[From the U.S. Government Printing Office, www.gpo.gov]
Coastal zone Intormation CONSTRUCTING A FLOATING Center TIRE BREAKWATER THE LORAIN, 0HIO EXPERIENCE March, 1982 City of Lorain TC 333 .l43 1982 CONSTRUCTING A FLOATING TIRE BREAKWATER - THE LORAIN, OHIO EXPERIENCE - Principal Author: D. Thomas Lee D. Thomas Lee & Associates 2200 West Erie Avenue Lorain, Ohio 44052 Editor: John G. Sulpizio Executive Director Lorain Port Authority Room 511, City Hall Lorain, Ohio 44052 Typist: Ruth Wiseman Executive Secretary Lorain Port Authority Reprodu ction: Goodyear Tire and Rubber Company Akron, Ohio 44316 Photocopy: D. Thomas Lee John G. Sulpizio Goodyear Tire and Rubber Company Funding: The Ohio Department of Energy Lorain Port Authority This report is available from the Lorain Port Authority at a $5.00 cost to cover postage and handling. A 65-slide presentation with written narrative is available from the Lorain Port Authority at a cost of $ 100. O:r (7rC LibrarY U . S . DEPARTMENT OF COMMERCE NOAA COASTAL SERVICES CENTER 2234 SOUTH HOBO'ON AVENUE CHARLESTON , SC 29405-2413 N This report was prepared, in part, with financial assistance from the Coastal Energy Impact Program, Coastal Zone Management Program administered by the Ohio Department of Energy. PREFACE In January, 1981 the Lorain Port Authority began the construction of a Floating Tire Breakwater, a relatively new technology in wave control, to expand recreational boating opportunities in the east harbor basin of the Port of Lorain, Ohio. The construction project represents the determination and perseverance of a small local agency trying to innovate solutions to local needs. Convinced that one must make the most of any situation and do it swiftly, the Lorain Port Authority pioneered the construction of the widest FTB built in the world. Its experience with this Floating Tire Breakwater is shared in this paper. The project planning, pre-construction activities, and actual construction technique are unique, yet representative of what can be accomplished by other local leaders. In this context, this report is offered as encouragement to those leaders, and as a contribution to the present literature. Little of theexisting literature presents a thorough description of "how to build"a FTB. In this paper, the reader is presented a detailed case study with a concentration on construction procedure. We hope it will contribute to the advancement of the technology, more widespread practical application, and access to a bountiful resource, the waterfronts of America. -2- TABLE OF CONTENTS Page No. 1. INTRODUCTION .................................................................. 6 Location ....................................................................... 6 Planning ....................................................................... 6 Funding ....................................................................... 7 11. FLOATING TIRE BREAKWATER TECHNOLOGY .................................... 8 Existing Literature .............................................................. 8 Site Visits ...................................................................... 8 Goodyear Design ............................................................... 8 Application to Lorain .......................................................... 9 111. PRECONSTRUCTION PLANNING .................................................. 10 Funding ....................................................................... 10 Bidding ........................................................................ 10 In-House Construction .......................................................... I I Construction Site ................................................................ I I IV. THE CONSTRUCTION PROCESS ................................................... 12 Tires .......................................................................... 12 The Belting ..................................................................... 13 The Flotation .................................................................. 16 Nuts and Bolts .................................................................. 18 Building Modules ............................................................... 18 Assembling The Mat ............................................................ 20 Anchors, Mooring Lines, and their Installation ...................................... 22 Towing and Connecting .......................................................... 24 Navigational Lighting ........................................................... 26 V. COST ANALYSIS .................................................................. 28 Budget Estimates ............................................................... 28 Unit Costs ..................................................................... 30 Foam ..................................................................... 30 Mooring System ............................................................ 30 Nuts and Bolts ............................................................. 31 Total Project Costs ....... 31 Unit Cost - Total Project ................................................... 31 VI. SHORT TERM OBSERVATIONS .................................................... 32 The Mooring System ............................................................ 32 Binding Material ................................................................ 32 Flotation ...................................................................... 32 Debris Collection ............................................................... 32 Seaweed and Sediment .......................................................... 32 Fish Population ................................................................ 32 Effectiveness ................................................................... 32 Ice Conditions .................................................................. 33 Public Response ................................................................ 33 VII. CONCLUSION AND RECOMMENDATIONS ......................................... 34 VIII. APPENDICES Acknowledgements .............................................................. 36 About People .................................................................. 35 Bibliography ................................................................... 38 -3- LIST OF FIGURES Figure: Page No. 1. Lorain Harbor 6 2. 1970 Site Plan 6 3. East basin area ...................................................................... 7 4. 1978 Site Plan 7 5. Phase I Development Plan ............................................................ 7 6. Module configuration ................................................................. 8 7. Tire mat 9 8. Worker dewatering tires ............................................................... 12 9. Branding ........................................................................... 12 10. Dewatering, branding, installation of flotation and stacking operations ...................... 13 11. Pile of tires unloaded from a 45-foot semi trailer ......................................... 13 12. Cutting conveyor belt squarely ........................................................ 14 13. Rolling out conveyor belt for cutting ................................................... 14 14. Cutting conveyor belt to length ........................................................ 14 15. Moving conveyor belt to slitting area ................................................... 14 16. Moving conveyor belt to cutting table .................................................. 15 17. Chalking out cutting lines ............................................................. 15 18.- Slitting belts ........................................................................ 15 19. Stockpiling belting material ........................................................... 15 20. Pneumatic punch operation ........................................................... 15 21. Woodhall and CETA workers putting flotation blocks in bags ............................. 17 22.' Heat sealing of bagged flotation blocks ................................................. 17 23. Worker installing flotation in tire using tire hook system .................................. 17 24. CETA employees at work installing flotation in tires ....................................... 17 25. Assembling modules ................................................................. 18 26. Installing bolts in the binding straps .............................................. I ..... 18 27. Tightening down the connector bolts ................................................... 18 28. Storing the modules ................................................................. 19 29. Warehouse filling up with tires ........................................................ 19 30. Tire preparation/ stacking ............................................................. 19 31. Connecting modules at river's edge on rubber pad ......................................... 20 32... Modules about to be dropped into position from carrier trailer at launch area ................ 20 33. First three rows of modules completed and ready for launching ............................ 20 34.. Pushing first sections into the water .................................................... 20 35. Modules entering the water ............................................................ 21 36. Hauling Modules from warehouse to launch area ......................................... 21 37. Forklift Pushing mat into the water .................................................... 21 39.' Offloadirig m6dules into position from trailer ............................................ 21 39. Mat section length approaching commercial channel ...................................... 21 40. Another row assembled, ready for pushing .............................................. 21 41., Completed mat sections moored near launch area ........................................ 22 42. Sandstone anchors being delivered to construction site .................................... 22 43. Shock absorber connection ........................................................... 23 44. Mooring line assemblies .............................................................. 23 45. Mooring line connection to anchor stone ................................................ 23 46. Installing connector cable to modules ................................................... 23 47. Loading anchor stones on work scow ................................................... 23 48. Loading mooring lines on work scow ................................................... 24 49. Setting marker for anchor locations ..................................................... 24 50. Setting anchor stones into water ....................................................... 24 51. Positioning mat section for hooking up moorings ........................................ 25 52. Making connection of mat to mooring line .............................................. 29 53. Temporary marker light positioned on modules .......................................... 25 54. Towing section for installation ........................................................ 25 55. Worker connecting modules in the water .................................................. 25 56. Pad eye-mooring line connection at pier ................................................ 26 57. Drawing of marking light ............................................................. 26 58. Diver connecting float bag to anchor-marker light ........................................ 26 59. Deflating float bag, positioning marker light mast and anchor ........................ ..... 27 60. Mast in position ..................................................................... 27 61. Mounting marker light to mast ........................................................ 27 -4- 62. Light, solar panel and battery ......................................................... 27 63. Marker light installation completed ........................ ; ........................... 27 64. Seaweed growth on tires .............................................................. 32 65. Effectiveness ........................................................................ 33 66. Effectiveness ........................................................................ 33 67. Effectiveness ........................................................................ 33 68. Long waves ......................................................................... 33 69. Long waves ......................................................................... 33 70. Ice conditions ....................................................................... 33 Introduction PLANNING LOCATION: The commission of a study entitled Recreational Boating and Co mmercial Docking Facilities.for Lor- Lorain, Ohio, situated along the U.S. north coast, is ain, Ohio prepared by Stanley Consultants in 1970 for in the middle of,the industrial Midwest region of the the Lorain Port Authori ,ty was the first documentation country. Located approximately 30 miles west of of the need for additional r6cr IeatiOnal, docking and Cleveland, it has its entire northern corporate bound- .comme .rcial marina facilities. This'study proposed a ary along the south shore of Lake Erie. Expanding development concept that combined the fu Iture com- inland fr'orn the banks of the Black River in the center of the city, Lorain has developed into,a community of rnercial needs for port development' with the future diverse, cultural -composition, a true "metropolitan" needs'for irecreational docking facilities. It proposed constructing additional commercial wharfage.in the city. It'relies heavily on industrial production, mainly outer harbor and a 950 berth marina. For the most ship building, steel making and auto-production as its part, the plan was considered impractical because of economic backbone. the cost of the large landfill areas that were required. Lorain's harbor, at the mouth of the Black River, Two significant aspects should be noted. Firstly, the was the site of the original settlement of the town in projected need for additional recreational docking 1811, and historically, it played a major role in the facilities justified the development of 950 additional development of the town and its industry. Lorain's docks in Lorain harbor. Secondly, the proposed site of harbor now provides services to all of the Great Lakes the development of the additional docking facilities region as a major bulk commodities port of call. was located in the east basin of the Lorain harbor. Incoming, outgoing, and trans-shipments of coke Interestingly, in every study since 1970, these same two breeze, iron ore, taconite, limestone, oil, sand and conclusions have been reached. (Figure 2) gravel cargoes move through its 30-foot-deep port facilities. The focus has been on Lorain as a commercial port Ou'r OR LAKE ERIE N and its harbor area has only recently been viewed as a CHANNEL 11111AL 11111111 owned boat yards and liveries had always existed along valuable recreational resource. While small privately LAKE APPROACH AS BREAKWATER the banks of the Black River, it was not until the 1950s tEDERA_LPROJ-EC-T that local government began considering proposals for LIMITS PROPOSED 11.111111. HARBOR DOCKING AREA recreational boat harbors. In 1967, the first public marina with 70 berths was developed by the