 order in Docket No. ER95-
300-000.

2. Illinois Power Company

[Docket No. ER96-1074-000]

    Take notice that on April 2, 1996, Illinois Power Company tendered 
for filing an amendment in the above-referenced docket.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

3. Ohio Edison Company

[Docket No. ER96-1234-000]

    Take notice that on March 28, 1996, Ohio Edison Company tendered 
for filing an amendment in the above-referenced docket.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

4. Northeast Utilities Service Company

[Docket No. ER96-1385-000]

    Take notice that Northeast Utilities Service Company (NUSCO) on 
March 25, 1996, tendered for filing, a Service Agreement with Koch 
Power Services, Inc. (Koch) under the NU System Companies' System Power 
Sales/Exchange Tariff No. 6.
    Koch also filed a Certificate of Concurrence as it relates to 
exchange transactions under the Tariff.
    NUSCO states that a copy of this filing has been mailed to Koch.
    NUSCO requests that the Service Agreement become effective sixty 
(60) days following the Commission's receipt of the filing.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

5. Union Electric Company

[Docket No. ER96-1386-000]

    Take notice that on March 25, 1996, Union Electric Company tendered 
for filing, a Transmission Service Agreement dated March 26, 1996 
between Tennessee Power Company (TPC) and UE. UE asserts that the 
purpose of the Agreement is to set out specific rates, terms, and 
conditions for transmission service transactions from UE to TPC.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

6. Northeast Utilities Service Company

[Docket No. ER96-1388-000]

    Take notice that Northeast Utilities Service Company (NUSCO) on 
March 25, 1996, tendered for filing, a Service Agreement and a 
Certificate of Concurrence with Commonwealth Electric Company (Com 
Electric) and under the NU System Companies' System Power Sales/
Exchange Tariff No. 6.
    NUSCO states that a copy of this filing has been mailed to Com 
Electric.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

7. Cook Inlet Energy Supply, L.P.

[Docket No. ER96-1410-000]

    Take notice that on March 27, 1996, Cook Inlet Energy Supply, L.P. 
tendered for filing an application requesting approval of rate 
schedule, clarification of jurisdiction, and petition for waivers, and 
blanket approvals.
    Comment date: April 25, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

8. Exeter & Hampton Electric Company

[Docket No. ER96-1430-000]

    Take notice that on March 28, 1996, Exeter & Hampton Electric 
Company (E&H) tendered for filing transmission rates contained in its 
Schedule PP, New Hampshire Retail Competition Pilot Program Service, 
Exeter & Hampton Electric Company, FERC Electric Tariff, Original 
Volume ______ (Schedule PP). E&H states that the transmission rates in 
Schedule PP are proposed to become effective May 28, 1996.
    Comment date: April 23, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

[[Page 16769]]

9. Portland General Electric Company

[Docket No. ER96-1434-000]

    Take notice that on March 27, 1996, Portland General Electric 
Company tendered for filing a letter requesting the Commission issue a 
supplement to FERC Electric Tariff 1st Revised Volume No. 2 (Rate 
schedule FERC No. 4) to reflect the name change from National Electric 
Associates L.P. to National Gas & Electric L.P.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

10. KC United Corp.

[Docket No. ER96-1446-000]

    Take notice that on April 5, 1996, KC United Corp. tendered for 
filing an amendment in the above-referenced docket.
    Comment date: April 25, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

11. Allegheny Power Service Corporation on Behalf of Monongahela Power 
Company, The Potomac Edison Company, and West Penn Power Company 
(Allegheny Power)

[Docket No. ER96-1460-000]

    Take notice that on March 29, 1996, Allegheny Power Service 
Corporation on behalf of Monongahela Power Company, The Potomac Edison 
Company and West Penn Power Company (Allegheny Power), filed a Service 
Agreement to add CINergy Services, Inc. as a Customer under Allegheny 
Power's Point-to-Point Transmission Service Tariff which has been 
accepted for filing by the Federal Energy Regulatory Commission. 
Allegheny Power proposes to make service available to CINergy Services, 
Inc. as of March 1, 1996.
    Copies of the filing have been provided to the Public Utilities 
Commission of Ohio, the Pennsylvania Public Utility Commission, the 
Maryland Public Service Commission, the Virginia State Corporation 
Commission, the West Virginia Public Service Commission.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

12. Cambridge Electric Light Company

[Docket No. ER96-1461-000]

