[Federal Register Volume 60, Number 127 (Monday, July 3, 1995)]
[Notices]
[Pages 34527-34529]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-16251]



-----------------------------------------------------------------------

DEPARTMENT OF ENERGY
[Docket No. ER95-132-000, et al.]


PSI Energy, Inc., et al.; Electric Rate and Corporate Regulation 
Filings

June 23, 1995.
    Take notice that the following filings have been made with the 
Commission:

1. PSI Energy, Inc.

[Docket Nos. ER95-132-000; ER95-133-000]

    Take notice that PSI Energy, Inc. (PSI) on June 19, 1995, tendered 
for filing a Notice of Withdrawal of emission allowance cost support 
data filed with the Federal Energy Regulatory Commission in the above 
referenced dockets per Interchange Agreements between PSI, Blue Ridge 
Power Agency and the City of Piqua, Ohio.
    PSI requests the withdrawal of such cost support data because 
similar information was filed and is covered under PSI's filing in 
Docket No. ER95-501-000 for the Interchange Agreements designated 
respectively as PSI Rate Schedule FERC Nos. 255 and 260 by the 
Commission.
    Copies of the filing were served on the City of Piqua, Ohio, the 
Public Utilities Commission of Ohio, Blue Ridge Power Agency, the 
Virginia State Corporation Commission and the Indiana Utility 
Regulatory Commission.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

2. Kohler Company

[Docket No. ER95-1018-000]

    Take notice that on June 14, 1995, Kohler Company tendered for 
filing an amendment in the above-referenced docket.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

3. Jersey Central Power & Light Company, Metropolitan Edison 
Company, Pennsylvania Electric Company

[Docket No. ER95-1202-000]

    Take notice that on June 12, 1995, GPU Service Corporation (GPU) on 
behalf of Jersey Central Power & Light Company, Metropolitan Edison 
Company and Pennsylvania Electric Company (jointly referred to as the 
GPU Operating Companies) tendered for filing a Service Agreement 
between GPU and Midcon Power Services Corporation, dated June 6, 1995.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

4. Portland General Electric Company

[Docket No. ER95-1203-000]

    Take notice that on June 12, 1995, Portland General Electric 
Company (PGE) tendered for filing a cancellation of Service Agreement 
No. 17 under FERC Electric Tariff, Original Volume No. 1 (PGE-1) and 
Service Agreement No. 38 under FERC Electric Tariff, Original Volume 
No. 2 (PGE-2) with Sacramento Municipal Utility District. PGE has 
requested that the Service Agreement cancellations be accepted by the 
Commission effective August 8, 1995. Copies of the filing have been 
served on the parties included in the Notices of Cancellation.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

5. Northeast Utilities Service Company

[Docket No. ER95-1204-000]

    Take notice that Northeast Utilities Service Company (NUSCO), on 
June 12, 1995, tendered for filing, a Service Agreement and a 
Certificate of Concurrence with the Citizens Utilities Company 
(Citizens) under the NU System Companies' System Power Sales/Exchange 
Tariff No. 6.
    NUSCO states that a copy of this filing has been mailed to 
Citizens.
    NUSCO requests that the Service Agreement become effective on June 
12, 1995.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

6. Interstate Power Company

[Docket No. ER95-1205-000]

    Take notice that on June 12, 1995, Interstate Power Company (IPW) 
tendered for filing a Transmission Service Agreement between IPW and 
Rainbow Energy Marketing Corporation (Rainbow). Under the Transmission 
Service Agreement, IPW will provide non-firm point-to-point 
transmission service to Rainbow.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

7. Texas-New Mexico Power Company

[Docket No. ER95-1206-000]

    Take notice that on June 12, 1995, Texas-New Mexico Power Company 
(TNMP) tendered for filing a Pre-PST New Mexico Transmission Operating 
Procedure entered into by and among TNMP, El Paso Electric Company, 
Public Service Company of New Mexico, and Plains Electric Generation & 
Transmission Cooperative, Inc.
    TNMP requests waiver of the Commission's notice requirements and 

