[From the U.S. Government Printing Office, www.gpo.gov]
PROJECT MANUAL FOR REHABILITATION OF THE PRESCOTT PARK SEAWALL PREPARED FOR City of Portsmouth New Hampshire Funding for this Project Manual and plans has been provided by a grant from the NH Coastal Program. PREPARED BY Kimball Chase Company, Inc. 40 Bridge Street Portsmouth, New Hampshire I'VV FEBRUARY 1986 PROJECT MANUAL Including Specifications for REHABILITATION OF THE PRESCOTT PARK SEAWALL Prescott Park Portsmouth, New Hampshire for the b $0EPARTMENT OF COMMERCE r4y of Portsmouth, New Hampshire I OJS~' L SERV 'CES CENTER 2234 SOUTH HOBSON AVENUE CHARLESTON, SC 29405-2413 o Property of c~c Libraryj Prepared By KIMBALL CHASE COMPANY, INC. 40 Bridge Street Portsmouth, New Hampshire 03801 (603) 431-2520 Engineer's Job No. 85-1227 Date of Issue: March 19, 1986 "The New Hampshire Coastal Program provided a grant to the City of Portsmouth for the preparation of this Project Manual and plans, which was financed in part by the Coastal Zone Management Act of 1972, as amended, administered by the Office of Ocean and Coastal Resources Management, National Oceanic and Atmospheric Administration" TABLE OF CONTENTS TITLE Division 0 - Bidding & Contract Requirements 00010 Invitation to Bid 00015 Instruction to Bidders 00020 Rehabilitation of Prescott Park Seawall 00022 Proposal 00025 Experience Statement 00030 Notice of Award 00040 Notice to Proceed 001C0 Standard Form of Agreement Between Owner and Contractor (NSPE Form 1910-8-A-1) 00110 Performance Bond 00120 Labor and Material Payment Bond 00200 Contractor's Affidavit 00210 Contractor's Release 00300 Change Order 00400 Certificate of Substantial Completion 00500 Standard General Conditions of the Construction Contract (NSPE Form 1910-8) 00510 Supplementary Conditions/Federal Requirements Division 1 - General Requirements 01010 Summary of Work 01050 Special Attention 01070 Abbreviations and Symbols 01150 Measurement and Payment 01310 Construction Schedules 01510 Temporary Utilities 01630 Substitutions and Product Options 01710 Project Cleaning 01720 Project Record Documents Division 2 - Site Work 02201 Excavation, Filling, and Grading 02223 Trench Excavation - Earth 02401 Dewatering 02648 Lawns 02653 Filter Fabric 02660 Erosion Control 02694 Footing Drains 02701 Sidewalks - Brick 02901 Granite Blocks Division3 03000 Concrete 03300 Cast-in-Place Concrete 03380 Cement Mortar Divisions 4 - 16 -Not Used SECTION 00010 INVITATION TO BID 3 ~~~~~~~~City of Portsmouth, New Hampshire 3 ~~~Sealed proposals will be received at the office of Purchasing Agent, 126 Daniel Street, Portsmouth, New Hampshire 03801, before or at _____p.m. on the day of , for the following described project. I ~ ~~~~~~REHABILITATION OF THE PRESCOTT PARK SEAWALL Plans and Specifications may be obtained at the office of Planning Department, 126 Daniel Street, Portsmouth, New Hampshire upon payment of $25.00 which will not be refunded. Plans and Specifications will be mailed upon receipt of an additional $10.00 to cover postage and handling. Plans may be reviewed at the following locations: 1. Office of Kimball Chase Company, Inc., 40 Bridge Street, Portsmouth, New Hampshire 03801. 2. Office of Planning Department, City of Portsmouth, 126 Daniel Street, Portsmouth, New Hampshire 03801. I ~ ~~~3. Office of Dodge Reports, 114 Bay Street, Manchester, New Hampshire 03101. 4. Office of Associated General Contractors, Fort Eddy Road, Concord, New Hampshire 03301. The successful bidder will be required to furnish a bid bond in the amount of 5% of the total bid, a performance bond in the amount of 100% of the Contract I ~ ~~Price and a Labor and Material Bond, also in the amount of 100% of the Contract Price. Attention is called to the fact that not less than the minimum salaries and U ~ ~~wages as set forth in the Federal Wage rates contained in the Contract Documents (said rates are subject to change) must be paid on this project, and that the Contractor must insure that employees and applicants for employment I ~ ~~are not discriminated against because of their race, color, religion, sex, or national origin. The City of Portsmouth reserves the right to reject any or all bids, to accept any bid, to waive any informality on bids received, and to omit and/or alter any item or items deemed advisable for the best interest of the City. Bids I ~ ~~ay be held by the City of Portsmouth, for a period not to exceed thirty (30) days from the bid opening date for the purposes of reviewing the bids and investigating the qualifications of bidder, prior to awarding the contract. 