[Federal Register Volume 60, Number 236 (Friday, December 8, 1995)]
[Notices]
[Pages 63027-63029]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-29925]



=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY


Federal Energy Regulatory Commission

[Docket No. EG96-20-000, et al.]


China U.S. Power Partners I, Ltd., et al.; Electric Rate and 
Corporate Regulation Filings

December 1, 1995.
    Take notice that the following filings have been made with the 
Commission:

1. China U.S. Power Partners I, Ltd.

[Docket No. EG96-20-000]

    On November 20, 1995, China U.S. Power Partners I, Ltd. 
(``CUPPI''), with its principal office at Church Street, Clarendon 
House, Hamilton HM11, Bermuda filed with the Federal Energy Regulatory 
Commission an application for determination of exempt wholesale 
generator status pursuant to Part 365 of the Commission's Regulations.
    CUPPI is a limited liability company organized under the laws of 
Bermuda. CUPPI will be engaged indirectly through an Affiliate as 
defined in Section 2(a)(11)(B) of the Public Utility Holding Company 
Act of 1935, and exclusively in owning, or both owning and operating a 
proposed coal-fired electric generating facility consisting of two 
electric generating units, each with a net rating of approximately 
300,000 kilowatts to be located in the People's Republic of China and 
to engage in project development activities with respect thereto.
    Comment date: December 21, 1995, in accordance with Standard 
Paragraph E at the end of this notice. The Commission will limit its 
consideration of comments to those that concern the adequacy or 
accuracy of the application.

2. Cenergy, Inc.

[Docket No. ER94-1402-002]

    Take notice that on November 9, 1995, Cenergy, Inc. (Cenergy) 
tendered for filing a letter supporting Cenergy's position in the 
above-referenced docket.
    Comment date: December 14, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

3. Mock Resources, Inc.

[Docket No. ER95-300-004]

    Take notice that on November 15, 1995, Mock Resources, Inc. 
tendered for filing an amendment to its October 30, 1995 quarterly 
report filed in the above-reference docket.

4. Commonwealth Edison Company

[Docket No. ER95-901-000]

    Take notice that on November 13, 1995, Commonwealth Edison Company 
tendered for filing an amendment in the above-referenced docket.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

5. Consolidated Edison Company of New York, Inc.

[Docket No. ER95-1694-000]

    Take notice that on October 20, 1995, Consolidated Edison Company 
of New York, Inc. tendered for filing an amendment in the above-
referenced docket.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

6. Greenwich Energy Partners, L.P.

[Docket No. ER96-116-000]

    Take notice that on November 16, 1995, Greenwich Energy Partners, 
L.P. tendered for filing an amendment in the above-referenced docket.
    Comment date: December 14, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

7. Texas Utilities Electric Company

[Docket No. ER96-267-000]

    Take notice that on November 2, 1995, Texas Utilities Electric 
Company (TU) tendered for filing three executed transmission service 
agreements (TSA's) with LG&E Power Marketing, Inc., Enron Power 
Marketing, Inc., and Electric Clearinghouse, Inc. for certain Economy 
Energy Transmission Service under TU Electric's Tariff for Transmission 
Service To, From and Over Certain HVDC Interconnections.
    TU Electric requests effective dates for the TSA's that will permit 
them to become effective on or before the service commencement date 
under each of the three TSA's. Accordingly, TU Electric 

[[Page 63028]]
seeks waiver of the Commission's notice requirements. Copies of the 
filing were served on LG&E Power Marketing, Inc., Enron Power 
Marketing, Inc., and Electric Clearinghouse, Inc., as well as the 
Public Utility Commission of Texas.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

8. Columbus Southern Power Company

[Docket No. ER96-346-000]

    Take notice that on November 14, 1995, Columbus Southern Power 
Company tendered for filing a Notice of Cancellation of FERC Rate 
Schedule Nos. 13 and 38.
    Comment date: December 14, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

9. Kentucky Utilities Company

[Docket No. ER96-364-000]

    Take notice that on November 15, 1995, Kentucky Utilities Company 
tendered for filing information on transactions that occurred during 
July 1, 1995 through October 31, 1995, pursuant to the Power Services 
Tariff accepted by the Commission in Docket No. ER95-854-000.
    Comment date: December 14, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

10. Pennsylvania Power & Light Company

[Docket No. ER96-366-000]

    Take notice that on November 15, 1995, Pennsylvania Power & Light 
Company (PP&L), tendered for filing with the Federal Energy Regulatory 
Commission two Service Agreements (the Agreements) between PP&L and 
American Municipal Power--Ohio (AMP-Ohio), dated November 1, 1995; and 
(2) Northeast Utilities Service Company, dated November 8, 1995.
    The Agreements supplement a Short Term Capacity and Energy Sales 
umbrella tariff approved by the Commission in Docket No. ER95-782-000 
on June 21, 1995.
    In accordance with the policy announced in Prior Notice and Filing 
Requirements Under Part II of the Federal Power Act, 64 FERC para. 
61,139, clarified and reh'g granted in part and denied in part, 65 FERC 
para. 61,081 (1995), PP&L requests the Commission to make the Agreement 
effective as of the date of execution of each, because service will be 
provided under an umbrella tariff and each service agreement is filed 
within 30 days after the commencement of service. In accordance with 18 
CFR 35.11, PP&L has requested waiver of the sixty-day notice period in 
18 CFR 35.2(e). PP&L has also requested waiver of certain filing 
requirements for information previously filed with the Commission in 
Docket No. ER95-782-000.
    PP&L states that a copy of its filing was provided to the customers 
involved and to the Pennsylvania Public Utility Commission.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