[[Page 34528]]
    that such contract be made effective as of June 1, 1995.
    TNMP asserts that the filing has been served on the parties to the 
contract and on the Texas Public Utility Commission and the New Mexico 
Public Utility Commission.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

8. Public Service Company of Colorado

[Docket No. ER95-1207-000]

    Take notice that on June 12, 1995, Public Service Company of 
Colorado (Public Service) tendered for filing Public Service Electric 
Coordination Service Tariff (Tariff). The Tariff proposes two service 
schedules: 1) Service Schedule A--Coordination Power and Energy; and 2) 
Service Schedule B--Power and Energy Exchanges.
    No new or modifications to existing facilities are anticipated to 
be required as a result of this Tariff.
    A copy of this filing has been served on the Public Utilities 
Commission of the State of Colorado and the Colorado Office of Consumer 
Counsel.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

9. Pacific Gas and Electric Company

[Docket No. ER95-1208-000]

    Take notice that on June 13, 1995, Pacific Gas and Electric Company 
(PG&E) tendered for filing: (1) an agreement dated April 12, 1995, 
between PG&E and the Sierra Pacific Power Company (Sierra), entitled 
Special Facilities Agreement for the Goldhill-Horseshoe Reconductor 
Project; and (2) a Corrected Service Schedule 1 to Appendix A of Rate 
Schedule FERC No. 72.
    Copies of this filing have been served upon Sierra and the CPUC.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

10. Pacific Gas and Electric Company

[Docket No. ER95-1209-000]

    Take notice that on June 13, 1995, Pacific Gas and Electric Company 
(PG&E) tendered for filing the Rainbow Energy Marketing Corporation--
PG&E Power Enabling Agreement between Rainbow Energy Marketing 
Corporation (REMC) and PG&E. The Enabling Agreement documents terms and 
conditions for the purchase, sale or exchange of economy energy and 
surplus capacity which the Parties agree to make available to one 
another at defined control area border interconnection points.
    Copies of this filing have been served upon REMC and the California 
Public Utilities Commission.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

11. Arizona Public Service Company

[Docket No. ER95-1210-000]

    Take notice that on June 13, 1995, Arizona Public Service Company 
(APS) tendered for filing a proposed Service Schedule D to the existing 
Power Sale Agreement between APS and Citizens Utilities Company 
(Citizens). Service Schedule D addresses various terms and conditions 
associated with integration of existing and planned generating units 
owned by Citizens into those operated by APS.
    The Parties request an effective date upon acceptance by the 
Commission.
    Copies of this filing have been served on the Arizona Corporation 
Commission and Citizens Utilities Company.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

12. Western Regional Transmission Association

[Docket No. ER95-1211-000]

    Take notice that on June 12, 1995, Western Regional Transmission 
Association tendered for filing signature pages to the Governing 
Agreement executed by four additional Members of the Western Regional 
Transmission Association--Seattle City Light, the Phoenix Area Office 
of the Western Area Power Administration, Fletcher Challenge Power 
Generation U.S.A. Inc. and Wickland Power Services.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

13. Virginia Electric and Power Company

[Docket No. ER95-1213-000]

    Take notice that on June 14, 1995, Virginia Electric and Power 
Company (Virginia Power), tendered for filing a Service Agreement 
between Niagara Mohawk Power Corporation and Virginia Power, dated May 
15, 1995 under the Power Sales Tariff to Eligible Purchasers dated May 
27, 1994. Under the tendered Service Agreement Virginia Power agrees to 
provide services to Niagara Mohawk Power Corporation under the rates, 
terms, and conditions of the Power Sales Tariff as agreed by the 
parties pursuant to the terms of the applicable Service Schedules 
included in the Power Sales Tariff.
    Copies of the filing were served upon the Virginia State 
Corporation Commission and the North Carolina Utilities Commission.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

