DEPARTMENT OF ENERGY
[Docket No. PR95-2-000]

 

Southeastern Natural Gas Co.; Notice of Petition for Rate 
Approval

November 29, 1994.
    Take notice that on November 22, 1994, Southeastern Natural Gas 
Company (Southeastern) filed pursuant to section 284.123(b)(2) of the 
Commission's Regulations, a petition for rate approval requesting that 
the Commission approve as fair and equitable rates for firm 
transportation service consisting of a demand charge of $4.15 per MMBtu 
and a commodity charge of 0.006 cents per MMBtu and a rate of $0.143 
per MMBtu for interruptible transportation performed under section 
311(a)(2) of the Natural Gas Policy Act of 1978 (NGPA). Southeastern 
also proposes to impose a shrinkage charge of 1.0% for section 311 
services.
    Southeastern states that it is an interstate pipeline within the 
meaning of section 2(16) of the NGPA and it owns and operates an 
intrastate pipeline system in the State of Ohio. Southeastern proposes 
an effective date of November 23, 1994.
    Pursuant to section 284.123(b)(2)(ii), if the Commission does not 
act within 150 days of the filing date, the rates will be deemed to be 
fair and equitable and not in excess of an amount which interstate 
pipelines would be permitted to charge for similar transportation 
service. The Commission may, prior to the expiration of the 150-day 
period, extend the time for action or institute a proceeding to afford 
parties an opportunity for written comments and for the oral 
presentation of views, data, and arguments.
    Any person desiring to participate in this rate proceeding must 
file a motion to intervene in accordance with sections 385.211 and 
385.214 of the Commission's Rules of Practice and Procedures. All 
motions must be filed with the Secretary of the Commission on or before 
December 13, 1994. The petition for rate approval is on file with the 
Commission and is available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 94-29752 Filed 12-2-94; 8:45 am]
BILLING CODE 6717-01-M