[Federal Register Volume 60, Number 73 (Monday, April 17, 1995)]
[Notices]
[Pages 19243-19245]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-9366]



-----------------------------------------------------------------------

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER94-1475-000, et al.]


Illinova Power Marketing, Inc., et al.; Electric Rate and 
Corporate Regulation Filings

April 11, 1995.
    Take notice that the following filings have been made with the 
Commission:

1. Illinova Power Marketing, Inc.

[Docket No. ER94-1475-000]

    Take notice that on April 5, 1995, Illinova Power Marketing, Inc. 
tendered for filing an amendment in the above-referenced docket.
    Comment date: April 25, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

2. Kentucky Utilities Company

[Docket No. ER95-580-000]

    Take notice that on April 10, 1995, Kentucky Utilities Company (KU) 
filed a modified Transmission Agreement between KU and East Kentucky 
Power Cooperative, Inc. (EKPC).
    Comment date: April 25, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

3. New York State Electric & Gas Corporation

[Docket Nos. ER95-738-000 and ER95-739-000]

    Take notice that on April 4, 1995, New York State Electric & Gas 
Corporation tendered for filing an amendment in the above-referenced 
dockets.
    Comment date: April 25, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

4. PECO Energy Company

[Docket No. ER95-796-000]

    Take notice that on March 24, 1995, PECO Energy Company (PECO) 
tendered for filing an Agreement between PECO and Stand Energy 
Corporation (SEC) dated March 1, 1995.
    PECO states that the Agreement sets forth the terms and conditions 
for the sale of system energy which it expects to have available for 
sale from time to time and the purchase of which will be economically 
advantageous to SEC. In order to optimize the economic advantage to 
both PECO and SEC, PECO requests that the Commission waive its 
customary notice period and permit the agreement to become effective on 
March 27, 1995.
    PECO states that a copy of this filing has been sent to SEC and 
will be furnished to the Pennsylvania Public Utility Commission.
    Comment date: April 25, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

5. Southern California Edison Company

[Docket No. ER95-831-000]

    Take notice that on March 31, 1995, Southern California Edison 
Company, tendered for filing the following power sale agreement between 
the City of Azusa (Azusa) and Edison, and the associated supplemental 
agreement to integrate the power sale agreement in accordance with the 
terms of the 1990 Integrated Operations Agreement (1990 IOA), Rate 
Schedule FERC No. 247:

 [[Page 19244]] 1995 Power Sale Agreement between the City of Azusa 
and The Southern California Edison Company (1995 PSA)
Supplemental Agreement for the Integration of the 1995 Power Sale 
Agreement between Southern California Edison and the City of Azusa 
(Supplemental Agreement)

    The 1995 PSA provides the terms and conditions whereby Edison shall 
make available and Azusa shall purchase Contract Capacity and 
Associated Energy During the Delivery Season of June 1 through October 
31 (5 months/year) during the years 1995, 1996, and 1997. The 
Supplemental Agreement sets forth the terms and conditions under which 
Edison will integrate the 1995 PSA pursuant to the 1990 IOA.
    Copies of this filing were served upon the Public Utilities 
Commission of the State of California and all interested parties.
    Comment date: April 25, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

6. Southern California Edison Company

[Docket No. ER95-832-000]

    Take notice that on March 31, 1995, Southern California Edison 
Company, tendered for filing the following power sale agreement between 
the City of Banning (Banning) and Edison, and the associated 
supplemental agreement to integrate the power sale agreement in 
accordance with the terms of the 1990 Integrated Operations Agreement 
(1990 IOA), Rate Schedule FERC No. 248:

1995 Power Sale Agreement between the City of Banning and The 
Southern California Edison Company (1995 PSA)
Supplemental Agreement for the Integration of the 1995 Power Sale 
Agreement between Southern California Edison and the City of Banning 
(Supplemental Agreement)

    The 1995 PSA provides the terms and conditions whereby Edison shall 
make available and Banning shall purchase Contract Capacity and 
Associated Energy during the Delivery Season of June 1 through 
September 30 (4 months/year) during the years 1995, 1996, and 1997. The 
Supplemental Agreement sets forth the terms and conditions under which 
Edison will integrate the 1995 PSA pursuant to the 1990 IOA.
    Copies of this filing were served upon the Public Utilities 
Commission of the State of California and all interested parties.
    Comment date: April 25, 1995, in accordance with Standard Paragraph 
E at the end of this notice.
7. Southern California Edison Company

[Docket No. ER95-833-000]

