[From the U.S. Government Printing Office, www.gpo.gov]
PLANNING FOR THE IMPACTS OF GUAM ENERGY FACILITY EXPANSION A PRELIMINARY ASSESSMENT COASTAL MANAGEMENT PROGRAM BUREAU OF PLANNING GOVERNMENT OF GUAM sp, W@ 1w, IRV, AGANA GUAM PREPARED BY, WALTER F. PINCKERT AND ASSOCIATES ENGINEERS AND CONSULTANTS - AGANA,GUAM TJ I NOVEMBER 1978 163.25 G8 P-61 1978 I Ax 09 This study was funded in part by a grant from the- U.S. Department of Commerce, Office of Coastal Zone Management, Washington, D.C. I- @. I-S I I I I I I P\ I ""n I rl@@ I ll-@ I r@ I % 1 @21 b 'A N I@z I I .91 Table of Contents Page List of Figures . . . . . . . . . . . . . . . . . . . . . . ... . . . iii List of Tables . . . . . I. . . . . .. . . . . . . . . . . . . . . . . 1v Chapter I INTRODUCTION A. The Program . . . . . . . . . . . . . . . . . . . . B. Guam Program Objectives .. . . . . . . . . . . . . . .1 C, Methodology . . .. . . . . . . . . . . . . . . . . 2 D.. Scope . . . . . . . . . . . . . . . . . . . . . . . 3 EXISTING SYSTEMS AND FUTURE DEVELOPMENTS A. Production Facilities . . . . . . . . . . . . . . . 8 B. The Distribution System . . . . . . . . . . . . . . 15 C. The Refinery . . . . . . . . . . . . . . . . . . . 21 D. Bulk Storage . . . . . . . . . . . . . . . . . . . 24 SELECTED IMPACTS OF ENERGY FACILITIES A. Thermal . . . . . . . . . . . . . . . . . . . . . . 39 B. Erosion and Sedimentation . . . . . . . . . . . . . 47 C. Oil Pollution . . . . . . . . . . . . . . . . . . . 52 0. Dredging and Filling . . . . . . . . . . . . . . . 57 E. Economic/Social Impacts . . . . . . . . ... . . . . 59 F. Visual Impacts . . . . . . . . . . . . . . . . . . 62 IV MITIGATION MEASURES FOR IMAJOR ENVIRONMENTAL IMPACTS A. Thermal Ef-l"luent . . . . . . . . . . . . ... . . . 65 B. S02 Removal . . . . . . . . . . . . . . . . . . . . 75 i Table of Contents Chapter Page V MEASURING THE IMPACTS; A METHODOLOGY FOR CEIP ENERGY FACILITY ASSESSMENT A. Economic Impacts . . . . . . . . . . . . . . . . . . 87 B. Environmental Planning Factors . . . . . . . . . . . 91 C. Social Impacts . . . . . . . . . . . . . . . . . . . 100 VI REGULATORY CONSIDERATIONS A. Overview . . . . . ... . . . . . . . . . . . . . . . 104 B. Air Quality . . . . .. . . . o . . . ... . . . . . . 106 C. Water Quality . . . . . . . . . . . . . . . . . . . 108 VII GENERAL CONCLUSIONS,-CEI MATRIX, FUNDING RECOMMENDATIONS A. General Concl usions . . . ... . . . . . . . . . . . 114 B. CEI Matrix . . . . . . . . . . . . . . . . . . . . . 114 C. Funding Recommendations . . . . . . . . . . . . . . 116 Bibliography . . . . . . . . . . . . . . . . . . . . ... . . . . . . . 124 APPENDICES 1. Central Terminal Station (CTS): OTEC-Ongoing Studies 130 2. Islandwide Power System - Approximate Averages for Peak Demand (KW), 1971-1978 . . . . . . . . . 140 3. Maps - Power Hardening . . . . . . . . . . . . . . . 145 4. Federal Participants in the Corps of Engineers Permit Review Process . . . . . . . . . . .. . 150 5. CEIP Interviews . . . . . . . . . . : * * I * * * 1 154 6. Letters and Data 8heet Sent to Interviewees . . . . 159 List of Figures Figure Page 1. Major Energy Facilities, Apra Harbor and Vicinity . . . . . 6 2. GORCO - Block Flow Diagram . . . . . . . . . . ... ... . . 22 3. Future Location, GIAT Fuel Storage . . . . . . . .. . . . . 37 4. Tanguisson SSP Thermal Plume . . . . . . . . . . . . . . . 37 5. Piti Channels . . . . . . . . . . . . . . . . . . . . . . . 42 6. West Piti Say . . . . . . . . . . . . . . . o . . . . . . . 43 7. Guam Average SO 2 Emissions . . . . . . . . . . . . . . . . 51 8. Guam Average NO 2 Emissions . . . . ... . . . . . . . . . . 51 9. Guam Average Particulate Concentrations o . ... . . . . 51 10. Wet Type Mechanical Draft Cooling Tower Schematic o 67 11. Dry.Type Mechanical Draft Cooling Tower (Colorado) . . . . 69 12. Major Process Variations for Use of Lime or Limestone for Removal of SO' for Stack Gases . . . . . . . . . . . . 83 2 List of Tables Table Page 1. Existing Generation Capacity . . . . . . . . . . . . . .. . 9 2. Available Power for Future Land Growth . . . . . . . . . . 10 3. Approximate Peak Demand Fluctuations, 1971-1978 12 4. Figuring New Plant Capacity . . . . . . . . . . . . . ... 13 5. Summary of Pole Hardening . . . . . . . . . . . . . . . . 16 6. Summary of Proposed Distribution Facilities . . . . . . . 20 7. Summary of GORCO Refinery Production Capacity . . . . . . 21 S. Summary of Esso Bulk Tankage . . . . . . . . . . . . . 25 9. Summary of Mobil Bulk Tankage . . . . . . . . . . . . . . 28 10. Summary of GPA Bulk Tankage . . ... . . . . . . . . . . . 31 ii. GORCO Crude and Product Bulk Storage Facilities 33 12. Product Flow - Major GORCO-Pipelines . . . . . ... . . . . 34 13. Effluent and Related Data Cabras and Piti SSP . . . . . 41 14. Tanguisson SSP Data . . . . . . . . . . . . . . . . . . .. 45 is. Sedimentation Impact on Coral Species Diversity . . . . . 48 16. Approximate Composition #T6 Residual Fuel Oil . . . . . . . 48 17. Summary Guam Ambient Air Quality Standards 50 18. S02 Episode Frequency Based on Wind Rose Data . . . . . . 51 19. Latest Summary of Port Oil Transfer Operations . . . . . . 52 20. A Selection of SO, Control Methods . . . . . . . . . . . . 82 21. Recreational and Historic Resources Potenti.ally Subject to Energy Facility Expansion . . . . . . . . ... . . . . . 97 22. CEIP Funding Matrix . . . . . . . . . . . . . . . . . . . 115 23. Approximate Cost Estimates for Selected Public Facilities. 119 1v I I I I I I I I. I I.. Introduction I I * I I I I 'A 1. Introduction A. The Program The Coastal Energy Impact Program was created by amend- ments to the Coastal Zone Management Act (CZMA) of 1972 and signed into law July 26, 1976. The purpose of the-CEIP program is to '-'provide grants and credit assistance to Coastal States and communities to help.them deal with the impacts of coastal energy development." (FR 43-37, 2/23/76) Guam, by virtue of having an active program under the CZMA, qualified as a recipient for funding under Section 308(C) of the Act for the purpose of Planning for the Consequences of Energy Facilities. Such grants shall be used for the study of, and planning for any economic, social, or environmental consequence which has occurr 'ed, is occurring, or is likely to occur as a result of the siting, construction, expansion or operation of such new or expanded energy facilities. (Sec. 308(C) CZMA) B. Guam ProgramObjectives 1) Examine selected impacts o.f energy facilities upon the community; 2) Determine immediate and in-place plans for expansion of existing energy facilities and the probable impacts of such expansion; 3) Discuss, as far as possible, projected plans for expected development of new energy facilities and the probable impacts of such expansion; 1 4) Develop method for evaluation of major impacts from new or expanded energy facilities; 5) Generally discuss the pertinent sections of the regu- latory process relative to the expansion and impacts of existing and devel.opment of new energy facilities; and 6) Recommend strategies available under CEIP for ob taining further federal funding. C. Methodology Evaluation of energy facility expansion was based on a range of."decision making" factors. Information available indi- cates that expansion of energy related facilities will occur in the.near future. These include electrical generating unit(s), the size of which will depend on load projection estimates, expansion of refinery capacity for production and storage, the establishment of a la-rg er petroleum reserve capacity for the island, signi-_ ficant upgrading of transmission lines, and retirement of the remaining 11.5 MW units at the Piti steam power plant and the pow er barge "Inductance." Other aspects of energy deyelopment are not as certain. For example, the development of an exten- sive Central' Terminal Station facility (CTS) has been proposed as has the development of an "alternative" power production method utilizing Ocean Thermal Energy Conversion (OTEC) prin- ciples rather than oil fired steam plants. Enlargement of off- loading, and storage facilities for the GORCO refinery as well as Mobil and Esso facilities are possible, but not certain as to timing. 2 Discussions with individuals involved with the develop- ment as well as assessment of resultant impacts provide the foundation for this study, while review of numerous scientific, economic, and social documents provide the depth. Such a wide range of considerations preclude an exhaus- tive examination of any individual project, however, sufficient detail is provided to construct policy decisions regarding the advisability or inadvisability of further investigation of a given course of action. In addition to impacts of energy facility development, the regulatory fr amework relative to Guam's' resources is dis- cussed. The thrust of present energy development must result in an accept able resolution of seemingly conflicting national and local goals: economic growth for maintenance of an accep- table living standard; conservation of scarce natural resources for future generations; reduced dependance upon foreign petro- leum resources, and e nvironmental protection, particularly of coastal waters. 0. Scope Three statements of local and national policy set the limits to this study: Agencies should "include in the decision-making process appropriate and careful consideration of all environmental effects of proposed actions ... (and to) avoid or minimize adverse effects of proposed actions and restore or enhance environ- mental qua-lity-as much as possible .... 11 Fed. Reg. Vol 40 7#72 @16815 Section 6.100 re National Environmental Policy 'Act of 1969 3 "It is ... the public polic y of Guam ... that a high quality environment be maintained at all times ... and that environmental degradation of land, water, and air... should not be allowed." P.L. 11-91 GEPA Enabling Legislation "The national objective of attaining a greater degree of energy self-sufficiency would be advanced by providing Federal financial assistance to meet.state, and local needs resulting from new or expanded energy activity in or on the coastal zone.11 CZMA Amendments of 1976 P.L. 94-370 Section 302(i) Congressional Findings Guam is faced with An especially difficult resolution of apparent conflict between those policies calling for a mini- mization of adverse enviro nmental impacts and those recognizing the need to expand energy facilities. Many persons feel that national policy and resultant local policy has been set without special consideration being given to the many attributes which set Guam apart from the 'average' locality for which regulations were developed. Others think that extenuating circumstances are not suf- ficient to warrant special consideration, and which, in the long-run,theoretically pay for themselves. It is not an impos- sible task to arrive at solutions satisfying the major part of the range of policy directives. The need for electric power, however generated, is not going to disappear. It will increase and will be more expen- sive as new technologies are developed and older technologies are required to adhere to "accepted" environmental standards. 4 This study examines the need for major energy facility And development, the means for achieving those needs and the factors necessary for arriving at a selection of alternatives providing the best mi x of sol uti ons to meet envi ronmental , eco- nomic and social considerations. - This study is concerned only with major facility expan- sion. For example, the various diesel power plants smaller than 5 MW are not considered to have significant negative impacts and are not addressed except for inclusion in calculating system- expansion. Generally, the diesels are small,.uneconomical, high maintenance, and used only in times of forced outages. 5 1 OTEC Sit-eT IMobil Tank Fa I rm rare vL.LA.4:c Cabras SSP Fuel Tank- "N ----- -- JR:L@j PO@qer"Plant CORCO Ofiloa@di 9 lFacilities iti Channe T uelin2 Wh a.--.(-,: s Pi eline C ssin .3 i @np Gorc tel Ea s emten'It Figure Maiar Energy Facilities,' Apra Harbor and Vicinity -S'C- 8 L of qO00,vec y of 4 A too V77 P Y $1 WT. TCINQ Lot-.439 508-43 Acres GORCO ICA -Existing.Systems and Future Developments II. Existing Systems and Future Developments A. Production Facilities The greatest impact of energy facilities on Guam to date has been from generating units. *The newest additions to the Guam power system were the two 66 MW Cabras units which do not meet the definition of new or expanded facilities acco-rding to the July 26, 1976 date established CEIP rule and reg-ulations. 1. Existing Plant Capability Progressions developed in the Bureau of Planning's 1976- 1977 report.Future Pow er Production and Transmission Alterna- tives, (Pinckert-1977) provided estima.tes."for the optimized capa- bility of new plants to meet future demand. For the purposes of this study, more exact definition of ass-umptions was prepared with cooperation from the Guam Power Authority. The capacity of existing pl ant was stated as "available for normal operationsil rather than nameplate capacity to accurately -reflect capability of the system to.meet demand. Several Navy diesel units pre- viously not indicated were included as available for emergency purpos-es even though their reliability is questionable. 8 Tabl e I : Existing Generation Capabili'ty I MW 1 Megawa'tt = 1000 Kilowatts UNIT NAMEPLATE AVAILABLE FO R CAPACITY NORMAL OPERATION Cabras SSP 132 MW 132 MW 2x66MW* units Tanquisson SSP 53.0 MW 50.5 MW 2x26.5MW units Piti SSP 67.0. MW 44 MW 2722-9 _Wu n i- t s 2xll.5MW units Inductance Power Barge 28 MW 25 MW lX78MW Steam Unit Tamuning Di'esels 8 MW 6 MW 4xZ.OMW units Dede-do Di'esels 8 MW 6 MW 4x2.OMW units Navy Diesels N/A 10 MW System Total: 273.5 MW A further breakdown of system capability makes allowance for main- tenance and forced outages, while current demand has been revised upward from 150 to 160MW to reflect latest demand statistics available. 9 Table 2: Mai ntenance Outage Plus Forced Outage, Minus Current Demand Equals Available Power for Fu- ture Load. Growth System Total 273.5 MW Less: Maintenance Outage (Largest Unit) 66 MW Less: Forced Outage (Next Largest Unit) 25 MW Total Rema ining 182.5 MW Less: Current Demand 160 MW Remainder to Meet Projected Load Growth 22.5 MW A derived equation will express the 'relationship between expected increase in demand, current demand, and the tine period of that inc.rease. The variable here is the rate of demand increas e. La- ter discussion of actual peak load demand will narrow the range of these growth figures: 160 (I+y)n 160 = 22.5 where 160 = Current Demand y= rate of demand increase (..1%-6%) - n = tine period of increase 22.5 =*MW currently remaining to meet projected growth solving for n (,+Y)n 1 .40625 nlog("t-t.y) log 1.140625 n log 1.140625 log (1+Y-T It was assumed that y would not exceed overall population growth; therefore, the range for this annual increase was set between 1%, 10 and 6%, and the equa tion solved for n. The result is the time at which the 22.5MW available for projected growth will have reached the point (0) where a new plant should go on stream. (y) Assumed Annual Demand Increase 6% 5% 4.5% 4% 3.5% 3% 2% 1.5% 1% (n) Number of Years When New Plant Should Go On Line 2.3 2.7 3.0 3.4 3.8 4.5 6.6 8 13 2. Annual Demand Increase Narrowing the__Choice Demand increase is based on peak demand. GPA maintains com- plete records of peak demand (See Appendix 2). Unfortunately, both the oi 1 embargo of 1973 - 1974 'and the devastating effects of Typhoon-Pamela in May of 1976 make estimates of annual peak demand increase difficult. The embargo, w,hile actually lowering KW demand for several mo*nths, had the overall impact of slowing increase in demand for an extended period. This would account for the rather slow growth in 1974 and 1975. Typhoon Pamela, an event which experts predict on the average of one in seven years, devastated large segmen ts of the distribution system as well as causing damage to generation equipment. While Guam can expect continuous and ra- ther- steep increases'in the cost. of fuel oil over the coming years, natural disaster occ.urances should not be depended on to keep demand growth down. Recent transmission system improvements will improve the system's ability to withstand typhoon damage. 11 Table 3 Approximate Peak Demand Fluctuations - 1971 - 1978 Source: GPA % INCREASE OR YEAR PEAK DEMAND-MW DECREASE FROM PRECE-DING YEAR 1971 123 1972 .131 6.6 19731 142. 8.5 1974 145 1.8 19752 148 1.9 1976 142 (3.7) 19773 148 4.0 1978 155 4.7 '71 '78 Avg. increase 3.4% 171 178 Total increase 26.0% Eliminating Boom and Bust Years 3.8% Assumption 3.0% l.- Direct effects of Arab oil embargo appear to have affected KW demand significanlty f or nearly. three -months, and reduced demand growth for much longer. 2. Typhoon Pamela in May, 1976, substantially re- duc-ed demand for nearly three months. 3. FY 1978 figures put actual demand at 150 MW, month- ly, averages significantly higher than previous years. Although 160 was used in above equation 155 seems to be a reasonable estimate for FY 19;8. Reserve rat.io should remain at approximately the largest plus the next largest unit as insurance against load-shedding, or service interruption during emergencies. (66 + 25 = 91 MW) 12 With these new assumptions, the capacity of the new plant can be estimated: * NPC = 160 (j+ ,y)n + RP + RG - EP = 160 (.I4y)n + 36.5 + 91 - 273.5 where * NPC = new plant capability (MW) 160 existing demand (.MW) y % of annual demand increase n time period of increase Plus a period of 5 years when an additional plant must be added RP Retired Plant RG Reserve Generation EP Existing Plant Table 4- Figurinq'New Plant Capability y n VALUES NEW PLANT (in percent) (in years) SUBSTITUTED CAPABILITY 6 2.3+5 160(l.07)7.3 -146 99MW 5 2.7+5 160(1.05)7 87_ 146 87MW 4.5 2.7+5 160(l.0451 -146 82MW 4 3.0+5 160(1.04)8.4@146 76MW 3.5 3.8+5 160(l .035@ 8 -146 71MW 3- 4.5+5 1600.03) -5-146 66MW 2 6.6+5 160(l.U2'1 ' b-146 55MW 1.5@ .8.8+5 160(l .015 13 8-146 5OMW 1 13.0+5 160(1.01)@8 -146 45MW 3- Conclusion New plant capacity of similar size to one of the Cabras units should immediately enter preliminary planning stages. 13 4. Other Factors Consi'dered While planners and economists do not foresee a boom of 68- 73 proportions, the general feeling given in recent months is cautiously optimistic that Guam can expect a general rise in economic activity in the next 3-5 years. While national econo- mists predict-longer term strength of the US economy with some immediate problems, expected population growth together with a slowly recovering econom y should keep power demand increases in the 2.8 to 3.5% range in the next 3 to 5 years. Recent publica- tion of the Gross Island Product of Guam (Calendar Years 1972- 1976), the fi.rst such study avail able, tends to support this con- clusion. The GIP, an overall indicator of the production of goods and services on the island is an excellent measuring-stick for the level of Guam's economic activity. Despite a decline from the 1973 and 1975 highs, the 1976 GIP reflects steadily in- creasing Pe*rsonal Consumption and Government expenditures, which make up the major demand sectors on the GIP product side. It is unfortunate that the 1977 figures could not be included in the study since the post-typhoon investment sector has improved con- siderably, as well as the value of Travel and Tourism to offset increasing deficits in the net exports sector of trades and ser - vices. Although.correlation is qu estionable, it is interesting to note that overall peak electric demand only declined between FY 1975 and 1976 (Typhoon Pamela), regaining the 1975 level in 1977, and is projected to reach the highest levels to date in 1978. Population will also continue to increase although at a de- clining rate. The Bureau of Planning's population estimates, 14 show, conservatively, an approximate doubling of the civilian population by the year 2000, with a military-p lus-dependants figure remaining steady at approximately 22,000; the total for 2000 being in the 170,000 range. The 1970 census mid-range pro- jection was considerably higher with growth rate decreasing from a 1970-1975 high of 4.48% to 2.56% in the mid-1900's, with a to- tal population of 240,000 projected for 2000. As major new generating capacity is added, units in the pre- sent system already*near or past economic operation should be re- tired. This comprises some 51MW of generating capacity including Piti units- 2 and 3, and the power barge Inductance. B. The Distribution. System 1. Existing System and Present Activities Like the i.sland generating plant, distribution re- sponsibility is also part of the Navy/GPA power pool agreement. Navy with only 25% ofthe system's generating capacity, controls the load-dispatching of power to island customers. GPA is ex- pected to assume this responsibility in the near future.. The distribution system s major elements include 115 KV and 34.5 KV lines connecting the various generating units with 115/34.5 KV substations, transformers, and 13.8 KV lines- from which individual facilities (homes, stores, etc.) draw power. Present Activity - Typhoon Restoration Primary and secondary transmission facilities were severely damaged by Typhoon Pamela. Most activity presently.ta- king place on the lines (poles) is part of-the typhoon restoration , ission f projects. The main objective of restoration of transn a- cilities is to increase resistance and to minimize damage in fu- ture natural disasters. Approximately $24 million will be expen- ded in the next 2-3 years specifically for replacing damaged por- tions of the power and telephone -system grids with typhoon-resis- tant, components. This "pole hardening" effort is being coordi- nated through the Officer in Charge of Construction (OICC) of the US Navy. Table 5 : Summary of Pole Hardening by Contract Package, Fund Distri- bution, Party Responsibility and Approximate Cost (In Millions of $) RES PONS I BLE, NAVY NAVY GOVGUAM AF AF AF APPROXIMATE TOTAL COST PARTY P115 P118 F-255 (X) (Y (Z) DT. CONTRACT AWARD Contract Pkg. and Number J Package (0207) X X X. X $9.991; 9/77 J Package change orders n/a. n/a n/a n./a--- n/a J-2 Package (0280) X 4.285; 9/78 115 KV Package (0273) X CX) 4,984; 6/78 34.5/13.8 KV Pkg. (0228) W +3.000; Est 12/78 Note:(X)indicates major responsibility Total Project Cost: and funding level +$24 million X indicates secondary participa- (includes cha-nge orders and other tion and funding level miscellaneous costs) 16 Summary of Contract Pack ages - ongoing pole-hardening projects "J" Package - (Total Cost: $9.991 million) 13.8 KV Lines GPA Agana Heights substation' to Fena pump station Marine Drive to NSO fuel farm Pit! substation to Naval Hospital Agana substation to Barrigada Route 8 to Barrigada booster 34.5 KV Lines Orote power plant to Piti substation Marine Drive to Polaris Point Piti substation to Adelup Point Adelup Point to Agana substation Agana substation to Marbo substation Marbo subs*tation to Andersen and Harmon substations Marbo substation to Harmon substation "J-2" Package (Total Cost: $4.285 million) 13.8 KV Lines Orote power plant to SRF substation Jct. Rts 5 and 12 to Bona Springs Marine Drive to Black oil tank farm Marine Drive to cold storage substation Nimitz substation to Adelup reservoir Route 3 to FAA Potts Junction to Ritidian Point Andersen gate to ammo. gate 34.5 KV Lines Orote power plant to cold storage substation (Cancelled) Marbo substation to Andersen substation Summary of "115 KV Package (GovGuam-GPA) (Total Cost Est..: $2-3 million) 34.5 KV Lines Tamuning substation to Marine Drive Barrigada substation to NAS (.Rt 10/8 Jct) substation (Cancelled) Y-Sengsong to Potts Junction (Cancelled) Apra Heights substation to Inarajan Apra Heights substation to "'til funds run out" 17 13.8 KV Lines Agana substation to Jct. Routes 10 and 4 Route 10 to Barrigada substation Medical Center of the Marianas to Tamuning substation Guam Memorial Hospital to Tamuning substation San Vitores Road to northern half of Marine Drive Y-Sengsong Road CJct. at 3 and 2) to Jct. at.R@ute 3 (S. ee Appendix 3, for maps.) Discussion The pole-hardenin g projects are by far. the most extensive activity occurring in any sector of the power.grid. By defini- tion of "new or expanded coastal energy activity", pole-hardening can be considered an "energy facility whose ... replacement, in whole or pa rt, takes place after July 26, 1976." (931.20-FR43- 37 at 7753) However, when the definition of significant ly af- fected" (931.14) is applied, there appears to be little or no additional demand placed on the island's public facilities in terms-of natural resources, or o verall economic and social sectors. Since the vast majority of the poles and lines are located on existi,ng rights-of-way, and the action of pole-hardening is essentially the replacement of wood Ctermite-pronel poles with prestressed concrete, the negative aspect is simply that the ex- isting objectionable blockage of land-to-sea views will be perma- nent. -It is doubtful, in our opinion, if sufficient argument could be put forth that "public access" in a visual sense has, therefore, been additionally impaired. Economic assessment of .this impact, in terms of dollar value, would be an interesting but possibly non-productive exercise. Following initial damage assessment from Pamela, the feasi- bility of underground line-placement was discussed with the Navy. 18 Conclusions based on a 1OX cost differential and the fact that typhoon funds could not be used for "upgrading" facilities seemed to preclude underground placement unless the Government of Guam could foot the entire bill. A conservative summary for "coastal lines" whose path had unique features worthy of protection would include: J package 35.4 KV line from the cold storage substation to Agana substation GPA package 115 KV line from the Agana substation to Harmon substation GPA package 13.8 KV lines for: MCM, GMH and San Vi- tores The Government did not have., at that time nor presently, the funds to even consider such an undertaking. 