city as part PROPOSED of the public works project that also built the city's first 4 RECREATIONAL MARINA AREA major sewage treatment facility. With an increasing '.:EAKIdATER AT R RD LLUTOIO L I ONTROL awareness of the Lorain harbor and its great potential OL AT as a major Great Lakes port, the city council, in 1964, OHIO voted to create a local port authority as prescribed SERVICE SC under State statute. With the creation of the Lorain Port Authority, an advocacy body was now in place to carry forward harbor and port planning and develop- COMMERCIAL ment. (Figure 1) DISTRICT Figure 2 While nothing of a tangible nature happened during the 70s to further develop Lorain's harbor, develop- 4 ments in the area just outside the harbor to the east led to renewed interest in fostering recreational boating opportunities in the east basin. In 1973 the U.S. Army Corps of Engineers, as part of its Congressional man- date to contain contaminated dredge spoils as a water 'w -44@ pollution control effort, determined that the area just < east of Lorain harbor adjoining the east shore arm would be the site for a Diked Disposal Area for dredge spoils taken from the Black River in its annual mainte- nance efforts. The Diked Disposal Area for dredge material containment was completed in 1978. A rub- blemound breakwater surrounds a 58 acre area which w en corn pletely filled, in 7 to 10 years by Corps estimates, will become reclaimed land and be given to the City of Lorain for public use. Recognizing the unique opportunity this develop- Figure I ment offered to the City of Lorain, the Department of 6.7 Community Development authorized Stanley Consul- specifically at developing "a program of site protection tants to re-examine the Lorain harbor under these new and marina implementation at Lorain harbor that circumstances and focus their attention on recre- would permit a marina to begin as early as 1980-198 L" ational use. Stanley Consultants completed their Lorain It should be noted here that the U.S. Army Corps of Harbor Recreational Area Study in December, 1978. Engineers was simultaneously examining the Lorain Their conclusion found that the east basin of Lorain harbor under a long-term study program for harbor harbor was the most ideal and economically practical improvements for commercial users and recreational area for marina development. With 58 acres of re- users. The Corps' study also identified the east basin as claimed land becoming available to support marina the primary marina site. Federal assistance for per- activities, it made the site even more desirable. (Figure manent wave protection structures might become 3) To quote some of their conclusions, "all marinas in available to Lorain in 10 to 12 years after the comple- the Lorain area are full and have waiting lists. Marinas tion of the Corps' study. This study is expected to be in the Cleveland area are also full, and long waiting complete in late 1983. lists exist at several spots. Lorain, being only 25 miles Bearing in mind the Corps' lengthy planning pro- from Cleveland, would be expected to attract boaters cess, the Stanley feasibility study was aimed at two from the major metropolitan area if necessary. There specific concerns. The first item was the provision of a seems little doubt that sufficient demand exists for temporary breakwater for the site that could serve as r small boat facilities in this area. Lorain Harbor has an adequate, economical wave protection until such time added advantage over many other marinas, because it as permanent structures could be developed. The could offer an excellent modern protected facility with second item was a short-term marina development easy access to the lake." (Figure 4) program. The results from this study recommended VICINITY MAP the construction and installation of a Floating Tire Breakwater in the east basin of Lorain harbor to pro- .... ROACH vide adequate wave protection for the development of a marina. FUNDING Although committed to pursuing the recommenda- tion of the feasibility study, the Lorain Port Authority found itself without the money to build a Floating Tire Breakwater. A search of State and Federal agencies that could fund the construction of a Floating Tire N.M: NO... -RV Breakwater began. The Ohio Department of Energy found the project to be unique and they entertained a grant application that could be funded under the Coast- Figure 3 al Energy Impact Program. Funds were awarded. The course was set for the Lorain Port Authority to .... .... build a Floating Tire Breakwater. Thus, the first step in the development of a new marina for the City of Lorain was to be a reality. (Figure 5) I R R Zla Figure 4 % The 1978 report was concerned primarily with pro- ject feasibility and did not address detailed analyses of physical, environmental and economic conditions af- Figure 5 fecting development of such a plan. In an effort to evolve a viable development program for a marina in the east basin of Lorain harbor, the Lorain Port Authority retained Stanley Consultants to prepare a Lorain Marina Feasibility Study. This study looked -7- Floating Tire Breakwater Technology able assistance in the early planning stages and through- out the actual construction. Goodyear's technical EXISTING LITERATURE: assistance and loaning of equipment considerbly eased The idea of floating breakwaters is not new. Litera- the pre-construction planning process. The Goodyear ture exists dating back to 1842, citing.the possible staff had a broad awareness of what was happening in usefulness of,such devices, but to reiterate the words of the field of FTB technology, When unable to answer a another writer, "the theory of floating breakwaters has specific question, they would help to find an answer. reflected an idea in search of a need." It now seems the This assistance was invaluable. need is at hand. Demand for coastal shoreline protec- tion continues to grow as more leisure time is trans- lated into increased, participation in recreational boat- GOODYEAR DESIGN: ing activities throughout the country. Extremely high Through the process of reviewing the existing FTB costs associate d with fixed-bottom-resting breakwater literature, making site visits to existing installations structures coupled with the demand for increased with consultants, the port authority developed a basic shoreline wave protection have been major factors understanding about FTB technology. Goodyear's spurring initial technological advancement in the design can best be described as a surface floating mat development of floating tire breakwaters. of interconnected modules of tires. The modules are Floating breakwater design utilizing scrap automo- actually 18 individual tires aligned in a specific pattern bile tires got. started in 1969 with the development of and bound together with rubber straps or chains. To the "Wave Maze" by H. M. Noble. Major advances visualize this pattern, imagine tires lying flat on the took place in 1972: when the Goodyear Tire and floor stacked on top of each other in a vertical fashion Rubber Company refined the design concept. The with a 3,2,3,2,3,2,3 layering pattern. As they are Goodyear-designed modular concept has since been, stacked, the binding material, (2 separate pieces) is the most practical and most utilized design for FTBs. woven through the tire pile, and connected together It became apparent while researching the existing with nuts and bolts. (Figure 6) literature on FTBs that much of the research, testing, and field use of FTBs has been with those of the Goodyear design. It seemed clear that in selecting a FTB design for Lorain that the Goodyear design was the way to go-based on its history. All other design concepts seemed to be in the research and testing phase of development. Published research information, on tying materials, flotation, mechanical connectors, per- mit considerations, wave energy transmission and measurement, and all other related topics relevant to FTBs is currently available. A bibliography of avail- able reports can be obtained from the Northeast Regional Coastal 4 nfo rmation Centerat the University of Rhode1sland and is referenced at the end of this report. Two publications that were frequently used in the early research in the Lorain project and throughout the 77777"W" actual construction were: Scrap Tire Shore Protection Structures, 1977, R. D. Candle & W. J. Fischer and Figure 6 Enhancing Wave Protection with Floating Tire Break- waters, 1978, Bruce DeYoung. To form the interconnected mat of modules, two additional tires are added to each module as "marry- ing" tires. These are interconnected to two tires on the edge of one module with two edge-tires of another module. The binding material is again woven through SITE VISITS: the tires and connected together with nuts and bolts. The investigation into FTB technology was not (Figure 7) strictly confined to researching the existing literature The binding material for the modules may vary from as the port authority prepared to undertake the FTB rope to chain to rubber belting. Belting is usually from project. Site visits to Dunkirk and Barcelona, N. Y. scrap conveyor belt material. All of these binding were made to see FTBs in use at these harbors. Discus- materials had positive and negative characteristics and sions were conducted with the agencies that were consensus was that rubber conveyor belting served as responsible for the construction and maintenance of the best binding material. these FTBs to uncover as much practical information The provision of supplemental flotation in the tires as possible. took on special significance. Early thinking in FTB Technical assistance from Goodyear was also solic- development reflected the view that a tire, when placed ited. Lorain's close proximity to Akron, Ohio, Good- in the water in a vertical position, would capture air in year's headquarters, allowed for easy site visits to the crown or upper one-third of the tire sphere. Lorain by Goodyear consultants who provided invalu- Anyone who has been around a lake shore or river- -8- I . Wave Attack w.0P the metal nuts and bolts were unacceptable due to salt water corrosion. Nylon bolts and nuts in salt water has proved to work well. In fresh water, such as Lake Erie, Typical it was recommended that all metal nuts, bolts, and S y N washers be hot-dip galvanized to retard normal rusting. The last aspect of concern was the anchoring system. _NX ,r. - @ - I Design criteria for this was available. The systems 'A @J described were similar to those that are used to anchor rC h.!, 'n' boats at single mooring points. The main difference KN seemed to be that larger weights were used for the anchors. The consensus on positioning of anchors U. . recommended spacing 50 feet on center for the leading Tire Module edge, or side of wave attack, and 100 feet on center for the leeward side, or shore side. APPLICATION TO LORAIN: With a basic understanding of the current FTB W.V. Attack technology, the port authority felt equipped to begin Area of preparing for the actual design of its FTB. As the Attenuated Wave -W... Di.flpatiph- ncid.et we-. literature clearly points out, the first issue to be deter- Floating Tire mined is the type of waves that are to be attenuated by Module the FTB. Wave analysis and FTB design work was left Mooring Chain to Stanley Consultants in their marina feasibility study Anchor effort. Their study evaluated the problems of water level fluctuation, the physical constraints of the harbor Harbor Be geometry, wave conditions outside and inside the har- Figure 7 bor@, and ice conditions. Of principal concern in prepar- front area can attest to the accuracy of this theory. ing to design a FTB is the wave data, specifically wave FTB thinkers logically concluded this same principle frequency, wave height, wave length, and wave steep- would apply to a FTB module. They postulated cor@ ness., From their study, Stanley Consultants concluded rectly. However, they also found that air is absorbed that: . into the water causing the module to lose it buoyancy, "From the analysis, waves in the 2 to 3 foot if the module rested calmly for an extended period. height range are possible throughout the This concern vanished quickly when it was realized development area. Waves of this height are that as soon as the wind starts to blow and cause wind unacceptable to a marina. Waves of this waves to develop, the movement of the modules in the height with short periods are within the choppy water was sufficient to replenish any lost air. limits that can be reduced by 50-70 percent They reasoned that they had a reliable flotation by temporary breakwaters. The resulting system. wave steepness is 3 percent. Temporary Well, not quite. They forgot to keep in mind that in breakwaters are relatively ineffective against almost every case when building an FTB, scrap tires long period waves; a 9-second, 3-foot wave are used to build the modules. Scrap tires are scrap will have a wave steepness of approxi- tires for one reason. They will not hold air pressure. mately the same (3 percent) as the short They have holes in them. In a FTB module, the tire will period waves, From the wave analysis, it rotate in the binding until the area with the hole is was found that all waves were within accep- above the waterline and the buoyancy is lost with the table limits of safe marina operation, or escaping air. If this happens to just a few tires in a could be adequately dissipated to within module, it will swiftly sink the entire module. It follows these limits." that if there are a lot of modules tied together, it just Stanley Consultants designed the size of the FTB takes the sinking of a few to pull an entire FTB down to needed to meet suitable marina development stand- the bottom. ards. The design criteria and methodologies are set This was exactly the case of the FTB at Barcelona, forth in the DeYoung publication mentioned earlier N.Y. It sank at its mooring from lost buoyancy. It had and Preliminar -1, Report On The Application Of Float- no supplemental flotation in the tires. The results of ing Tire Breakwater Design Data, 1978 by V. W. this bad experience was that the U.S. Army Corps of Harms and T. J. Bender. Engineers, in issuing the permit to build the Lorain It is not within the scope of this study to report on FTB, required that supplemental flotation be,installed design criteria and methodologies. It is recommended in every tire used in the FTB. A further discussion of that ,the above-mentioned publication be studied be- the application for permits will follow in the next fore designing an FTB. Stanley's recommendation for /,4 section. Lorain was that a FTB 600 feet long (86 modules) by 80 The most successfully used connector systems for feet wide (I I modules) would provide the necessary attaching the binding material together has been protection for a marina development in the east basin standard machine bolts and nuts with washers top and of Lorain harbor. It is noteworthy that the 80 foot bottom. In salt water installations, it was found that width would prove to be the widest FTB ever built. -9- BIDDING The project took an unexpected turn. Stanley Con- sultants, after careful analysis of wave and bathometry data, recommended a FTB design of 80 feet (I I modules) wide by 600 feet (87 modules) long to reduce waves to an acceptable size,to permit marina develop- ment. The estimated total cost for the recommended Preconstructi.on Planning FTB design was $63,100. This size, and its attendant cost estimate, much to the surprise of the port author- FUNDING: ity, wIas almost twice' as large as what was planned for Several months before Stanley Consultants' feas@ibil-.. in the ODOE grant application and exceeded the grant ity study was completed, it was evident to the port amount by one-third. , authority that a Floating Tire Breakwater would be thc'@ There was a glimmer, dhope, however. In the prepa- most economical and effective way to provide wave ration of their cost estimate, the consultants included protection at the prop'osed marma site. This early the costs of paying for scrap tires and the cost of paying awareness enabled them to research the FTB tech- for conveyor belt material. The port authority had nology, already made arrangements with the area tire dealers During this same period, the port authority learned to have,all the scrap tires donated to the project, and a of the availability of state funding through the Ohio' local steel company was todonate its scrap conveyor Department of Energy and its Coastal Energy Iop'act belt material. The estimate for these two items totaled Progr .am. Armed with this information, the poit' $18,000. With this. sum subtracted from the total, the authority forged ahead with an application to fund the' new estimated cost was placed at $45,100. This total Floating Tire Breakwater. It was determined that the estimated cost approximated the ODOE grant amount Dunkirk site was similar to Lorain's site. Therefore, it and the port authority felt reassured. With competitive decided to utilize Dunkirk's basic design and project bidding for the construction work, the final project the budget requirement Is by updating Dunkirk's costs costs were anticipated to be within the ODOE grant of to current dollars after inflation. $43 800. The, port authority submitted an application to, .