3 ~~~This project will be funded by the Federal Government and, as such, the successful Bidder must comply with all Federal regulations. Failure to do so will result in termination of the Contract. SECTION 00015 This document has important legal consequences; consultation with an attorney is encouraged with respect to its completion or modification. STANDARD FORM OF INSTRUCTIONS TO BIDDERS Join tOy Issued by PROFESSIONAL ENGINEERS IN PRIVATE PRACTICE A practice division of the NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS and by AMERICAN CONSULTING ENGINEERS COUNCIL and by CONSTRUCTION SPECIFICATIONS INSTITUTE 1978, NAIIUNAL SOCILTN OF PROFESSIONAL ENGINLIR9 2029 K STREET, N.~W., UWASHINGTON, D.C. 20006 AMF RI( AN CoNt Li ING ENGINEFRS COL( II 1015 I1 H Sir I I 1. N W.. WASHINGION. D.C. 2000) CONSTRL'C( I()N SPI (IFICATIONS INSTITU'TI 1150 17TH STREIT, N.W., WASHINGTON, D.C. 20036 These Instructions to Bidders have been prepared for use with the Owner-Contractor Agreements (NSPE-ACEC Docu- ment 1910-8-A-1 Ior 1910. -A-2; CS1 56467. 56468, 1978 editions) and with the Standard General Conditions of the Con- siruction Contract (NSI'L-ACEC Document 1910-8; CSI 56474, 1978 edition). Their proisions are interrelated and a change in one ma} nccessitate a change in the others. Comments concerning their uage are contained in the Commentary to the Documents. NSPE-ACEC 1910-9, 1978 edition. NSPE-ACEC 1910 12 t197lk diiion) CSI 56466 1. Wietned lerms%. 4.3. Onl request Ownter will provide each .Bidder access IC) Terms used in ~~~~~~~~~~~thes Intrcton to Bidr hc r eie hSI 0conduct Such in'.estigations and tests as each Bid- Term, sed inlhc~vlivortc~ons -o Biders hc r eie der ~enis neccesarN for submission of his Bid. in the Standard Uenet al Conditions of the Construction Con-5 tract, NSP[L-ACI-C Document 1910t-9. CSl 56465 (1978 edi- 4.4. The lands uipon %,.hicli the Wsork is to he performed. tionN) hac [ tic meanings, assigned to, t hem in the General C'on- riielt-of-msas el forccc' thereto and oother land, designated di on, 1 he term -StiSccessful Bidder'' means, the lcsetvct for use hN (Cont rator in per for iniig t]he Work are ident nfied qualtified. responsible Bidder to %N horm Owner (on the basis of iln the Su pplemenrtat Conditions. GeneIral Requircments Or OC nets~ csaltiationt a, hereinafter provided) makes an assard. IDra-wings.I 4.5. Thec sulmntissiott of' a Bid is ill eons: it ut anl iflontro- 2. (opies of BiddinI4 D~ocurners. vetiible representation b% the Bidder that he has complied 2.1. ('niplcicct, vtthe Biding Docnicnijil th es-mniCryT requirenierit of' thi,, Article 4 and that the 2.1 (omicieset'ot te Bidingl~ocmeirs inthe ur~- ContactDocument, are sufficient in scope and detail to b(- IInd lot tIhe depo1it 'itni. II ans stated itt the, Adierrtise. indicate and eons e' under-standitte of all iterms and condi- metl or Ins tationt tti.1. hi obut.ink-d iroill Fniineel (unless tions for performnuce of the Wsork' a noiltci i ssi;ne office is desigitated in ithe Adsernisment oar in tat ott tIt Bid) The dlep,-itis kill be refunded to Bidder-s 5. Interpretations. niet, iinsitt a ood coiditor is thnd rtir n ifi alBi ueinin: fot All quest ion, a ho-ot the meanine ot iniert of the Contract Bids. dais' l~~~~~~~~~~~ocumnti ,t shall be stibititnes it, f-t~iciser in %,sritinp Replies Bids ~~~~~~~~~~~~~~~will be issuted b~ Addenda lmailet rdlsed d oalparties re- 2 2.Complete set, ot B1I&II: ti ouet hall be used in corded bN Engineer a', has ing received the Bidding Docu- preparing Bids; neither Ossner nor Enrineer assume arny re- mients. Questions, receised less than ten days, prior to the date sponsibhiir for errors or misinterpreataions resulting from for opening of MNd will not be ansssered. bnl% questions an- the use of inrlomrplete sets of Bidding Documents. sisered b% formal ssritten Addenda will be binding. Oral and 2.3. 