2. Future Develoement - GPA Proposed Major Capital Improvements, Transmission A number of improvements and additions to present distribution facilities have been proposed. As most of these are tentative plans, GPA officials are not able to predict which alternatives will be adopted. As presented, the list proposes some $45 million for transmission facil ities over the next 22 years. Develop- ments up to 1986 are the most important given expiration date of CEIP, and totals approximately $21.5 million. 19 Lack of Available Studies This listing was obtained from the Gov Guam Bu- reau of Planning. The only readily available written verifica- tion of such projects appears on "systems" maps in GPA annual re- ports, and GPA map "Feeder Line G-PA-Distribution, Island-wide Power System," dated January 1, 1976. Commenting on the impacts of projects based on such information is s peculative at best. Table 6 Summary of Proposed Distribution Facilities GPA (START) YEAR FACILITY PROPOSAL ESTIMATED COST 0978 dollars) 1979 Dededo substation $ 80,000 *Dispatcher Control Center 2,000,000 1980 Pipeline (stor *age-Cabras Plant 100,000 **Tumon substation C22.4 MVA) 280,000 Apra substation (10/12.5 MVA) 40,000 Talofofo substation (10/12.5 MVA) 46,000 1981 34.5 KV Talofofo-Merizo Line 500,000 Merizo substation (10/12.5 MVA) 650,000 1982 *Adelup substation C10/12.5 MVA) 650,000 *Pagat substation C10/12.5 MVA) 6509'000 1983 34. 5 KV Pagat-Marbo Line 300,000 *Agat substation (80 MVA) 2,500,000 1984 *115 KV Agat-Apra Jct Loop Lines 2,500,000 *Talofofo substation (50MVA) 2@0009000 1985 *115 KV Apra Jct-Talofofo Lines 32000,,000 1986 *Chalan Pago substation 700,000 *34.5/13.8 Chalan Pago/Barrigada Lines 1,500,000 *Yigo substation (112 MVA) 4,000,000 Notes: MVA = MegaVolt Amperes = 1000 (KVA Source: GPA or KiloVolt Amperes) = Total cost distributed over or more years; indicated year shows start of project = Includes cost of temporary facility 20 C The Refinery The GORCO refinery is located on an irregularly shaped piece of land of 508.43 acres in Agat. Rated at 29,500 bbl/day until 1977, recent completion of the JP-5 (commercial jet fuel) unit raised the capacity of the refinery to approximately 35,000 bbl/day. Table 7 Summary of GORCO Refinery Production Capacity-Approximate CAPACITY PRODUCT (bbl/day) LPG 700 JP-4 12,000 JP_5 5,000 Diesel 6,000 Residual 12,000 Asphalt 250 f Source; GORCO The crude fractioner is the refinery's basic unit. Crude is hea- ted and then passed through the fractioner where it reaches boil- ing temperature.. At various temperatures and pressures, lighter products are drawn off (LPG, distillates), the residual and as- phalt being drawn out the bottom. After passing through several treatment processes, the final products are piped to respective storage facilities. The existing plant does not have a cracking unit and does not produce gasoline. No firm details were available on specific expansion plans. Officials did mention that the Small Business Administra- tion raised the ceil ing on the definition of "small refiner" to 50,000 bbl/day from 30,000 bbl/day; therefore, it could be ex- 21 pected that'GORCO will continue '%-.o expand to 40.,000.bbl/day, in the near future, and eventually to 50,000 bbl/day. Figure. G L) AM OIL ANO REFINING COMPANY, INC, BLOCK FLOW DIAGRAM Source: GORCO FUEL GAS VAPORIZER T-;CATi.,jG LPG 700 E/O PG ST RA,3a 4 &16 S TA 8 (L I Z E (Turbine Fuel JP-4 12, 000 EI0 STORA 1'0 V. a 4uuu Ail) CRUDE C14ARGE DISTILLATE (Diesel) C..RUDE @5.ooo 8/0 CRUOE DISTILLAT.71 STORAGE STORAGE 1,200 me CRUDe FRACTIONATOR RESIDUAL FUEL OIL 12';000- 8/0 FUEL OIL Treating phalt STORAGC 250 B/D -0-skstora&e 760 %IFJ F :L GAS Ur 1@1 @R LPG q@'T if; C A T 1=11 G 0@ 7 0 EI/O L 22 Present demands on public facilities are small, although GORCO is the private sector's largest power user. Ci- ting water availability as a major constraint to expansion, the general manager was uncertain as to how the problem will be solved. One well is presently in operation on the premises from which water is treated, used in the refining process, cleaned and aerated, then flows into the Navy sewer system. One 24" Navy-owned water main provides* water for the fire-protection grid. Although the Public Utility Agency of Guam (under coopera- tive use agreement with the Navy) receives payment from GORCO for piped water used, the line itself is Navy property, as is the source of the water, Fena Reservoir. Discussions with Navy officials indicated that they eventually see an end to this cooperative agreement and that "PUAG should meet the civilian community's water needs" and not the Navy. 'Some 2.5 million gallons per day are soTd to PUAG by the Navy. The bulk of this is for the Agat-Santa Rita area where the refinery is located. It appeare d that the Navy fore- sees a continuation of a split system whereby Navy will meet its own needs. Officials did not care to elaborate on potential water-sources and referred to current studies by Barrett and As- sociates as perhaps providing answers. Fire protection at the GORCO refinery is felt to be sufficient on-site although coordination is maintained with GovGuam and military units. Foam or light water capability, as well as the firewater loop and sprinkler systems are GORCO-run. Most employees of the plant have been extensively trained in 23 fire fighting methods. The foam unit trailer has a 1,500.gp-m rating and all light product tanks have foain-protection capa- bilities. Insurance requirements, it was stated, are exceedingly vigorous and no additional burdens on local fire facilities were seen as.resulting from expansion plans. The GORCO facility is extremely well screened from public rights-of-way, and does not impinge upon surrounding land uses., Atmospheric emissions are well within federal EPA and lo- cal standards. The general manager did not foresee any problems with future expans ion meeting environmental protection standards, except in the case of wetlands on the property which comprise a high eprcentage of the 20% of GORCO property considered "unde- velopable". D. Bulk Storage Alarge percentage of bulk storage tanks are located on federal p.roperty. According to military sources, it is not ex- pected that expansion of military bulk storage facilities will place additional demands on Guam's public facilities. Bulk storage facilities where major expansion might place additional demands on Gov Guam include: - Esso Eastern Inc. CCabras Island@ - Mobil Petroleum Co., Inc. (Cabras Island@ - Guam Oil and Refining Co. (Cabr-as Island and AgatJ - Guam Power Authority CCabras Island, Tanguisson) - Guam International Airport Terminal (Tamuni.ng) 24 1. Esso Eastern Inc. - Existing Facilities Esso tanks are located on approximately 6 acres of Tand leased from the Guam Economic Development Authority. Table 8:- Summary of Esso Bulk Tankage CAPACITY TANK GALLONS BARRELS PRODUCT 1,389,631 33,086 Gasoline MOGAS97 #2 1,200,521 28,584 Gasoline 91 Octane Unleaded #3 283,872 6,759 LSADO (low sulphur Diesel #4 .2,131597 50,752 Jet Fuel AA-1 #5 2,130,932 50,736 Jet Fuel AA-1 #6 406,905 9,688 Gasoline 91 Octane Unleaded Source: Esso East.Inc. Esso does not own or control off-loading facili- ties but works under cooperative agreement with GORCO. In the event of tanker scheduling conflicts, Esso maintains a secondary agreement for use of Mobil Petroleum Company's facilities adja- cent to the Mobil storage tanks. 25 2. Esso - Future Development Of the approximately 6 acres being leased from GEDA, 3 are in use, 1 has been subleased to GORCO deballasting facilities, and 2. remain available for future expansion. This appears adequate for the foreseeable future. Dema-nd for jet fuel is the major component of Esso operations with gasoline a distant second. Alternately known as AA-1, Jet A-1 JP-1, or DPK Cdual purpose kerosene), the Esso jet fuel bulk ta.nks were designed to serve more than existing demand. The TWA pullout from the Pacific area further decreased demand for jet fuel, and allows the present reserve margin to be sufficient for some-time. Recent discussions with CAB indicate that ad- ditional airline service for Guam appears to be possible in the near future. Should this occur, according to Esso's General Manager, it is certain that the demand f or jet fuel will in- crease significantly and most probably would mean the cons.truc- tion of an additional 50,000 bbl tank on unused portions of the Esso land-lease from GEDA. The primary public facility concern if this and other expansion should occur, should be fire protection, as the Government of Guam has no capability for dealing with oil or petroleum product fires. Of secondary concern relative to need- ed public facilities may be oil spill containment, where again GovGuam has no capability. In both cases,-it was evident that the Navy and Coast Guard would be heavily relied upon in the event of a disaster. 26 No problem was seen by the general manager inso- far as -meeting land-use and environmental r,.egulations for future facility development. As new facilities probably will be for bulk fuel storage, Federal Spill Prevention Control and Counter- measures (SPCC) as well as GEPA water quality standards can be easily met with present construction standards. Dikes surround- ing the tanks are designed at 120% of tank capacity, and sho-uld be sufficient to contain a rupture. Recently installed on the volatil e fuel tanks (gasolinel, the so-called "ultra-float" sys- tem provides a floating seal which prevents vapor build-up be- tween the top of the liquid and the tank roof, thereby eliminat- ing a potential fire hazard. 27 3. Mobil Petroleum Company, Inc. Mobil's bulk tankage is located on approximate- ly 11 acres of land on Cabras Island, 5 of which are under long-term lease from Guam Economic Development Authority (on harbor side of road), the balance of 6 acres is leased on a 5-year renewable-lease from the U. S. Navy. Table 9: Summary of Mobil Bulk Tankage - Cabras Island TANK CAPACITY NUMBER GALLONS BARRELS PRODUCT 3 756,000. 18,000 Auto Diesel Oil 5 2,604,000 62,000 Premium Mogas 7 1,764,0.00 42,000 Jet A-1 8 1,314,600 31,300 Not in service 9 1,260,000 30,000 Diesel 10 1,764,000 42,000 Auto Diesel Oil 11 1,344,000 32,000 MP 12 6.30,000 15,000 Indust.Fuel Oil 13 126,000 3,000 Slop 14 315,000 7,500 Avgas (100/1310) 16 117,600 2,800 Asphalt S51 17 315,000 7,500 Asphalt AP-3 78 2,604,000 62,000 Unleaded mogas 19 2,604,000 62,000 Jet A-1 20** 1,764,000 42,000 MR Source: Mobil Petroleum Company, Inc. Missing numbers indicate tanks removed from service Tank 7120 replaced older tanks dismantled after typhoon damage (See Section 4). Offloading is carried out on the Mobil fueling pier near the tank farm. The pipelines are such that the products can be taken from or distributed to GORCO's and Navy's fuel piers as well as the GORCO refinery. Recently, over $100,000 was spent improving 28 the pier facility; however, no additional requirements were placed on public facilities. Permits were all reviewed and approved by the appropriate authorities. Mobil also leases and operates the present Guam Airport Authority's tank farm at the air terminal.. By agree- ment, Esso and SOCAL. al-so use the facility. The present ar- rangement is a lease agreement with Guam Airport Authority subject to renewal in March of 1979. 4. Mobil' - Future Development The Cabras Island terminal will not be under- going any major development in the next 5-7 years., according to the.general manager. Up to 1986, the only new facilities will-be replacements for those tanks which have ended their practical service life. The Marianas Yacht Club will be allowed to con- tinue operations on Mobil land until such time as they are able to find a suitable per-manent site. When tank #20 was built,. to replace typhoon-damaged tanks, certain waivers were made with adjoining-GORCO and Esso facilities, to allow construction near the latter's property lines such.that the Yacht Club would not be disturbed. Mobil does not see any great change in leasing and development policies until the final decision is made about relocation o.f the present ammo wharf at Hotel Wharf, as all the Mobil facilities are within the e-xisting blast zone. Mob.il's present facility at the'airport will be 29 dismantled at the time that the GAA-owned and Lockheed-run facility comes on li ne. Mobil and Esso will simply Provide the fuel to the Airport Authority. The.general-manager did not foresee 'any signi- ficant additional demands on public facilities as a result of Mobil activities. This could be somewhat qualified by'disc,us- sion of Government of Guam responsibilities, if and when the ammo wharf is moved. It.was felt that present fire protection and oil-spill contingency.plans are more than adequate, given the exemplary manner in which.present operations by all petro leum importers are carried out. Again, it was stated that Mobil facilities meet all. federal standards and that no problem is seen with meet- ing land-use and environmental requirements in tank placement or pier maintenance activities. S. GPA - Existin2 Facilittes GPA's major bulk storage facilities are locatednear the eastern end of Cabras Island. Two major tanks are loca- ted on land acquired from the Navy; the land has ample room for two additional tanks of the same size. Two day-storage tanks located on the Cabras Power Plant site were originally designed for Residual Fuel Oil #6- for burning in the Cabras boilers. Upon completion of the two large storage tanks which can feed the boilers of both the Navy Piti plant and the' Cabras plant directly, one of the day-storage tanks is used for the storage of low-sulphur fuel in the event of an "emergency 30 episode This "episodic contingency plan" was initiated as an interim measure to satisfy EPA air-pollution, State Imple- mentation Plan (SIP). Table lb:. Summary of GPA Bulk Tankage CAPACITY TANK GALLONS BARRELS PRODUCT #1 Cabras 4202000 10,000 #6 Residual Fuel Oil #2 Cabras 920,000 10 000 Low Sulphur #3 Cabras 1T,281,200 268,600. #6 Residual #4 Cabras 11,281,200 268,600 #6 Residual #5 Tanguisson 4201.000 TO,000 #6 Residual 6. GPA Future Development Assuming that no major new generating facilities are developed except at the Cabras Island site, two additional tanks will be needed at the time a 4th Cabras unit goes into operation. This date is uncertain at present, but will unques- tionably be post-1986. Presently, the large storage tanks can be served directly from GORCO's Agat ref inery or the GORCO fuel wharf. A pipeline is being considered in the near future which would con- nect the large storage tanks directly to the Cabras boilers. An additional one or two tanks of the 10-20.,000 bbl. size are being considered for on-site storage of low-sulphur fuel. 31 New equipment including both pipelines and heat- ers may be-required if any of the.generation units are required to burn low sulphur fuel, or if the price of low sulphur fuel becomes,competitive with the price of mid-eastern crude. 7. GORCO - Exi-sting Bulk Storage and Pipel'i*ne Facilities Crude and-.product storage occupies the major part of the developed portion of Guam Oil and Refining Company's Agat complex. (See Table. 11 : GORCO Crude and Product Bul k Storage Facilities, which follows.) GORCO owns and maintains its own off loading fa- cilities on approximately 3 acres of GEDA-leased land to the com- mercial port. The fuel pier offloads 10-15 tankers in the 40- 80 thousand gross ton class, comprising 70-80% of the port tank- er's traffic. Esso maintains a joint use agreement with GORCO for the use of offloading facilities. GORCO is presently leas- ing the two large GPA storage tanks. Pipelines Although both Mobil and Esso facilities,can be serviced from the GORCO pipeline network, the main lines consist of two 24" and two 16" pipes which connect the fuel pier to the Agat refinery via the Piti channels, and Marine Drive easements. (Se e Figure 2 . ) I It is these lines which prevent development of the inner Piti. channels for a keelboat harbor-of-refuge or marina use, since at low tide only craft of shallow draft can safely pass over 32 Table 11: GORCO Crude and Product Bulk Storage Facilities TANK CAPACITY N'UMBER PRODUCT GALLONS BARRELS 12-1901 Crude 18,900,000 450,000 1902 Crude, 18,900,000 450,000 1903 Crude 12,600,000 300,000 1904 Diesel/Marine 12,600,000 300,000 1905 JP -4 8,400,000 200,000 1906 JP-4 8,400,000 200,000 1907 JP-4 .8,400,000 200,000 1,908 JP-4 2,310,000 55,000 1909 JP-4 2,310,000 55,000 1910 Residual Fuel Oil 1,680,000 40,000 1911 Residual Fuel Oil 1,680,000 40,000 1913 Crude/Turbine/Slop 840,000 20,000 1916 Distillate 42,000 -1,000 1919 Nayy Distillate 2,310 55 1922 JP-5 12,600,000 300,000 1923 Crude 12,600,000 300,000 1924 Jet A-1 2,100,000 50,000 1925 JP-5 2,100,000 50,000 1926 LPG 210,000 5,000 12-1204 A LPG 21,000 500 1204 B LPG 21,000 500 1204 C LPG 21,000 500 1927 OFM 840,000 20,000 1928 JP-5 1,260,000 30,000 1929 OFM 420,000 10,000 193.0 JP-5/DFM 420,000 10,000 1931 Naphtha 840,000 20,000 1917 Water 840,000 20,000 Approximate Total Tankage: 3,127,500 bbl. UNDER CONSTRUCTION 1932 Crude 21,000,000 500,000 1933 Crude 21,000,000 500,000 33 the crossing. At the time of construction, pipes adhered to all permit requirements according to the.general manager. Table 12: Product Flow -Major GORCO Pipe lin es APPROXIMATE LINE PRODUCT FLOW RATE* ROUTE (BBL/HR) 1. 2419 Crude. 3-12,000 Cabras-Refnry 2. 2411 RFO #6 7-12,000 Refnry-Cabras 3. 7611 JP-4 5,000 Refnry-NFD 4. 1611 Multi-Produ ct Varies All Points Pumping rate depends on capacity of ship's pumps 8. Expansion - Bulk Storage, Pipelines, Deballasting Bulk Storage No specific plans for major new expansion of GORCO bulk storage facilities are available at the present time. Two 500,000 bbl... storage tanks have received the necessary permits and construction is underway. GEPA records show GORCO permit applications for nine 500,000 barrel tanks dated 5/30/75. GORCO officials indi- cated this development was considered as a result of projected retirement,of aging storage facilities*on foreign soil including Japan and the Philippines. The project is still considered viable and may be revived in the next few years, although the 34 number of tanks may be reduced to six or less. App'ro-ximately 20% of GORCO's land is considered 7 unusable due to wetlands and steep slopes. Officials indicated that expansion mo,st probably will be within the ap.proximately 500 acres of GORCO land holdings. It is fairly certain that additional product tank- age will be increasing as refinery operations expand from the pre- sent 35,000 BPD capacity to 50,000 BPD in the not-distant fu ture. Specific plans are not available as to the nature of product tank- age expansion. P i p e 1 i n e s No specific plans are available for e_xpansion of pipelines. GORCO officials,.aware of impending EPA air-quality standards, are in discussion stages of a low-sulphur pipeline from the refinery to Cabras. Additionally, there is a possibi- lity of a pipeTine from Commercial Port to the proposed GIAT storage facilities. Planning for these.developments is in pre- liminary stages. The two 24" and 16" lines crossing the Piti channels will probably have to be moved in the future, according to GORCO officials. It is uncertain as to who will pay for this rather expensive undertaking, since, as mentioned, construction was in accordance with federal and loca'l requirements in 1969. 