    Take notice that on March 31, 1995, Southern California Edison 
Company (Edison), tendered for filing a Supplement to the Supplemental 
Agreement (Supplemental Agreement) to the 1990 Integrated Operations 
Agreement (1990 IOA) for the integration of San Onofre Nuclear 
Generating Station (SONGS) and the associated Firm Transmission Service 
(FTS) Agreement with the City of Anaheim (Anaheim), Commission Rate 
Schedule FERC No. 246.12 and No. 246.13.
    The Supplement amends the Effective Operating Capacity for SONGS 
Unit 2 during Fuel Cycle 8 for the purposes of determining Anaheim's 
Rated Capability and Contract Capacity under the Supplemental Agreement 
and the FTS Agreement respectively and corresponding Capacity Credit 
under the 1990 IOA. Edison is seeking waiver of the Commission's 
requirement for 60-day prior notice and requesting an effective date 
concurrent with the beginning of Fuel Cycle 8.
    Copies of this filing were served upon the Public Utilities 
Commission of the State of California and all interested parties.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

8. Boston Edison Company

[Docket No. ER95-834-000]

    Take notice that on March 31, 1995, Boston Edison Company (BECo), 
tendered for filing a Service Agreement and Appendix A for LG&E Power 
Marketing, Inc. for the sale and/or exchange of power from time to time 
pursuant to BECo's Electric Tariff, Original Volume NO. 6. BECo 
requests that this Service Agreement and Appendix A become effective on 
April 1, 1995.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

9. UtiliCorp United Inc.

[Docket No. ER95-844-000]

    Take notice that on March 31, 1995, UtiliCorp United Inc., tendered 
for filing on behalf of its operating division, Missouri Public 
Service, a service agreement under its Power Sales Tariff, FERC 
Electric Tariff Original Volume No. 10, with City of Columbia, 
Missouri. The service agreement provides for the sale of capacity and 
energy by Missouri Public Service to City of Columbia, Missouri, 
pursuant to the tariff and for the sale of capacity and energy by City 
of Columbia, Missouri, to Missouri Public Service.
    UtiliCorp requests waiver of the Commission's regulations to permit 
the service agreement to become effective in accordance with its terms.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

10. UtiliCorp United Inc.

[Docket No. ER95-845-000]

    Take notice that on March 31, 1995, UtiliCorp United Inc., tendered 
for filing on behalf of its operating division, Missouri Public 
Service, a service agreement under its Power Sales Tariff, FERC 
Electric Tariff Original Volume No. 10, with Electric Clearinghouse, 
Inc. The service agreement provides for the sale of capacity and energy 
by Missouri Public Service to Electric Clearinghouse, Inc. pursuant to 
the tariff and for the sale of capacity and energy by Electric 
Clearinghouse, Inc. to Missouri Public Service pursuant to Electric 
Clearinghouse, Inc. Rate Schedule No. 1.
    UtiliCorp also has tendered for filing a certificate of concurrence 
by Electric Clearinghouse, Inc.
    UtiliCorp requests waiver of the Commission's regulations to permit 
the service agreement to become effective in accordance with its terms.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

11. Western Resources, Inc.

[Docket No. ER95-847-000]

    Take notice that on March 31, 1995, Western Resources, Inc. (WRI), 
tendered for filing a proposed change to its Federal Energy Regulatory 
Commission Electric Rate Schedule No. 242. WRI states the purpose of 
the change is to provide generation deferral service to the City of 
Ellinwood. The change is proposed to become effective June 1, 1995.
    Copies of the filing were served upon the City of Ellinwood and the 
Kansas Corporation Commission.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

12. Maine Public Service Company

[Docket No. ER95-851-000]

    Take notice that on March 31, 1995, Maine Public Service Company 
(MPS), tendered for filing a modification to its FERC Electric Tariff, 
Original Volume No. 1, Power Sales Tariff. Specifically, MPS proposes 
to modify its rate schedule to allow for market pricing of sales from 
specific generating units as well as from system supply and to make 
various other minor changes. MPS proposes an effective date of June 1, 
1995.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice. [[Page 19245]] 

13. Tampa Electric Company

[Docket No. ER95-852-000]

    Take notice that on March 31, 1995, Tampa Electric Company (Tampa 
Electric), tendered for filing three agreements with the Reedy Creek 
Improvement District (RCID): (1) a new Contract for Interchange 
Service; (2) a Letter Agreement that amends an existing Letter of 
Commitment under interchange Service Schedule D; and (3) a Contract for 
the Sale and Purchase of Capacity and Energy. Tampa Electric requests 
that its existing interchange service schedules and letters of 
commitment be redesignated as supplements to the new Contract for 
Interchange Service.
    Tampa Electric proposes an effective date of June 1, 1995, for the 
tendered agreements and requested redesignations.
    Copies of the filing have been served on RCID and the Florida 
Public Service Commission.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.
14. Central Power and Light Company