-6sing the best available narrative of how to con- ODOE for $43,800 to construct the FTB at the pro-' struct a FTB, Constructing Floating Tire Breakwaters, posed site. After a. short period of grant application by Neil Ross, as the backbone, the port authority evaluations, the ODOE informed the port authority of developed its bid documents. Included were all requite- its intent to fund its applica tion to construct a Floating ments from the Corps of Engineers, necessary legal Tire Breakwater. With this good news, the port author- instruments, and bonding requirements, With the ity immediately set out to finalize the grant agreement documents completed, the port'authority advertised with th 'e ODOE and secure the necessary permits for for. bids. Because the construction of a FTB was a new building the FTB. experience for local contractors, a pre-bid conference was scheduled to help builders familiarize themselves with the FTB technology. This conference was con- PERMITS: ducted by a consultant from Goodyear. A total of 13 contractors picked up the bidding documents, which An application for a construction permit was sub- was judged to be a reflection of the locally depressed mitted to the U.S. Army Corps of Engineers District construction economy rather than true interest in the Office in Buffalo, N.Y., and to -the City of Lorain project. Of those who obtained bid documents, only Building Department. The Corps' application trig- four firms attended the pre-bid conference. At the bid gered a typical governmental review process by other opening, only four contractors made submissions. The agencies with possible jurisdiction, as well as, thepub- bids ranged.in price from $89,247 to $269,307, and far lic notice and comment period. This processing was exceeded 'the amount of the construction grant of compl .eted with.out problem. The Corps issued a con- $43 800 from the Ohio Department of Energy. Insuffi- struction permit with two requirements for the con- cientfunds forced the port authority to reject all bids struction, (1) that all tires used in the breakwater were and re-evaluate the entire pr J to have foam flotation added to them, and (2) that each Oject. tire used in the breakwater be hot iron branded with 11/2 inch or larger letters (LPA) prior to installation. The reason for the foam flotation was to avoid sinking, The reason for the tire branding wa 's to limit the port authority's liability for retrieving stray floating -tires washing up on private beaches along the lake shofe,. The Lorain Building Department determined that no permit would be required from its office because this type of construction was outside its area of respon- sibility. 10- IN-HOUSE CONSTRUCTION: CONSTRUCTION SITE: With the port authority's commitment to enhancing After resolving who would build the FTB, the next recreational opportunity, the decision was made to question became where would it be built. FTB reports proceed with the FTB development as an "in-house" suggested that the work site be at water's edge as near construction project. To do so would require a much to the mooring site as possible. Work sites at water's greater involvement by the executive director in round- edge were suggested so that the modules could easily be ing up a workforce and coordinating the construction placed in the water so that "in the water" assembly of effort. A strategy was developed to garner a commit- the mat could follow. This approach mandated favor- ment from the Lorain City Government from the able weather and water temperatures. For building a Comprehensive Training and Employment Act (CETA) FTB in the winter months, as the port authority Program for the labor force for building the FTB. expected to do, building the modules on the ice at the After a period of negotiation with the city administra- mooring site posed a possibility. The FTB would be tion and local trade union representatives to resolve completely assembled with mooring lines and anchors concerns about loss of union jobs, an agreement all laid out on the ice. As the ice melted away every- between the city and port authority was reached. The thing settled into its proper position. This method city would provide up to five job training positions to offered real possibilities for the Lorain project. How- the port authority for the purpose of building the FTB. ever, with a January start-up, there would not be suffi- The port authority decided to hire a construction cient time to get the 946 modules pre-assembled on safe manager to oversee the project. It would be the con- ice at the mooring site. struction manager's job to set up and manage the The early planning for the project identified the day-to-day construction operations. The construction Federal spending beach as the site best suited to con- manager would also: (1) assist the port authority with struct the FTB. Permission was requested for use of the cost evaluation and inventory of sources for material site and was granted by the U.S. Army Corps of Engi- necessary for the FTB; (2) coordinate the timely pro- neers who controlled it. However, with the prospect of curement of required materials and subcontract work constructing the FTB during the winter months, the as necessary; (3) research and design all implementa- suitability of this site diminished with its exposure to tion strategies and special construction techniques and winter's bluster off the lake. A 26,000 square foot hardware necessary for the project; (4) provide daily warehouse along the bank of the Black River approx- coordination and supervision of the CETA employees imately one mile upstream from the mouth was identi- during the project construction. fied. The size of the warehouse perfectly suited the After solicitation for proposals to provide construc- needs for constructing the FTB. It contained adequate tion management, four proposals were received. The floor space to receive and store all of the tires, and to Board of Directors retained a manager based upon house all of the operations of constructing the modules. experience, commitment, interest, and price. The site along the Black River, with its 1200 foot bulkhead at the river's edge, offered the ideal condi- tions for launching the modules. Arrangements were made with the owner to lease the site for the construc- tion of the FTB for a lump sum of $1,500. The rent was low and the arrangement constituted a contribution by the owner. With a plan for b uilding, management and staffing program, and an ideal site for constructing the Float- ing Tire Breakwater, the work was ready to begin. The Construction Process The elimination of tires with exposed and sharp metal.belting became very important. Knowing that A thorough discussion of the construction process is workers w Iould have to swim around these tires while the primary focus of this report. It is felt by many FT-13 be,It,in*g.modules.together made everyone aware of the experts that the, experience of the Lorain Port Author- dange'f of,Ipersonal injury in the water. An area of the ity adds substantially to the existing construction war,ehouse was designated to store'the unusable tires, technology With innovations in the areas of flotation, moorings anchor systems, and construction tech- niques For this reason, as much detail as possible will be included in this section to aid future FTB builders. It is, by no means, intended to be considered the final' word in "how to do it." Further improvement in con- struction technology is surely needed and will come with mote experience in the field. The section is arranged into discussions of the indi_' vidiial components 'used in the construction, the'pro- cesses involved in building the modules and assem- bling the mat, assembly and installation of the anchors A and mooring*system, transporting and attaching the mat to the mooring system, and installation of the marking device, Every effort is made to give the reader a feeling for the chronology, of events to aid in under- Figure 8 standing the over-all process. and it *ame common for as much as 10 percent of in the beginning, little actual work with the tires' ;. each delivery to be. discarded. tdok p1ace. Passingthe word to the tire dealers in the The tire branding o perati on, required in the Corps area and having them bring the tires to the constrUc- o.f, Engineers' permit, was kept simple, but seemed a tibn site took much more time than had been expected. re,al-Inuisance due to.r its lack of utility to the overall Many of the early days we:re spent preparing the ward- construction of the FTB. To put the brand on the tires, house for construction activity. The four-man CETA ; - 11 - . .. a set offour.meta,l branding irons with 11/2 inch-long crew and construction manager revitalized the'pre- letters "LPA" on each iron was purchased. These irons viously un6 'sed warehouse by ihstalling new doors and were fabricated at a loc,al sheet metal business. The locks,'buildirig'a shelter area for use as an office a and irons were attached.,to a. 24 ihch-long metal handle with eating area, and constructing work tablesthat could be I wood hand gri,p,..To heat the.branding irons, gas-fired used for various tasks during the,project. Simultahe*7 plu mibers lead pots were used, putting the iron directly ously, telephone and electrical service for lighting" over the 'flame until red hot, removing and imme- general use and equipment were being installed. Dur- diately applying to the sidewall area of the tire. (Figure ing this period, the CETA employees, who were all 9) There was usually enough heat stored in an iron to unskilled workers with various backgrounds, ga:V'e the immediate impression of being an industrious group of brand 3 or 4 tires per heating. With the use of two or three irons, using one while the others were reheating, good-natured individuals. For the most part this c'on-. a continuous branding operation was achieved. A sys- tinued to be the case throughout the project. tem evolved whereby one ma n would pull tires from the pile, deice or dewater, inspect, and roll the tire to the branding station. Another man caught the incom- ing tires, laid them on their side for the branding, then TIRES: quickly picked up the branded tire and rolled it into the Tires began arriving at the site during the second week of the project. Almost all of the scrap tires were stored outdoors before being delivered. This meant that nearly all the tires had large chunks of ice frozen inside the tire casing as one might expect during the middle of January. After unloading the tires, the ice was removed. By bouncing the tire on its tread and quickly flipping it over the ice fell out. This same method was used to remove the water in the tires in warmer weather. 0 The deicing and dewatering operations were wet and dirty activities. It necessitated wearing rubber gloves and water-proof boots to work. The worker would also closely inspect the tire to assure that it was the right size, 14 or 15 inch, and that it did not have any large 7 holes, broken rim beads or large amounts of sharp metal belting protruding through the rubber. (Figure 8) Figure 9 - 12- temporary storage area. Branding consumed the time of a third person. The fourth man stood in the tempor- ary storage area and stacked the branded tire for later use. As the project progressed, the need for temporary storage was eliminated by moving the tire directly to the foam installation process that will be discussed .7 later. (Figure 10) An electric branding iron was tried, but without much success. The electric branding iron would not get hot enough to make a good brand. The idea of using electric branding irons in other projects should not be ruled out. They have been successfully used by others. One positive feature of the branding operation was Figure I I 18,920 - plus about 2500 rejects had been delivered to the construction site. A total of 21 different -firms made deliveries of tires during that 15-week period. THE BELTING: The port authority, in its planning for building the FTB, asked local steel plant officials at the U.S. Steel Corporation to donate any scrap conveyor belt mate- rial that might be available in the mill. Fortunately, this request received a favorable response, and U.S. Steel agreed to provide the scrap belting, as long as the port authority made the arrangements to have it hauled out of the plant. This agreement was made several months before the project actually started. Except for a van that was loaned to the port author- ity by the City of Lorain Park and Recreation Depart- Figure 10 ment and a fork lift that was rented for use during the project, all other equipment for the project had to be its portability. As more tires were processed, floor rented or borrowed. Without the exceptional coopera- space was quickly used up storing tires. With delivery tion from the various divisions of city government and trucks driving into the warehouse, it was possible to benevolent volunteers who assisted by loaning equip- spot the unloading wherever convenient. The ability to ment and time, the project would have been more relocate the branding operation kept handling of the costly. tires downto the bare minimum. Using a large dump truck from the Park and Recrea- Receiving an adequate supply of tires was a key tion Department and a volunteer's dump truck, the aspect of the project. It became clear that the local tire first, load of belting was transported from the steel dealers were not going to be able to provide enough plant to the construction site. Due to the weight of the tires, given the construction