'Deba I las@ting As the refinery's capacity increases, there will be an additional demand for deballasting facilities to accommo- 35 date additional tanker traffic. Each tanker arrives with 40- 50,.000 bbl. of'salt water in the holds; this must-be processed and discharged "free of oil" or less than 10 parts per'million. Existing deballasting facilities are being.up- graded, however, for additio nal land will be required. GORCO would prefer acquiring Navy land for this purpose, but is also planning for a location adjacent to the large GPA storage tanks. One preliminary plan ind-icates an impounding basin and setting ba- sin on GPA property behind Tank ..'rl. Area. required is about 1.5 times the size ofthe diked area of one .268,600 bbl. storage tank. A lagoon rather than tank system is envisioned. 9. GIAT Guam International Air-Terminal_, New Tankage As part or air-terminal improvements, new-bulk storage facilities will be located just off Route 16.. Exist-- ing tankage will be dismantled at the time the Lockheed-super vised project is completed. Tankage for the GIAT-owned site is presently designed for 3 x 10,00.0 bbl. tanks and one 15,000 bbl. tank. It was the opinion of the Lockheed consultant that faci- lities including water, fire-protection, and public safety were sufficient as the storage area is a self-contained unit a nd must meet stringent federal regulations. 36 pigure j_: Future L@cation, GTAT Fuel ra e 7 7 GO @ 1 4 /1// -7 7 KEY-.- -7 APRON RELATMME LEASE LOTS. AIRPORT--RELATED USE'LEASE LOTS. AIRPORT AND CCMNITY RELATED USE LEASE LOTS. FUEL STORAGE AND DELIVERY LEASE LOIS. Source:GIAT Master 1E ROUTE IOA AND ROUTE 16. Plan, 1977 AIRPORT SERVICE ROAD. UTILITIES, SLOPE AND DRAINAGE EASEMEru5; % . ....... Z -A t 'I Source: Uog Marine Laboratory Figuri@ 4 Diagrammatic Representation of Tanguisson SPP Thermal Plume 37 0 I I I I I I I I I III. Selected impacts. ofIEnergy Facilities I I I I I I I I I I III. Selected Impacts o-f Energy Facilities A. Thermal Studies carried out before, during and after construc- tion And subsequent operation of both the Tanguisson and Cabras steam power plants indicate the specific nature and extent of thermal effluent 'on two rather different near-shore and rela- tively shallow marine environments. Results conclusively show that thermal effluent as a result of power plant operations has altered many aspects of the marine environment. The studies' recognition of the importance of biological variability resulted in detailed observations of the "before environment," thereby narrowing the cause of observed changes to power plant operation. 1 Piti Channels While overall' generalizations are sometimes mis- leading, impact studies of thermal effluent in the Pit.i channel area seem to indicate that damage is confined to relatively restricte d, already greatly-altered areas (Amesbury et al, 1977), and have not been of*major significance in terms of a continuous and increasing threat to the overall quality of the marine envir- onment within Apra Harbor. Construction activities associated with the building of Cabras Power Plant have probably had a more serious and lasting impact to date than have plant operations. (Marsh, Chernin, Doty, 1977) 39 the most serious recorded environmental effect ... was caused by unnecessary and careless operation of a bulldozer on the Piti Reef (Marsh, Doty, 1975) (Marsh, Gordon, 1974) It should also be noted that temperatures an Ti-dal Flat B exceeded 340C over a wide area as was the case for Tidal Flat C. These high temperatures likely resulted from solar insolation rather than the influence of power plants. (Marsh, Doty, 1975) Power plants impose a more constant temperature on the outfall area than otherwise would occur. This more constant temperature is in the upper part of the natural range ... (Marsh, Gordon, 1974) Reinforcing 1975 observations - operations of the Cabras Plant were not expanding the areas enclosed within specific isotherms- beyond pre-existing con ditions, when onT the Piti Plant was operating. (Marsh, Doty, 1977) Piti channel and Commercia l.Port areas have greatly altered by dredging, land filling, and construction. (Pinckert, 1978) 40 Table 13: Effluent and Related Temperature Data'- Cabras and Piti SSP Plant Combined Effective Approx. Max. Delta T Actual Monthly Averag- Operating Capacity Effluent Flowl (Design)l Mean 2 Intake vs Outfall Temp. Temperature Piti 44. MW 64,000 gpm 5.6"C 30.8'OC 1.60C SSP (100F) (87.40F) (2.90F) Cabras 132. MW 120,000 gpm 5.6-8.30C 32.OOC 2.80C SSP (10-150F) (89.60F) (50F) Inner Channel Ambient Apra Tidal Flat Harbo@ Temp. TemperatureS3 Range Flat A 29.5-32.50C (85.1-90.5.'o F) Flat B [email protected] 27.2-29.40C (83.3-92.30F) (80.9-84.90F) 1. Marsh/Gordon (1974) 2. Marsh/Chernin/Doty (1977) Flat C 3. Marsh/Gordon (1973) 28-33.60C 4. Emery (1962) .(82.4-92.50F) 41 vACtiT SEAPLANE CLUB RAMP 0 1 2 3 4 5 CABRAS SCALE Im A 100) ISLAND COMMERCIAL, PORT A Oil 'k. Buoy BLACK.11 FACI LTY ACTUAL LOCATION OF BUOYS I & A OFF MAP BUOY REDA Buoy RED 4 CL ,UPPER pill C"A", 'K, A z LOqE,Vk TIDAL FLAT C > eORAL RY- ANNF I , _ 2,@ - Ir - - - -JQqRN W I CORAL TIDAL FLAT SEE 190 iwzr Figure 5: Major features of the area affected hy the effluents of the Piti and C Inputs of Iwater from the power plant outfalls ari--, indicated'by arrows. filled to provide the construction site for the Cabras Power Plant. pEEF 10"E ALGAL WEST- PITI E U: REEF UJ; COfAL ZONE FLAT LA: C, I AT/ A.RE rD CABRAS IIDW@ ISLAND I %A SAND & RUBBLE _.@: - ZONE 'D\V'C -11@ 4- IN. VO 4:r- .0r, P\,)tl -or,, REEF FLAT SANTOS CABRAS ISLA D PARK POWER PLANT to HOOV BEACH uso n PITI POWER PLANT 0 Figure 6 West Piti Bay showing th e major features in the area of the Piti and The location of the aamaged area was determined in conjunction.with 2. Cabras Island/Piti Channel Area Summary The sum total of the data r*eviewed seems to indi- cate that while the power plants certainly add a hazard in terms of increased temperature to the Piti Channel area: - the overall impact is not significantly greater than the impacts of natural solar insolation; and - the significance of the impacts are further reduced given the extreme alteration of the Piti Channels from past development; and - expected development to the west of the Piti Channels adjacent to the commercial port will continue to severely alter "natural" conditions of the area. - despite power pl.ant thermal intrusion, Piti Channels and lagoon frequently used recreationalareas for fishing, picnicking, and heavy weather boat anchor- age. Conclusions to the effect that "anything goes" inso- far as continued development of energy facilities on Cabras Island should not be infer-red here. It should be noted that the causeway built to the island obstructed the natural flow of water through the Tepungan Channel, thereby arti ficially estab- lishing an area subject to solar insolation to a greater degree. It was probably more coincidence that location of the power plants and their heat plumes took advantage of this situation whereby heate d effluent has a less-than-usual impact on. the environment. Given this situation together with expected devel- opment in the port area, it would.seem reasonable to conclude that future energy facilities would not significantly increase the present impacts. However, extreme care should be taken by the developer of future fac ilities not to exacerbate this mar- ginally acceptable situation. 44 3. The Tanguisson Experience Located on the north-east coast of Guam, the GPA/ Navy Tanguisson power plant has been under observation since operations commenced in October 1971 (unit #1) and December 1972 (unit Table 14: Tanquisson SSP Data* Capacity Approx. Max. Mean Intake Mean Outfall Mean Max. Reef Flat Ambient Ocean Effluent Flow Temp. Range Temp. Range Delta T Temp. Range Temp. Range 50.5 MW 35,000 gpm'' 26.9-29.511C 32.5-37.OOC 70C 30-330C 27.6-29.30C (80.4-85.10F) (90.5-98.60F) (12.60F) (86.0-91.40F) (81.7-84.7"F) *Note: Data from same sources a's Table 1. Unlike the Cabras Island/Piti Channel location, the Tanguisson plant was built directly adjacent to the narrow fringing reef and within a beach strand e nvironment. Thermal effluent has directly affected a sig nificant portion of reef. By c oincidence, during the period of June-September 1968 the coral-eating crown- of-thorns.starfish (Acanthaster Planci) devastated the area sea- ward of the. reef front zone killing over 95% of reef building corals. Thus, the study could not be based upon actual observed kill, but rather on observed re-growth patterns in effl.uent- affected vs. non-effluent *areas. The overall conclusion is that the Tanguisson thermal effluent is responsible'for the destruction of some 20,000 m2 of the coral reef commu*nity. While other factors such as biofouling treatment (since discontinued) played a part in initial biota damages, "There.is no doubt that the thermal effluent from the 45 Tanguisson power plant is responsible for the death of herma- typic (reef-building) corals along the reef margin," (Neudecker, 1976). Not limited to coral impacts, "Fishes that are charac- teristic of the reef flat (many are territorial species) aban- doned the plume area. The same was true for crustaceans and echinoderms." (Jones, et al, 1973). Generally speaking, upper tol erances for corals is 30' - 33C. At 4*C above summer ambient temperatures (28.5*C), eighteen species of reef corals died within 6 - 14 days, at VC above ambient, in 6 days or less. While corals are reset- tl.ing in the Aca.nthaster-dev astated areas outside ofthe tempera- ture plume, "...there is no evidence of coral resettlement in the reef margin area within the influence of the effluent." Neudecker (1976, 1977) specifically investigated the growth of coral transplants in and near Tanguisson effluent, as well as the effect of coral removal on the rest of the community. Con- clusions indicate that the obvious is true, "When corals die, many species closely associated with them either die or move to a more favorable area." (Neudecker, 1977). Furthermore, the long term possibility is that "...,biogeochemical and physical erosion ... will result on the reef platform opposite the power plant." (Jones, et al, 1973). The good news is that the area of kill does not appear to be expanding and is directly proportional to the generating capacity of the plant, and unless the generating capa- city is increased or additional toxic chemicals are introduced, the kill area should remain stable. (Neudecker, 1976). 46 Erosion and Sedi'mentatior, Effects of erosion and sedimentation are a constant threat with large scale onshore or nearshore energy facility development, particularly in areas having significant amounts of eroded and weathered volcanic overburden. The best example of such impacts, although not related to energy, was caused by improper and poorly timed site preparation on steep slopes of the Nimitz Hill housing estates. Resultant sedimentation caused a. massive coral kill in Agat Bay. Energy-related projects of similar and greater magnitude have been discussed, but no defi- nite plans are available. Several-studies are available addressing the impacts of siltation and sedimentation on the marine environment. The most recent, Sedimentation Studies at Fouha and Ylig Bay, (Randall, Birkland, 1978) was designed to scientifically assess the effects of sediments on reef systems.. The natural gradient of coral growth, was compared with the gradients of suspended sedimentation to determine a cause/effect relationship. Once gradient values are established, with further model develop- ment, they could be applied to different reef environments to predict sedimentation impacts due to increased input from land and coastal development. The following table is derived from the above study. 47 M Table 15: Summar y of Sedimentation Impacts on Coral Species Diversity INDICATORS EFFECT Time Area Sediment Number of Substrate Load Species Coverage 6 weeks 4.4 cm2 1 6 grams over 100 12 % 30 40 grams less than 10 2 % Source: (Randall, Birkland, 1978) In effect this study conclusively supported previous observations that,"alteration of coral diversity follows a simi- lar gradient of high to low levels of sedimentation ...... (Basline Study, p. 25). To date initial construction has had the greatest impact as far as site and surrounding area impacts. There is no record of continuing siltation or erosion caused by energy facility operation. B. Atmospheric Emissions l.. General Guam's major power plants use 7#6 Residual fuel oil for-firing boilers. Resultant emissions include sulfur oxide*s, carbon oxides, nitrogen oxides, and particulates. Table 16: Approximate Composition, 1#6 Residual Fuel Oil As Presently Fired Carbon 87 83 % Hydrogen 9.5 % Sulfur 2 2.5 % Ash .01 % Note: "Low Sulfur" crude - contains only trace sulfur. 48 The major concern on Guam is sulfur dioxide given its well documented impacts as a pollutant. Unfortunately for Guam, SO2 regulations are based for the most part on major population centers in the continental U.S. where sulfur oxide and other emissions directly and negatively affect people, buildings and biota surrounding the source. Except for infre- quent episodes, most S02 drifts with the prevailing winds over the ocean, falls into the water and is absorbed by natural pro- ces.ses. When prevailing winds direct S02 emissions toward popu- lated areas, the power plant contingency plan goes into effect based on sampling station readings inland from the Cabras lsla@d Plants. The boilers are switched to low sulfur fuel until the winds switch.to a more favorable direction. Under such a system, sul fur oxides have essentially no effect on Guam's envi ronment. Guam's standards are contained in the Guam Air Quality Implementation Plan which is currently under revision from 1974. NSPS or New Source Performance Standards apply to the Cabras Plant since construction began after August of 1971. New stacks for the Piti Plant are nearing completion which will exhaust gases at a higher level. Tanguisson seems to be accept- able'at present, pending outcome of enforcement discussions. 2. Emission Standards Pertinent standards include sulfur oxides, particu- late matter, and nitrogen oxides. 49 Table 17: Selective Summary of Guam's Ambient Air Quality Standards Indicators Sulfur Oxides Particulates Nitrogen Oxides Annual Mean 60mg/m3 (0.02ppm)2 60mg/m3 (0.02ppm) 100mg/m3 24 hr. max.1 365 (0.12ppm) (geometric mean) NA I hr. maxl 1300 (0.5ppm) NA NA I 4 hr. max 650 (0.25ppm) (8 hr) 360mg/m NA 1 Permitted once a year Source: GEPA 2 Micrograms per cubic meter PPM = parts per million During 1975 1977, the ambient level of sulfur oxides (measured in the vicinity of the Cabras and Piti plants) measured 13 micrograms/m3, far below the 60 micrograms/m3 National Standard' Nitrogen oxide concentrations are well within EPA standards a nd should remain so if the trend over the past 3 years contin-ues. Power plant.operations do not contribute signifi- cantly to the relatively.high particulate concentrations season- ably evident on Guam as 1AF6 RFO does not produc:e significant amounts of fly-ash or particulates. Of greater importance is the coral base of approximately 50% of Guam, and the fact that particulate readings are only taken in the area of intense particulate-producing activities. An extremely heavy concen- tration.of large, fast moving*trucks over roads in poor repair on coral-base Cabras Island.is probably the main producer of particulates. 50 Table 18: S09 EOi-@odd 'Frequency Based on Wind Rose Data Wind Wind Direction % of time Direction % of time (from) (from) N 1.4 S 2.7 NNW 1.2 SSE 3.9 NW .7 SE 7.9 WNW .7 ESE 21.0 V4 W .7 E 26.5 WSW .6 ENE 19.9 Sw .9 NE 7.4 SSW 1.7 NNE 2.4 Probable S02 Episode, 6.5% (US Navy) F-i-gure 7: Quam- Average @SO2 EMIAsions (EPA Requirement = 60 nij/=j,Xvg./yr. 40 Source: EPA w 30 20 10 (Qrtrs) 1 2 .3 4 1 2 3 4 1 2 3 4 M 1975 1976 1977 Figure 8: ..Guam-Average-NOy--Emissions- -MA-.Re-qu=e?nent-pp--100-.'mg/m3 Avg./yr. 20-- Source: EPA 10.- (Qrtrs.)l 2 3 4 1 2 3 4 1 2 3 4 Figure 9: Guam Average Particulate Concentrations (EPA Requirements - 60 mg/m-3 Avg./yr.) 03200 Source: EPA A 15JD 100 Source,* EPA 1-4 -w , a .'4 1 2 3 4 1 2 -3 (Qr-trs C. Oil Pollution 1. Off Loading Operations Tankers entering Apra are in the 100,000 DWT (dead weight ton) range or below given the anchorage's limited bottom depth, maneuvering room, facilities., and tankage requirements. Most tankers are in the 40-80,000 gross ton category. Approxi- mately 4 ships per week a n the long term average off load at GORCO, Mobil and Navy Facilities; 10-15 per month-(70-80%) are GORCO/Mobil tankers, the balance being Navy and ESSO. National figures of polluting incident s in and around U.S. waters indi- cate Guam spills totalled 216 barrels in 1977, too small an amount to contribute to a percentage of the national total. (U.S. Coast Guard, 1978). Table 19: Latest Summary of Port Oil Transfer Operations Period Barrels 1977 4th Quarter 6.7 million 1978 Ist Quarter 5.13 million 1978 2nd Quarter 5.6 million Source: U.S. Coast Guard Coast Guard figures show 111 ship transfers and 9 barge transfers (44,000 bbls) took place in the 2nd quarter 52 of 1978. These together with the 100-p-lus transfer operations in the first quarter of 1973 resulted in 12 very minor spills, most of which were simply sheens. The Apra Harbor marine environment has not been exposed to impacts of significant oil pollution. Bottom sedi- ments and marine organisms are free of petroleum derived hydro- carbons. 2. Spill Impact Tropical waters because of relatively constant stresses are more vulnerable to large-scale spills than temperate or arctic marine systems due to the latter's adaptability to change. A recent NOAA National Marine Fisheries Bulletin stated that while it is not possible to predict the environmental im- pact of a spill, se veral factors govern the overall impact: - type of oil spilled - how much - physiography of the area - weather conditions at the time - biota of the area - previous exposure of the area to oil - season - exposure to other pollutants - treatment of the spill A tanker grounding within the harbor would pro- bably be at low speed and would suggest that a maximum accident, the entire cargo being lost, probably would not occur. The physiography of the harbor is such that while several wetlands may be affected, bottom sediments are mostly unconsolidated and 53 not particularly rich with plants, clams, mollusks and other bottom dwellers. However, heavy oils or crude reaching the bottom would remain for an extremely long time, before natural oxidation occurred. Compared to the richness and diversity of other portions of*the fringing reef, Apra Harbor does not have exten- sive coral growth. Some of this has alre ady been exposed to significant amounts of sedimentation. The fact that the har- bor has not been exposed to large amounts of hydrocarbon pol- lutJon means that those organisms directly affected.would pro- bably be devastated. Depending on the location of the spill, prevailing winds from easterly directions would encourage suspended pol- lutants to move in the direction of the harbor mouth. As well as fouling bottoms and shorelines adjacent to and along the drift of a spill, prevailing northerly swells at the harbor mouth may result in additional heavy fouling a-t Orote Point. Surface movement away from the S'asa and Atantano River wetlands or the eastern end of the harbor would be aided by the "doni- nant westward outflow of water in the area on both ebb and flood tides." (Marsh et al , 1977 Estuaries are particularly susceptible to the impacts of oil pollution where the kiTling of bottom-dwelling plants and animals generally loosens bottom sediments causing both erosion and movement of the pollutant to new areas. Major effects of spills in other locations has been destruction of 54 bottom vegetation, wildlife and birds, foulin g of beaches, rocks, harbor facilities, moored boats and the devastation of biologically productive shallow water bottoms. Locally, im- pacts would not be critical once floating oil left the harbor and sank in the deep waters immediately adjacent to the harbor entrance. The deep ocean bott oms off the coast are not particu- larly suitable for marine resource exploitation, nor do they appear to pl ay a significant part in the maintenance of the shallower water biota. A port consultant stated that a large spill within the harbor could be more easily contained than in other locations since the inner harbor could be effectively separated from the outer harbor and that water turbulence would be minimal under normal conditions. If an incident could be dealt with in a relatively short period of time, much damage can be completely avoided. The Coast Guard, the Port Authority, and officials of Mobil, ESSO, GORCO, OPS and Navy feel that extensive dis- cussion of "maximum accident scenarios" such as these are slightly alarmist in nature. Even with substantially increased tanker traffic it was felt that traffic control measures, highly efficient inspection and 'supervisory operat.ions, the ability of the Coast Guard's contingency plan to deal with a spill situation, and the relative ease of spill containment in Apra Harbor significantly reduces the spectre of an all-out ecological disaster. 55 3. Oil Spill Contingency Plan The Marine Safety Office (MSO) located at the Commercial Port has recently completed drafting of Guam's Oil Spill Contingency Plan. The MSO, as established by Federal law, has authority vested in the Captain of the Port dealing with: - fire protection a.nd prevention - storage control - entry control tug standby - bi-annual ship inspections - yacht documentation - .1 i censi ng - charter boating. The contingency plan itself contains listings of all equipment available through private as well as Federal and local government sources and outlines procedures for noti- fication and mobilization of equipmen t and manpower in the case of a spill. The Coast Guard emphasized that the cleanup is the responsibil ity of the pollutor, and Coast Guard parti- cipation should not be in actual cleanup operations except under extraordinary circumstances, where the responsible party would be assessed for the costs. The Oil Spill contingency funds can be used for cleanup and prevention purposes pursuant to amendments to the Clean.Water Act, effective 28 December 1977. The Coast Guard estimated that in the event of a major spill the national regional strike force established under the Federal Water Pollution Control Act could be operating on Guam within 10 days. 56 Spill prevention regulations dealing primarily with vessels cover a range of potential pollution sources including hoses, drip pans, ship-to-shore communications, opera- tions manuals, ship transfer operations, investigations of haz- ardous substances and cargo sampling. No ship is allowed to offload until an inspection is completed . Proof of a valid insurance (FMC) certificate is mandatory- D Dredging and Filling .The best Guam documentation of energy-related dredging and filling activities is contained in Marsh and Go rdon's "Marine Environmental Effects of Dred ging and Power Plant Construction in Piti Bay and Piti Channel, Guam" (1974). Fur- ther study of major dredging/filling impacts has been carried out during construction of the Agana Boat Basin and Sewer Treatment'Plant, .the Northern District Wastewater Outfall, in small projects including OHL's dock/groin on Cocos Island, and various bridge construction activities. Review of these studies indicate: - area of impact is generally limited to t he area actually dredged and/or filled; - turbidity and sediments place a temporary stress on surrounding areas, but not necessarily lethal if, (a) reasonable precautions are taken and (b) natural flushing of the affected area is not interfered with; the use of silt screens and (when possible) operation timing to coincide with tidal and climatic condi- tions can reduce temporary stress significantly. 