11. Florida Power Corporation

[Docket No. ER96-85-000]

    Take notice that on November 21, 1995 and November 28, 1995, 
Florida Power Corporation tendered for filing amendments in the above-
referenced dockets.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

12. The Washington Water Power Company

[Docket No. ER96-367-000]

    Take notice that on November 15, 1995, The Washington Water Power 
Company (WWP), tendered for filing with the Federal Energy Regulatory 
Commission pursuant to 18 CFR 35.12, an Agreement for the sale of up to 
130,000 megawatt hours of energy during the period January 15 through 
April 15 for each of the years 1996 and 1997 to the City of Seattle, 
Washington.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

13. Florida Power & Light Company

[Docket No. ER96-368-000]

    Take notice that on November 15, 1995, Florida Power & Light 
Company (FPL), tendered for filing proposed service agreements with 
Industrial Energy Applications, Inc. for transmission service under 
FPL's Transmission Tariff No. 2 and FPL's Transmission Tariff No. 3.
    FPL requests that the proposed service agreements be permitted to 
become effective on December 1, 1995, or as soon thereafter as 
practicable.
    FPL states that this filing is in accordance with Part 35 of the 
Commission's Regulations.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

14. Florida Power & Light Company

[Docket No. ER96-369-000]

    Take notice that on November 15, 1995, Florida Power & Light 
Company (FPL) filed the Contract for Purchases and Sales of Power and 
Energy between FPL and Koch Power Services Inc. FPL requests an 
effective date of November 16, 1995.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

15. Maine Public Service Company

[Docket No. ER96-370-000]

    Take notice that on November 15, 1995, Maine Public Service Company 
(Maine Public) tendered for filing an unexecuted Transmission Service 
Agreement for Network Service for Houlton Water Company under Maine 
Public's Transmission and Ancillary Services Tariff.
    Maine Public has requested that the service agreement become 
effective on January 1, 1996 and requests waiver of the Commission's 
regulations regarding filing.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

16. Cleveland Electric Illuminating Company

[Docket No. ER96-371-000]

    Take notice that on November 15, 1995, Cleveland Electric 
Illuminating Company (CEI), tendered for filing its proposed FERC 
Tariff No. ____ under which it is proposing to sell capacity and energy 
to eligible purchasers for resale under competitive market conditions 
and Electric Power Sales Agreements between CEI and each of the 
following power marketers that desire to purchase power and energy from 
CEI at non-cost-based rates: A. Catex Vitol Electric, L.I.C., B. 
Citizens Lehman Power Sales, C. Enron Power Marketing, Inc., D. Louis 
Dreyfus Electric Power Inc.
    CEI proposes to make the Tariff and each of the accompanying 
Electric Power Sales Agreements effective as of January 16, 1995.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

17. Southern California Edison Company

[Docket No. ER96-385-000]

    Take notice that on November 17, 1995, Southern California Edison 
Company (Edison), tendered for filing a Letter Agreement (Letter 
Agreement) with the City of Banning (Banning). The Letter Agreement 
modifies the Rated Capacity and Minimum Take Obligation referenced in 
the Supplemental Agreement to the 1990 Integrated Operations Agreement 
for the integration of Banning's entitlement in San Juan Unit 3, 
Commission Rate Schedule No. 248.28. 

[[Page 63029]]

    Edison requests an effective date of January 1, 1996.
    Copies of this filing were served upon the Public Utilities 
Commission of the State of California and all interested parties.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

18. Public Service Electric and Gas Company

[Docket No. ER96-386-000]

    Take notice that on November 17, 1995, Public Service Electric and 
Gas Company (PSE&G), tendered for filing an initial rate schedule to 
provide fully interruptible transmission service to National Fuel 
Resources, Inc., for delivery of non-firm wholesale electrical power 
and associated energy output utilizing the PSE&G bulk power 
transmission system.
    Comment date: December 15, 1995, in accordance with Standard 
Paragraph E at the end of this notice.

Standard Paragraph

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in 
accordance with Rules 211 and 214 of the Commission's Rules of Practice 
and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such motions or 
protests should be filed on or before the comment date. Protests will 
be considered by the Commission in determining the appropriate action 
to be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a motion to 
intervene. Copies of this filing are on file with the Commission and 
are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 95-29925 Filed 12-07-95; 8:45 am]
BILLING CODE 6717-01-P