schedule. During the first material, three trips into the steel mill were necessary three weeks of the project, a total of 1800 tires were to get all of the belt that was needed for the project. The delivered. At that rate, it would take over 33 weeks to last trip necessitated the use of a large 15-ton dump gather the 18,920 tires needed to build the FTB. The truck from the City Street Department to pick up a construction sc 'hedule was projected at 20 to 25 weeks 5,000 square foot roll of belting. total. This reality triggered a concerted effort by the The conveyor belt material donated by U.S. Steel project manager to research, identify and contact other had been' used in its coke plant. The rolls varied in potential suppliers. Goodyear helped to find addi- width from Yto 5'and in thickness from V2" to 3/4" and tional suppliers. Other tire manufacturers in the Akron had 5 or 7 plies of nylon reinforcement. After rolling a area, all the area (a 75-mile radius) tire recappers, and small roll out on the floor, it was realized that the used tire distributors were contacted. In the end, it was material was much heavier and stiffer than expected. A an area recapping firm and two Akron area used tire few strips, 3" wide by about 15' long, of belt were cut distributors that saved the day. The recap firm was using utility knives for prototype testing. It was found able to make two or three deliveries per week with an by assembling of a module, that the narrow 3" wide average of 300 to 400 tires per delivery. The two used strips of belt were not very flexible and fairly difficult tire distributors brought their tires on 37' or 45' box to bend into the over-lapped position required for trailers, holding an average of 900 to 1200 tires. (Figure bolting together. After consultation with Goodyear, it 11) The only challenge was to get them unloaded as was decided that the module binding straps would be quickly as possible. During one five-day period, nearly 1 V-6" long. The connecting straps for attaching the 3000 tires were delivered. At the end of the 15th week module together to form the mat would be T-0" long. It of the project, all tires necessary to build the FTB was decided that all the straps would be 4" wide. 13 - The next challenge was to efficiently cut the wide rolls of conveyor belt material into the strapping. Thinking on the subject started with the identification of alternatives. These included using a heavy duty industrial vertical handsaw, portable circular saws, a. self-propelled concrete cutting saw, or sharp bladed knives. Checking with a few companies who specialized in cutting,the belting, the handsaw method was recom- mended as the best and most efficient way to get thejob done. The cost of buying or leasing a new or used vertical handsaw far exceeded what the project could afford. The circular saw and concrete saw method were tested on the material. Both of these methods proved unsuccessful due to the high speed rotation of the Figure 13 cutting blades. This caused tremendous heat buildups on the blade and subsequent burning and smoking of the material. Cutting small sections with these saws led to filling the entire building with a dense smelly smoke, making these approaches totally unacceptable. Hand cutting with knives, originally thought as too difficult and time consuming to seriously consider, was the only alternative left. The work of cutting the conveyor belt- ing to size began. This process began with the building of two I I foot, 6 inch long and two 7 foot long wood jigs. These jigs, with parallel straight edges were laid on top of the belt, which had been rolled out on the floor. Squarely cut- ting the wide belts to the right lengths eliminated the need to measure each piece before cutting. (Figure 12) With the large warehouse floor, it was possible to roll out as much as 200 lineal feet of belt at one time. Because the rolls of belting were so heavy, the only way Figure 14 to roll it was to push it with the fork lift. (Figure 13) After the belt was cut into the required length, it was stacked into small piles and moved with the fork lift to the cutting area for slitting the 3, 4 and 5 foot wide pieces into 4 inch wide strips. Figures 14, 15) The 24-foot long slitting table was able to hold two '4 Figure 15 second man was stripping away the piece being cut. The cutting and stripping had to be performed in uni- Figure 12 son to prevent the knife from binding in the rubber. of the I I foot, 6 inch long pieces of belt, and the entire This method of cutting proved to be vigorous work for crew working in two-man teams was able to work at the men and was the cause for grumbling until they the slitting table at one time. To cut the belt into strips, became accustomed to it. (Figure 18) As each strip of .M2% Off#- I "'W' the men would position each large piece on the table belting was cut, it was placed in a storage pile near the and place cutting lines at 4" centers across the entire pneumatic air punch that punched the holes in the belt. width of the belt using a standard construction chalk This pile of belting grew to a size of 30 feet in diameter line. (Figures 16, 17) Working together, one man by 6 feet tall. (Figure 19) A total of 2050 long strips and pulled the knife blade through the material, while the 1820 short strips, which was equivalent to 36,315 lineal 14 - on belt cutting. Most days were broken up by unload- ing tires, deicing and/or dewatering, branding, or other tasks. The use of a compressor and pneumatic punch needed for punching the bolt holes in the belting mate- rial was pre-arranged with Goodyear. As the project U start-up date approached, Goodyear was notified and the necessary arrangements were made to have the equipment shipped to the construction site. The equip- ment was to be shipped by truck from a Goodyear manufacturing facility in the Brownsville, Texas area to Lorain. The delivery of the equipment was delayed and did not arrive at the construction site until the sixth week of the project. Ted Woodhall, a retired Goodyear engineer, came to Lora' n to assist in setting Figure 16 up the equipment for operation. A highly qualified engineer, Woodhall had been involved in FTB devel- opment work and brought with him a wealth of practi- cal information that was invaluable throughout the project. Goodyear, through Woodhall, had the punch and die sets machined for use on the pneumatic punch. It kly discovered however, that the punch and was quic A4 die set that had been made up was not going to work. The die was to punch two holes with one motion by the pneumatic ram, each property @paced. The belting was WE, @t, so tough, (i.e., the composition of the rubber, the nylon ply reinforcement, and the age of belt) it resisted the punch from penetrating through the belt when maxi- mum pressure was applied. This forced the machining of a new set of dies that would punch a single hole. Figure 17 Woodhall redesigned the new die and had it machined in Akron. Upon his return a week later, he had the new punch and die sets. With a spacing index it was possi- ble to punch the two holes individually on each end of the belt with exactly the right spacing to allow for proper alignment when lapping the ends together for bolting. With only slight adjustment to the system, everything worked well. The only maintenance in the "A' operation was resharpening or replacing the punch about once a week, as it dulled enough to ineffectively V N, cut the rubber and push the plug out. (Figure 20) Figure 18 Figure 19 Figure 20 feet or 6.88 miles of 4" wide belt, were cut over a A four wheel cart, typically used in lumber yards, five-week period. Other work was performed during and built with a 4 foot wide by 12 foot long deck, was this period and very few full days were spent working used to transport a large supply of the belts to the area - 15 - next to the pneumatic punch. This permitted the punch material. This material was resistant to chemical deg- operator to increase his efficiency by eliminating fre- radation from gasoline or other petroleum base mate- quent trips to the belt pile. The cart continued to be rials. This is important in marinas where there is the useful for moving other material and equipment possibility of gasoline spills and other types of cleaning throughout the project. The help provided by Good- solvents being flushed into the water. year and Woodhall in this operation was extremely Most manufacturers applied a protective coating beneficial. over their flotation blocks or installed them inside waterproof aluminum or plastic containers. One manu- THE FLOTATION: facturer recommended replacing the material when it Research on flotation began very early. The focus wears out because it is so inexpensive. was upon urethane foam flotation as recommended in Styrofoam was, in fact, a viable flotation device for the most recent FT13 literature. Cost estimates from an FTB. With research into purchasing G.R.-type sty- Stanley Consultants and the unsuccessful bidding sug- rofoam, it was discovered that it was a highly special- gested that as much as 25 percent of the budget could ized product manufactured only by special order. Use be devoted to the flotation material. It was important in the FTB would require a special design of size and to know exactly what we were going to get for our shape for the foam blocks. The cost estimate for the money. Since urethane foam for marine flotation was engineering and subsequent production of G.R. styro- foam flotation was far too high for the program basically alike from all manufacturers, the key in budget. selecting a supplier was the price. Knowing that 9,460 Research continued leading to a solution. An afford- pounds was needed, the quantity of 10,000 pounds was I I a convenient figure to use for cost comparisons. After able design was finally evolved. This idea called for using standard styrofoam shaped in a triangular comparing four quotes, the best price was offered by volume. The dimensions were to be based upon a the General Latex Company in Ashland, Ohio. Ash- right-angled triangle with an A chord dimension of 6 land is only about 40 miles from Lorain and the con- inches, a B chord dimension of I I inches, a C chord or struction manager made a visit to the General Latex hypotenuse dimension of 121/2 inches and a volume plant to learn more about the product. New informa- depth of 6 inches. To protect this triangular "block" tion surfaced about the product and led to a search for from chemical and physical degradation, it would be alternatives to urethane. Urethane foam is a two-part bagged in a 10 mil extruded polyethylene bag and heat chemical product. The chemicals used in the system are sealed. Two of these bagged blocks would be installed highly volatile. Extreme care and safety are necessary into the crown of each tire. in handling. In hand mixing, as was proposed, it was With this approach, the need for special engineering, necessary to maintain a warm air temperature (60' to manufacture of special molds, and molded production 70' Fahrenheit) to get the proper chemical reaction were eliminated. Using standard styrofoam cutting and the proper flotation quality. The work area had to tools and cutting the blocks out of large standard sized be properly ventilated for the health and safety of the billets, the unit cost per block came in at $.27. Total workers. The chemicals would be rendered useless if exposed to freezing temperatures. Curing time was 24 cost per tire, which included two blocks sealed in two hours in warm air for achieving the desired quality. bags, was $.78 per tire. The $.78 per tire cost was 60 Construction was planned within an unheated 26,000 percent higher than the material cost for the urethane square foot A-frame warehouse with a maximum ceil- foam estimate. After adding labor, and utilities to the ing height of 40 feet. Had the project been scheduled in urethane foam cost, a much smaller difference between the summer months, the site would have been ideal, the two systems existed. Coupled with a concern for but the project's starting date was in January. Although the health and safety hazards of working with toxic the construction and heating of a small work space for chemicals, the decision to go with the styrofoam flota- foaming and curing was considered, the total expense tion was made. for such exceeded the budget. Subcontracting the ure- Tuscarora Plastics, Inc., of New Brighton, Penn., a thane installation off-site was also too expensive. The company specializing in molded styrofoam provided search for alternatives really did not go too far. There technical assistance during the evolution of this design. was sufficient documentation in the FTI3 literature to Even though their specialty was molding styrofoam, indicate what had failed in previous experiences. Sty- rather than cutting and shaping from billets, Tusca- rofoam or expanded polystyrene had been tried and rora was the lowest bidder for 38,000 triangular blocks successfully provided the necessary flotation quality. of styrofoam. Nonetheless, it had certain undesirable qualities. The Three manufacturers of plastic bags were consulted material was susceptible to physical degradation when in the Cleveland area. A consensus emerged on the exposed to chaffing, to chemical degradation with type of product and its specification calling for a 10 :exposure to petroleum distillates, and to water per- inch x 16 inch, 10 mil extruded tubular polyethylene meability. If the skin of the styrofoam could be coated bag. Price quotations for this material led to Aabaco, with a protective cover, these problems could be Inc, of Cleveland, being selected to supply the bags. eliminated. Aabaco also supplied the heat sealing equipment for This notion led to discussion with floating dock sealing the bags. (Figure 21) builders who used styrofoam for dock flotation. Most The order for the styrofoam blocks was placed dur- of the companies molded their own Oolystyrene and ing the second week of the project. The first shipment used a special raw material called G.R. (gas resistant) of material was to be delivered four weeks from date of 16- To get the most efficiency from the operation required two men. One man operated the heat sealer and another man placed the styrofoam blocks in the bags, maintaining a constant supply for the heat sealer. There were 225 blocks of foam in each carton and 180 ilk 4 @Jr,17 cartons in the whole job. Maximum production in one 8 hour day was 2,000 blocks, but that was the excep- tion rather than the rule. The monotony of the opera- tion led to more "creative" scheduling of the workers' time to avoid boredom. Time soon came to insert the styrofoam blocks into the tires. Thought a minor task, it quickly became a m or problem. The styrofoam blocks, to be stuffed aj into the crown of the tires, were specifically designed with a width of 6" to ensure that they would be firmly clamped by the beading of the tire. The dimension between the rim beads is about 3" to 4" on a 14" or 15" tire. This required the spreading of the rim beads suffi- ciently to stuff the 6" wide block between the beads. It was difficult to spread the rim bead, hold it open, and stuff two blocks with only two hands. When two men tried to do it, arms got in the way, and fingers got @g pinched. A standard tire spreader, used in gas stations, s tried without much success. Although it did spread INNER&,, wa the tire enough to insert the blocks, it was very