57 Other than damage caused by an errant bulldozer, "...the Piti reef flats which were disturbed by dredging in Tepungan Channel have returned more or less to their origi- nal state," and " ... most of the fine silt deposited on the reef flat has been now swept away, a nd the substrate appears much as it did before." (Marsh, Gordon, 1974). It appears that the major caveat to dredging and fil- ling operations is the necessity of the operation, and if necessary, the extent of the operation. As far as energy facilities are concerned, the record is good on both counts in addition to the fact that extensive new dredging and fil- ling operations of the marine environment do not appear immi- nent. Possible exceptions could be port expansion activi- ties which may include parts of the GORCO docking area, and additional outfall related work which could result from EPA actions requiring effluent control mitigation measures. Suf- ficient area adjacent to the existing Cabras Units Cbuilt on reclaimed.land) was provided through the foresight of the project engineer to avoid future dredging and filling activi- ties. Tepungan- Channel was al so designed to be able to serve additional plant capacity. Shoreline stabilization and channel maintenance on the Tanguisson plants did not cause long-term impacts outside of the actual construction area. Should GORCO or other entities decide the location of pipelines crossing the Piti Channels be altered, a dredging 58 will be required, but impacts should not be of major impor- tance given the already greatly altered (man-induced) marine environment. In conclusion, it appears that required dredging and filling operations directly related to energy facilities have been carried out in a fairly responsible manner, and.aside from one major avoidable incident, have not caused impacts greater than expected. E. Economic/Social Im2acts The economic and social impacts of availability'of a dependable source of electric power has been widespread and penetrating. A drastic change in the short run would be detri- mental to the island's lifestyle. Guam would be more susceptible to increasing costs of energy if it were not for the presence of the GORCO refinery on island. Without such a fa ci lity,' civilian supply of genera- ting plant fuel (Residual 71r6) and others would be more at the mercy of international marketplace fluctuations, as well as a good deaT higher in price and less-certain in availability. Operation of many projected bases of Guam's economy, (tourism, light manufacturing) are energy dependent with the possible exception of agriculture. Lifestyle, particularly in the area of hou sing and related domestic amenities, is increasing its dependence on electric consumption. Block con- crete houses with little emphasis on good insulation, natural 59 ventilation, and increasing reliance on total and constant air conditioning will hasten spending of larger proportions of disposable income on energy. It is true that a vigorous conservation program would slow the demand for power, and thereby postpone the need for future production facilities. This will call for programs stronger than public information. Even if recently passed National Energy Legislation does not provide adequate incentive for persons to conserve power and fuel consumption, the rising prices brought about by deregulation of petroleum product prices may force a change in attitudes. It is hoped by economists that price deregulation will make alternative energy sources more competitive with petroleum. How does all this affect Guam? Guam imports all of its petroleum, most of which comes from the Persian Gulf. Pro- jected energy facility expansion will continue to be based on petroleum unless a significantly increased effort on the part of Govern'ment of Guam is made to attract afternative power production methods such as OTEC and to strongly encourage con- servation practices. Studies carried out by Mobil and British Petroleum mark 1990 as the year when demand for crude begins to outstrip production. Only 12 years remains until that date, during the course of which Guam's population, industry and overall demand for power continue to rely on petroleum. Accor- ding to the Mobil study, desire of oil-exporting nations to hold production below capacity could advance the shortage era to 60 as early as the mid-1980's. (Petroleum Encyclopedia, 1977). Generating plants must be designed such that fuel supplies can be guaranteed for the life of the plant, usually 30 years. A Chase Manhattan Bank subsidiary predicted that world-wide petroleum consumption will grow at 3% per year, and starting in 1980 crude prices will grow at 2% faster than inflation and increase steadily in the 1980's as the world productive capacity is reached. Presently GORCO pays between $12.00 to $12.80 per barrel for Persian crude. This is up from $2.59 per barrel in January of 1973. Of equal concern has been the eroding position of the U.S. dollar as the oil-price yardstick. Abandonment of this could mean that OPEC countries may not even accept U.S. dollars as payment for oil, although Saudi Arabia has assured the U.S. that it will continue. The economics of Guam's industries and businesses must plan the continued escalation of energy costs, and the people. of Guam in their.'domestic situations must recognize that continued increases in power dependency, etc. may even- tually erode quality of life on the island. Recent GPA expansion plans indicate that all expansion will be self- financing, eg. long term bonds issued on the future-pay back of customers.. The penalties for an economy and social structure based on petroleum derived energy have been inter- woven -with Guam's relatively urbanized lifestyle. Unfortu- nately, these costs cannot be offset by the CEIP program as the 61 .burdens are not being caused by increasing costs of public facilities resulting from energy facility expansion, but by the very reliance on a diminishing resource in the fac e of a world-wide demand increase. F. Visual Impacts Like the countenance of an ugly duckling, th e appear- ance of most energy facil.ities appeals mostly to its creators. Power generating units are large and unattractive as are trans- mission lines and bulk storage tanks. Guam's master planning effort in land-use and parks and recreation have addressed loca- tional and profile considerations for energy facilit ies. With the possible exception of location of certain transmission lines, Guam's bulk storage, refining, and production facilities are fairly well separated from areas of highl y conflicting use. Even though the Cabras and Piti plants are highly visible, it is.an area which is primarily commercial/industrial in nature, and whose use has not significantly prevented multiple use and recreational use from occurring. A notable exception could be Bechtel's port master plan which placed a Cproposed) "boatel" within the property lines already designated for future e-xpan- sion of power-plant bulk storage facilities. Others include the placement of high visibi*lity transmission lines through the middle of residential and conservation (open space) areas, and the construct-ion of lines and access roads across wetlands. Often situations like this occur as a result of the lack of lead time-planning. 62 The GORCO refinery, even when expanded to its projec- ted 50,000 bpd size, is one of the best camouflaged operations on the island, and demonstrates the beneficial aspects of good siting, further wetland intrusion notwithstanding. Double rows of power poles on either side of Marine Drive are unfor- tunate visual blights, however, until some as yet undiscovered source can provide approximately 10 times the construction funds for underground pl acement, they will remain. Certain power personnel favor scattered power-pTant sites of the Tanguisson type as one solution to visual and locational difficulties, while others prefer location of pro- duction facilities in one spot with easy access to f'uel and support facilities as the best means of solving pollution as well as concentrating visual impacts in a particular area. Suggested use of plants and shrubbery to mask such 'unattra@tive facilities as busbars (at port entrance) and village substations is not favo-rably received from most power people based on defined responsibilities.. We would suggest that this type of activity should originate at the community or island-beautification level for facilities not subject to newer more st"ring.ent siting contro'ls. 63 I I. I I I I I; I I IV. Mitigation Measures for Major Environmental Impacts I I I I I I I 0 R A IV. Mitigation Measures for Major Environmental Impacts This cha pter will briefly discuss a number of methods available to mitigate some of the more controversial impacts associated with electric power production. It is not the intent of this discussion to specifically recommend that such methods be employed on Guam, but rather to inform decision makers of the options available if it is decided that effects or present and proposed energy facilities are unacceptable. A number of methods available are not suitable for either economic or resource-availability reasons. Whil e it is the responsibility of the industry or agency to adhere to environmental standards, and to the maximum extent possible not degrade ambient nat ural conditions*, the costs (including environmental) of such control measures must be passed to the consumer if the Power Authority is to maintain an operational efficiency anywhere near break-even. A. Thermal Effluent 1. Cooling Water The pur.pose of cooling or circulating water in steam power plants is to condense steam exhausted off the turbine. Cooling water required for this purpose increases in temperature 10 to 15'F. About 100 lbs. of cooling water is needed per pound of steam condensed. A cooling water supply is thus required which is 100 times larger than the flow rate of steam exha usted to the- condenser In the past, cooling water demands were met by simply locating a power plant 65 adjacent to a readily available and abundant water supply. However, significant environmental damage occurs as a result of heated effluent raising ambient temperatures of receiving water beyond the tolerance of organisms within the plume. 2. Atmospheric Coolinq Methods for reducing hot water effluent impacts can be divided into 2 major groups; atmospheric cooling (towers, lagoons) and modified intake or outfall structures. For plants less 200/MW capacity, mechanical or induced (i-d) draft cooling towers can be employed. The concept of cooling towers was developed to serve areas with limited water supplies whereby cooling water follows a more- or-less closed system between the condenser and the heat transfer mechanism, the tower or lagoon. A portion of the heated cooling water in the lagoon system or wet type cooling tower is lost through evaporation. Fresh water used in atmospheric cooling systems because of the obvious problem of sa.lt residue in evaporation p.rocesses. 3. Wet and Dry Type Mechanical (Induced) Draft Cooling a. Wet Type (Fig. Hot cooling water from the main condenser is fed into a distributing "header" (0), falls through holes in a pan onto a dense framework of wooden slats (C) below. The water is broken up into small droplets and creates a thin film over the surf ace of the slats. Air drawn in through side louvers (A) by means of large i-d fans 66 (B). The draft carries away vapor created by evaporation as the droplets fall @rom.slat to slat. Cooled water falls to collecting basin at base of,tower. About 75/O'-of the cooling takes place through'evaporation and the remainder by heat transfer (conduction) to the-air. LI A Np- Figure 10: Wet Type Mechanical Draft Cooling Tower Humidity is an extremely important consideration, along with air temperature._ The primary performance factor is how close the cooled water temperature in the collecting basin can approach the wet-bulb temperature of cooling air entering the tower. The higher the relative humidity the less efficient the evaporation and heat transfer rates of the tower. Advantages: effly-ent impact: cooling tower would eliminate heated effluent impacts on the Piti channel & Tanguisson reef- front areas. 67 dredging: eliminates the need for dredging of intake and outfall channels. Disadvantages: space: a rough estimate for Cabras cooling towers for 3x66MW units might be as much as 3 times the area occupied by the present 2x66MW units. fresh water: Salt wat er cannot be used in wet type cooling because of salt residue resulting from evapora- tion processes. Water require- ments would be approximately equal the amount of steam ex- hausted by the turbine. At average daily rate this "make- up" water would amount to some 20 gal/MW or 1.3 million gallons per day. Based on an estimated 1-978 island wide capacity of some 30 million gallons per day from.all sources, cooling for just the existing 2x66MW Cabras. pTants by this method might require as much as 4.3% of the island's total water production. Compared to the salt water requirement of some 138.2 million gallons per day (over 100 times the fresh water requirement), this appears quite small, but when considered in terms of limited fresh-water resources, it is far from a workable solution. -cost: The cooling towers alone are roughly estimated to have a price tag which could approach 20/00 of the total cost of power plant with an ocean water cooling sy'stem, not counting additional land requirements. efficiency: With an annual average relative humidity of at least 66% every month, with night time levels commonly at 84% year round, and with air temperatures rarely 68 falling below 72'F, Guam is not an ideal location for i-d cooling. visual/other: High profile, blocklike structure, large steam plumes. Plumes contain bio fouling chemicals and others con- centrated in the evaporation process. noise: Like a squadron of helicopters at 200 feet. b-. Dry Type,: A "dry type" mechanical or induced draft cooling tower works on much the same principle as an engine radiator. Without going into detail, the costs of such a system given the hardware requirements would be much higher than the wet-type, and even less efficient. This limits the ability of the plant at theoretical maximum (which is impossible to attain) to cool hot condenser water to dry-bulb or actual temperature is 85*F, this is the theoretical minimum temperature to which the water can be cooled; under actual con- ditions t he water could be cooled only to 92-95'F. 71 ---------- F. 0. T@. . M I @M"@794 No. 4 cooling Fig. Public Service Company of Colorado, Cherokee Unit tower, iso,oco gpm., 35o-mw unit. (Photograph by Public Service company of Colorado) Advantages: effluent impact: dry-type cooling tower, like the wet-type would eliminate heated effluent impacts on the marine environment. water demand: the dry-type tower is a closed system running on nearly pure fresh water. Elimination of direct atmospheric cooling means the need for "make-up" water is eliminated for all practical purposes. Disadvantages: space:. lower efficiency of dry tower would require more space than wet-type tower. cost: dry cooling tower cost could approach 30% of the total plant cost. efficiency: efficiency of a dry type tower on Guam would limit cooling to 7-10OF above ambient air temperature. existing equipment write-off: same as wet-type noise: same as wet-type visual impact: approximately the same structure, steam plume is absent. power consump- tion: hi gh 4. Lagoons/cooling Ponds A lagoon or cooling pond like the towers, serves as a heat sink which transfers thermal energy developed during 70 the plant cycle to the atmosphere via thermal radiation, or conduction, and by evaporation. This is not a new concept having been actively investigated since 1927. Factors for consideration include solar and atmospheric radiation, amount of condenser water (hot) entering the lagoon, ambient pond temperatures, amount of rainfall, pond inflow or makeup water, relative humidity, shape and depth of the pond, wind speed, of,inflow and outflow geometry, and number and type of induce d heat and exchange aides such as aerators and agitators. Limiting factors are space amount of solar radi- ation, makeup water, and depth. Studi es have shown that shallow water temperatures on Guam often equal or exceed out- fall temperatures due to solar heating. Area required for ponds without captial intensive sprays on agitators vary between 1 and 4 acres per megawatt of production capacity. As these estimates are based on plants in temperate climates having cold winters and constant, relatively low water inflow temperature, Guam area requirements would probably be closer to the 3-5 acre range. For Cabras island, the existing 2-x66MW plant plus the proposed unit would require almost 100 acres of pon ding basin of +15 foot depth, while required watershed to supply the basin is ten times that much. Wi.th ad.dition of mechanical agitators or sprays the area could be reduced, but the capital investment could easily double the cost of the installation. Unless parts of 71 the harbor itself are used in combination with increasing inflow with perhaps additional tide-gated culverts from the Tepungan channel, the cooling pond approach does not seem particularly attractive. For an area such as Tanguisson, a cooling pond would create major difficulties since the entire pond would have to be dredged or excavated, and inflow or makeup water is absent except for peripheral lens seepage. "In one recent estimate, cooling ponds would be expected to increase generating costs by perhaps 15100, and dry-towers perhaps 30%, with evaporative towers in between. In terms of billings to the public, installation of those heat dissipation methods could increase the retail rate from 5 to 10 percent." (Reitze, 1974) 5. Modified Intake/Outfall Structures a. By-pass cooling Direct pumping of intake water to the outfall, effectively by-passing the plant itself could halve the Delta T if pumped at the same rate as the intake inflow. According to GPA sources, this would probably be the least expensive method of lowering the temperature differential, but would require a mixing basin large enough and deep enough to achieve pond mixing. EPA officials are uncertain at present as to enforcement procedures of the 1.5'C Delta T required by water quality standards. I.t may be that bypass cooling installations would actually cause greater permanent damage to the reef 72 system than the hot effluent from the Tanguisson plant does now. If mitigation measures. were required, it is possible that halving the existing differential might be acceptable. To meet the 1.50F (0.90C) range presently required from the existing Tanguisson differential of 6.6*C-7.6'C, a volume of mixing water equal approximately eight times the present 35,000gpm or 280,000gpm is needed. In addition to excessive cos-t, it-is probable that significant enlargement of the intake channel would be required as well as an excessively large mixing pond. The cost of such an installation would be high, perhaps in the $7-8 million .range. A small er installation, such as one halving the existing temperature would require additional pumps of the same capacity as existing intake pumps, a mixing pool adjacent to the outfall, and either an induction system or a mechanica 1 mixing system. Minimum size of the pool would be in the 100'x40'xl5' range. Mechanical mixing would probably be more effective than an induction system and might require 2 or 3 large propellers or other agitation machinery. Such an installation is roughly estimated to increase station service power requirements from +1.5% up-as high as 3 to 3 1/2%. This means that busbar power or power available to consumers (as well as station revenue) would decrease by as much as 2%. For a location such as Tanguisson, the environmental impact could be that a greater area is destroyed 73 than is presently effected by heated effluent. In addition, unlike equipment life itself, the shore structures, channels and intake pipes would be permanent, existing long after the plant has ceased operations. Over a period of years, this additional cost would be considerable. Construction costs alone could reach $4 million. b.. Intake Modification It is uncertain at present Whether or not a deep outfall would meet EPA requirements since.the temperature diffe,rential would-ac tually increase directly proportional to the depth even though actual'impact on marine organisms may be substantially lessened. If deep ocean outfalls would not be acceptable, a deep intake line could lower the temperature of intake water sufficiently to meet EPA requirements. This would be an expensive and technologically innovative approach since no intake channels or pipes in the world reach to depths even approaching what would be required at present flow rates. For example, one alternative discussed involved the placement of two 42-inch pipes to a depth of 500 feet at a 45'0 slope directly off the Piti intake channel at Cabras Island. Cooling water could be drawn in at approximately 250C (77*F), which is 5*C. (91F) cooler than the ambient surface temperature of 300C (860F). The exit temperature of the effluent would be in the 29-30"C (860F) range, thus, meeting EPA standards. Over 2700 feet of 43-inch pipe would 74 be required; 2 x 750' to reach a 500 foot depth, and an addi- tional 2 x 600' to run from the end of the channel to the plant. Four additional pumps approximately the same size as the existing pumps could be arranged in a connected double-y configuration such that both condensers could be operated (at a reduced rate) for maintenance and cleaning. Open channels would not be practicable given atmospheric heating effects, thus, as-indicated above, the pipes would have to be run the entire length of the intake channel. The-cost of such an undertaking would be extreme. Given the fact that nothing of a similar nature has been attempted, it can be assumed that actual costs would exceed estimates based on conventional construction practices and equipment. It is not possible within the scope of this study to accur ately cost the project. B. S02 Removal. 