0%tner and Engineer in making opies iddn ter interpretations, or clarifications msill be isithout legal Documents, available on the abose terms do so only. for the purpose of obtaining Bids on the Wsork and do not confer a 6. Bid Securit). license or grant for anN other use.3 6. 1. Bid Security shall he made payable to Om ner, in an 3.QaiiainofBdes amount of five percent of the Bidder', maximum Bid price Qualifications of Bidders. ~~and in the form of a certified or bank check or a Bid Bond To demonstrate qualifications to perform the Work, each (on form attached. if a form is prescribed) issued by a Surety Bidder must he prepared to submit within five days of Own- meeting the requirements of paragraph 5.1 of the Genea er's request written e% idence of the types set forth in the Sup- Conditions.U plementary Conditions, such as financial data, prev-ious expe- 6.2 The Bid Securit- of the Successful Bidder ssill be re- rience and e,,idenze of authoritv to conduct business in the- ss hre he rojct i loate. Ech Bd mst on- tained until such Bidder has executed the Agreement and 3 jurisdiction furnihe the Prectuired loctactSecuit. Eahsid heruso t wion- lain esidence of Bidder's qualification to do business in the fu.se teeqidCoratSur. %N heeuo i- stale ishere the Project is located or covenant to obtain such be returned ,if the succesatul Bidder fail' to esecute and de- qualifiation pior to %~ard o t h e cotract.liser the Arecemenit and furnish thle required C ontlract Secu- qualification prior to assard of the contract.rits, i it hinl 15 dat. s ci the Notice oi Ass ard. 0ss ner ntaN a n- nul ilic Noti.ce o1 -\ssard and thec Bid Sx:curits of that Biddelr 4. Examination of Contract Documents and Site. will be forfeited. The Bid Seenrits ot arts Bidder mshorn Oss ner belies Cs to hat N I a ruastitiable clanic ot rceising the 4.1 Before s-ubrniitinc a Bid. each Bidder must (a) exam- a\sard nma% be retained bx Own ter until thec varlier ol the Se%- inc the Contract Documents, thoroughly. (b) visit the site to enth daN after the "effectise date ot the -\reci'(which fami hiari,-e hims~elf msith local conditionis that ma~ in an~ I Cr IIIi, de fi neid i I I hei (IuC I I alI (oidit nios b0N Os niet Io Con- manner affect Coll, progress Or performance of the 'Work, tractor and the required ( ontract 'IeUrits is luriwihed or let~ familiar ic hirntcit si ii h federal, starte and local la,.ks. thle sid frtdas jJL it c I la,, 11It.1iii- NOi 'SCUrits ot ordinances -rurle and reeulat ions. that maN in any manner oilier Bidders wsill be ret U riled kIs In lIt sit L ii~ da% , ot Itic Bd 3I affeci cost, progress or performance of the WVork; and (dl opcititie slud% and 5arefull% corrclate 13.ddcrs~ ,oservations vmith the Contract Document- 7. Contract Time. 4 2 Rcicer-nc i, niade ii the ',u-p1L-rnniar% Conditions The number of days ssithin ishich. or the dat % mhishch. the lorthle idenitifi,,j; or; of those reports, of ins estigations and Nkmiir i to be completed fihic( otirraci T ne'stforth inthe tssof subsurface atid latent physical conditions at the Site Bid Form and isill be iti~uded tii the Agreement. or othierwise affec~tinL, costI, progress~ or performance of the Vsork which hase been relied upon by Engineer in preparing 8. Liquidated D~amages.3 the Draw.ings and Spet-itications. Omsner mill: make copies of Provisions for liquidated damnages. if any. are set forth in the such reportsr asailablc to any Bidder requesting them. These Agreement. reportsr are not guaranteed at, to accuracy or completeness, nor are they part of the Contract Documents. Before sub- 9. Substitute Material and Equipment. mitting his, Bid ceh Bidder msill, at his own expense. make - suc~h additional investigatiirtis and tssas the Bidder maN The C ontract, if awarded, isill