[Federal Register Volume 60, Number 23 (Friday, February 3, 1995)]
[Rules and Regulations]
[Pages 6657-6658]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-2707]



=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
18 CFR Part 157
[Docket No. RM81-19-000]

Project Cost and Annual Limits

Issued: January 31, 1995

AGENCY : Federal Energy Regulatory Commission.

ACTION : Final rule.

-----------------------------------------------------------------------

SUMMARY: Pursuant to the authority delegated by 18 CFR 375.307(e)(1), 
the Director of the Office of Pipeline Regulation computes and 
publishes the project cost and annual limits specified in Table I of 
Sec. 157.208(d) and Table II of Sec. 157.215(a) for each calendar year.

EFFECTIVE DATE: January 1, 1995.

FOR FURTHER INFORMATION CONTACT: Martin A. Burless, Jr., Chief, Branch 
I, Division of Pipeline Certificates, OPR (202) 208-0581.

SUPPLEMENTARY INFORMATION:

Publication of Project Cost Limits Under Blanket Certificates

Order of the Director, OPR
    Section 157.208(d) of the Commission's Regulations provides for 
project cost limits applicable to construction, acquisition, operation 
and miscellaneous rearrangement of facilities (Table I) authorized 
under the blanket certificate procedure (Order No. 234, 19 FERC 
61,216). Section 157.215(a) specifies the calendar year dollar limit 
which may be expended on underground storage testing and development 
(Table II) authorized under the blanket certificate. Section 157.208(d) 
requires that the ``limits specified in Tables I and II shall be 
adjusted each calendar year to reflect the `GNP implicit price 
deflator' published by the Department of Commerce for the previous 
calendar year.''
    Pursuant to Sec. 375.307(e)(1) of the Commission's Regulations, the 
authority for the publication of such cost limits, as adjusted for 
inflation, is delegated to [[Page 6658]] the Director of the Office of 
Pipeline Regulation. The cost limits for calendar years 1982 through 
1995, as published in Table I of Sec. 157.208(d) and Table II of 
Sec. 157.215(a), are hereby issued.
    Note that these inflation adjustments are based on the Gross 
Domestic Product (GDP) Implicit Price Deflator rather than the Gross 
National Product (GNP) Implicit Price Deflator, which is not yet 
available for 1994. The Commerce Department advises that in recent 
years the annual change has been virtually the same for both indices. 
Further adjustments will be made, if necessary.

List of Subjects in 18 CFR Part 157

    Natural gas.
Robert J. Cupina,
Deputy Director, Office of Pipeline Regulation.
    Accordingly, 18 CFR Part 157 is amended as follows:

PART 157--[AMENDED]

    1. The authority citation for Part 157 continues to read as 
follows:

    Authority: 15 U.S.C. 717-717w, 3301-3432; 42 U.S.C. 7101-7352.


Sec. 157.208  [Amended]

    2. Table I in Sec. 157.208(d) is revised to read as follows:


Sec. 157.208  Construction, acquisition, operation, and miscellaneous 
rearrangement of facilities.

* * * * *
    (d) * * *

                                 Table I                                
------------------------------------------------------------------------
                                                       Limit            
                                         -------------------------------
                  Year                      Automobile     Prior notice 
                                          projected cost  projected cost
                                          limit (col. 1)  limit (col. 2)
------------------------------------------------------------------------
1982....................................      $4,200,000     $12,000,000
1983....................................       4,500,000      12,800,000
1984....................................       4,700,000      13,300,000
1985....................................       4,900,000      13,800,000
1986....................................       5,100,000      14,300,000
1987....................................       5,200,000      14,700,000
1988....................................       5,400,000      15,100,000
1989....................................       5,600,000      15,600,000
1990....................................       5,800,000      16,000,000
1991....................................       6,000,000      16,700,000
1992....................................       6,200,000      17,300,000
1993....................................       6,400,000      17,700,000
1994....................................       6,600,000      18,100,000
1995....................................       6,700,000      18,400,000
------------------------------------------------------------------------

* * * * *


Sec. 157.215  [Amended]

    3. Table II in Sec. 157.215(a) is revised to read as follows:


Sec. 157.215  Underground storage testing and development.

    (a) * * *

                                Table II                                
------------------------------------------------------------------------
                          Year                                 Limit    
------------------------------------------------------------------------
1982....................................................      $2,700,000
1983....................................................       2,900,000
1984....................................................       3,000,000
1985....................................................       3,100,000
1986....................................................       3,200,000
1987....................................................       3,300,000
1988....................................................       3,400,000
1989....................................................       3,500,000
1990....................................................       3,600,000
1991....................................................       3,800,000
1992....................................................       3,900,000
1993....................................................       4,000,000
1994....................................................       4,100,000
1995....................................................       4,200,000
------------------------------------------------------------------------

* * * * *
[FR Doc. 95-2707 Filed 2-2-95; 8:45 am]
BILLING CODE 6717-01-P