slow to operate, requiring precise alignment of the tire in the M spreader. After the blocks were inserted, it was difficult Figure 21 to remove the tire because the spreader's hooks would order. An earlier delivery would have been preferred, be pinched between the block and the bead. but the manufacturer insisted upon making full truck The construction manager designed a more simple load deliveries for reasons of economy. Delivery of the system from heavy gauge sheet metal. A flat hook, plastic bags coincided with this timetable. There was bolted upright to a table, had a bend at its top. When plenty of work with the tires and belts, so time was not the tire was set vertically on the table with the sidewalls wasted waiting for the styrofoam blocks. facing the worker, he could easily catch the outside rim The blocks and bags arrived at the construction site bead in the hook and spread the tire open by pulling on during the seventh week of the project, one week later the inside bead. This freed his other hand to stuff the than expected. The heat sealing equipment was as- foam block into the tire and easily unclip the tire from sembled and a work area for the bag sealing operation the hook by tipping the tire and sliding it out. With a established. The heat sealer was a simple piece of little practice, a worker was able to pick up a tire, set it equipment. It was manually operated by a foot pedal in position in the hook, stuff both blocks of foam, that closed a spring-hinged, 14-inch jaw and opened unhook the tire, and roll it into temporary storage in automatically when foot pressure was released. Elec- less than 10 seconds. (Figure 23) tric heat in the upper and lower jaws was thermostati- cally controlled. It took some practice to learn how long to keep thejaws closed on the bag to avoid a faulty seal. (Figure 22) @ 07"'N r Z@ AWL Figure 22 Figure 23 17- Three of these flat hooks were bolted to a 4' by 8' table allowing three men to work at this operation. With the hooks bolted near the edge of the table, ample k sur I 52A face remained to stockpile the foam blocks within easy reach. Mounted on a table, the operation was portable, allowing it to be moved. This eliminated additional steps to move the tires to the work area. Work at this operation was also tedious. (Figure 24) "Ar f-7 A Figure 24 NUTS AND BOLTS: Figure 25 Nylon nuts and bolts were originally plantied for use in the FTB project. In the research to identify suppliers and costs, it was learned that they were much more expensive than comparable metal nuts and bolts. It was determined that there was not a critical need to use nylon rather than metal fasteners. The metal would rust in the fresh water, but not to a point of causing the bolt to fail.. In fact, the rust was thought to be a positive v- V factor. Nylon nuts and bolts came loose from the con- stant motion of the FTB in the water. Deforming the threads curtailed this occurrence but required an addi- tional step in construction. The expected rust forma- tions on the metal nuts and bolts were expected to lock A; the nut tightly and prevent any possible dethreading. This would serve to minimize annual maintenance. After pricing suppliers, an order for the bolts, nuts Figure 26 and washers was placed with the Freedom Fastener throughout the project. Two men would hold the belts Company of Lorain. The order contained 8,500 Y8"- 16" in front of them and two men would stack the tires. The bolt and nut sets and 17,000 one inch diameter men stacking the tires took care to drop the tire onto washers. They would all be American made. It was the stack so that the foam flotation was positioned recommended that all of the connectors be hot dip opposite them. (Figure 25) galvanized to prevent the excessive rust buildup. With the galvanizing, the bolts and nuts were expected to rust enough to prevent dethreading. BUILDING MODULES: Existing literature addresses itself to building mod- 4744 ules. As that literature suggests, two tire stacking racks were built according to recommended specifications. The experience with using the racks was not very suc- cessful. After the module was assembled on the rack, and the binding straps bolted tightly together, the Q, module was tipped over on its side to remove the rack. But the rack would not move. It had become tightly bound to the tires. The entire crew pulling on it could 0 41" not remove it. The heavier binding material was Will exceeding the very small tolerance allowed in the rack Figure 27 N 7 design. Had the rack been fabricated with removable posts, it would have worked. An alternative for assem- When all 18 tires were in place, the belt holders bling the modules of having two workers holding the would pull out any slack in the belt and compress the belts and weaving them through the tires was tried. stack of tires by pressingdown on the top layer. Simul- This system worked very well, and its use continued taneously, two workers were getting the nuts, bolts and - 18- washers ready for bolting the belting together. Each release itself from the forks and settle into its upright would work with one of the belt holders to get the bolt position. To set the modules on the horizontal layer the holes to align and push the bolts through the belting. lift operator would pick up the module by sliding the (Figure 26) Large one-inch diameter washers were forks underneath and lifting the module in its horizon- always installed on both sides of the belt to prevent the tal position. He would move the module into its stor- bolts from pulling through the holes in the belt. The age position, lower the forks, and slide them out by nuts were finger tightened and both workers using backing up. (Figure 28) hand wrenches would pull down on the nut until the It was important to employ an efficient method of washer started to cup the rubber belt surface. Four storing the completed modules inside the warehouse. It men working in this manner were also able to build a was undesirable to store them outside because of pos- module in 4V2 to 5 minutes. (Figure 27) sible vandalism, especially to the flotation blocks. After assembling a module, the workers would allow Keeping the modules dry until they were launched it to fall on the floor with the flotation side of the into the water eases their handling. Inside storage module on the bottom, move to another location, and required that sufficient floor space be left available for start assembling another module. The fifth man in the the continuing production of modules and for receiv- crew using the fork lift, picked up the module and ing and unloading additional shipments of tires. The moved it to a storage area. A number of ways of storage system employed helped to maintain the room stacking and placing the modules in storage was tried. needed for working, although toward the end nearly all The best was to stand the modules vertically on end, the available floor space became covered with tires. the same way as when built, leaning them against each (Figure 29) other, starting from a wall and working out. One layer It became clear that the production of modules of modules would be placed horizontally on top of could not be accomplished by completing all of the those standing on end. Two modules standing on end, sub-assembly operations first and then proceeding . ... ... with a continuous module building process. Since it was unknown when all of the tires needed to construct the 946 modules would finally be delivered, combining the operations in a day's work seemed to be more effective. To complete the project in a 20 to 25 week period, module production had to be completed by the 19th week of the overall project. With starting the construc- 0 AIV 4 tion of the modules during the 10th week, completion wou Id be necessary over the next nine week period, quiring building approximately 100 modules per re week. A goal of 30 modules per day was established. Building 30 modules required 540 "prepared" tires and 60 belts punched. To have the 540 "prepared" tires Figure 28 and the belting available each day meant operating the leaning against each other, provided just enough area sub-assembly operations during the first part of the to place the horizontal module on top, and the foam day, usually until noon, leaving the afternoon to build blocks in the tires made the modules standing on end modules. To meet the daily goal for the module pro- rigid enough to support the weight of the top module. duction, at least 1,080 blocks of foam had to be bagged To pick up the completed modules with the fork lift, and sealed each day. Utilizing the men most efficient at the operator would lift the module by hooking the this operation enabled it to keep pace. However, it was forks under belting. The operator could carry the usually necessary to keep the operation running while module to the desired storage area and place it in trucks were being unloaded, deicing/ dewatering or tire position. When the full weight of the module was branding was being performed by the other workers. resting on the floor again, it would automatically The tires used in these early stuffing operations were drawn off from tires already branded and stored within the work area. It quickly became apparent that the way in which the tires were stacked after the foam was installed affected the efficiency in the module building process. After different stacking arrangements were tried, the one that contributed most to the module building process was a system where tires were stacked horizontally - six tires high and six rows wide. When the modules were built, the tire stacking took place right in front of the "prepared" tire stacks, eliminating N a lot of unnecessary steps. (Figure 30) The completion of the last of the 946 modules came on the second day of the 19th week of the project. The concept of having daily and weekly production goals Figure 29 paid off. Module production averaged construction of - 19- 10 modules per hour, utilizing a four-man crew. The largest number of modules produced on a continuous basis in one day was 50 modules and that was limited only by running out of "prepared" tires and belts. The completion of the last module really marked the end of the first phase of the project. Figure 31 it was possible to haul nine modules on the trailer. By P carrying two additional modules out with the fork lift after the trailer was loaded, the I I modules needed to make a complete row were at river's edge. (Figure 32) Figure 30 ASSEMBLING THE MAT: Assembling the modules into the mat and launching was the next phase of construction. Assembling the -the-water" operation. It mat was thought an "in seemed undesirable based on two concerns: the CETA workers had no training for working in the water, creat- ing liability, and the lake temperature was expected to be too cold for extended periods of exposure. There % had to be a more efficient way to accomplish the work. The process to be used to assemble the mat was to attach all of the modules together at the river's edge and push or pull them into the river. After considering the spectrum from manually pushing to using bulldoz- ers,it was decided that the fork lift was able to push@ the Figure 32 mat. To begin building the first mat, the first three rows of Work began to prepare the site for the assembly modules were married together. A perimeter bridle, a operation. The work area was a 150' stretch of sheet- piled river bank with a 4 foot drop to the water. The continuous length of belting, (actually short belts area was very rough and required grading to allow a bolted together) was laced through the tires of the flat and level working surface to hook the modules modules forming the edges of the mat. When the first together. The finished grade was elevated slightly three* rows were assembled and the perimeter belt in above the top of the sheet pile to prevent the modules place, the launching of the first row into the water began. (Figure 33) from hanging up as they were pushed over the edge into the water. With the plan to push the modules and slide@thern into the water, a slippery surface was needed. Bear in mind that the plan called for sliding full width (80' wide, I I modules sections) into the water at one time which posed considerable friction. Some of the unusa- ble rolls of conveyor belt material were rolled out over the area where the modules would be hooked together and slid into the water to form a rubber launching pad. (Figure 31) The rubber belting as a pad to slide the modules into the water worked extremely well. To move as many modules as possible at one time, a 28' long dual axle open frame trailer was borrowed. A 24' long by 8' wide plywood deck was built on the trailer, and proved to be a perfect module carrier. After Figure 33 a day of practice at stacking the modules on the trailer and hauling them out to the assembly and launch area, -20- the modules had completed its work. The pushing of the next roNv into the water would quickly follow. It generally took three pushes - one in the middle and one on each end - to slide the whole row into the water and keep the entire mat in a straight line posi- tion. (Figures 36, 37) N Figure 34 To push the modules more effectively using the fork lift, a 16'long 6" diameter steel pipe was used as a push bar. The pipe had two slots cut into it that allowed it to 77@ fit onto the forks. This made it possible to apply pres- sure along 16 feet of the landside edge of the mat. (Figure 34) The plan for launching the first three-row Figure 36 section dictated pushing it far enough to have the first row of modules floated in the water completely. The second row hung over the edge of the bulkhead and the third row sat completely on the land near the edge of the bulkhead. (Figure 35) With the third row in this position, the fourth row would be married. The plan worked perfectly, and not one person had to enter the water to hook up a module. Figure 37 As soon as the row was launched, the fork lift returned to the warehouse. The driver pulling the module trailer would move into position. The workers would push the modules from the trailer, spotting them in position as the trailer moved down the row. When the trailer was completely unloaded, the truck would turn around and return to the warehouse for another load of modules. Workers at the launch area aligned the modules and made the required hookups and con- tinued installing the bridle around the perimeter. Using this system, eight to nine complete rows of the FTB mat were completed each day. (Figure 38) A Figure 35 The assembly process quickly became very efficient. As soon as the trailer carrying the nine modules was loaded, it left the warehouse followed by the fork lift carrying two modules hung vertically from the forks. While the driver of the truck pulling the trailer waited Figure 38 near the assembly area, the fork lift would drop off the It was not possible to build all 86 rows of the FTB in two modules it was carrying, then move away to pick one long piece because it would project into the Fed- up the push bar. The push bar was located so that the eral channel of the river and would interfere with the fork lift driver did not require any assistance in attach- commercial traffic. This made it necessary to build ing it to the forks, By the time the fork lift driver had four sections of mat, each 150' in length. (Figure 39) the push bar ready, the crew working on *connecting Each section took three