be on the basis, of material and I deern ne:cessarN to determine his Bid for pertormanCe Of the equipment described in the Draw--ings- or specified in the Speci- Work in accordance is ith the time, price and other terms and fications without consideration of possible substitute or 'or- conditions iot the C ontrati Dt liurneriiNs. equal" filtts. Whenever it is, indicated in the Drawings or 2-i speicificd it) the Specifications, that a substitute or "or-equal'' under the signature and the official addres of the Partner- iteit of titater itt or equipment may be furnished or used by ship mus;t be shoss n beloss the signaturc: Colit, actot if acceptable it) [tiginveer, application for such B- 1.5Alnace uth ye rpitdblv h in- cep-tanice will not be consideted by [tigineer until after the 1.. Al naIe muth ypdo rntdblstesga effct e ateofthe Apreement ". The procccdur for submit. -ie til of att such applicatlion lrt Conmti ator and considerati~on II .6. The Bid shallt contain an ad.lnossledgment of receipt I ~ ~~~b\ ['IttI L'c1 is set forth in paragaraphs 6.7, 6.7.1 and 6.7.2 of of all Addenda (the ttunbers of which shall be filled in on h .ie il (I otcidif C ontt'o sshich mas be supplemented in the the Bid Form). I 1.7. The address it) ms ich communications, regarding the I lit~~~1. Suhciinlraviicsrs e~c. Bid are to be directed must bc show n. I f. I . It the StIpplelIICiUetta ConditiOtis requirei the identit'. 12. Submission of Bids. tit certain suktti llact1or' aiid othier persons' anid organiza- ioiiis to be: stibtititc teio ()ssncr in ads ance of the Notice of Bids. shall be submitted at the time and place indicated in the U a~~~~-xiid, lie atpxitett Stii~ cc-' ii Biddc; . and tins\ other Ins itation to Bidland shall bc included in an opaque sealed en- Dxfdie so rLIi'd.sill ssit bitt scs n davs al icr the daN of %elope, marked msith the Project title and name and address ol ft h,: id operitiliv akilsi[tit, Mto l Is itic li-i of all Stibcont ract ors the Bidder and accompanied t\ thc Bid SecurTy1 and other re- Fij "0cl pclt n ~iiii,ti or viti/alion, htttlll.fiine those ssho quired doctinienis. If the Bid is etilt throUglt the mail or tither UTf 1 W11s11 Ilie PrI1i'J ici alitem of inaietrial and equipment t dealsers system the sealed eveclopeshall be enclo-ed in a sepa- p:ky"o'Lf-do t0 fthc'ept t11oil', of the Mork as' to ss hich suche rate ens. el ope mmith the notatiotn "BlD 1)r*NC OSED" on the IdeitIItIIIa t ott is 'I0 r equired Stich lvis shall he accompanied face ther eof. 1,s aim c\flciitien: Ntatemlent xsit h pertitnent itiformaltion as~ to I s~~~~~inmila rproject and other evidence (if qualification for each 13. Modification and 'A ithdraA al of Bids. such1 Subconitttacor. person and organization if requested by 31 i, a emdfe rmlirm ya prpi ss net:. If Ossner or E'rteineer after due insestig-acion has ate1 Bdocmn ma'U be modifed (in wthedrasnn by anBi muspt- reasottable. to atese Sdbocmnt uraceudittomanr, oht hBerus '~ctilott an% prooe Sucnrcoohr b-sctd n eiered to t he place where Bids are to be persn o orea ii ar in. it er iasbefoe gvin th Noice submitted at any time prior to the opening of Bids. I ~ ~~~(it \ssard request the apparent Succe-sful Bidder to submit an acceptable: subtitute ssithour all increase in Bid price. If 13~.2. If, witihin tssenty-four hours after Bids are opened, the apparent Sucxcssful Bidder declines to make any such any Bidder files a dul\y signed written notice with Owner and substitution. the contract shall not be awarded to such Bid- promptly thereafter demonstrates to the reasonable satisfac- der, but his declining to make any such substitution will not tion of Owner that there was a material and substantial mis- constitute grounds for sacrificing'his Bid Security. Any Sub- take in the preparation of his Bid, that Bidder may withdrass contractor, other person or organization so listed and to hi,, Bid and the Bid Securirs mill be returned. T'hereafter. sshom 0\sner or Engineer does not make ssritten objection that Bidder ssill be disqualified from further bidding on the prior to the uisnu of the Notice of Avsardmsill becdeemed ac- Work. Ceprable lo OssN ner and Engineer. 