NUCLEAR REGULATORY COMMISSION
 

Duke Power Co.; Consideration of Issuance of Amendments to 
Facility Operating Licenses, Proposed No Significant Hazards 
Consideration Determination, and Opportunity for a Hearing

[Docket Nos. 50-369 and 50-370]
    The U.S. Nuclear Regulatory Commission (the Commission) is 
considering issuance of amendments to Facility Operating License No. 
NPF-9 and Facility Operating License No. NPF-17 issued to Duke Power 
Company (the licensee) for operation of the McGuire Nuclear Station, 
Units 1 and 2, located in Mecklenberg County, North Carolina.
    The proposed amendments would change the Technical Specifications 
to increase Main Steam and Pressurizer Code Safety Valve Setpoint 
Tolerances.
    Before issuance of the proposed license amendment, the Commission 
will have made findings required by the Atomic Energy Act of 1954, as 
amended (the Act) and the Commission's regulations.
    The Commission has made a proposed determination that the amendment 
request involves no significant hazards consideration. Under the 
Commission's regulations in 10 CFR 50.92, this means that operation of 
the facility in accordance with the proposed amendment would not (1) 
involve a significant increase in the probability or consequences of an 
accident previously evaluated; or (2) create the possibility of a new 
or different kind of accident from any accident previously evaluated; 
or (3) involve a significant reduction in a margin of safety. As 
required by 10 CFR 50.91(a), the licensee has provided its analysis of 
the issue of no significant hazards consideration, which is presented 
below:

    The proposed amendment will not result in a significant increase 
in the probability or consequences of any previously analyzed 
accident. The valve lift setting is challenged only after a 
transient has been initiated and is not a contributor to the 
probability of any transient or accident. The transients which 
involve pressure increases which would potentially challenge the 
safety valves have been analyzed to determine the consequences of 
delayed or premature valve actuation at the extremes of the new 
setpoint tolerances. These analyses show that all applicable 
acceptance criteria are met using the wider tolerances.
    The proposed amendment will not result in the creation of any 
new accident not previously evaluated. As noted above, the setpoint 
tolerance only affects the time at which the safety valve opens 
following or during a transient, and is not a contributor to the 
probability of an accident.
    The proposed amendment will not result in a significant decrease 
in a margin of safety. The limiting transient in each accident 
category has been analyzed to determine the affect of the change in 
lift setpoint tolerance on the transient. In each case, the results 
of the analyses met all applicable criteria.
    Bases on the above, it is conclude that no significant hazard 
considerations exist.