1. Low Sulfur Fuel The simplest method for eliminating SO2 emissions, though presently most expensive in terms of fuel cost, is to burn low sulfur 'fuel rather than the present relatively high sulfur (2-2.5%) residual fuel oil. GPA has already looked into this alternative based on a continuous survey of a la.rge number of companies asked to submit bids for low sulfur fuel'. This investigation is a part of the ongoing District Court deliberations. Latest results are outlined.in a May 12, 1978 report. Out of the companies asked, only one, GORCO, submitted a proposal to supply low sulfur fuel. 75 Based on present cost, a minimum of $11 million would be added to fuel costs alone during the first year. In addition, GPA would have to provide guarantee deposits of an estimated $6.6 million. These figures do not include the cost of new equipment such as pipeline heaters required as a result of a high paraffin content of the low sulfur crude. There is also a question if importation of crude priced some 35% higher th an existing fuels would be in line with present national efforts to reduce U.S. expenditures on imported petroleum. GORCO, having submitted the sole bid, is continuing its investigation relative to low sulfur fuel logistics and equipment problems. If present trends continue, it is reasonable to expect the price of high sulfur crude to begin to approach that of low sulfur crude, thus making the in- stallation of expensive scrubbing equipment questionable as the price differential decreases. This situation bears close scrutiny, an.d would support the adoption of a wait-and-see attitude rather than a buy-equipment-now approach. 2. Seawater Scrubbing GPA is actively pursuing the appl ication of innovative technology for S02 controls, if required. Based on the principle that the natural alkalinity of seawater can be used for the absortion of SO 2 without the myriad of problems caused by lime scrubbing and"other 'Methods, Guam is felt to be 76 an ideal location for this process. Although the processes are slightly different, similar systems have been used on Australian zinc smelters since 1949, and on London's Battersea Power Station since 1934. Generally speaking, an ocean water scrubber is a short-circuit of the natural S02 cycle. The objective is to transfer S02 from the atmosphere, where it is considered a serious problem, to the sea where its affects are mostly diminished. This short circuit eliminates airborne S02 and whatever little acid deposition would occur on Guam. The immediate concern should be the effects of increased S02 in a volume of seawater: 1. The sulfur content of the water is increased by 20%; 2. The absorbed SO occurs mainly as sulfite at first but sl8wly reforms to sulfate using 0 in the receiving waters. This effectNely lowers the COD or chemical oxygen-demand. 3. The ph of the seawater is lowered from it's usual level of 7.5-8.5 to 6. 4. Other elements, including 'Crace amounts of nickle and vandium are.collected in the seawater scrubbing process. The main problems here are the lowered COD and 011. Sulfur content per se does not appear as a main concern although details are lacking. The simplest method of replacing oxygen is aeration. An aeration basin would be required a part of the scrubber together with a substantial mixing with ambient seawater or passage through an alkaline 77 bed for restoration of ph. An aeration basin capable of hand- ling a 120,000 gpm flow with a retention time of about 30 minutes is estimated to have a size of approxi'mately 200' x 150'x 15'. Costing (without site specif'ic details) came to approximately $4.7.million for the two existing Ca'bras plants as of April '78. Construction time was estimated at 17-23 months. Direct costs pe r year were estimated to be in the $1.3 million range. Because' of the s-ystem's ability to collect trace heavy metals in the process, as well as the increased sulfur content of the water, direct transport to the open sea is strongly suggested. This is mostly to prevent buildup over extended periods of time of elements which could have detrimen-tal effects on receiving waters not subject to constant and high-volume mixing. 3. Other SOP Removal Systems A number of process, more than 50 and their major variations, are commer cially available for sulfur dioxide removal. Despite claims to the contrary, all appear to have significant operational, environmental, and capital costs. This section will briefly discuss, some of these methods but cannot recommend the adoption of any particular system given the extreme complexity of environmental engineering and capita 1 considerations involved. Material has been taken from 78 various papers and technical documents presente d;at a USEPA/ Control Systems Lab sponsored Symposium on Fuel Gas Desulfuri- zation held in late 1974 in Atlanta, Georgia. The complete conference papers a re in the Guam EPA library. Sources are credited only when materIal is taken directly. Despite the age of the material, few really new processes appear to have shown promise with the notable exception of seawater scrubbing. 4. Brief Discussion of Selected Systems a. Direct Oxidation - Contact Sulfuric Acid This process basically passes the flue gas through a fixed catalyst bed where sulfur dioxide (S02), in the presence of oxygen, is converted to S03 and then absorbed by sulfuric acid in an absorption tower. Monsanto has deve- loped a modification of the process such that the "strong S02 is not required, but rather will operate on the dilute S02 concentration in plant stacks. The modification however is based on the fact that the stack gas enter the process at high temperature (8500F) or be heated to that temperature. The Cabras plants have a stack gas temper ature in the 300'F range. The Monsanto process (cat-ox or catalytic oxidation) would be required for these plants, meaning extensive and expensive plant modification, in addition to handling and disposing of su.lfuric acid. Star-tup and operational problems have pre- vented efficient operation of some pilot projects. 79 b Absorption/Stripping Sodfum Base Scru*bbing (Wel'l'man-'Lord Pro-cess) Flue gas is absorbed into a solution of sulfite, bisulfite, and sulfate, converting some sulfite to bi- sulfite and some of the abso rbed SO2 to sulfate. Pure gaseous so is aerated in the scrubbing process and can be further pro- 2 i cessed to liquid S02. sulfur, and sulfur-ic acid. Sulfate formed in the process must be removed as purge (.or waste) to- gether with thionates and thiosulphates. Although the process itself is relatively simple, and the scrubbing agent is re-cre- ated during the process, the main disadvantage is with the con' taminates resulting, a'nd their dispo.sal. Further research is underway for improving the system. Odor, of course, is another major problem in any processes creating sulfur as a by-product. Ammonia Scrubbi n g Also called the Ammoniu-m Bisulfate Regenera- tion Process, this system uses an ammoniacal solution rather than sodium to absorb SO from flue gases, and to regenerate the'scrub- 2 bing agent. Acid is added to the final solution to produce ammo- nium sulfate, a fertilizer, and evolved SO 2 is used in the pro- duction of sulfuric acid. Again, the scrubbing agent must be im- ported and the products exported; the system requires large amounts of power, the chemicals are explosive, and the equipment expensive. 80 c. Wet Lime/L.imestone'Systems Limestone Scrubber- Fl.ue gas is contacted to a slurry of water and finely-ground li-mest one. Scrubber discharge goes part- ly to settling pond where solid sludge settles, overflow from pond or part of scrubber discharge is recycled to scrubber. Li'me Scrubber The same as above, except that lime is used rather than limestone. d. Dry Limestone Injection Pulverized limestone is injected directly into the power plant boiler, similar to wet limestone/boiler in- jection, above. Rather than pass thro.ugh a slurry scrubber, how- ever, the limestone calcined to lime reacts at high temperature with the SO2 and excess 02 in the boiler and f orms calcium sul- fate which is removed as a solid by..mechanical precipitators. Problems include low removal efficiency, boiler plugging and de- graded precipitator performance, resulting from higher dust loading. Guam's power plants are not equipped with-electrosta- tic precipitators, as fly-ash is absent from boiler fuel, for all practical purposes. Precipitators are used on coal-fired' plants. e. Other Processes Other processes such as s crubbing flue gas with a soluble alkali and producing an insoluble product such as calcium sulfite are being inve stigated. Such a process has the advantage of high efficiency, and elimination of scaling, cor- rosion and plugging problems, The process known as "double alkali 81 scrubbing" regenerates the scrubbing agent with another insoluble alkali such as lime. For Guam, disadvantages would still be waste disposal and alkali import. Table 20 A Selecti'on 'of Sul'fur Oxi'de Control' Methods PROCESS PRODUCT PROBLEMS 1. Direct oxidation Sulfuric Product difficult to han- Contact Sulfuric Acid dle; expensi-ve to trans- Acid Cnodified port; hard to store;limi Cat-ox process) ted local market;*stack gas heating required; @questionable reliability 2. Absorption/Strip- Strong High energy consumption; ping: so2 limited S02 market;sul.- Ammonia Scrub- fate and polythionate/ ber thiosulfate disposal-re- Sodium Sulfite/ quired; expensive bisulfite 3. Di rect Reduction Sulfur Strong SOZ and low 02; Natural gas expensive intermediate Coke processes; high secon- Hydrogen dary emissions 4 Wet L.ime/Limestone Calcium Waste disposal; equipment @Scrubbing Sludge plugging, scaling; sec.on- dary pollution; Guam lime not suitable (Arthur G. McKee and Company, 1974) 82 I I I I I I I I I V. Measuring the Impacts A Methodology_for_CEIP Energy Facility Assessment I I- I I I I I I a m 9AS TO STACK STACK GAS SCRUBBER CaCO3 PUMP SETTLER 'r&qK C3SO3+ CZS04 TO WAST.1 OF LJ!,'.,ESTO" METHOD 1. SCRUEBER ADDITION AE GAS ro sua STACK C2COj GAS sc.Rues" CALCMER FUMP SETTLER i 'Cao CaS03 +CZS04 TO AS175 METUOD 2. ZC8UVPER APOIT14W OF LIME GAS TO STACX CZO CTAS BOILER SCRUBBER SAMER CaCQ3 C3503 C3504 TO WAST E MUN-00 3. MUR INJECTION L :ER pump W4 FIGURE 12. Malor Process. Variations For Use Of Lime or,_Limestone For Removal of S02 From Stack Gases 83 V. Measuring the Impacts - A Methodology for CEIP Ener.U Facility Assessment Methods for evaluation of impacts by major facility develop- ment range from the U.S. Department of the Interior's "Monster Matrix" to EPA's Environmental Impact Statement. While the lat- ter must be prepared as a matter of ca use, a method for evalu- ation of a range of impacts by energy facility development is needed for CEIP and othe'r decision-makers. For the purposes of this study, a number of "Planning fac- tors" have been derived to consider the most essential economic, environmental and social impacts of'proposed energy facility development. Compliance to existing comprehensive plans is a factor considered on a case-by-case basis and is not treated as a separate factor. A. Economic l.- Government fiscal condition: Ne t external change. Employment: Long term, short term, % change. 3. Land values: Changes in a) Surrounding use b) Right-Of-ways c Aesthetics, poll'ution B. Environmental 4. Air quality: Change in ambient conditions. 5. Water quality: Change in ambient conditions. 6. Audio-electromagnetic: Change in ambient noise and electromagnetic radiation levels. 85 7. Open space/green areas: Change in existing vege- tation. 8. Rare and endangered species: Changes in number or types. 9. Wildlife,'vegetation: Major changes in existing abundance or diversity. 10. Disaster: Susceptibility of expanded facility to natural disaster. C. Social 11. Landmarks: Cultural, historic or scientific land- marks destroyed, significantly altered, or made inaccessible. 12.. Recreation: Destruction, or change-in "usability" or pleasantness of recreational facilities. 13. Transportation: Change in duration or severity of congestion. 14. Housing:..Change in locational demand for nearby housing' units. 15 Education: Change in demand for schools, specific courses, student density. 16. Community self perception: Number of people whose community living conditions will be signi- ficantly altered. 17. Shortages: Improvement of living conditions caused by previous shortage of energy such as brownouts or forced outages. 86 A. Economic Impacts The economic controversy which always accompanies major investment in new energy facilities is as much a part of Guam's power industry as in any other region. While cer- tain aspects of plant selection and economics of alternative choices are mentioned in sections of this study, the major economic impact" considerations will revolve around addi- t1onal public facilities required as a direct result of new or expanded system components. These "externals" or secon- dary costs are the major focus of t he economics section si.nce the major objective is..to ascertain what part of the public sector is going to bear the cost burden of these new public facilities, if any. We are assuming that plant costs, method of financing, and general economic well-being of the Guam Power Authority and other private sector participants will be handled as a matter of course. We are only interested in new public facility costs, not in recommending internal fiscal policy of the energy industry. Factor 1. Net Change in Local Fiscal Conditions "Net change" involves computation of expected revenues less operating expenditures, less capital expenditures in pub- lic facilities outside of the energy facility itself. Revenues rdeally, revenue projections for assessing external eco- nomic impacts for-energy development would include a facility's 87 effect on real property revenues (increasing or decreasing tax base directly attributable), changes in income-based reve- nues (income and sales tax dir ectly attributable), expected changes in population unit revenues (new federal funds gener- ated by the facility),-and increased revenues from public utili- ties. Operating Expenditures The term operating expenditures here should not be con- fused with annual- operating costs of the plant itself such as fuel, labor, maintenance, supplies, etc. Operating expendi- tures here include additional costs in* public facil ities require-d including, for example, new sewer or water lines, pub- lic safety measures (additional police or fire protection), relocated recreational amenities, new roads, possible upgrading of public transportation. Although change in "educational institutions" has been included under planning factors, it is doubtful Jf energy facility development will directly result in demand for a new school or library. Capital Expenditures Factors include total cost, percentage of total cost allocatable to-energy facility expansion and method of financing by the agency responsible. The latter is especially important since, other than planning and environmental grants, the major form of aid offered by the CEI program consists of loans and/or bond guarantees. 88 Present forms of financing public facility expansion include general revenues from tax receipts (Government of Guam general fund), federal grants, user charges through revenue bonds (bonds issued on the basis of expected revenues), or general obligation bonds for those facilities not paid with user charges. CEIP loans or bond guarantees could substantially reduce the financial risk to th e Government of Guam of new public facilities by underwriting the responsibility of loan or bond payment if such obligations will be dependent on future (and sometimes uncertain) revenues. It is.important to take advan- tage of every penny of support available as this sort of assis- tance can help to reduce the lag between public infrastructure investment and new revenues from new development. Factor 2. Employment Changes in the labor market attributable to major new energy development will include temporary increases in short term A&E,. construction and related trades. A greater number of long term plant personnel, both supervisory and opera tions, will comprise the major long term impacts. A few public sec- tor jobs, particularly in the public safety fire/emergency area may also result. Important for Guam is the origin of this labor and whether it will provide a primary local benefit or merely short run benefits in terms of increased spending of temporarily increased payrolls. The overall result will, hope- fully, be a slight decrease in the unemployment rate. 89 Factor 3. Changes in Land Values Land value changes usually accompany major energy faci- lity development. On Guam, areas for expansion are usually adjacent to existing facilities, which, for the most part, are surrounded by federally owned or controlled lands. This sub- stantially reduces or dampens any spectacular dollar changes in land values. In a case such as Tanguisson Power Plant, although scenic and recreational value of the area may have been reduced, further commercial an@d industrial developmen-t and increasing earning capacity of the land would not be in accordance with existing community needs or objectives. For example, the Navy's Guam-land-use plan indicates the return of certain lands at Cabras Island (at fair market price) to the Government and private sectors. Given its loca- tion adjacent to t he port, as well as existing nearby energy, availability, it is doubtful that additional plant capacity at Cabras would substantially increase the land value. Power transmission corridors can reduce the value of residential, tourism, recreational, or natural areas if impro- perly or carelessly sited. At best, they may increase the taxable potential of the land because of possible commercial/ industrial development. This is particularly true of power transmission corridors following transportation and other utility corridors. It is often difficult on Guam to gauge such impacts given the often artificially high land values to begin with, as well as sporadic nature of control over development exercised by enforcement agencies and regulatory commissions. 90 Application of Economic Planning Factors Because design specifics are not available, economic fac- tors are generally discussed on a case-by-case basis in ChapterVII. dealing with some of the more promising developments which might qualify Guam for CEIP funds. At the time specifics are avail- able, more detailed anlysis will be possible. B. Environmental Planning Factors Factor 4. Changes in_Water Pollutants Generating facilities, to date, have been responsible for the major percentage of energy-related water quality im- pacts although storage tanks and pipeli'n'es have t.he greatest potential. Thermal effluent, suspended and dissolved solids, toxic chemicals, dissolved oxygen and a range of petroleum products, and construction debris constitute the major con- siderations. Heated effluent and dredging/filling activities in the past have had the greatest impact on the quality of coastal water. While negative impacts can be accurately assessed at the relatively isolated Tanguisson plant, quality of receiving waters adjacent to the.Cabras plant are affected by other activities including commerc ial port ship operations, previous dredging, and natural processes such as significant solar water heating of shallow reef flats, tend to lessen the. overall impact of additional facilities. "Reduction of quality" in receiving waters is generally based upon expected 91 change of existing marine environment as a major index- This could be extremely problematic with a land-based as opposed to floating, "spar-type" OTEC facility. Introduction at the sur- face of large amounts of extremely cold water (43-44'F) could completely alter the existing regime, even if mi-xed with the heated effluent from conventional plants. In terms of produc.- tivity potential, the cold, nutrient-rich water has incredible possibilities; it is yet an untested case as to whether EPA would consider cold waters with a more than 1.5*F (0.9*C) Oel*ta T.