    Take notice that on March 29, 1996, Cambridge Electric Light 
Company (Cambridge), submitted for filing proposed FERC Electric 
Tariffs for Point-to-Point Transmission Service (Point-to-Point Tariff) 
and for Network Integration Service (Network Tariff, Collectively 
Tariffs). The proposed Tariffs are modeled after the Commission's pro 
forma Tariffs accompanying its notice of proposed rulemaking on open-
access transmission in Docket No. RM95-8-000. The Point-to-Point 
Tariff, upon its effectiveness, will supersede the existing FERC 
Electric Tariff for Firm Transmission Service, First Revised Volume 3 
and the FERC Electric Tariff for Non-Firm Transmission Service, First 
Revised Volume 4. Cambridge requests that the Commission accept these 
proposed Tariffs and permit them to take effect without suspension, 
condition or modification, as of May 28, 1996. In addition, Cambridge 
requests waiver by the Commission of any requirements of the 
Commission's rules and regulations, as well as any authorizations, as 
may be necessary or required to permit these Tariffs to be accepted by 
the Commission and made effective in the manner proposed herein.
    As required by the Commission, once the final rule for the Open 
Access NOPR is issued, Cambridge will modify these tariffs, as 
necessary, to ensure that they are consistent with the substantive 
requirements in the final rule.
    Copies of the filing were served upon the Town of Belmont, the 
Massachusetts Bay Transportation Authority and the Massachusetts 
Department of Public Utilities.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

13. Public Service Company of New Mexico

[Docket No. ER96-1462-000]

    Take notice that on April 1, 1996, Public Service Company of New 
Mexico (PNM), tendered for filing pursuant to Sec. 205 of the Federal 
Power Act, 15 U.S.C. 824d, and Sec. 35.13 of the regulations of the 
Federal Energy Regulatory Commission (Commission), (18 CFR 35.13), 
changes in rates for certain transmission services. PNM states that it 
proposes amendments between PNM and the following parties: Western Area 
Power Administration (Western), Plains Electric Generation and 
Transmission Cooperative, Inc. (Plains), Incorporated County of Los 
Alamos, New Mexico (IAC); Navajo Tribal Utility Authority (NTUA); 
Southwestern Public Service Company (SPS); El Paso Electric Company 
(EPE); City of Gallup, New Mexico (COG); and Kirtland Air Force Base 
(KAFB).
    PNM's filing includes the following amendments to rate schedules 
for transmission services:
    (1) Amendment Number Two to Contract No. 8-07-40-70695, Contract 
between PNM and United States Department of Energy Western Area Power 
Administration Salt Lake City Area Integrated Projects. (FERC Rate 
Schedule No. 86.)
    (2) Amendment Number One to Service Schedule F to the 
Interconnection Agreement Between PNM and the Incorporated County of 
Los Alamos, New Mexico. (FERC Rate Schedule No. 60.)
    (3) Amendment Number Three to the Agreement for Wheeling Service 
between PNM and the Navajo Tribal Utility Authority. (FERC Rate 
Schedule No. 27.)
    (4) Amendment Number Two to Agreement to Wheel Power between PNM 
and Plains Electric Generation and Transmission Cooperative, Inc. (FERC 
Rate Schedule No. 25.)
    (5) Amendment Number Two to Service Schedule 1 to the 
Interconnection Agreement between PNM and El Paso Electric Company. 
(FERC Rate Schedule No. 9.) Amendment Number One to the PNM/EPE 
Operating Procedure No. 9.
    (6) Amendment Number One to Special Delivery Agreement for 
Federally Allocated Salt Lake City Integrated Projects Power and Energy 
between PNM and Southwestern Public Service Company. (FERC Rate 
Schedule No. 83.)
    PNM's filing also includes amendments to the following rate 
schedules for firm network transmission service to Plains, to reflect 
that Plains will be charged its load ratio share for service under such 
agreements:
    (1) Service Schedule G to the Master Interconnection Agreement 
between PNM and Plains.
    (2) Letter Agreement Implementing Certain Temporary Arrangements 
between PNM and Plains Relating to Plains' Demands in Excess of 328 MW.
    PNM's filing also includes the following amendments to rate 
schedules for firm point-to-point transmission and ancillary services, 
to charge customers under these rate schedules separate rates for such 
services:
    (1) Amendment Number One to Contract No. DE-AC04-89AL57511 between 
PNM and the Department of Energy, on behalf of Kirtland Air Force Base.
    (2) Amendment Number Two to the Contract for Electric Service 
between PNM and the City of Gallup, New Mexico.
    PNM requests an effective date of June 1, 1996, for the foregoing 
amendments, with the exception of the amendment to the Agreement to 
Wheel Power between PNM and Plains, for which PNM requests an effective 
date of July 1, 1996.