14. Virginia Electric and Power Company

[Docket No. ER95-1214-000]

    Take notice that on June 14, 1995, Virginia Electric and Power 
Company (Virginia Power), tendered for filing a Service Agreement 
between Pennsylvania Power & Light Company and Virginia Power, dated 
May 15, 1995 under the Power Sales Tariff to Eligible Purchasers dated 
May 27, 1994. Under the tendered Service Agreement Virginia Power 
agrees to provide services to Pennsylvania Power & Light Company under 
the rates, terms, and conditions of the Power Sales Tariff as agreed by 
the parties pursuant to the terms of the applicable Service Schedules 
included in the Power Sales Tariff.
    Copies of the filing were served upon the Virginia State 
Corporation Commission and the North Carolina Utilities Commission.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

15. Virginia Electric and Power Company

[Docket No. ER95-1215-000]

    Take notice that on June 14, 1995, Virginia Electric and Power 
Company (Virginia Power), tendered for filing a Service Agreement 
between CNG Power Services Corporation and Virginia Power, dated May 
15, 1995 under the Power Sales Tariff to Eligible Purchasers dated May 
27, 1994. Under the tendered Service Agreement Virginia Power agrees to 
provide services to CNG Power Services Corporation under the rates, 
terms and conditions of the Power Sales Tariff as agreed by the parties 
pursuant to the terms of the applicable Service Schedules included in 
the Power Sales Tariff.
    Copies of the filing were served upon the Virginia State 
Corporation Commission and the North Carolina Utilities Commission.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

16. Boston Edison Company

[Docket No. ER95-1216-000]

    Take notice that on June 14, 1995, Boston Edison Company (Edison), 
tendered for filing a Service Agreement and Appendix A under Original 
Volume No. 6, Power Sales and Exchange Tariff 

[[Page 34529]]
(Tariff) for Cambridge Electric Light Company (Cambridge). Boston 
Edison requests that the Service Agreement become effective as of May 
22, 1995.
    Edison states that it has served a copy of this filing on Cambridge 
and the Massachusetts Department of Public Utilities.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

17. Boston Edison Company

[Docket No. ER95-1217-000]

    Take notice that on June 14, 1995, Boston Edison Company (Edison), 
tendered for filing a Service Agreement and Appendix A under Original 
Volume No. 6, Power Sales and Exchange Tariff (Tariff) for Commonwealth 
Electric Company (Commonwealth). Boston Edison requests that the 
Service Agreement become effective as of May 23, 1995.
    Edison states that it has served a copy of this filing on 
Commonwealth and the Massachusetts Department of Public Utilities.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

18. Portland General Electric Company

[Docket No. ER95-1218-000]

    Take notice that on June 13, 1995, Portland General Electric 
Company (PGE), tendered for filing a Service Agreement under FERC 
Electric Tariff, Original Volume No. 2 (PGE-2), with the Springfield 
Utility Board. PGE has requested the Service Agreement be accepted by 
the Commission, effective August 1, 1995. Copies of the filing have 
been served on the parties included in the Certificate of Service 
attached to the filing letter.
    Comment date: July 7, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

19. Morro Energy L.P., S.E.

[Docket No. QF95-121-000]

    On June 22, 1995, Morro Energy L.P., S.E. tendered for filing an 
amendment to its December 28, 1994, filing in this docket.
    The amendment pertains to technical requirements and the ownership 
structure of the small power production facility. No determination has 
been made that the submittal constitutes a complete filing.
    Comment date: July 13, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

Standard Paragraph

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 825 North Capitol Street, N.E., Washington, D.C. 
20426, in accordance with Rules 211 and 214 of the Commission's Rules 
of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
motions or protests should be filed on or before the comment date. 
Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of this filing are on file with the 
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 95-16251 Filed 6-30-95; 8:45 am]
BILLING CODE 6717-01-P