- to be unacceptable as is apparently the case with the hot-water effluent. A-floating OTEC plant would avoid this potential impact. A major risk in development of energy. facilities is the threat of oil pollution. This is particularly true of major storage facilities which may require an increase in tank.er traf-, fic ei ther through Apra Harbor or near the reefs of Guam (Agat Bay). According t.o almost all sources, the probability of such an accident approaches 100% over a period of 20 years in areas of,medium to heavy tanker traffic. Typhoons and earthquakes in- crease the risk for such an event. Factor S. Chang es in Air Quality SuT fur oxides (S09) are the main pollutant of petro- leum-fired steam plants on Guam. The fuel used to fire the Piti, Tanguisson and Cabras steam plants is a #6' residual fuel oil with a maximum sulfur content of 3.51/0, and produces an S02 stack 92 emission in excess of federal and local ambient standards, which are the same as National Standards. Although the ambient levels are below the minimum national standards, the problem is with stack emissions. The low ambient levels together wi'th completion of the new Piti stacks, and operation of the "emergency episode plan" (e.g. switching to low sulfur fuel when winds blow stack gas land- ward) may be acceptable'to National EPA until the situation is resolved through the courts. Factor 6. Audio and Electromagnetic Radiation Audio quality could be defined as the extent to which noise levels change as a result of increased activity and reduces the desirability of surrounding land areas for particu- lar uses. While not a major problem in the Cabras Island com- plex, expansion of the Tanguisson and other sites could.result in an unacceptable audi o level for surrounding recreational uses. Electromagnetic Radiation (EMR) has recently been found to produce severe health hazards over long periods of time. This definitely is a consideration in the location of future high voltage transmission lines adjacent to residential areas, educational institutions, and other facilities in which people consistently congregate. Factor 7. Open Space/Green Areas A rather straightforward indication of impact is the amount of land area required for expansion or new development 93 which would directly result in a reduction of existing or poten- tial open space and/or gree n areas. Submerged lands are con- sidered as open space. Related environmental factors are rare and endangered species (8), wildlife, vegetation (9), and disaster (10) . Factor 8. Rare and Endangered Species Recent stop-work. orders on massive utility projects demonstrate the importance of rare and endangered species in the siting of major facilities. While not expected to present major problems for Guam in terms of limited applicability of the National Endangered Species listing,' thought should be given to species endangered at the local level. Local endan- gered spe cies will be considered in this study's evaluation of expected expansion, and hopefully will be afforded more pro- tection with designation of critical habitats as areas o-f particular concern under the CZM program. Factor 9. Plants and*Animals, Changes in Abundances and Diversity Marine fishes, corals, algae, etc., are considered together with terrestrial wildlife and vegetation. Past faci- lity development has resulted in minor to major changes in both the marine and terrestrial regimes. A number of studies provide a basis for projecting impacts. While it is impossible to predict the effect of, for example, an increase of 5% of heated effluent to individual species in an area already affected, 94 it is possible to use a linear expansion to predict the area of additional impact. Factor 10. Disasters, Natural and Manmade Guam is subject to frequent typhoon and earthquake haz- ards and related secondary impacts such as flooding and slumping. In addition, several analyses*have been carried out dealing with such things.as maximum accidents at hotel wharf ammunition dock and n-uclear accidents. For the purposes of this study, war or nuclear events are not considered for obvi ous reasons, however given the frequency of natural events, both the facility itself and siting considerations are of major impor- tance in e-stablishing a susceptibility factor for expanded energy facilities. The major question here would be, "Is the facility adequately protected?" For CEIP purposes, investment in public safety facilities is of prime importance to minimize the-risk to the persons in the immediate-area. Additionally, adequate respons e mechanisms to major.spills resulting from disasters. is vital. Factor 11. Recreation A number of recreational resources ranging from swim- ming beaches and tourist destinations to potential storm refuge boat anchorage, national park, and major marina are located adjacent or very near to existing and potential power genera- tion and bulk storage facilities. Most of the island's major critical areas with respect to fragile natural resources, major population centers, and 95 cultural and historic sites should be relatively safe from severe locational impacts of present and future power and energy facilities. What areas do face potential damage can be pro- tected with a modicum of common sense planning. Parks and recreation officials did not feel that any major recreational or historic resources would be directly threatened by expected energy facility expansion. Provision should be made, it was stated, for continued access to beaches, anchorages and other areas on Cabras Island presently used by the public. Provision for future development should include plans,for boating anchorages in the inner Piti channels, especi- ally alteration or addition to transfer pipelines presently limiting access to the channels. Conc ern was expressed rela- tive to the Agat Bay - Asan - Pi-ti offloading and bulk storage concept as well as any major expansion of th e Tanguisson power pTant complex. Historic sites such as Inarajan Village, and scenic vistas including Pago Bay, Talofofo Bay and the Facpi Point to Nomna Bay coastal area were singled out as being par- ticularly susceptible to poorly located generation, power pole, or other development. The Department of Parks and Recreation has prepared specific guidelines for transmission facilities. The following table provides an assessment of recrea- tional and historic resources which are or may be subjected to energy related impacts. 96 Table 21 Recreational and Historic Resources Potentially Subject to Impacts of Energy Facility Expansion Resource Control Existing or Impact or Name and or Potential Potential Location Ownership Energy Facility Impact;. Notes NCS Beach GovGuam Tanguisson SSP Navy & Private Thermal and Air North NCS Navy Tanguisson SSP Effluent, Pollution, Beach Shore Structures, Oil Spill (pipeline) Visual, Noise NCS Reef Navy (submerged land) Tanguisson SSP Puntan dos GovGuam Tanguisson SSP Potential Air Pollution Amantes (extremely rare with Dededo existing plant) Glass Navy Cabras/Piti SSP; Air Pollution, Potential Breakwater Esso, Navy, Mobil Access problems, spill Apra Harbor GPA bulk storage (ship and/or pipeline, offloading and bulk storage) transfer opera- tions; proposed large scale bulk storage Hotel Beach Navy Cabras Island Marianas Mobil Yacht Club Petroleum (Private) (leased) Cabras Island Apra Harbor Navy Shoreline alteration, Mangroves Sasa (submerged erosion and siltation & Aguada River land) are possible with Wptland_q -large-scale inland bulk (Rhizophora sp.) storage complex; oil spill 97 Table 21: (continued) Resource Control Existing Impact or Name and or Potential Potential Location Ownership Energy Facility Impact; Notes Jade Shoals Navy Cabras/Piti SSP; Possible impact from (submerged Esso, Navy, Mobil increased levels of land) GPA bulk storage heated effluent; oil -offloading and spill transfer opera- tions; proposed large scale bulk storage Piti Channels Navy Possibl e OTEC Possible access problems (adjacent to Impacts for proposed storm Cabras SSP) (speculative) anchorage; oil spill Luminao Reef Navy Possible cold water (submerged effluent problems land) (OTEC) Orote Beaches Navy Only probable effect 1,2,3 GabGab would be from a major Beach oil spill War in GovGuam, Offshore super Visual, oil spill, Pacific DOI tanker offloading shoreside facilities Nat'l Park Private & mooring, bulk Asan/Agat storage Tipalao GovGuam, Offshore super Oil spill, shoreside Beach to Private, tanker mooring facility construction Facpi Point DOI .& offloading (facility very (8 beaches) facilities speculative) Scenic Hwys: GovGuam, 115 and 34.5 KV Possible visual impacts Agat-Umatac Private lines & poles if lines are not properly Umatac-Merizo planned Merizo-Inarajan Inarajan-Talofofo Talofofo-Yigo Bay 98 Tabl e 21: (continued) Resource Control Existing Impact or Name and or Potential Potential Location Ownership Energy Facility Impact; Notes Historic Sites: Navy Cabras/OTEC Site disturbance; Quarantine 250 yd West expansion improbable from Station (1914) of Piti energy facility Channel expansion Inarajan Private 34.5 & 13.8 KV Possible visual impact Village lines if lines not properly planned Facpi Point to GovGuam 115, 34.5, and Visual impacts with lines Nomna Bay Private 13.8 KV.lines High potential for Federal and poles; severe erosion, sedimen- generating tation, visual, recrea- facilities tional, thermal, dredging, etc. impacts from generating facility 99 C S o c i a 1 Factor 12. Landmarks: Cultural, Historic, Scientific Any type of project has the potential of destroying sig- nificantly altering, preventing free access, or otherwise impairing landmarks. To date, this has not been serious inso- far as energy facilities are concerned. The major problem in the future is with transmission line'placement, development of super-port type facilities adjacent to War-in-the-Pacific National Park sites, and possible degradation of areas such as Inarajan Historic District, or the entire southern coastal area. Interviews with University of Guam Marine Laboratory staff and local and national Fish and Wildlife personnel have indicated that a strong tendency exists within the scientific community to consider the coral reefs themselves as scientific landmarks. This, in addition to fairly vigorous EPA water quality s.tandards mea:ns that future impacts will be closely monitored. Whether-or not the abovecategories are presently under national recognition such as national natural landmarks or the national historic register is rather irrelevant other than the additional regulatory mus cle it provides. The fact that a site or area is recognized on the local level is adequate to demand special attention by developers. Because a landmark may be altered is not in itself suf- ficient to preclude development. The benefit of the facility must be,weighed against such things as its rarity, importance to the public, and distance to t.he closest similar example. 100 Landmarks: Cultural/Historic Inarajan Historic District Quarantine Station, Cabras Island (1914) War-in-the-Pacific National Park and specific sites therein. Scientific Jade Shoals Apra Harbor Apra Harbor Mangroves (between Polaris and Drydock Points) Atantano and SaSa Wetland Luminao Reef NCS Reef Front Facpi Point Factor 13. Transportation Major facilities can have major impacts on transporta- tion patte rns. Such things as congestion, interference with future rights-of-way by poles, lines, and transformers, increased traffic flow, or elimination of existing access can all result. Although major flow or congestion problems do not appear to be a major expected impact on land, shipping flow could be substan- tially increa-sed placing undue pressures an the Port Authority and related Government of Guam services. Factors 14 and 15. Housing/Education Not considered to be of major importance, these two factors nevertheless should be considered even if a remote chance exists for additional public.facilities and/or educa- tional curriculum changes. Since most residential areas are located far enough away from expansion areas, there is little impact expected, however in the Piti and.Agat areas, a major 101 development may cause some problems. It is expected that the new Community College or the existing vocational programs can take care of any additional curriculum demands caused by energy facility development. Given the size of the island, it is not expected that new housing d-emand will result from the placement of energy facilities. Factor 16. Comm unity Self-Perception' More of a value judgement than measurable impact, a simple statement will be made based on the previous factors as,to whether the total character of a village or community will be significantly changed as a result of energy facility development. Factor 17. Shortages Improvement of a vital service provides socialo@psycho- logical benefits in that more reliable product results. Improve- ment or expansion of different segments of the power grid will have a proportionately different effect on elimination of power or energy supply fluctuations or inconsistencies. 102 VI Regulatory Considerations VI Regulatory Consideratidns A. Overview Guam, because of its smal 1 size,, insularity, and I imi - ted per capita demand for power d.ue to lack of heavy industry, is not subject to a number of pressures requiring an individual energy industry regulation process. Department of Energy ap- proval (formerly under the jurisdiction of the Federal Power Commission) was not needed for construction of the Cabras I & 2 units since interstate transmission was not a factor. 1. Federal Permits The primary mechanism for review and comment on energy facility development having impacts on waters of the U.S., coastal and otherwise, is the U. S. Army Corps of Engineers per- mit. Appendix q contains a comprehensive listing of those agen- cies and persons. 2., Local Permits and Review The process and authorities of local permit pro- cedures have been discussed extensively in the Bureau of Plan- ning's CZM 306 Document, and Barrett and Associates' recent re- port, "Environmental Management Study". It is not the intent of this report to repeat discussions of points already identified in other studies. Generally, difficulties in the regulation process revolve around the need for: a. Clarification of Building Permit, Clearing, Grading Processes; 104- b. SDRC/TPC/TSPC - Process clarification, un- derstanding of duties, Relationship of Law, R'egulations, Authority and Application of sa:me; C. Clarification of GEPA vs. Federal EPA En- vironmental Impact Review Process including coordination with Corps'of Engineers; d. Improved Enforcement Procedures. (Barrett and Associates: Environmental Management Study, 1978) 3. Seecifi'city Deftnition With additional guidance in the form of Resort- Hotel, flood-plain and wetland regulations, in addition to ex- isting erosion, emission and water-quality regulations, the on- going task of process clarification should provide Guam with an excellent regulation system for energy facilities. One resolution needed, according to EPA, is the definition of receiving water. It is difficult to apply-a regu- lation specifying a 1.5* F delta T, if the exten't of a mixing zone is not specifically defined. It it is.defined as immediate- ly adjacent t o the outfall, then we can expect major effluent requirements on existing new source and future facilities. Emission controls will be. facing much s ame type of review. 4. Nati'onal' And Territorial Interest The CZM document, the Comprehensive Development Plan and local regulatory processes rec ognize both the territori a] and national interest in the development and siting of major facilities. 105 5 Public Facilities Commission The role of the Public Facilities Commission (once operational) is uncertain at the present time' as to par- ticipation in the regulation of energy-related matters. 6. APC's (Areas of*Particular Concern) As additional areas of particular concern (APCs). are established and regulations developed, major energy facili- ties, like all developmen t, must adhere to the extent that local regulatory bodies deem sufficient. Local regulatory commissions must apply regulations in a manner consistent with the program document and the guidelines under which federal funds are being received. B. Air Quality 1. Leqal Arbi tration The process by which Guam shall come into line with federal statutes is contained in the,island's State Im- plementaion Plan (SIP). A series of legal actions in the form of suit and counter-suits are seeking more exact process defini- tion: CA. 75-064 GPA vs. Administrator, EPA, Russell Train CA. 75-066 US vs..GPA Results, to date, are not conclusive: A compliance order was issued January 30, 1976. This initially set up the Emergency Episode Plan and outlines other procedures for GPA compliance. An Interim Consent Order, on January 21,1976, was changed by an Amended Interim Consent 106 Order on August 28, 1976, under District Court Decision CA-75-066, and granted relief from immediate compliance with New Source Performance Standards (NSPS) for a period of three years Meanwhile, reports on various aspects of the S02 problem are sub- mitted to the District Court every six months, while various pro- posals are developed to seek a middle ground for Guam-oriented compliance. 2. GPA Activities To avoid installation of questionably useful and very expensive scrubbing equipment, GPA has proposed additional t-ime be given for investigation of innovative technology, sea- water scrubbing, to solve the S02 problem, if the courts ulti- mately decide Guam must adhere to stateside standards. GPA is applying to the District Court for further amendments to prevent assessment of non-compliance penalties based on innovative tech- nology investigation. Concurrently, GPA is applying to GEPA for a DCO (Delayed Compliance Order) to allow for non-compliance with NPDES without penalties, pending studies on the process and the environmental acceptability of seawater scrubbing. Three years are being proposed to study seawater scrubbing, one for determining the data base, and two for studies on critical aquatic organi sms and extrapolation of laboratory results for determining actual impacts. The Clean Air Act Amendments of 1977 raised some questions about Guam procedures. Specifically, Section 113(d) (12) of the Amendments called into question the validity of orders, particularly the Amended I.nterim Consent Order. In a sub- mission to Honorable C.ristobal C. Duenas of the District Court 107 of Guam, GPA's attorney, Hogan and Hartson, raised the ques- tion, however, both GPA and GEPA counsels subsequently agreed that the validity of the Amended Interim Consent Order had not been changed. In other developments, several actions are being proposed: Source Cr'ather than area) based data should be developed for sulfur dioxide, relative to terrain dispersion and model certifica- tion information. Present measurenents do not specifically test the stacks, but rath- er the.general Cabras Island/Co,mmercial Port area. Develop and support legislation e_xempting Guam from S02,regulations. C. Water Quality 1. General Point source di-scharges are required to adhere to regulations promulgated by GEPA under the National Pollution Discharge Elimination@Systems CNPOES). By authority of Guam Pub- lic Law 9-76, the Water Pollution Control Act @Title X, Ch apter II, Sec tion 9950.5 .[b], jel) of water-quality standards became effective on September 25, 1975.. Section II of the regulations established standards for: microbiological requirements (fecal coli- form) pH nutrient material dissolved oxygen - total dissolved solids - salinity and currents - suspended matter - turbidity radioactive materials temp-eratu.re 108 toxic.substances pesticides Of major interest to the* power industry is Sec- tion II b(9) of the regulations which states: "Water temperature shall not be changed-more than 1.5' F C.9'CJ from natural con- ditions." This applies to all surface waters excep't those "flow- ing over the land (e.g., sheet runoff) or water confined in chan- nels with intermittent flow". CSec I B.[21 Jc]). Uniform application of these water-quality regu- lations under authority granted to GEPA could force a reduction of thermal effluent impact on Guam's coastal waters. The op- posing argument, that Guam's encircling waters are a part of the largest heat.sink on earth, thus diminishing the relative impact of effluent, has more validity on Guam than in most places. The fact remains that the entire cost of whatever thermal effluent reduction measure is required will be passed on to the consumer. It should, ideally, be left to the local authorities to weigh the benefits of either approach and arrive at an equitable solu- tion. The danger of such a resolution lies in the pencha'nt for local governments, usually with recurring fiscal difficulties, to Ignore the long- range impacts in favor of short-run capital investment savings, and to reject any voluntary actions until the situation becomes critical and expensive to redress. Environmental policy makers, in the face of re- stricted clean fuels availability and the parallel drive for re- laxation of environmental controls, have failed to reach agree- ment on the national level as to the.guidelines for compromise 109 which must occur. Guam EPA is caught in the 'Middle with the un- pleasant task of forcing expensive effluent controls on plants in locations whose actual impact is not s.ignificant at the is- land's major production site. Until the definition of mixing zo.ne is specifically addressed, and until (U.S.). Department of Energy and Environmental Protection Agency policy makers decide on the effect of changed'condi tions, the local dilemma will re- main. 2. Additional Safeguards Proposed areas of particular concern (APC's) un- der the Tand-use planning effort,- building permit and SDRC/TPC/ TSPC process clarification, establishment of an adequate sea- shore reserve, and active participation and review of submerged Jands permits, and detailed review and comment within the Corps of Engineers permit-review process provides a,more than adequate regula tory framework for maintenance of water quality and pro- tection of fragile resources. The EPA process will continue its e-fforts to more specifically define the degree of flexibility un- der the national mandate. 3.' Other Water-QUality Considerations The preceding has focused on strict application of controls relative to heated effluent. Application of controls for other pollutants seems reasonable. Some questions may arise if a seawater scrubbing sy-stem is contemplated on more than a speculative level. It does appear that both GPA and GEPA are at- tempting to reach an equitable solution to a difficult problem. 110 4. Federal Water Pollution Control Act and Amend- ments (Oil Spills) The Federal Water Pollution Control Act of 1972 provided new strength for controlling point source discharges of oil and hazardous substances and generally replaced the Refuse Act of 1899. A major weakness of the latter was lack of penal- t i e s . Generally, the FWPCA: a. prohibits discharge of oil and hazardous substances in U.S. waters; b. gives EPA jurisdiction over inland spills; c. requires an FMC (Federal Maritime Commission) certificate for ships indicating type of spill insurance (presently this is $120' per gross ton, or + $14 million limit); d. established revolving contingency funds ($20 thousand for Guam) for spills of un- known origin, or as contingency monies for sloppy cleanups by responsible parties; e. established the national regional strike force to mobilize experts at the site of major spills; f. established fines for spilling ($5000) and not reporting spills ($10,000). On Guam, the reaction to enforcement of FWPCA has been excel- lent. In the first year 36 validations occurred, the second year 19, and last year only 11 incidents occurred, as operators and industry became more cognizant of stiffer penalties. The Clean Water Act of 1977 strengthened the FWPCV by broadening the definition of U.S. waters to 100 miles, making offenders responsible for the restoring and restocking of natural biota, and increasing the liability of onshore facilities from ill $8 to $50 mill ion. Additionally, if a third party were respon- sible for a spill Ct.he ship's leasee), the.ow-ner can prosecute for charges. The law also provided that the contingency fund could be used to avoid a potential spill by offloading or pump- ing tanks of vessels in troubl e'.* 112 V I I General Conclusions, CEI Matrix, Funding Recommendations VII. General Conclusions, CEI Matrix, Funding Recommendations A. General Conclusions 1. Public facilities on Guam external to Guam Power Authority have not and are not expected to be severely bur- dened by expected expansion or development of new energy genera- ting and transmission facilities. 2. Environmental quality and availability or access to recreational areas has not been and should not be severely affected by expansion or development of new energy generating and transmissi-on facilities. 3. No in-place plans other than typhooh restoration and very low impact power grid maintenance and development acti- vities were in evidence during the course of this study. 4. Several projects in preliminary planning stages, especially in the refinery and bulk storage sectors could place significant pressures on environmental quality, recreation and conservation, land, and the cost of future public facilities. 5. EPA-mandated control standards will be more pre- cisely defined in the light of Guam's unique conditions. 6. Facility planning and open discussion of projected activities is somewhat restricted among the energy sector's various admi ni strators . 