    The NRC staff has reviewed the licensee's analysis and, based on 
this review, it appears that the three standards of 10 CFR 50.92(c) are 
satisfied. Therefore, the NRC staff proposes to determine that the 
amendment request involves no significant hazards consideration.
    The Commission is seeking public comments on this proposed 
determination. Any comments received within 30 days after the date of 
publication of this notice will be considered in making any final 
determination.
    Normally, the Commission will not issue the amendment until the 
expiration of the 30-day notice period. However, should circumstances 
change during the notice period such that failure to act in a timely 
way would result, for example, in derating or shutdown of the facility, 
the Commission may issue the license amendment before the expiration of 
the 30-day notice period, provided that its final determination is that 
the amendment involves no significant hazards consideration. The final 
determination will consider all public and State comments received. 
Should the Commission take this action, it will publish in the Federal 
Register a notice of issuance and provide for opportunity for a hearing 
after issuance. The Commission expects that the need to take this 
action will occur very infrequently.
    Written comments may be submitted by mail to the Rules Review and 
Directives Branch, Division of Freedom of Information and Publications 
Services, Office of Administration, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555, and should cite the publication date and page 
number of this Federal Register notice. Written comments may also be 
delivered to Room 6D22, Two White Flint North, 11555 Rockville Pike, 
Rockville, Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. 
Copies of written comments received may be examined at the NRC Public 
Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC 
20555.
    The filing of requests for hearing and petitions for leave to 
intervene is discussed below.
    By July 21, 1994, the licensee may file a request for a hearing 
with respect to issuance of the amendment to the subject facility 
operating license and any person whose interest may be affected by this 
proceeding and who wishes to participate as a party in the proceeding 
must file a written request for a hearing and a petition for leave to 
intervene. Requests for a hearing and a petition for leave to intervene 
shall be filed in accordance with the Commission's ``Rules of Practice 
for Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested 
persons should consult a current copy of 10 CFR 2.714 which is 
available at the Commission's Public Document Room, the Gelman 
Building, 2120 L Street, NW., Washington, DC 20555 and at a local 
public document room located at Atkins Library, University of North 
Carolina, Charlotte (UNCC Station), North Carolina 28223. If a request 
for a hearing or petition for leave to intervene is filed by the above 
date, the Commission or an Atomic Safety and Licensing Board, 
designated by the Commission or by the Chairman of the Atomic Safety 
and Licensing Board Panel, will rule on the request and/or petition; 
and the Secretary or the designated Atomic Safety and Licensing Board 
will issue a notice of hearing or an appropriate order. As required by 
10 CFR 2.714, a petition for leave to intervene shall set forth with 
particularity the interest of the petitioner in the proceeding, and how 
that interest may be affected by the results of the proceeding. The 
petition should specifically explain the reasons why intervention 
should be permitted with particular reference to the following factors: 
(1) The nature of the petitioner's right under the Act to be made party 
to the proceeding; (2) the nature and extent of the petitioner's 
property, financial, or other interest in the proceeding; and (3) the 
possible effect of any order which may be entered in the proceeding on 
the petitioner's interest. The petition should also identify the 
specific aspect(s) of the subject matter of the proceeding as to which 
petitioner wishes to intervene. Any person who has filed a petition for 
leave to intervene or who has been admitted as a party may amend the 
petition without requesting leave of the Board up to 15 days prior to 
the first prehearing conference scheduled in the proceeding, but such 
an amended petition must satisfy the specificity requirements described 
above.
    Not later than 15 days prior to the first prehearing conference 
scheduled in the proceeding, a petitioner shall file a supplement to 
the petition to intervene which must include a list of the contentions 
which are sought to be litigated in the matter. Each contention must 
consist of a specific statement of the issue of law or fact to be 
raised or controverted. In addition, the petitioner shall provide a 
brief explanation of the bases of the contention and a concise 
statement of the alleged facts or expert opinion which support the 
contention and on which the petitioner intends to rely in proving the 
contention at the hearing. The petitioner must also provide references 
to those specific sources and documents of which the petitioner is 
aware and on which the petitioner intends to rely to establish those 
facts or expert opinion. Petitioner must provide sufficient information 
to show that a genuine dispute exists with the applicant on a material 
issue of law or fact. Contentions shall be limited to matters within 
the scope of the amendment under consideration. The contention must be 
one which, if proven, would entitle the petitioner to relief. A 
petitioner who fails to file such a supplement which satisfies these 
requirements with respect to at least one contention will not be 
permitted to participate as a party.
    Those permitted to intervene become parties to the proceeding, 
subject to any limitations in the order granting leave to intervene, 
and have the opportunity to participate fully in the conduct of the 
hearing, including the opportunity to present evidence and cross-
examine witnesses.
    If a hearing is requested, the Commission will make a final 
determination on the issue of no significant hazards consideration. The 
final determination will serve to decide when the hearing is held.
    If the final determination is that the amendment request involves 
no significant hazards consideration, the Commission may issue the 
amendment and make it immediately effective, notwithstanding the 
request for a hearing. Any hearing held would take place after issuance 
of the amendment.
    If the final determination is that the amendment request involves a 
significant hazards consideration, any hearing held would take place 
before the issuance of any amendment. A request for a hearing or a 
petition for leave to intervene must be filed with the Secretary of the 
Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555, 
Attention: Docketing and Services Branch, or may be delivered to the 
Commission's Public Document Room, the Gelman Building, 2120 L Street, 
NW., Washington, DC 20555, by the above date. Where petitions are filed 
during the last 10 days of the notice period, it is requested that the 
petitioner promptly so inform the Commission by a toll-free telephone 
call to Western Union at 1-(800) 248-5100 (in Missouri 1-(800) 342-
6700). The Western Union operator should be given Datagram 
Identification Number N1023 and the following message addressed to 
David B. Matthews petitioner's name and telephone number, date petition 
was mailed, plant name, and publication date and page number of this 
Federal Register notice. A copy of the petition should also be sent to 
the Office of the General Counsel, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555, and to Mr. Albert Carr, Duke Power Company, 422 
South Church Street, Charlotte, North Carolina 28242, attorney for the 
licensee.
    Nontimely filings of petitions for leave to intervene, amended 
petitions, supplemental petitions and/or requests for hearing will not 
be entertained absent a determination by the Commission, the presiding 
officer or the presiding Atomic Safety and Licensing Board that the 
petition and/or request should be granted based upon a balancing of the 
factors specified in 10 CFR 2.714(a)(1)(i)-(v) and 2.714(d).
    For further details with respect to this action, see the 
application for amendments dated May 5, 1994, as supplemented June 13, 
1994, which are available for public inspection at the Commission's 
Public Document Room, the Gelman Building, 2120 L Street, NW., 
Washington, DC 20555 and at the local public document room located at 
Atkins Library, University of North Carolina, Charlotte (UNCC Station), 
North Carolina 28223.

    Dated at Rockville, Maryland, this 15th day of June 1994.

    For the Nuclear Regulatory Commission.
Victor Nerses,
Project Manager, Project Directorate II-3, Division of Reactor 
Projects-I/II, Office of Nuclear Reactor Regulation.
[FR Doc. 94-15023 Filed 6-20-94; 8:45 am]