days to complete. As each -21 - Figure 39 Al, Figure 40 ...... .... .. Figure 42 T mu hoped that he could confirm what to use and add quantifiable recommendations before materials were ordered. It was determined that the anchors and mooring Figure 41 lines were undersized for heavy storm conditions. It section was completed, it was pushed completely off was decided to use five-ton anchors and mooring lines the dock and towed to a temporary mooring site along with a 18,000 pound working load limit. Arrangement the river. A small 14' fiberglass runabout with a 25 for the anchors called for 18 anchors to be employed, H.P. motor that was loaned to the project was used to 12 placed along the windward side with 50'spacing and move the sections of the FTB. Everybody was sur- six anchors placed along the leeward side with 100' prised at how easily the section could be moved. None- spacing. To help prevent anchor-dragging in storm theless, it was difficult to maneuver or steer the large conditions, it was also planned to place the anchors mats into an exact position with the small boat. Con- into holes dug in the lake bed. struction of the entire 86 row, 600' length FTB was A search was then made for materials meeting the completed in 13 working days without the need of one required specifications. Materials had to be cost con- person doing any work in the water. The FTB was scious and easy to handle. A decision was made to use ready for installation at its permanent mooring site, 5-ton sandstone blocks based on their cost which pending the placement of anchors and mooring lines, equalled the material costs involved in making the by the 22nd week of the project. (Figures 40, 41) concrete blocks. This eliminated the time and effort required in manufacturing the concrete blocks at the construction site. (Figure 42) ANCHORS, MOORING LINES, AND THEIR Selecting the material for the mooring lines Was a INSTALLATION little more difficult. Three alternatives 'were consi- The selection of the weight of the anchors and size of dered; galvanized wire rope, chain, and nylon web mooring lines was a topic of considerable research. belting. All three offered the required strength. In Recommendations were carefully considered and eval- looking at chain, it was realized that it would be unac- uated. ceptable in terms of weight and cost. Weight per linear The one great fear that preoccupied the construction foot for an 18,000 pound working load, was very high. manager throughout the planning and building of the In the 60' lengths for each mooring, line, it would be FTB was the possibility of the FTB breaking away or impractical, if not impossible, to handle from a small dragging its mooring. Such was the case in previous work boat. The cost per foot was also higher than the installations. The data on mooring forces in FTBs was other two materials considered. probably the least documented. The nylon web belting was the least expensive of the To provide some additional confidence about the three materials. Further research showed it had been anchors and mooring lines, a naval architect from the unsuccessfully tried as an underwater binding mate- I ptz,@., local shipyard was consulted. Every piece of available rial. Experience had shown that sand and sand drifts data on mooring forces in FTBs, Stanley's recommen- occurring in wave conditions, acted on the nylon belt dations, a complete description of the FTB, and a site like a cutting abrasive. In as little as seven days time, it visit were made available to the naval architect. It was could cut through a nylon belt. The knowledge of this -22- usually rest on the lake bottom and would rise off the bottom only when forces on the FTB became severe. tt The tires were connected into the mooring line using thimbled eyes in the cables and continuous loops of chain laced through the tires. (Figures 43, 44) The connection of the mooring line to the anchor stones and to the modules required special considera- . . . ... tion. Installing I V2" solid steel bar stock through a pre-drilled hole in the sandstone with steel plates welded to the top and bottom of the bar provided the needed connecting point on the anchor. An open- IV, swaged socket on the end of each mooring cable could be connected to the I V2" bar in the anchor stone by Figure 43 pulling the pin in the socket, sliding the jaws of the - socket around the bar, and reinstalling the pin. (Figure 45) To connect the mooring line to the modules, a separate 3/4" diameter piece of cable was used. This cable was woven through the entire module to better 'SQ N V Ak, Figure 45 Figure 44 effect was enough to decide against nylon belting. Galvanized wire rope, commonly referred to as cable, was the material selected for the mooring lines. Sized to meet working load requirement of 18,000 pounds meant using an I 1/ 8" diameter material. The weight of the cable was not light by any means, but compared to about one-fourth the weight of compara- ble strength chain. The cost of the cable was about one-half the cost of the chain. However, with the addi- Figure 46 tional cost for specialized fittings on the ends of the distribute the weight and load. Woven through the cable to facilitate connection to the anchors and the module, the ends of this cable which had swaged thim- FTB added, the cost of the cable was only slightly less ble eyes, would be connected to the mooring cable than the chain. which also had a swaged thimble eye, using a 12-ton In planning the use of the wire rope, shock to the working load galvanized safety shackle. (Figure 46). cables during storm conditions could be expected. The Using this connecting method allowed for the mooring shock to the cables was expected to be the major line with shock absorber to be attached to the anchor contributor to cable fatigue and breakdown. As a stone and placed as one unit on the lake bottom. A means to limit the shock and prolong the cable life, it floating marker was attached to the loose end of the was decided to install a shock absorber into each moor- mooring line with a 1/4" "reach line" for retrieval. The ing line. Two truck tires were selected for the shock cables attached to the modules were installed before absorber in each mooring line. The two truck tires the FTB sections were towed to the site for installation. attached together were placed in the mooring line Final attachment required pulling up the loose end of about 10'from the anchor. In this manner, they would the mooring line from the bottom and connecting it to -23 - the ends of the cable woven through the module. This system worked very well during the final installation and required only three men working from the small @4, work boat. "E, The installation of the anchors and mooring lines on An, the lake bottom was the only work in the project that required using subcontract labor and equipment. A local marine contractor with a 50-ton derrick barge, tug and work scow was contracted to complete this work, After the 18 mooring lines with their shock absorbers had been assembled on the dock at the con- struction site, the subcontractor moved his equipment to the site and loaded all 18 anchor stones and the mooring lines onto a work scow alongside the derrick barge. (Figures 47, 48) When loaded, the equipment was towed to the east basin site for installation. At the Figure 49 site, the first chore was to lay-out the locations for the help prevent the shock absorber tires from getting anchors. Using a measuring chain in a skiff and a fouled on the anchor. Having the scow loaded with the transit located on the government pier, floating mark- anchors on the inside of the derrick barge, (i.e., the side ers were dropped for the locations of the anchors. where the FTB would be positioned) allowed the (Figure 49) When this was completed, the derrick workers to stretch the mooring lines to the approxi- barge and scow were moved into place. mate position of the final connection. (Figure 50) This greatly aided the final connection to the FTB by reduc- ing the amount of stretching needed to raise the end of the mooring line to the surface. While the anchors were being placed, pad eyes were being welded to the government pier. Because of the proximity to the water, the welding was performed from a boat moored alongside the pier. To set the 18 stones required two full days of work. With the completion of setting the anchors and pad eyes, everything was ready for towing the FTB sections from their temporary mooring up the Black River to the permanent installation site. Figure 47 '10 Figure 48 Using a clam bucket, a hole was excavated in the lake bottom for the anchor stone. The clam bucket was removed and stone hooks for picking up the sandstone anchor were attached to the derrick's crane. The anchor stone was lifted from the scow with the moor- ing line attached to it and placed into the hole in the Figure 50 lake bottom. The mooring line was stretched out and dropped into the water as the anchor was lowered to _ 24- TOWING AND CONNECTING: from dusk to dawn to mark the end of the FTB. A With the services of the harbormaster, the port standard street barricade, used for marking roadway authority harbor patrol boat, and a volunteer, the first hazards, was borrowed from the city utility depart- section of the FTB was towed I V2 miles from the con- ment. Typical of these barricades, it had an amber- struction site to the east basin. On this first tow the colored battery-operated flasher. To satisfy the Coast harbormaster's tug was positioned at the front of the Guard requirements, the amber flasher was changed to FTB section (80'x 150') pulling and the other two craft a green-colored flasher. The barricade and flasher were were tied off to either side of the section near the rear. mounted to the seats of a 14' aluminum open fishing This method of towing, while easy when going in a boat. The boat was pulled on top of the modules, straight line, was awkward to maneuver in the Black chained, and padlocked to the modules to prevent River. The towing consumed approximately 13/4 hours. theft. (Figure 53) The boat made it easy to relocate as The positioning of the first FTB section required the each additional section of the FTB was added. Installa- towing crafts to be particularly careful. The section tion of the other three sections followed the same was positioned by sliding the mat over the floating procedure with minor adjustments. To gain additional markers tied to the ends of the mooring lines. The control and maneuverability of the FTB section, the towing craft had to be careful not to run over the harbormaster's tug pushed, rather than pulled, the floating markers to avoid fouling in the propellers, to mat. The other two boats were positioned along the prevent sinking or cutting and thereby, losing the sides of the mat at the front. This permitted greater location of the mooring lines. (Figure 51) Performed steering ability at the front of the section by having the successfully the workers in the small work boat were boats increase or decrease their individual speed. Tow- able to connect the mat to the anchors at the shackles. ing proceeded more confidently in the river. (Figure After the initial two connections were made the tow 54) craft was able to move away and the balance of the connections were made. (Figure 52) All of the tow boats were radio-equipped to prevent confusion. If a connection was difficult to make because the section had drifted out of position, a tow craft standing by would push the section by running its bow against the tires, All connection on the first section required three hours. Figure 53 01 A 71 Figure 54 Figure 51 Installation of the last three sections required men working in the water for the first time. These three - ---------- --- required hookup to the previously installed sections A section and to the moor, ng lines. As the section was moved into position, the workers prepared to enter the water, wearing life jackets and carrying the necessary tools, extra nuts, and bolts. Working in two man teams, they connected the mats together at outside #4' corners to prevent the section from drifting. The mar- rying tires and belts were attached to the end of one of the sections. The team opened the belt, properly posi- tioned the marrying tire and belting, and bolted the belting back together. (Figure55)The crew in the work boat began connecting the mooring lines, using the tow boats to shift the position of the FTB section as required to relieve strain. The workers in the water Figure 52 finished connecting the nine remaining modules to- A temporary marking light required by the U.S. gether, a task that really did not require more than one Coast Guard had to be installed. The light had to flash hour for each of the three sections. Connecting the -25 - ing the port authority with publicity about the FTB di and its final installation. Through this effort, a positive image of the technology and the Lorain Port Authority commitment to development in the Port of Lorain was shared with many. NAVIGATIONAL LIGHTING: A permanent navigational light had to be installed at the end of the structure. The specification of U.S. Coast Guard called for a structure a minimum of 10' above the water level. The light had to be green and display at 15, but not more than 30 flashes, per minute. VZ The light source was to be a tungsten incandescent type light with independent power source, to be operated from sunset to sunrise and visible for one mile on a clear dark night. These specific requirements led to Fioure 55 working with Penwalt Automatic Power, Inc. of mooring lines required more time because of the need Houston, Texas, a manufacturer of navigational aids. to reposition the mat due to wind drift. Nearly a full Other factors about the light and its structure had to day's work was required to tow and connect each be considered. These included the need for a buoy-type section to its permanent mooring. (Figure 56) After since the tire modules would not support a structure each section was anchored, the temporary marking required to be 10'above the water. Furthermore, cost light would be relocated to the end of the new section. was a concern and it needed to be virtually mainte- While this system worked well, it was not without nance free. problems. First, the sinking of two markers did occur, Automatic Power's solution to these requirements requiring a diver to locate the lost end of the mooring was a light mounted atop a tension-anchored buoyant line and reattach a new marker and line. Locating the mast. The mast would stand upright from its anchor by mooring cables was not difficult, but entailed patience the use of 1500 pounds of buoyancy mounted to the since the visibility was poor and the diver searched by mast and held submerged below the surface. The feel. Second, two leeward side anchors had been posi- design called for a 11/4-ton anchor attached directly to tioned incorrectly causing the mooring line to be short. the bottom end of the mast. The mast would elevate the It was easier to add cable to the mooring line for the light to a minimum of 10'above the water level during connection. Extra cable for these two anchors, and for high water, and even higher as water levels dropped. two other mooring lines that were too tight, were The lamp atop the mast would be a standard off-the- ordered. With the extra cable installed in the mooring shelf ty'pe lamp with a solid state six volt flasher sys- system, the entire 600' length of the FTB fell into an tem, with a .5 seconds on, 3.5 seconds off flashing eye-pleasing straight line. sequence, controlled by an electronic photo sensitive eye, have a six place automatic bulb changer to reduce required maintenance, and powered by a solar charged battery system with five-year battery life expectancy. The mast structure was designed and constructed of steel pipe and bracing for permanent installation for summer and winter conditions. (Figure 57) The total cost for the marking light, anchor and "'RM' installation was $3,446.37. The least expensive mark- ing light considered, it was thought the best alter- native. The installation of the marking light proved to be easy. Two divers using a float bag eliminated the need A for heavy lifting equipment and a higher cost. (Figure T 58). With the float bag, the anchor and mast could be @7@ attached at the surface of the water and towed to its permanent location. Deflating the float bag, allowed the anchor and mast to sink into position. (Figure 59) Figure 56 With the mast placed in the water (Figure 60), the marking light unit was then attached to the top of the The completion of the construction and installation mast from a work boat. (Figures 61, 62). This of the FTB took about six weeks longer than originally entire operation required four hours. planned, due to the delayed receipt of some of the With the marking light in place and operational, the mooring lines. Actual work weeks amounted to a total entire FTB project was complete. (Figure 63) of 24 and reflected favorably on the planning for the project. Special assistance was provided by Goodyear, assist- -26- 155W LOTUN Ell x7tKy VEWL 'A' w DE-TWL 'A' Figure 59 "A-A" Figure 57 Figure 58 Figure 60 -27- Figure 62 WWI-, Figure 61 . . . . . . . . . . I Figure 63 -28- Cost Analysis BUDGET ESTIMATES: Two early cost estimates evolved. First, the costs included in the application for funds from the Ohio Department of Energy. This budget was computed using existing literature (adjusted for inflation) and the design of a 28 foot by 1000 foot FTB as observed in Dunkirk, N.Y. FLOATING TIRE BREAKWATER 1980 Cost Estimate 570 Modules x 20 Tires/ Mod 11,400 Tires Item Quantity Unit Cost Total Cost 1. Scrap Tires 11,400 .20 $ 2,280. 