7.. Lack o.f emphasis on lead time planning creates a fluidsituation whereby new ideas crop up literally over- night. Proposals could surface any time which may substantially increase Guam's funding eligibility. B. CEI Matrix-Funding Possibilities Energy Facilities iIn preliminary planning stages may qualify Guam for CEIP funding, particularly planning monies. The lack of in-place plans limits the availability of public facility.CEIP aid, however it is expected that several major projects will be on line prior to the 1986 program termina- tion date. The. following matrix indicates the source and possi- bility of receiving such funds as a result of Drojected expan- sion. A discussion of marginal and probable CEIP funding poss.ibilities follows the matrix. 114 Table 22: CUP Funding Matrix Keys: 1. + 66MW generating unit IV. Refinery Expansion a) Cabras location b) Other location V. Powerline Hardening & Expansion II. Central Terminal Station VI. Pipeline Construction (CTS) III. OTEC Plant a) Floating Spar CEIP Planning Funds (308(c)) b) Land Based 1. Negligible - No CEIP $ 2. Marginal - Possible CEIP $ 3. Significant - Probable CEIP $ Planning Factors I II III IV V VI a b a b Economic 1. Net change - Local Fiscal Conditions a. Revenues 1 1 3 2* 2* 1 1 1 b. Operating Expenditures 2 2 2. 2* 2* 1 1 1 c. Capital Expenditures 2* 3 3 2* 2* 2* 1 1 2 Employment a. Temporary 1 2* 2* 2* 1 1 b. Permanent 1 1 1 1 1 1 1 1 3. Land Values Changes 1 1 3* 1 1 1 1 1 Environmental 4. Water Quality 2* 3* 3* 3* 2* 2* 1 2* 5. Air Quality 2* 3* 1 1 1 2* 1 1 6. Audio & Electro- magnetic R d 2* 3* 1 1 1 1 1, 1 7. Open Space/Green Areas 1* 3* 3* 1 2* 3* 1 1* 8. Rare and Endangered Species 2* 3* 3* 2* 2* 3* 1 2* 9.. Plants and Animals 2* 3* 3* 3,@ 2* 3* 1 2* 10. Disaster Suscepti- bility 1 3* 3* 1 2* 1 1 1 11. Recreation 1 3* 3* 2* 2* 1 2* 2* Social 12. Landmarks 1 3* 3* 1 1 1 2* 1 13. Transportation 1 1 3* 1 1 2* 1 1 14. Housing 1 2* 2* 1 1 1 1 1 15. Education 1 1 1 2* 2* 1 1 1 16. Community Perception 1 2* 2* 1 1 1 2* 1 17. Shortages 1 1 1 1 1 1 1 1 115 C. Funding Recommendations. 1. Generating Facilities (I on chart) Planning is in preliminary stages, no specific plans are available. Cabras location would reduce overall impacts as land area and infrastructure are available and use is compatible with surrounding uses. Al.so no additional dredge and fill would be required. a. Cabras Location, CEIP Funding Possibilities (1) Additional Public Safety Equipment - fire equipment. objective: reduce fire hazards in Cabras Island Energy facilities. authority: Department of Public Safety Chief Wusstig. Rresent status:, Piti Station (GovGuam) has a single basic structural pumper Tocated 1/2 mile from Cabras and Piti generating units, I mile from Mobil and Esso storage facilities. No foam unit is readily available. Perhaps 50-75% of the cost of additional units could be attributed to petroleum stor- age, offloading and electric generating units. 116 presentstatus: no firm plans; planning funds can be used for: - operating expenditures: determine abil- ity of DPS to operate an additional unit at Piti , if needed. - environmental: plan for generating unit's as well as mitigation equipment's impact air and water quality, marine environ- ment (plants and animals and rare and endangered-species). CEIP funding: 308(c); primary source - the fund. Procedures - same as with present grant. Funds should be applied for when design RFP's are requested, possibly 1983. Amount: Undetermined; close coordination should be established and maintained with GPA such that CEIP studies do not over- lap with GPA studies. b. Other Locations for Generating Unit (1) Public Facilities An Agat or other location may mean a s ub- stantial investment in water lines, roads, and other facilities. Depending on speci- fic location, funds under 308(d) (1), (2) 117 2-resent financing: OPS equipment is wholly funded through general fund. Present federal funds can only be used for communities of less than 10,000 persons, and then only for "minor" .equipment. CEIP fundj_nj: 308(d) (1), (2); primary source, the Fund; Procedures - RuTes and Regulations Section 931.48. Amount: (OPS figures) Basic Pumper - $92,000 Foam Unit, Crash & Rescue Unit $110-125,000. Action: Investigate ability of the Department of Public Safety (DPS) to receive federal loans, as well as estab- lishing a repayment process. Obtain more specific needs statement (e.g., pro- jected CIP needs), and investigate im- plications of Navy ownership of Cabras Island. (See also planning funds below). (2) Planning Funds - Cabras Location for Generating Unit objectiv determ.ine specific impacts of designed generating facility. 118 cou'ld be applied for.PUAG has recently been granted authority to obtain loans. Table 23: Approximate Cost Estimates for Selected Public Facilities (.Source: DPW; Barrett & Associates) Facility Size Cost/Unit Roads, Pavedl 2 Lane $ 70,000/1000 ft. H- 20-24 Class 3 Lane $110,000/1000 ft. 60 tons 4 Lane $150,000/1000 ft. (80 ton w/safety factor) 5 Lane $190,000/1000 ft. 6 Lane $270,000/1000 ft. Water Lines 6 inch $30/ft'. 12 inch $40/ft. 16 inch $45/ft. Notes: Road prices are in 1976 $ Units, add 15%/yr. for approximate update (DPW) 2. CTS - Central Terminal Stati on (II on Matrix) Discussion of the CTS concept appears in AppendixI Probability of project realization to the scale envisioned is low, however the economic, environmental, and social impacts are poten- tially the largest of any civilian sector activity ever proposed for Guam. 119 Planning funds under 308 (c), would be vital as a first step should the project become a reality, thereafter public facility loans or bond guarantees under 308 (d) (1) & (2) would be probable. The U.S. Coast Guard commander indi- cated that a sophisticated traffic control system is not pre- sently needed due to low traffic flow, but with a full-sized CTS facility, addftional studies would be necessary. 3. OTEC.(III on Matrix) -As indicated in the CEIP matrix, a floating spar- type plant would have a significantly smaller environmental impact than a l'and-based plant. A suggested use for 1979 CEIP funds allready allotted under 308 (c) would.be:. a. coordinating and evaluating all OTEC related studies being carried-out relative to a Guam location; b. more intensive studies of alternative sites for a land-based. and sea-based facility. An investigation, "Locational Impacts of Alternative OTEC Facility Sites" would be appropriate at this time. These might include Cabras I'sland, Agat Bay, and Cocos Island for the spar-type plants. Focus of study might be impact of shore-side support facilities for 120 the installation, and comparison to the greater impacts of a land-based facility of the type prop osed by TEPSCO. 4. Refinery Expansi .an -(IV on Matrix)- a. Public Facil'ities Noted in Chapter II was the fact that water availability poses a constraint to refinery expansion in the light of the Navy's desire to end the cooperative water supply arrangement now in effect for the Agat-Santa Rita area. The GORCO well presently supplies 1.7 million gallons per month (gpm) and the Navy lines some 255,000-450,000 gpm. Even with the maxi- mum demand, this constitutes only 1.1% of the 39 million gpm presently consumed by the commu- nities of Agat and Santa Rita. This ratio will decrease-in the future. Thus it appears that propontioned energy facility contribution to the cost of piped-in Northern-lens or Ugum Dam water, (both schemes being 10 or more years in the future), would be negligible. b. Planning Funds Planning funds might be applied to the study of impacts of expanded tankage facilities relative 121 to planning factors 4, 5 and 7-9 as indicated on the matrix. These funds should be applied for when specific design plans are available, again under 308 (c). S. Powerline Hardening and Expansion (V on Matrix) These projects being already underway, would be difficult to change. An attempt might be made through coopera- tion with the Navy and the Department of Parks and Recreation to ensure that projected line hardening in the southern areas do not interfere with land to sea vistas or Inarajan historic district. If this is deemed necessary, a small portion of already allotted 1979 CEIP funds might be used. 6. Pipeline Construction (VI on Matrix) Present plans are still in discussion stages. Planning 308 (c) funds might be used in 1980 to study impacts on water quality, plants and animals, rare and endangered species, and recreation for alteration of Piti channel pipes, or low sulfur lines projected to run along existing easements from Cabras to GORCO refinery. It should be remembered that these projects will both require a COE permit, and studies, if necessary, should not overlap. 122 I I t I . I I I I I Bibliography I I I - I I I I I I I Bibliography A. Books, Texts D. L. Krenkel,Frank L. Parker (eds.), Engineering Aspects of Thermal' Pollution, Vanderbilt University Press, 1969. A. W. Reitze, Environmental Planning: Law of Land and Re- sources, North American International, Washington, D. C., 1974. P. S. Scharnman, T. Muller, Measuring Impacts of Land De- velopment, The Urban Institute, Washington, D. C., 1975. B. G. A. Skrotzki, W. A. Vopat, Power Station Engineering and Economy, McGraw-Hill Book Company, New York, 1960. A. C. Stern, ed., Air Pollution, Aca demic Press, New York, 1968. B. Government of Guam Reports, Studies, Documents, Papers, Publications Government of Guam, Department of Commerce (R. C. Krueger), The Gross Island Product of Guam, 1978. ,Statistical Abstract, Guam, Volume 8, 1977. Government of Guam, Guam Energy Office, Burke, A Prelimina- ry Management Study of, he Guam Petroleum Storage System and the Feasibility of the Establishment of a Guam Petro- leum Reserve, 1976. Energy Flow Charts, 1976, 1977. Government of Guam,.Environmental Protection Agency, Guam Water Quality Management Plan, 1978. Erosion and Sedimentation Control Guide for Guam, 1977. Air Quality Implementaion Plan, 1974, 1977. Guam Air Quality Implementation Plan, 1977. Fourth and Fifth Annual Reports, 19.77, 1978. 124 Government of Guam, Fourteenth Guam Legislature, Report on the Special Study Commission on the Guam Supertanker Port, 1978. Government of Guam, Department of Law, Government Code of Guam, Volumes 1-111, 1970. Government of Guam, Department of Parks and Recreation, Outdoor Recreation on Guam, 19-7.3. Guam Comprehensive Outdoor Recreation Plan,1977. Government of Guam, Bureau of Planning, Comprehensive Develop- ment Plan, 1978. Land-use Plan, 1978. Community Design Plans, 1973. Overall Economic Development Plan, 1977. Growth Policy for Guam, 1977. Guam Coastal Management Program, 1978. Flood Hazard, Wetlands, Rules and Regulations,1978. Coastal Management Technical Reports, Vol 1, 1977. Population Projections, 1976, 1978. Interim Territorial Emergency Plan, 1977. Coastal Planning Bibliography, 1978. Adaptation and Adjustment to Hazard s on Guam: An Analysis, 1977. Government of Guam, Guam Power Authority, Annual Reports, 1973-1977. Official Statement Relating to $17,50O,000 Re- venue Bond Series B 1972 Issue. ,(Extract) Capital Improvement Needs Summary Request,, FY 1979-2000. C. University of Guam, Marine Laboratory Reports, Studies University of Guam, Marine Laboratory, Annual Report, 19.76-19.77. Contributions, Technical Reports, Environmental Survey Reports, Miscellaneous Reports, and M. S. Theses, 1978. 125 ... (Amesbury et al) Marine Environmental Baseline Report, Commercial Port, Apra Harbor, Guam. Eldridge, Dickinson, Moras, Marine Survey of Agat Bay 1977. Jones, Randall, A Study of Biological Impact Caused by Nature and Man-Induced Changes on a Tropical Reef,1974. Marsh, Chernin, Doty, Power Plants and the Ma- rine Environment in Piti Bay and Piti Channel, Guam: Observations and General Summary, 1977. Marsh, Gordon, Marine Environmental Effects on Dredging and Power Plant Construction in Piti Bay and Piti Chan- nel, Guam, 1974. Neudecher, Effects of Thermal Effluent on the Coral Reef Community of Tanguisson, 1976. Neudecher, Development and Environmental Quality of Coral Reef Communities Near the Tanguisson Power Plant, 1977. Randall, Birkland, Sedimentation Studies at Fou- ha Say and Ylig Bay, 1978. Randall, Lassuy (Extract), Preliminary Findings: Delta T and Chemical Seawater Studies for OTEC, 1978. Rupp, Larson, A Marine Environmental Survey for the GORCO Deba1lasting Faci1ity Outfall, Cabras Island, Guam, 1972. D. Miscellaneous Government of Guam-Sponsored Studies, Regu- 1ations Barrett and Associates, Inc., Environmental Management Study, Fi- nal Report, 1978. Bechtel, Inc., Program for Development of Apra Harbor, 1977. University. of Hawaii (Smith, Chave, Kam:), Atlas of Kaneohe Bay, 1973. Tokyo Electric Power Services Company, Ltd. (TEPSCO), Proposal for Ocean Thermal Energy Conversion Plant in Guam Island, 1977. 126 E. Proceedings, Conferences Proceedings: Fourth Annual OTEC Conference, Division of Solar Energy, U. S. Energy Research and Development Administration, New Orleans, Louisiana, 1977. Symposium on Flue Gas Desulfurization, Control Systems Labora- tory-Sponsored), U.S. Environmental Protection Agency, Atlanta, Georgia, 1974. F. Reports, Studies, Miscellaneous U. S. Federal Government U. S. Army, Corps of Engineers, Moore, Raulerson, Chernin, McMa- kin, Inventory and Mapping of Wetland Vegetation in Guam, Tinian, Saipan, Marian Islands, 1977. Price, Cultural Resources Reconnaisance, Cabras Island, Apra Harbor, Territory of Guam, 1977. Permit Program, a Guide for Applicants, 1977. U. S. Environmental Protection Agency, Implementation Plan Re- view for Guam as Required by the Energy Supply and Environmental Coordination Act, Research Triangle Park, North Carolina, 1975. Federal Interagency Committee on Evaluation of State Air Imple- mentation Plans, Projected Utilization of Stack Gas Cleaning Sys- tems by Steam-Electric Plants, Washington, D. C., 1976, U. S. Environmental Protection Agency, An Engineering-Economic Study of Cooling Pond Performance, U.S. Government Printing Of- fice, Washington, D. C., 1970. U. S. Department of the Interior, R. W. Miller, Guam Needs Assess- ment, 1978. U. S. Congress, Office of Technology Assessment, Renewable Ocean Energy Sources (OTEC), Washington, D. C., 1978. U. S. Department of Commerce, National Oceans and Atmospheric Administration, National Marine Fisheries Service, Effects of Oil on Marine Ecosystems: A Review for Administrators and Policy Ma- Makers, Seattle, Washington, 1974. Office of Coastal Zone Management, Coastal Ener- gy Impact Program, Administrative Procedures, FR Volume 43, Num- ber 37, Washington, D. C., February 23, 1978. 127 G. Periodicals, Company Magazines,Reports Babcock and Wilcox Company, S-team, Its Generation.and Us e, New York, 1972. Chicago Bridge and Iron Company CCBI), "Transshipment Terminal, CBI News, Oak Brook, Illinois, September, 1977 Exxon Corporation, World Energy Outl'ook, New York, 1978. General Electric Corporation, Steam Turbi'ne.Generztors, Con- densing and Noncondensing Applications., Chicago. H. Personal Corresoond ence and Intervi'ews CSee Appendix 5 for listing.) 123 I I I I I , - I I I I .Appendix 1. I .. I I I I I I I I I Appendix 1 I. Central Terminal Station - Summary 11. OTEC - Ongoing Studies - Discussion I. Central Termi'nal Station (CTS) Conceived in response to rejection of a Palau location for a so-called superport, interest generated in the 1"'4th Guam legis- latu re for an alternative location for such a facility resulted in a preliminary study, "Report of the Special Study Commission on the Guam Supertanker Port". Proposal To establish a crude oil transshipment facility on Guam to meet Japanese demand for "a more stabilized and secure source of energy", by construction of a facility capable of storing a 90- day crude supply for Japan. Ra-tionale VLC C & ULCC (Very Large Crude Carrier and Ultra Large Crude Carrier) ship construction of the 250,000 to 500,000 deadweight- ton (DWT) range has made use of traditional routing through the Malacca straits impossible due to maneuverability and draft of vessels. Supertankers must go further south and east to Lombok strait between Borneo and Celebes. The traditional tanker route has thus been shifted east of the Philippines, making a storage 130 facility feasible for Palau, the P hilippines or the Mariana I s 1 a n d s Requirements A one-day demand of crude oil for Japan, 4.72 million bar- rels, would require 7.5 tanks of a 629,000 bbl. capacity. One of these tanks, approximately 2-1/3 times the size of the GPA storage tanks, would require + 10 acres of flat land. An ini- tial phase of a 20-day supply mentioned in the report would re- quire 150 tanks and 1,500 acres of flat, geologically stable land. The ultimate plan of 90-days' storage capacity would re- quire 675 tanks on 6,750 acres of land. The fact is that no suitable land area exists for such a massive development, with- out substantially altering tremendous areas of steeply sloped, geologically unstable, conservation-designated land. Details for each potential location are discussed in the report. Impacts There are no positive environmental impacts possible under this project Massive erosion and sedimentation, destruction of wetlands, estuaries, rivers and associated wildlife and water ha- bitats, visual pollution, s.ignificant demands on existing public facilities Croads, water) and extreme'threats of massive oil spills are a certainty. The fact that Guam is located in one of the most active earthquake zones on earth, where strong earth- quakes occur more frequent ly than in California, should raise a flag of cautio n to massive development of steep volcanic slopes as should the frequency of typhoons to siting of other energy fa- cilities in flood-prone areas, without adequate wind and water 131 resistant as well as containment capabilities. Of further interest is the fact that an Agat location for the Cabras.generating units, as area with very similar geologi- cal characteristics as the proposed CTS sites, was rejected due to potential erosion problems,.geologic stability factors, and associated engineering costs. Economically, the project would mean a sizeable influx of alien construction workers and very temporary benefits to local industry. Gross receipts taxes are premature to project, since some relaxation or grace period is common to attract such indus- try in the first place. Additional permanent employment would be marginally beneficial to the island; however, since the pro- ject is foreign-owned, it can be assumed that personnel, except in lower-skill jobs, would be from off-island. Such is the case for a much smaller facility located on Bonnair in the Dutch An- tilles, north of Venezuela. Bonnai'r Faci'li'ty t- A Brief Comparison The Bonnair transshipment facility, located just off the coast of Venezuela, transfers Near East Crude brought in on su- pertankers into 8,660,000 bbl. tanks, to smaller tankers for transshipment to the U. S. The tanks, similar in size to those projected for Guam are 272 feet in diameter and 68 feet tall. "The island was selected for this facility also because it lies well south of hurricane alley.. never has been struck by a hur- ricane ... and the last severe tropical storm touched the island in 1886." Four of the facility's 8-main tanks are located less than 600' from the water's edge, on fla,t, geologically stable * (Source: CBI News', 5/77) 132 land. Two supertanker berths lie approximately 500' offshore and about 1200' from the tanks, themselves. Such conditions are not even comparable to those on Guam. Study Gaps While the commissionis report establishes the rationale for the project as the necessity of VLCC & ULCC's carrying crude oil east of the Philippines, the opening paragraphs state that "con- struction of berthing facilities for tankers in excess of 250,000 OWT could never be realized nor could accommodating activities such as refineries Cetc.). ..be supported here. Later in the re- port, a distinction between a transshipment facility and a CTS is hinted-at but never discussed. According to port consultants and the U. S. Coast Guard, the feasibility of such a project is very questionable without the use of the large tankers. CEIP Funds Should further invest.iga tions continue on the feasibility of the CTS, a large amount of CEIP planning funds should immedi- ately be.utilized for impact investigation. Given the investment even for initial phases as well as potential i-mpacts, a.good deal of funding should be available under Section 308 Cc'). Applica- tion should be made as soon as further studies are completed, gi- Ying more than a speculative basis for the CTS. 133 II. OTEC - Ongoing_Studies - Discussion Local OTEC Studies, ProJects Two ongoing studies have been funded by the Guam Energy Of- fice in addition to a recent series of proposals developing through the University of California's Berkeley Lawrence Labora- tory. OTEC Data Sea-rch, R. Randall, UOG Marine Lab, +$ll 000; by November, 1978 Purpose: Temperature le7els to 3,000 feet, water chemistry, slope and bottom topography, bottom substrate and ocean current study review. Comments: Preliminary partial summary of findings available August, 1978, Dennis Lassuy Cg.raduate student) assisting on project. Siofouling Stu dies, Dr. C. Birkland, UOG Marine Lab +$3700. Purpose: Examine rate of slime formation, bacterial growth, and calcium carbonate.disposition; correlation of data with Guam biofouling rate with other regions. Comments: Slow start due to administrative financial problems. In a related activity, a represen- tative from Battelle visited Guam December 1, 1977, for initial DOE biofouling experimental facility location. 134 The only results from this visit appear to be. a dis- claimer by the Battelle representative that any commitments were made to locate the facil ity here. C2/8/78) Department of Energy (DOE) DOE is actively involved in range of OTE'C feasibility stu- dies. Federal funds continue to be awarded for technical, eco- nomic, financial, legal, and planning aspects of OTEC develop- ment, several criteria for which Guam more tha'n qualifies when compared with other potential sites. Two problems are evident in the securing by local firms of DOE/OTEC.grants. One is concerned with.general ignorance on the- part of W-ashington people and its contractors that Guam not only exists, but should be a prime candidate for OTEC location. GEO and GPA recognize this "low visibility" problem-and are investi- gating methods of solution. In fairness to the federal government, however, erroneous impressions of Guam's potential could be partially attributed to a questionably accurate report prepared by the U. S. Navy and not coordinated with local expertise or Gov Guam (1975: "Suita- bility of Guam from an Environmental Aspect as a Potential Site for OTEC Plants") which stated essentially that OTEC plants on Guam are not feasible due to adverse effects of cold effluent sur- face discharge on warm water near-shore flora and fauna. The se- cond problem may be that local A & E firms are simply not receiv- ing RFP's from DOE. Often even the RFP's that do reach Guam are several weeks late, making widespread distribution impossible. Obviously, local conditions are best known by local firms, especi- 135 ally such things as economic, demographic, financial and social conditions. Presently, increasing interest is being generated for Guam, mostly because of i.rrefutable data i-ndicating site su- periority over other locations. Lacki.ng is knowledgeable and vi- gorous Washington, D. C., representation as well as a financial commitment by Gov Guam to OTEC CHawaii recently appropriated some $10 million for such activities). DOE RFP's which have reached Guam, albeit rather late for serious consideration include : - 1. RFP 4784406, Argonne Natio-nal Laboratory, for "Design and Construction of an OTEC Seacoast Test Facility". COnly 45 days to analyze, dis- tribute, prepare and send proposals.). Action letter sent to Argonne subcontractor indicating inadequate time pe riod but a continuing interest. 