[Docket No. ER95-853-000]

    Take notice that on March 31, 1995, Central Power and Light Company 
(CPL), tendered for filing a Coordination Sales Tariff. Under the 
Coordination Sales Tariff, CPL will make Economy Energy, Short-Term 
Power and Energy, General Purpose Energy and Emergency Energy Service 
available to customers upon mutual agreement. CPL simultaneously 
submitted for filing seven unexecuted Service Agreements establishing 
Houston Lighting & Power Company (HL&P), Lower Colorado River Authority 
(LCRA), Medina Electric Cooperative, Inc. (Medina), South Texas 
Electric Cooperative, Inc. (STEC), Southwestern Electric Service 
Company (SESCO), Texas Municipal Power Pool (TMPP), and Texas Utilities 
Electric Company (TU Electric) as customers under the terms of the CST-
1 Tariff.
    CPL has asked for expedited consideration and waiver of the 
Commission's notice requirements to the extent necessary to permit an 
effective date of April 1, 1995. Copies of this filing were served on 
HL&P, LCRA, Medina, STEC, SESCO, TMPP and TU Electric and the Public 
Utilities Commission of Texas and are available for public inspection 
at CPL's offices in Corpus Christi, Texas.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

15. Kentucky Utilities Company

[Docket No. ER95-854-000]

    Take notice that on March 31, 1995, Kentucky Utilities Company 
(KU), filed a transmission services tariff and a power sales services 
tariff and several revisions to its interconnection agreements. KU 
states that the purpose of the filings is to authorize transmission 
services over the KU transmission system and to effect market-based 
rates for its off-system power and energy sales.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

16. Northeast Utilities Service Company

[Docket No. ER95-855-000]

    Take notice that on April 3, 1995, Northeast Utilities Service 
Company (NUSCO), tendered for filing, a Service Agreement to provide 
non-firm transmission service to Citizens Lehman Power Sales (Citizens) 
under the NU System Companies' Transmission Service Tariff No. 2.
    NUSCO states that a copy of this filing has been mailed to 
Citizens.
    NUSCO requests that the Service Agreement become effective sixty 
(60) days after receipt of this filing by the Commission.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

17. Black Hills Corporation

[Docket No. ER95-856-000]

    Take notice that on March 31, 1995, Black Hills Corporation, which 
operates its electric utility business under the assumed name of Black 
Hills Power and Light Company (Black Hills), tendered for filing an 
executed form service agreement with Enron Power Marketing, Inc.
    Copies of the filing were provided to the regulatory commission of 
each of the states of Montana, South Dakota, and Wyoming.
    Black Hills has requested that further notice requirement be waived 
and the tariff and executed service agreements be allowed to become 
effective April 1, 1995.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

18. Southern California Edison Company

[Docket No. ER95-857-000]

    Take notice that on April 3, 1995, Southern California Edison 
Company tendered for filing a supplemental agreement, associated 
procedure and letter agreement to the 1990 Integrated Operations 
Agreement with the City of Banning (Banning), Commission Rate Schedule 
No. 248.
    The supplemental agreement, procedure and letter agreement 
establish the terms and conditions for the integration of Replacement 
Capacity Resources purchased by Banning under the Conformed Western 
Systems Power Pool Agreement. Edison is requesting waiver of the 
Commission's 60-day notice requirements and is requesting an effective 
date of March 27, 1995.
    Copies of this filing were served upon the Public Utilities 
Commission of the State of California and all interested parties.
    Comment date: April 26, 1995, in accordance with Standard Paragraph 
E at the end of this notice.

19. Interstate Power Company

[Docket No. ES95-28-000]

    Take notice that on April 6, 1995, Interstate Power Company filed 
an application under Sec. 204 of the Federal Power Act seeking 
authorization to issue up to $70 million of short-term debt on or 
before December 31, 1996, with a final maturity date not later than 
December 31, 1997.
    Comment date: May 5, 1995, in accordance with Standard Paragraph E 
at the end of this notice.

Standard Paragraphs

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 825 North Capitol Street, N.E., Washington, D.C. 
20426, in accordance with Rules 211 and 214 of the Commission's Rules 
of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
motions or protests should be filed on or before the comment date. 
Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of this filing are on file with the 
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 95-9366 Filed 4-14-95; 8:45 am]