2. Urethane Foam 6,600 lbs. .95 6,270. 3. Chain 20,000 ft. .95 19,000. 4. Anchors (handmade) 500 lb. 30 40.00 1,200. 5. Anchors (250 lb) 15 20.00 300. 6. Mooring Chain 3,000 ft. .95 2@850. 7. Labor estimate - 2 hrs/bundle-build & install 1,136 hrs. 7,950. 39,850. 8. Administration @ 5% 1,950.- Total: $41,800. 9. Contingencies 2,000'.' .$43,800. Later, after Stanley Consultants had finished their wave analyses, a second budget evolved based upon a 80 foot by 600 foot FTB and adjusted unit costs. REPRESENTATIVE COSTS FOR FTB CONSTRUCTION AT LORAIN Item Quantity Unit Cost Totat Cost Scrap Tires 18,920 tires $ 0.20 3,800 Foam Flotation 9;460 lbs. 0.95 9,000 Scrap Conveyor (Belt Strips) 28,400 ft. 0.50 Seaward Concrete Anchors 1,800 lbs 13 anchors 105.00 1,400 Leeward Concrete Anchors 900 lbs. 14 anchors 70.00 1,000 Anchor Mooring Chain One-Half Inch Open Link 1,600 ft. 1.05 1,700 Labor Construct (I hr/ module) 946 hrs. 15.00 14'200 Install (1.25 hr/ module) 1,183 hrs. 15.00 17:800 $63,100 The port authority, having received a commitment The four bids varied from $89,247 to $269,307. All bids for belting and scrap tires, still believed the project was were rejected and the port authority decided to build feasible. Excluding these costs, the consultants' total the FTB in-house. With a labor commitment from the estimate was $45, 100, a figure very close to the $43,800 CETA program, a third budget was developed. This grant award. Surely, it was thought, competitive bid- budget took into consideration the donation of labor, ding would close the gap. tires, and belting, but retained a category for supervi- The competitive bidding process proved otherwise. sion to cover the expense of a construction manager. -29- LORAIN PORT AUTHORITY Floating Tire Breakwater Work Budget General Fund Estimated Cost I .Supervision $12,000 2. Insurance 500 3. Site Lease 1,500 4. Utilities 1,000 5. Leased Equipment 3,000 6. Hand Tools 500 7. Lumber 1,000 8. Chains, Bolting, Anchors 3,000 9. Foam 12,000 10. Other Sub-contract 2,000 11. Marking Buoys 5,000 12. Contingencies 2,300 $43,800 As ari aid to understanding the work budget, an 7. Lumber: The cost of lumber and other material explanation of each item follows: necessary to repair the warehouse for the project and 1. Supervision: The expected cost of the construc- materials needed for tables and other equipment used tion manager for the project under a professional ser- in the construction of the FTB. vice contract entered into between the port authority 8. Chains, Bolting, Anchors: This category is self- and the construction manager. Unexpectedly and explanatory. The original cost estimate was based on fortunately for the project, the 'Salary for the some early price quotes for chain and anchors. This, of construction manager was eligible under the CETA course, changed drastically when the anchor and program which freed money for expenses. mooring line design was changed and the cost of the 2. Insurance: Special insurance possibly required sandstone anchors and galvanized wire rope was used. for employees working in the water. The need for 9. Foam: The cost of urethane changed, but from insurance for employees was eliminated totally in the the.urethane foam system to the styrofoam block and project. The State Workman's Compensation in- polyethylene bag system. surance handled through the CETA payroll provided 10. Other sub-contract: Costs for specialized help. adequate protection and no additional insurance was The marine contractor hired for setting the mooring required. and anchor system was the main expense. The original 3. Site Lease: This cost was based on an agreement estimate reflected the cost of a lighter system. Costs for with the landlord that fixed the lease cost, regardless of grading and site preparation at launch area were also duration. included. 4. Utilities: Electric and telephone. Also included 11. Marking Buoys: All of the costs of acquiring the were charges by the electric utility company for instal- buoy, anchor and installation. ling a three-phase, 440-volt electrical service to the 12. Contingencies: Fuel costs for fork lift, boats, warehouse and the cost of an electrician's time and branding iron, mooring rope, safety, and first aid material for installing the electrical panel, lighting and material, and other unexpected costs. utility plugs inside the warehouse. 5. Leased Equipment: Monthly rental costs of the fork lift and portable field toilet. 6. Hand Tools: For the purchase of necessary hand tools, including special tools or equipment such as the branding irons, tire spreader brackets, and lifejackets. 30'- ACTUAL COSTS: In the final analysis, the project exceeded the ODOE grant by $7,622. This shortfall was offset by the port authority adding $6,000 from its general fund and selling off some of the accumulated equipment at the end of the project. The primary cause for the higher than expected project cost was the increased expense of the mooring and anchoring system. -These extra expenses in the mooring system were viewed as a go od investment in light of the potential -hazard of under- designing. Final distribution of expenses appeared as follows at close-out: FLOATING TIRE BREAKWATER Work Budget October 31, 1981 Estimated Cost Expense To Date Balance Budget 1. Supervision $12,000.00 $ $12,000.00 2. Insurance 500.00 500.00 3. Site Lease 1,500.00 1,500.00 4. Utilities 1,000.00 3,904.98 -2,904.98 5. Leased Equipment 3,000.00 4,203.27 -1,203.27 6. Hand Tools 500.00 @496.03 3@97 7. Lumber 1,000.00 789.87 210.13 8. Chains/Bolting 3,000.00 12,826.95 -9,826.95 9. Foam 12,000.00 14,738.63 -2,738.63 10. Other Sub-contract 2,000.00 5,754.00 -3,754.00 11. Marking Buoys 5,000.00 3,446.37 1,553.63 12. Contingencies* 8,300.00 3,762.52 .4,537.48 $49,800.00 $51,422.62 ($1,622.62)" Gross CETA Wages at Close-out - October 31, 1981 $51,652.00 (with fringes) *The sum of $6,000 appropriated by port authority, 7-14-81 **Recaptured by selling reuseables UNIT COSTS: MOORING SYSTEM FOAM The mooring system was made of 18, 5-ton sand- Two styrofoam blocks sealed in 10 mil poly- stone anchors, 20 mooring lines, each 60 feet long, and ethylene were required for each tire - 18,920 two intermediate connecting lines from the govern- total tires. ment pier. The mooring lines connected to each Foam - 38,000 block x $.274 $10,411.67 anchor, consisted of one 3/4" galvanized wire rope sec- Bags - 38,000 bags x .1139 4,326.96 tion as the connector at the modules, two I V8" galva- nized wire rope sections, the two truck tires as shock Total Cost: $14,738.63 absorber, two sections of 5/8" chain and two hammer- Unit Cost per tire $.78 locs for connectors of the tire shock abs6rbers, and one 12-ton safety shackle. The two 60'lines attached to the government pier were 11/8" galvanized wire rope, 3/4" wire rope module connectors, and 12-ton safety shack- les. The last part of the mooring system was two 25' long Y8" chain sections attached to the government pier at intermediate points on pier end of the FTB. These were connected to 3/4" galvanized wire rope module connector with 12-ton safety shackles. -31 - Anchors 9 18 @ $125. freight inc. $ 2,250.00 Mooring Line * 18 pcs. 3/4" x 30 ft. 6x19 IWRC galvanized wire rope 2/gal. thimble swaged Components both ends @ $68.62 ea. 1,235.16 9 18 pcs. I V8" x 35 ft. 6x25 IWRC galvanized wire rope w/ gal. thimble swaged both ends @ $173.04 ea. 3,114.72 e 18 pcs. 11/8" x I I ft. 6x25 IWRC galvanized wire rope w/ open swaged socket one end and galvanized thimble swaged other end @ $118.76 ea. 2,137.68 * 2 pcs. I V8" x 60 ft. 6x25 IWRC galvanized wire rope w/gal..thimble swaged both ends @ $258.84 ea. 517.68 * 4 pcs. 3/4" x 20 ft. 6xI9 IWRC galvanized wire rope w/gal. thimble swaged both ends @ $51.26 ea. 205.04 9 36 pcs. Y8" x 5 ft. herc-alloy chain @ $36.40 ea. 1,310.40 e 42 pcs. Y8" hammerlocs @ $12.78 ea. 536.76 9 26 pcs. 12-ton safety shackles @ $23.56 ea. 612.56 9 54 ft. V used chain @ $2.50/ ft. 135.00 Total, less discount $11,956.95 Unit cost per mooring line/ anchor combination 18 @ $ 607.34 Unit cost per mooring line to pier connection 4 @ $ 280.72 NUTS AND BOLTS Hot-dipped galvanized plated nuts, bolts, and wash- ers were used as the belt connector for the modules. The sizes of bolts and nuts used was Y8" - 16 x 13/4" capscrew and Y8" - 16 hex nut. The washers were Y8" flat washer, I"O.D. Each bolt, nut and two washer set cost $.1024 each. While approximately 8,000 sets were needed for the project - 8,500 sets were purchased. 8,500 connector sets @ $.1024 each $870.00 TOTAL. PROJECT COSTS: Material and Project Support: $ 51,422.62 Labor Cost: CETA Labor - $5.37/ hr. x 5.78 men x 960 total hours $29,814.00 Fringe Benefits $ 1. 10/ hr. x 5.78 men x 960 total hours 6,104.00 Total CETA Labor $35,918.00 Supervision - $15.00/ hr. x 960 total hrs $14,400.00 Fringe Benefits $ 1.39/ hr. x 960 total hrs 1,334.00 Total Supervision $15,734.00 Total Labor Cost $ 51,652.00 Total- Project Cost $103,074.62 UNIT COST - TOTAL PROJECT Material and Project Support per Module (946) $ 54.36 Total Labor Cost per Module (946) 54.60 Total Project Cos -t per Module (946) $ 108.96 Total Project Cost per Square Foot (I I modules. - 80 ft. x 86 modules - 600 ft. 48,000 sq. ft.) $ 2.15 Total Project Cost per Lineal Foot (i.e. 600 ft.) $ 171.79 In summary, early budgets were based on existing and donated to the project. Furthermore, the labor literature, which zontained limited costing data about rates paid to the CETA employees may be lower than relatively few installations. The biddingexperience evidenced: what might be expected in other locales. It is fair to 1. limited- general contracting knowledge of FTB conclude that anyone preparing to bid on FT13 to a construction, and 2. a diversity of opinion on con- general contractor can expect these factors to increase st.ruction methodology. the total costs above those experienced by the Lorain The reader is cautioned and reminded that many Port Authority. hours of time, and valuable equipment were loaned -32- Short Term Observations SEAWEED AND SEDIMENT: The FT13 installation in the east basin of Lorain Growth of seaweed on the tires below the water line Harbor was completed on July 23, 1981. In the six- has been tremendous. Growth has been observedto be month period since the installation, constant observa- as much as three feet long on some tires. (Figure 64) tion and monitoring of the FT13 has taken place, with Storm action seems to trim some of the seaweed as the visual inspections from a boat, observation from shore tires work against each other. Icing throughout the during storm conditions, and under-water inspections winter is expected to strip away all algae. by divers checking the mooring system. From these Accumulation of sediment inside the tires has been. observations the following findings are offered: non-existent. Previous study of the area showed very little movement of bottom sediment. For this reason, no holes were punched in the tires to allow sediment to THE MOORING SYSTEM: filter out. Current opinion is that these holes arenot. An inspection of the mooring system by a diver was effective unless they are large enough to prevent plug- performed six weeks after the installation. During that ging by sea life (i.e. 4-inch square or larger). six-week period, the FT13 was exposed to two storms. Although no specific data on the storm conditions was collected, both storms exposed the FT13 to very rough lake conditions. The diver checked the condition of cables, the shock absorber truck tires, and the anchors. The inspection of the cables was performed by running a piece of cloth over the cables by hand to feel for any strand break- down. None was detected. The inspection of the shock absorber tires did reveal altered conditions. At the time of installation, a diver inspected the shock absorber tires and they were lying flat on the bottom. The later inspection revealed the shock absorber tires had repositioned themselves so that they were standing in a vertical position on the bottom. This had to be caused by the storm forces on the cables which lifted the shock absorbers and reposi- tioned them. Inspection of the anchor stones indicated that there had been no movement. All connectors (i.e. safety shackles, chains, and hammerlocks) were in good condition. 