[[Page 16770]]

    Copies of the filing have been served on Western, Plains, LAC, 
NTUA, SPS, EPE, COG, KAFB, and the New Mexico Public Utility 
Commission. Copies of the filing are available for public inspection at 
PNM's offices in Albuquerque, New Mexico.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

14. Louisville Gas and Electric Company

[Docket No. ER96-1463-000]

    Take notice that on April 1, 1996, Louisville Gas and Electric 
Company (LG&E), tendered for filing a service agreement between LG&E 
and Michigan Public Power Agency (MPPA) under Rate PSS--Power Sales 
Service.
    A copy of the filing has been mailed to the Kentucky Public Service 
Commission.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

15. Wisconsin Public Service Corporation

[Docket No. ER96-1464-000]

    Take notice that on April 1, 1996, Wisconsin Public Service 
Corporation, tendered for filing an executed service agreement with 
Aquila Power Corporation under its CS-1 Coordination Sales Tariff.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

16. Florida Power Corporation

[Docket No. ER96-1465-000]

    Take notice that on April 1, 1996, Florida Power Corporation, 
tendered for filing a service agreement providing for service to Delhi 
Energy Services, Inc. pursuant to Florida Power's power sales tariff. 
Florida Power requests that the Commission waive its notice of filing 
requirements and allow the Service Agreement to become effective on 
April 2, 1996.
    Florida Power requests that the Commission waive its notice of 
filing requirements to allow the Service Agreement to become effective 
on the date listed above.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

17. Kansas Gas and Electric Company

[Docket No. ER96-1466-000]

    Take notice that on April 1, 1996, Kansas Gas and Electric Company 
(KGE), tendered for filing a proposed new service schedule under the 
Second Supplement to the Electric Interconnection Agreement (the 
Operating Agreement) between KGE and Western Resources, Inc. (Western 
Resources). KGE states that the proposed service schedule provides for 
the sale of capacity under the Operating Agreement (Supplement No. 27 
to FERC Rate Schedule No. 93) between KGE and Western Resources.
    Copies of the filing were served upon Western Resources, Inc. and 
the Kansas Corporation Commission.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

18. Western Resources, Inc.

[Docket No. ER96-1467-000]

    Take notice that on April 1, 1996, Western Resources, Inc. (Western 
Resources), tendered for filing a proposed change to its Federal Energy 
Regulatory Commission Electric Rate Schedule No. 235. Western Resources 
states the purpose of the change is to provide generation deferral 
service to the City of Sabetha. The change is proposed to become 
effective June 1, 1996. Copies of the filing were served upon the City 
of Sabetha and the Kansas Corporation Commission.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

19. Western Resources, Inc.

[Docket No. ER96-1468-000]

    Take notice that on April 1, 1996, Western Resources, Inc., 
tendered for filing a participation power agreement and a firm 
transmission service agreement between Western Resources and the City 
of Burlington, Kansas and an electric service agreement between Kansas 
Gas and Electric Company and the City of Burlington, Kansas. The 
agreements are proposed to become effective June 1, 1996.
    A copy of this filing was served upon the City of Burlington, 
Kansas and the Kansas Corporation Commission.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

20. Northeast Utilities Service Company

[Docket No. ER96-1469-000]

    Take notice that on April 1, 1996, Northeast Utilities Service 
Company (NUSCO), tendered for filing, a Service Agreement and a 
Certificate of Concurrence with the Vermont Electric Cooperative, Inc. 
(VEC) under the NU System Companies' System Power Sales/Exchange Tariff 
No. 6.
    NUSCO states that a copy of this filing has been mailed to VEC.
    Comment date: April 24, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

21. David M. Wilks

[Docket No. ID-2954-000]

    Take notice that on March 27, 1996, David M. Wilks (Applicant) 
tendered for filing under section 305(b) of the Federal Power Act to 
hold the following positions:

Director; President and Chief Operating Officer--Southwestern Public 
Service Company
Director--Utility Engineering Corporation

    Comment date: April 26, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

22. Robert H. Spilman

[Docket No. ID-2955-000]

    Take notice that on March 28, 1996, Robert H. Spilman (Applicant) 
tendered for filing an application under section 305(b) of the Federal 
Power Act to hold the following positions:

Director--Virginia Electric and Power Company
Director--NationsBank Corporation

    Comment date: April 26, 1996, in accordance with Standard Paragraph 
E at the end of this notice.

Standard Paragraph

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
motions or protests should be filed on or before the comment date. 
Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of this filing are on file with the 
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 96-9439 Filed 4-16-96; 8:45 am]
BILLING CODE 6717-01-P