2. RFP #ET-78-R-02-0019, DOE Chicago Operatfons Of- fice, "Electric Utility System Planning Studies for OTEC Power Integration". (.Extension to Oc- tober 2, 19-78,.granted to Guam for RFP prepara- tion.) The latest development is that Fairchild's Stratos Division has been awarded the contract and that Guam, through a contract amendment coordinated by Dillingham Corporation, will be included as a participant together with Hawaii and Florida. Further de- tails should be available shortly through W. F. Pinckert and As- sociates. 136 Berkeley Lawrence Laboratory - Department of Energy Re- search - Four-Phase Study Discussion: Lawrence Laboratory has been contracted by the Depart- ment of Energy to evaluate "Bio-ecol.ogical Concerns" of OTEC development. Guam's involvement could be in several increments: 1. Literatur*e Search CTentatively Approved - $10- 15,000): Exhaustive review of biological-ecologi- cal data presently available which would be of value for OTEC development. (UOG Ma-rine Labj 2. Data Collection: Based on literature search, es- tablish program for "standard bi-monthly measure- ments" for such things as temperature, chemistry, and current variations and seasonality effects Shipboard time wilT have to be contracted out Effort will be made to utilize Guam expertise. Proposal required by seventh month of Phase I. 3. Long-term Data Collection': Establishment and maintenance of "augmented measurements" program. Phase II data evaluated and ongoing monitoring system established. This would continue even af- ter plant construction. 4. Final Writeup : Sum total of data evaluated in fi- nal form, probably would be the basis for plant construction. Time frame uncertain.at present time. 137 Tokyo Electric Power Services Company (TEPSCO). One OTEC possibility involved the discussion of a Japan- based firm to construct a plant on Guam. A very preliminary discussion paper was prepared by TEPSCO for Ithe siting on Guam of a cost of some $32 million for a land-based 4 x 2.5 MW plant. Further discussions indicated that a DOE/GPA/TEPSCO coordinated effort was not feasible under present plans. The current status of the project is uncertain. 138 I 14 I I I I I I I I Appendix 2. 1 . I I I I I I I I I Appendix 2 Islandwide Power System - - Approximate averages for peak demand (K'IV) 1_972-1978 MONTH MTHLY QTRLY 6 MOS ANNUAL AVERAGE AVERAGE AVERAGE AVERAGE 1972 Jan 118,350 Feb 120,800 120,800 Mar 120,800 Apr 125,000 123,600 May 126,400 126,400 Jun 127,900 131,100 Jul 131,300 Aug 133,000 135,200 Sep 141,200 138,600 Oct 144,400 Nov 142,000 142)000 Dec 139,500 1973 Jan 134,900 Feb 134,700 136,500 Mar 140,000 Apr 144,700 140,800 May 147@200 145@000 Jun 143,200 142,200 Jul 146,600 Aug 146,300 148@300 143,600 Sep 151,900 Oct 151,800 Nov 151,100 147,000 MONTH MTHLY QTRLY 6 HOS ANNUAL AVERAGE AVERAGE AVERAGE AVERAGE 1974 Jan 126,500 Feb 132,700 132,800 Mar 139,100 138,500 Apr 144,100 May 143,700 144.4300 Jun 145,000 144,800 Jul 142,900 Aug 149,600 148,400 Sep 152,800 151,100 Oct 156,600 N ov 154,600 153,700 Dec 150,000 ............ Jan 143,300 Feb 141,000 143,300 Mar 145,600 146,800 Apr 147,500 May 153,200 1SO,300 Jun 1502300 147,500 Jul 143,600 Aug 144,100 145,900 Sep 150,000 148,200 Oct 153,900 Nov 147,600 1501500 Dec 150,000 141 I-IONTH MTHLY QTRLY 6 MOS ANNUAL AVERAGE AVERAGE AVERAGE AVERAGE 1976 Jan 146,000 Feb 143,000 144,700 Mar 145,000 141,200 Apr 146,000 May 143,000 137,700 Jun 119,000 142,200 Jul 128,800 Aug 140,200 138,900 Sep 1472500 143,300 Oct 147,000 Nov 149,000 147@700 Dec 147,000 1977 Jan 146,000 Feb 142,000 144,000 Mar 144,000 143,800 Apr 143,200 May 144,000 143,600 Jun 1432700 147,900 Jul 141,000 Aug 155,000 150,000 Sep 155,000 152,000 Oct 156,000 Nov 154,000 154,000 Dec 151,000 142 MONTH MTHLY QTRLY 6 MOS ANNUAL AVERAGE 'AVER-AGE AVERAGE 'AVERAGE 1978 Jan 144,900- Feb 141,800 144, 900 Mar 148@100 Apr 151,500 149,550 149,550 May 156,000 Jun 155,000 154,200 Jul 147,700 Source: Guam Power Authority 143 I I I I I I I I I Appendix 3. I -1 I I I I I I I St L -4, rv zp rx 1A17474YVII gY-,?M4V-.,AA)eNA T @5n ffT. oi- I. A -77 17: 4 ptW7 svp r 'JIAV'7 'T .01 Vim 77 - =V27r N. .2-R! :@Lfi Z 4 -4 R, , Mtt cc ftZA 2.7 r ru VUTUBPZRH ZBnOa :c XICIRZCICTV wl @.A;E'131 Ir WI&IT I Liss" jr 14- IL T A"S P., T" @ifl- kq _gv 5 WI I,j Ll 50415,11 UP ;IR fiWA VCI@ 11AE w% I YU In .3p, 7:1 .51V AM @N ii 1Y j-g., A. YX 4;11h ;Ali-.i Ar 0. lip, I C" M MW111111, ': j PIT nYi p 4;@ ENY'Orw 1@-, APO VP g7 wag AS PZ A t pi. 1 q 0_- Aln EN f. 40Y.Mi. "t,3vt, -i V1,4 I 11 wit :,j. g opvv.@ V@ , OT '. 0; , 1 .- . , . . -,,;, ! .0, ::tn a pgl q 6 N P 1@', Mw f r -40 1. 1,04 -SN", Kig? P@ Mr -:0Z, ,SOIL. R '-R 14 16092 MR, 7;5_51sl 'ON X't.7'i F Vt BA42et UA4 Z:: - 7!q, .:";7 iT AVASWAUVP 4 r, @..Aq z7 % Z.V, A NE:E M- R_ im -57 .It .It .It C@r -mT; hil R ZWM@ -aw Y4 .1,4 Y4 -Y4 1: IM V Y: @'elVMef --,Y?4 . . . . . . . . . . jz w nO 1 d7 v II!, IT I Its fit ICU Y "Im, AQ 1 .1 qg)g 1 4 t X g"'I ZV -up. K A v -M a 1 1-4, 1 14 5, NX, t4 N 51: INE v, 'A X a 11 A . . . . . . . . . . ...... ..... I I I I I I I I I Append.ix 4 I I I I I I I I I I Appendix 4 Federal Participants in the Corps of Engineer's 'Permit Rd-,@ie-rw Process. MENBERS OF CONGRESS Honorable Spark M. Matsunaga, United States Senate, Washington, D.C. 20510 United States Senator, P. 0. Box 50124, Honolulu, HI 96850 , Honorable Daniel K. Inouye, United States Senate, Washington, D.C. 20510 United States Senator, 300 Ala Moana Blvd., Rm 6104 Honolulu, HI 96813 Honorable Cec Heftel, House of'Representatives, 322 Cannon House Office Bldg, Washington, D.C. 20515 Representative in Congress, 300 Ala Moana Blvd, Rm 4104, Honolulu, HI 96850 Honorable Daniel K. Akaka, House of Representatives, 415 Cannon House Office Bldg, Washington, D.C. 20S15 Representative in Congress, 300 Ala Moana Blvd, Rm 5104, Honolulu, HI 96850 FEDERAL GOVERN@ENT IIQDA-<DAEN-CWO-tN)--WASH-DC---2Oal4 HQDA (DAEN-CWZ-G) WASH DC Z0314 Board of Engineers for Rivers and Harbors, Kingman Bldg, Fort Belvoir, Virginia 22060 Director, Defense Mapping Agency, Hydrographic Center, ATTN: INS12, Washington, D. C. 20390 Defense Mapping Agency Depot, Hawaii, Hickam AFB, HI. 968@S3 Director, HQ USAF (PREV), Washington, D. C. 20330 Commandant, Fourteenth Naval District, Box 110 (Code 002), Pearl Harbor, HI 96860 Commander, Fourteenth Coast Guard District, 300 Ala Moana Blvd, 9th Floor, Honolulu, HI 96850 Commander, Fourteenth Coast Guard District, ATTN: Office of Aids to Navigation, 300 Ala Moana Blvd, 9th Floor, Honolulu, HI. 96850 CommanAer in Chief, U. S.'Pacific Fleet, Pearl Harbor, HI 96860 Commander, Pacific Division, Naval Facilities Engineering Command, Pearl Harbor, HI 96860. Commander in Chief, Pacific Air Force, Hickam. AFB, HI 96853 Regional Director, Pacific-Asia Region, Federal Aviation Administration, ATTN: Planning/Appraisal Staff, APC-4,,; P. 0. Box 4009; Honolulu, HI 96813 Regional Director, National Park Service, US Dept of the Interior, ATTN: interagency Archeological Services, 450 Golden Gate Ave., Box 36063, San Francisco, CA 94102 Commander, Pacific Division, Water Quality Lab, Naval Facilities Engineering Command, Pearl Harbor, HI 96860 Mr. Jerry Delli Priscoli, Institute for Water Resources, Department of the Army, Corps of Engineers, Kingman Building, Ft. Belvoir, VA 22060 Chief, National Park Service, Office of Archaeology & Historic Preservation, 5113-L Street, Washington, D.C. 20240 ..150 FEDERAL GOVERNM.E-NT (tont'd) Director, National Ocean Survey, NOAA (C322), U. S. Department of Commerce, Rockville, Maryland 20852 Director, Pacific Marine Center (CPM 101), National Ocean Survey, NOAA, U. S..Department of Commerce, 1801 Fairview Ave, East, Seattle, Wash-ington 98102 Bureau of Outdoor Recreation, Pacific Southwest Regional Office, U. S. Department of the Interior, 450 Golden Gate Ave, Box 36063., San Francisco, CA 94102 U. S. Geological Survey, Water Resources Division, 300 Ala Moana, Bl'vd... Rm. 6110, P. 0. Box.50166, Honolulu, HI 96850 Regional Director, Southwest Region, National Marine Fisheries Service, NOAA, U. S. Department of Commerce, 300 South Ferry St, Terminal Island, CA 90731 Administrator, Western Pacific Programs Office, National Marine Fisheries Service, P. 0. Box 3830, Honolulu, HI 96812 Regional Administrator, Region IX, U. S. Environmental Protection Agency, Permits Branch, E-4, 215 Fremont Street, San Francisco, CA 94105 Re.gional Director, Region 1, Fish and Wildlife Service, U. S. Department of the Interior, P. 0. Box 3737, Portland, OR 97208 Area Supervisor, Division of Ecological Services, Fish and Wildlife Service, U. S. Department of the Interior, 300 Ala Moana Blvd., Rm 5302, Honolulu, HI 9681.3. Secretary's Field Representative, Pacific Southwest Region, U. S. Department of the interior, 450 Golden Gate Ave, Box 36098, San Francisco, CA 94102 Chairman, Advisory Council on Historic Preservation, National Park -Service., Washington, D. C. 20240. Chief, National Park Service, Arizona Archeological Center, U. S. Department of the Interior, P. 0. Box 49008, Tucson, Arizona' 85717 Director, National Park Service, Hawaii State Office, 300 Ala Moana Blvd., Sji4&;:_-e 6305, Box 561-65, Honolulu, HI 96850 Federal Inrormation Center, P. 0. Box 50091, Honolulu, HI 96850 Director,, Coastal Engineering Research Center, Kingman Bldg, Fort Belvoir, VA 22060 Director, Office of Territorial Affairs, U. S. Department of the fnter'ior, Washington, D. C. 20240 Resident firector, Federal Aviation Administration, Route 008,, Finegayan, Guam 96912' Commander,@U. S. Naval Forces, Marianas, FPO San Francisco 96630 Dept of the Navy, OICC NFECC, M. I., FPO San Francisco 96630 National Aeronautics and Space Administration, Guam Station, Dandan, Guam 96916 U. S. Public Health Service, Agana, Guam 96910 Manager, Bureau of-Land Management, Pacific Outer Continental Shelf Office, U. S. Department of the Interior, 300 N. Los Angeles St, Rm. 7127, Los Angeles, CA 90Q12 Only PNs for Summary of Permit-Actions -General Permits 151 FEBERAL GOVERNMENT (CON'T) National Weather Service, National Oceanic and Atmospheric Administration, Route-8, Agana, Guam 96910 Small Business Administration, P. 0. Box 927, Agana, Guam 96910 U.. S.-Attorney's Office, P. 0. Box Z', Agana, Guam 96910 Guam Observatory, P. 0. Box 8001, MUO #3, Agana, Guam 96910 Commander, Anderson Air Force Base, APO San Francisco 96334 Commander, U. S. Coast Guird, Marianas Section, FPO San Francisco 96630 Commander, U. S.. Coast Guard, Marine Safety Office, FPO San Francisco 96630 Commander, Naval Air Station, FPO San Francisco 96630 Fleet Weather Control, FPO San Francisco 96630 Commander, Naval Magazine, FPO San Francisco 96630 Commander, Naval Station, FPO San Francisco 96630 Commander, U. S. Navy Public Works Center, FPO Sari Francisco 96630 Commander, Ship Repair Facility, FPO San Francisco 960630 Commander., Naval Supply Depot, FPO San Francisco 96630 Commander, Submarine Squadron Fifteen, FPO San Francisco 96630 Federal Highway Administration, Bridge Division - HNG-31, 400 7th Street, S.W., Washington, D ..C. 20590, CPNs for Summ. of permit Actions & Gen Permits 152 I I I 1, i I I I I Appendix 5 I I I I I I I I I I I Appendix , 5 'CEIP I'ntervi'ews Party Date Subject 1. Guam Power Authority 8/2/78 OTEC and CEIP Guam Energy Office 2. Mgr.-Guam Power Authority 8/3/78 GPA OTEC Participation 3. Mgr.-GORCO 8/4/78 Preliminary CEIP Discussions 4. DRS. Tsuda, Amesbury, Winter and Eldredge UOG Marine Lab 8/11/78 Literature search, Energy Facility Impact Discussions S. U.S. Coast Guard Seminar Saipan 8/17, 8/18 Coast Guard Spill Responsibilities, 6. Guam EPA Contingency Plans Mssrs. Branch, Wong, Pontemeyer, Cabrera 8/21 Preliminary CEIP Discussions SO and Water Quality iegu- lations 7. Guam EPA Pontemeyer 8/24 Air Quality Regula- tion Revision Plans, Problems with exis- ting Systems 8. Mgr., Guam Power Authority 8/25 Delivery of Pre limi- nary Projections 9. Guam Power Authority, Mssrs. Smith, Benavente, Cabrera 8/27 Transmission grid expansion, SO 2 and water quality pollu- tion Economics Sales and Peak Demand Data 10. U.S. Navy- OICC Cmdr. Zimmerman 8/31 Power System Harden- ings, Navy Contract Administration, Navy Transmission Facilities 11. Mobil Oil Corporation Mr. R.S. Rideout 8/31 Preliminary CEIP Infor- 154 mation Requests CEIP Interviews cont' Party Date Subject 12. Esso Eastern, Inc. MT. Bish Parmar 8/31 Preliminary CEIP In- formation Requests 13. Guam Power Authority MSSRS. Cabrera, Tablante 9/1 Detailed Discussions on 115KV Lines, Plans for Expansion 14. Esso Eastern Inc.. Mgr., Bish Parmar 9/5/78 Detailed facility Expansion and Impacts Discussion 15. GEPA, John Cabreza 9/5/78 Bulk Storage Infor- mation 16. UOG Marine Lab Dick Randall Dr. J. Marsh 9/6/78 Detailed Discussion on UOG/US DDE OTEC Study Participation Detailed discussion on Cabras Plant Im- pacts on Marine Envr. 17% U.S. Coast Guard Ens. Burndett, MSO 9/7/78 Oil Spill Contingency Plans, Port Tanker Traffic Patterns, Traffic Control and Safety Requirements Spill Cleanup, Regio- nal Strike Force 18. Dept. of Public Works Highway Planning, Benavente; Highway Engineering, R. Quijano. 9/11/78 Highway Construction costs, coordination with power line loca- tion, joint use agree- ments 19. Dept. of Parks and Recreation Mr. Robert Cruz, Dave Lotz, Gary Stillburger 9/11/78 Energy Facility Impact on Recreation, Recrea- tion Facilities, Historic sites, Tan- guisson/NCS plans, compliance with NPDES requirements 155 Party 20. DPW/PUAG Mr. B. Dela Rosa Mr. Joe Guitierrez 9/12/78 DPW Coordination w/Navy hardening pro- jects; waterline costing, placement, sizing and use by Energy Facilities. 21. Department of Public Safety Asst. Chiefs Mesa, Taijeron 9/13/78 Preliminary CEIP Dis- cussion, Detailed discussion of equip- ment needs, oil ?ire capabilities and bud- geting for new equip- 22. GEPA ment. Mr. R. Pontemeyer 9/15/78 Latest of So 2 strategy, 23. GEPA Mr. J. Branch 9/16/78 GPA.thinking on water quality standards and effluent regulation, 24. Guam Airport Authority Lockheed Fuel Consultant Mr. J. Mazanti 9/18/78 Details on plans for expanded fueling facil ties at the Terminal, 25. Marine Int'l., Joint Ventures Captain Tarr 9/21/78 Port Traffic Opera- tions and increased traffic due to possi- ble energy facility expansion, 26. Mobil Oil Corporation Mgr. - Mr. Barney 9/22/78 Detailed facility expansion and impact discussion. 27. GORCO Mgr. Mr. F. Cochran 10/22/78 Detailed facility expansion and impact discussion, 28. U.S. Navy PWC 10/3/78 Lt. Cmdr. Layman Navy Energy Facility Power Consultant R. Duncan Expansion plans; Chief Facilities Engineer power pool agreement) water arrangements, 156 Party Date Subj'ect 29. GORCO Production & Sales Mgr. 10/3/78 Chemical processing and Frank Santos output data, water availability expansion of tankage. 30. Marine Int'l, Joint ventures Mr. D. Reiss 10/17/78 CEIP and Port Operations 31. Dept. of Public Safety Chief Wusstig 10/17/78 CEIP and fire safety 32. U.S. Coast Guard facilities expansion. Captain of the Port 10/18/78 Traffic control systems & possible CEIP parti- cipation. 33. Barret and Associates Scott Kvandal 10/18/78 Specific discussions on Agat-Santa Rita water consumptiom & GORCO refinery, plans for new water lines, costings. 34. U.S. Army Corps of Engineers Mr. Frank Dayton 10/19/78 COB permit process, CEIP and federal review of permits, 157 I I I I I I I I I Appendix 6 1 I I I I . I I I WALTER F. PINCKERT & ASSOCIATES To[: 477-7550 Engineers and Considtants Telex: 721-6181 P.O. BOX 2636. AGANA, G UAM 96910 -Subject:' Guam's Coastal Energy Impact Program (CEIP) Dear Sir: The Government of Guam, by virtue of having an active program under the U.S Department of Commerce Coastal Zone Management Program, is eiigible for funding under the Coastal Energy Im- pact Program. Financial assistance is available to GovGuam and its agencies in the form of outright grants, or repayment assistance for such things as public facilities needed as a result of new or expanded coastal energy activity, facility impact planning, or unavoidable losses to coastal environmental and/or recreational facilities. The initial.study to be prepared by Walter Pinckert & Associates is concerned with Planning for the Consequences of Energ Facil- -ities. In order to qualify for future funding from the @1.2 C, 'billion allotted over the next 10 years,- it is-necessary to identify specifically the type of energy facilitydevelopment which will occur now and in'the future. ?'Energy activity" is defined to include not only power produc- tion facilities, but pipelines., transmission facilities, refin- ing E@nd-storage systems, deepw'ater ports, and associated equip- ment and/or facilities.. To qualify as "new or expanded" such facilities must be those whose siting, construction, expansion, ..initia'1 operation, or repl@Lcement, in whole or part, takes place after July 26, 1976. Themajor questions which we will be asking are: 1) What is happening now and what will be happening in the next 10 years (1986) as far as energy facility development is concerned. 2) What specific plans are available now. What level of planning activity is presently be-ing carried out and in the near future. .3) What additional public'facil'ities 'do you foresee as- being nec.essary as a result of planned expansion or construction of these energy facilities. 1.59 What ate your siting, licensing or leasing policies for additional land areas for new or expanded facil- ities, if any. .5) Do you foresee any great difficulties posed by envi@ron- mental regulations insofar as-development of additional facilities are concerned It is recognized in Guam's new Land-Use Plan, Community Design Plans, Comprehensive Development Plan, Port Master Plan, and the Coastal Management Program that energy facilities will be one of the most critical components of coastal as well as. economic development for Guam. With proper planning Guam can share the burden of future expansion with the Federal Government,, The attached sheets provide some additional information relative- to this program. We are furnishing the foregoing as advance information on the CEIP program and shall call you by telephone to arrange a mutually convenient date to discuss the implica- tion of the program.in relation to your activities now and as planned,in the future. your cooperation. 'Thanking you for Sincerely., WALTER F. PINCKERT Attachments: a/s 160. ATTACIU4ENT General Information for CEIP, Coastal Energy Impact Program Note: The following information has been derived from the final regulations of the U. S. Department of Commerce for the Coastal Energy Impact Program. These are found in the Federal Register, Volume 43, No. 37 of Thursday, February 23'p 1978.- PROGM11 ASSISTANCE @ Four basic kinds of assistance are available through the CEIP. 1. Planning Grants are available to Guam to help prepare for the Zonsequences of all new or expanded energy facilities in the Coastal Zone.' Since on Guam theentire island is considered to be a part of the Coastal Zone all energy facilities qualify for examination under a planning grant. Such things as physical impacts and methods of amelioration, summation of natural and recreational resources in the area of proposed expansion, and location and scheduling of required new public facilities would !be examples of subjects to be addressed under the present planning grant. A specific example might be the location, design, construc- tion, and equipping of a.fire station serving the special needs of energy facility emergencies. 2. Credit Assistance may be available to Guam in the form of direEt loans or guarTntees of loans or bonds. In the example above, a new fire station may be nebded as a result of GORCO, GPA, or oil company facility expansion. Although the community tax base will eventually be expanded, there will be a lag between the time the new fire station is needed and the time the actual revenues from the facility are realized. The CEIP will provide financial backing for Guam as it seeks to acquire funds through borrow-ing so that public facilities and services can be provided when needed. 3. Repayment Assistance*i%rould be available to Guam in the event that it is not able to meet its .CEIP credit obligations because revenues from energy facilities fail to materialize as expected. This amounts to a guarantee that a community receiving CEIP assistance will not sustain.a net fiscal loss from coastal energ .7 activity. For example, suppose Guam expanded its sewage treatment plant and has put in place new water and sewer lines to accomo- date ex-oected additional infrastructure pressures as a result of energy @acility expansion; however, conditions change so that expected revenue is not realized. Thus the expected increase in tax.revenue which had been counted on tocover the loan or bond obligation which financed the public facility will not be forth- coming. In such a case, the obligation can 'be covered from @CBIP funds. The circumstances under which this could happen are: 161 1) If Guam had taken a direct loan from the CEIP, or had utilized a CEIP guarantee; and 2) There is a change in scope of the energy activity such that sufficient revenues do not materialize as projected. Repayment assistance can consist of modification of credit terms, refinancing, a supplemental loan, or a repayment grant. 4.. Environmental Grants could be available to help prevent, -reduce, or repair Fa-mage to or loss of valuable env-ironmental or recreational resources. If, for example, the siting of an eneTg-y facility in the past resulted in the loss of or damage to a public beach or boating facility, a community could use CEIP grants to purchase access rights to a similar beac.h or boat facility area. CONPLIANCE WITH OTHER FEDERAL REQ.UIREMENTS Projects funded with CEIP"funds must be carried out in compliance with relevent re- quirements of other Federal laws, especially the Federal Water Pollution Control Act as amended, the National Environmental Protection Act (NEPA), the Clean Air Act, and the Rivers and Harbors Act. 162 iiiiimmiiililli@imii 3 6668 14109 7479