4 BINDING MATERIAL: Inspections of the binding material showed no vis- ible breakdown or deterioration of any of the bindings. Nearly all of the galvanized nut and bolt connectors in the belts evidenced rusting, as expected. Figure 64 FLOTATION: FISH POPULATION: The flotation has worked effectively. A few of the No evidence of an increase in fish population was foam blocks have been dislodged by the storm action. detected in the area by local fishermen. No measure- These were retrieved from the shore to be saved for ments of fish-life near the FTB were recorded, and therefore an accurate picture of the situation is impos- reinstallation in the spring. The total loss amounts to sible. Other experience with FTBs has shown increases 25 pieces. It is believed that these blocks may not have in fish populations nearby. The Lorain installation been snugly fitted in the tires as a result of the launch- presents a real opportunity for further study in this ing or dislodged by swimmers attracted to the installa- area. tion. The loss of these blocks of foam does not seem to present a problem. The level of freeboard of the EFFECTIVENESS: modules has remained the same since launched. The six-month observation period has provided opportunity to see the effectiveness of the FTB at work. The breakwater works effectively in reducing DEBRIS COLLECTION: the short period (3'to 4'waves). Under the storm condi- The FTB has proved to be a good collector for debris tions observed, the water along the leeward side of the and flotsam. This has not proved to be much of a FT13 was reduced to calm water. (Figures 65,66,67) No problem and storms seem to flush most of the debris wave measuring devices were placed in the area to from the modules. accurately record wave heights, thus the amount of the -33- rolling through the FTB is evermore evident, (Figures 68,69) These long period waves will pose little problem to installing single point moorings behind the FTB; how ever, further study of a floating dock system is required. Amendments to the installation are being evaluated to counteract this site specific problem. V" EMU Figure 68 Figure 65 Figure 69 ICE CONDITIONS: The breakwater was exposed to floating ice-packs during the month of December, 1981 without any vis- ible problem. Since January, 1982 the FTB has been completely frozen in the ice with the entire east basin area ice-covered. (Figure 70) No signs of problems are evident as of March, 1982. Further observation during the spring thaw will be conducted to evaluate the Figure 66 effects of the ice on the FTB. It is anticipated that no problems will be experienced. Figure 67 attenuation cannot be quantified. These devices will be installed in the spring. The observation period has evidenced a wave action Figure 70 that the FTB has been ineffective in attenuating. With the configuration of the fixed breakwaters in the east basin area, long period waves are occurring along the government sheet-pile pier to which the FTB is at- tached. These longer period waves roll beneath the FTB, as if the FTB was riding the wave. Apparently, there is a multiplication of wave energy. With the installation of the FTB, the short period waves are reduced and the existence of the long period waves 34- THE PUBLIC RESPONSE: 3. Utilizing the procedures employed in this project, Local public response to the breakwater installation a doubling of the production rate could be attained was very favorable and was probably the result of the with the employment of four additional workers. This joint public relations effort of Goodyear and the would allow the sub-assembly operations to run simul- Lorain Port Authority. As the result of media coverage taneously with the building of the modules and provide about the installation, many inquiries have been a continuous flow of "Prepared" tires to that opera- received about available dockage, which will soon be tion. Workers trading tasks during each day is recom- installed. mended to overcome the repetitious and boring nature Another unexpected number of inquiries about the of the tasks. FTB and its construction have been received from 4. The ease of the second method of towing (two around the country, as the result of the national wire boats forward) the breakwater sections suggested that services, leading to inquiries from as far away as it would have been far more practical to have towed Southhampton, England. This interest from around and installed larger sections of the FTB than in this the world bodes well for the future of FTB develop- project. It is suggested that sections up to 50 modules ment. long can be easily towed and installed, assuming good weather conditions; This can save a lot of time. Conclusions and Recommendations FOR THE FUTURE: The experience of constructing and installing the This first hand experience with scrap tires as wave FTB in the east basin of Lorain harbor has to be energy absorbers, has proven their effectiveness in considered a success. Although the basic goal of build- attenuating waves. This fact encourages further use of ing a breakwater durable enough to remain in place scrap tires as a solution to other hydraulic problems. year-around for 10 years with a minimum of annual The need for protected water space for recreational maintenance is believed achieved, the test of time will boating opportunities has been documented. An even be a better judge. greater demand for shoreline protection is evident The goal of minimizing work in the water was throughout the country. With the high costs for con- accomplished. The need for assuring the permanence ventional breakwaters solutions to erosion problems, of the breakwater was fulfilled with the redesign and utilizing scrap tires is becoming economically practical. installation of a stronger, heavy-duty mooring line/- Existing FTB literature cites that research and anchor system. And finally, the overall project was development have been conducted to examine the considered to have been performed in a timely and effectiveness of utilizing scrap tires for shore erosion cost-effective manner. control, but much more is needed. Scrap tires, with The nature of the project as a one time, public their proven ability to absorb wave energy, non- agency undertaking, had a direct bearing on how the degradable quality, low cost and relative abundance, construction activities evolved. Investment in tools make them an ideal material for solutions to hydrau- and machinery which could have greatly expedited lics problems. Their use for shoreline erosion control, many of the operations in the project were unafforda- lake and river bank protection, beach replenishment, ble. Implementation of such equipment would have beach retention, and other applications are waiting to greatly improved production and efficiency in building be explored. modules. However, the budget of the project did not The prevalent perception of scrap tires as a waste allow it. Nonetheless, building systems and procedures material needs to be changed so that a valuable raw described earlier were employed with success. material resource fulfills a new usefulness. From the Lorain experience, further suggestions to facilitate a similar project are offered: 1. Because of delays in getting tires, delays in receiv- ing the conveyor belt, and other factors that caused delay in getting into module production, it is recom- mended that a pre-construction period be expected. At least a one-month period before construction should be expected. One paid staff person can arrange details for stockpiling tires, getting material ordered, making the necessary improvements required at the construc- tion site, and the making of other necessary ar- rangements. 2. If the styrofoam block and bag system is used as a flotation device, it is suggested that a glue, adhesive, or other fastening device, be tried to more permanently secure the flotation blocks to the inside of the tire. This was not tried and effectiveness is yet undetermined. Loss of the flotation blocks has not proven to be a serious problem, but a cost-effective means of gluing or fastening would add another degree of security to the overall system. -35 - ABOUT PEOPLE THE AUTHOR: David Thomas Lee, called Tom by his friends, was the construction manager for the Lorain FTB. With that experience he served as the principal author for this report. It was Tom's innovative, yet practical, approaches that guided the project to completion. After study at Mount Union College, Alliance, Ohio, Tom received his Bachelor of Architecture degree from the State University of New York at Buffalo in 1973. Tom has a multi-dimensional background having served as a field engineer, prototype engineer, graphic designer, construction supervisor, rehabilitation ad- ministrator, and construction manager. His work has been with the private and public sectors. Tom is self- employed as a consultant offering multi-functional services. Tom is 33 years old. He and his wife, Carol, are the parents of Amy and Joshua. They are avid sailors, and Tom has served as the business manager and commodore of the Lorain Sailing Club and com- modore of the Lorain Yacht Club. THE EDITOR: John G. Sulpizio is the Executive Director of the Lorain Port Authority, an agency which concentrates upon economic, industrial, and recreational develop- ment on the waterfront. His commitment to improving that waterfront where he grew up, led to the decision to build and funding of the FTB. John is a 1969 graduate of Cornell University, Ithaca, N.Y. and holds a Bache- lor of Arts degree. John has held various positions in the field of community development. Prior to joining the Lorain Port Authority in 1978, he was the chief planner for the City of Lorain. John is the president of the Council of Lake Erie Ports, a director of the Chamber of Commerce, and active in professional and civic affairs. Recently, he served as a panelist at the Second Annual Conference on Floating Breakwaters in Seattle, Washington. John is 35 years old and is spending his spare time completely rebuilding a 90- year-old homestead in the center city for his wife, Patricia, and himself. They are expecting their first-born. -36- Acknowledgements The author and the Lorain Port Authority would like to recognize and thank the many companies and individuals who so generously donated materials, equipment, personal time, technical assistance or moral support, in the construction of the breakwater and the production of this report. Their help was integral to the success of both endeavors. A. & C. Tire Company, Amherst, Ohio - Tires American Auto Wrecking, Lorain, Ohio - Tires American Ship Building Company, steel plate B. Beatty, B. B. Bradley Company, Technical assistance Certified Oil Company, Elyria, Ohio - Tires Chets Sunoco, Avon Lake, Ohio - Tires City of Bay Village, Ohio - Tires Conrads Goodyear Tires, Lorain, Ohio - Tires Deichler Tire Company, South Amherst, Ohio - Tires Doane Electric Company, field trailer Ed's Sunoco, Lorain, Ohio - Tires Elmira Tire Company, Lorain, Ohio - Tires Ferraro, E. Finegold, Frank, CETA Administrator, Lorain Francis, Ray, Naval Architect, AmShip Company, Technical assistance Goodrich, B.F. Tire Center, Lorain, Ohio - Tires Goodyear Tire and Rubber Company, Akron, Ohio, pneumatic punch and air compressor Gordon Baugh Tire Company, Cleveland, Ohio - Tires Greszler, Richard, boat and towing assistance, welding Hess, M. United McGill Corp. Technical assistance Independent Oil Company, Elyria, Ohio - Tires Jaycox, Captain Robert, Harbormaster, boat and towing assistance Jaycox, Robert, Jr., boat Jones, R. General Latax Corp., Technical assistance Kalister, P., United Garage Door Company Lee, Carol, Amy, and Joshua, Love, support, and proofreading Lee, Robert, Durfip truck, module carrier trailer, work boat, temporary marking light boat, personal time and support Leggett, Mort, Goodyear Tire & Rubber Company, support Leigh, G., Aabaco Plastic Products, Technical assistance Lucus Plumbing, portable welder Mercer, R. G., Goodyear Tire & Rubber Company, Technical assistance Morrison Tire Company, Navarre, Ohio - Tires Muzik Brothers Sunoco, Lorain, Ohio - Tires North Eaton Tire Company, North Eaton, Ohio - Tires Oakwood Plaza Union 76, Lorain, Ohio - Tires Otis, R., Meeco Marinas, Inc., Technical assistance Pacemaker Plastics, Inc., Technical assistance Pecora, R., Mechanical assistance Pierson, R.M., Goodyear, Technical assistance and support Rt. 254 Sunoco, Lorain, Ohio - Tires S. & A. Smith Tire Company, Grafton, Ohio - Tires Saefkow, W., Foam Master, Technical assistance Schleitet, Robert F., Tuscarora Plastics, Technical assistance Shuster, Charles, skin diving Stoltz, G., Areo Polymers, Technical assistance Sulpizio, John G., Lorain Port Authority, Editing and Administration Thomas, Bill, Service Center, Lorain, Ohio - Tires Tolley, H. A., Goodyear Tire & Rubber Company, Technical assistance and support - 37- United Garage Door Company, lumber cart, cutting torches United States Steel Corporation, Lorain, Ohio, donation of conveyor belt material, 11/2" steel bar stock Warehouse Tire & Recap Company, Grafton, Ohio - Tires Willig, Ralph, Tire Company, Akron, Ohio - Tires Wiseman, Ruth, Lorain Port Authority, Typing Woodhall, E.D. "Ted", Goodyear Tire & Rubber Company, Technical assistance and support Last, but certainly not least, deserved acknowledgement to the Board of Directors of the Lorain Port Authority for its foresight of a better tomorrow. James A. Byrd Dan B. Canalos Wayne Conn Roger E. Doane William B. Gow, Chairman Richard Greszler George G. Llewellyn, Jr. Ralph W. Miller Stanley A. Orlowski These acknowledgements express the appreciation of the Lorain Port Authorit v and the Author. The listing of a corporation or individual name does not necessarily constitute their endorsement of the technology or the statements contained herein. -38- BIBLIOGRAPHY This list of publications represents reference infor- mation used in planning and constructing the Floating Tire Breakwater in Lorain and research sources for this report. Bishop, C.F. 1980. Design and Construction Manual for Floating Tire Breakwaters. National Water Research Institute of Canada for Inland Waters, Burlington, Ontario, Canada. Candle, R.D. & Fischer, W.J. 1977. Scrap Tire Shore Protection Structures. Goodyear Tire and Rubber Company, Akron, Ohio. Davis, A.P., Jr. 1977. Evaluation of Tying Materials for Floating Tire Breakwaters. University of Rhode Island Marine Technical Report #54, Kingston, Rhode Island. De Young, B. 1978. Enhancing Wave Protection With Floating Tire Breakwaters. Cornell University Sea Grant Extension Program Information Bulletin #139, Ithaca, New York. Giles, M.L. & Sorensen, R.M. 1978. Prototype Scale Mooring Loads and Wave Transmission for a Floating Tire Breakwater. Army Corps of Engi- neers Coastal Engineering Research Center, Fort Belvoir, Virginia. Harms, V. W. 1979. Data and Procedurefor the Design of Floating Tire Breakwaters. New York Sea Grant Institute, Albany, New York. Kowalski, T. & Ross, N.W. 1975. How to Build a Floating Tire Breakwater. University of Rhode Island Marine Bulletin #21, Kingston, Rhode Island. Penny, B.C. 198 1. Performance Analysis of Test Sec- tion Floating Tyre Breakwaters. Lyttelton Harbor Board, Christchurch, New Zealand. Ross, N.W. 1977. Constructing Floating Tire Break- waters. American Chemical Society Symposium: Conservation in the Rubber Industry. Shaw, G. & Ross, N. W. 1977. How to Builda Floating Tire Breakwater. University of Maine/ University of New Hampshire Cooperative Institute Sea Grant Program. Stanley Consultants, 1970. Recreational Boating and Commercial Dock Facilities, Lorain, Ohio. Lorain Port Authority, Lorain, Ohio. Stanley Consultants, 1978. Lorain Harbor Recrea- tional Area Study. Coastal Zone Management Program and the City of Lorain Department of Community Development, Lorain, Ohio. Stanley Consultants, 1980. Lorain Marina Feasibility Study. Coastal Zone Management Program and the Lorain Port Authority, Lorain, Ohio. Woodhall, E.S. 1980. Breakwaters as an Aid to Mari- nas, Shore Erosion Control and Marine Life. Presentation Paper, Ohio Sea Grant, Floating Tire Breakwater Conference. February, 1980, Fire- lands College, Huron, Ohio. -39- 1982 JUN -1 AM 10:-5 MAIL ROOM DATE DUE GAYLORDINo. 2333 PRINTED IN US NOAA COASTAL SERVICS CENTER LIBRARY 36669141086647