DEPARTMENT OF ENERGY
[Docket No. CP95-59-000]

 

El Paso Natural Gas Co.; Notice of Request Under Blanket 
Authorization

November 9, 1994.
    Take notice that on November 4, 1994, El Paso Natural Gas Company 
(El Paso), P.O. Box 1492, El Paso, Texas 79978, filed in Docket No. 
CP95-59-000 a request pursuant to Sections 157.205 and 157.212 of the 
Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 
157.212) for authorization to construct and operate a delivery point in 
Yavapai County, Arizona for Citizens Utilities Company (Citizens) under 
El Paso's blanket certificate issued in Docket No. CP82-435-000 
pursuant to Section 7 of the Natural Gas Act, all as more fully set 
forth in the request that is on file with the Commission and open to 
public inspection.
    El Paso proposes to construct and operate a new delivery point on 
the 20-inch Maricopa County Line to permit the firm transportation and 
delivery of natural gas to Citizen's residential and commercial 
requirements in and near the City of Prescott, Arizona.
    El Paso says that the proposed delivery to Citizens will be 
accomplished without deteriment or disadvantage to El Paso's other 
customers and that upon receipt of the requested authorization it will 
amend Exhibit B of the Transportation and Service Agreement between El 
Paso and Citizens (dated August 28, 1991; initial transportation report 
filed October 29, 1991 in Docket No. ST92-371-000).
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Sec. 157.205 of the 
Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the 
request. If no protest is filed within the time allowed therefor, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 94-28212 Filed 11-15-94; 8:45 am]
BILLING CODE 6717-01-M