1(1.2. Ini cotruacts- mshere the Contract Price is on the basis 14. Opening of Bids. of IC(-iost-the-Wuork Plus a fee, the apparent Successful Bidde& pirt h oieo sad hl dnisi srt (Cross, out inapplicable ssord) Bids will be opened (publicly) itig to Oss tiwt those portions of tfte \s\ ork liar such Bidder (piatl proposes to subcontract anid al'ter the Notice of Assard may 41NhnBd r pndpbil hys l edaod otul% subcontract other portons of the Work ssith Ossnrers an nasrato h amountsd of the bas Bi' anmjo \sTIiteTI c:Dtt'ett alternates, (if anN ) ssill be made asailablc after the opening of I(1.3~. No ( ontract or shall be: tequitied ito emplo\ any Sub- Did' fia rasi tal'J1T 11 hmh 42 object Bidit a openWd i anel ab'tract of the has Teitloll,'thil! ~ ~ ~ ~ ~ ~ ~ arsam information %s il (not) f b madc'as atlable to Bidder, II. Bid -i rm I I. 1' hic Bid I itl tI i' aria5liled Icieto-. addiltional COPiR-s 15. Bid,, 14) Remain Ope-n. 10 b bititied ton Ltwiiiei All B~id, shall remain OPenI for sods1 dass altert the daN of iht I Dx I uit' itlit be~onilete ittml o by ~pe. Bid openintV, but (Ws ncr miiy . in hts sole. discretion, frelst I 12, 3;JI etal, llk~lhe oniit.ILI.1ill]Il O bi tye- any Bid arid return the Bid Tco iloIOthasae S~tIIC -i lit Bid priket eail C'0tent Oil tfIL It'111 Iitius he stated ptirI'iadte ss \itds :ttuld tiMiiritet1. Ili s,ise Of .iifi~t L01111 % Itd, " ill take 16. Am ard of (ontradi. PI c'x~~~~~~lelict'. ~~~~~~16.1 . Ossner resers.es thic right tio refect tiny and all Bids, 1( I 1 3. lead, by cot it-itott'iii its be sctitci,: in lie cor- msaise ainy and all tn fonrna~lt es attd to ticegottate con! rae porate tiatric h 11 stlipreident (if a t:Ce-prcsidcrtt (of other tertits %%i tt it h Sti,,:essfitl Bidder - and the rih gto 1( isregar( 0111, ale iiiti atiinipaimid bsesdcio authority tlo all nonconfornitni. norinresponsise or conditional Bids. DIN s"gitI atid liet Qoiiporate seall tituis be atttsed atid attested hs ci epaticies cs hemcc ssord, and figures ssill be resolved it 11,ses teliat s oi at) aissrtam itt etetar\ . I lie corporate ad- fas(it of msord,. Dl~icrepancies bctssectu thlie indic~ated sumn o the partner- resuIlsed itt favor (it tlhe corurect sunli. I 3Bd %prnrhpim eceic nteprnr 16.2. itt es aluatting: Bids. Oss ier shall consider the quali hr I~ ~ ~~~~) sf ntu faulte atidinced b% a partttet . 'Ahose, trc irrtl appear caiitios oif the Biddlers. ssh fietit rir nor the Bids comply s miti the prescribed requirements, and alternates and unit prices if 17. Performance and Other Bonds. requested in the Bid forms. It is Owner's intent to accept al- lernates (if anys are accepted) in the order inn which the% arc Paragraph 5.1 of the General Conditions and the Supplemen- listed in the Bid form but Oncer may accept them in any tary Conditions set forth Owner's rcquiremets% as to per- ~order or comn~bination. ~formance and other Bonds. When the Successful Bidder delivers the executed Agreement to Owner it shall be accom- 16.3. Ounet may consider the qualification, and experi- panied by the required Contract Security. encc of Subcontractors and other persons and organizaltions 1. Signing (if Agreement. (incliudiln tlirosc , ho are to furnis`h the principal item of nmaterial or equipment) proposed for tho.se portions of tlie W'hen Ouner gives a Notice of Award to the Successful Bid- WVork az to which the idenliti oi Subcontractors and other der. itl ill be accompanied by at least three unsigned counter- pcrTSon and orlanizartiol nmut he submitted as provided in parts of the Agreement and all other Contract Documents. ithc Supplernltars Conditions. Operating costs, main- Within fifteen days thereafter Contractor shall sign and de- terancc con'iderainor,. performance data and guarantees of liver at least three counterpart, of the Agreement to Owner materials and equipment many also be considered by Ou nter. usith al: olter Contract Documents attached. 'ithin ten days thereafter O()ner will deliver all fulls signed counterparts to 16 4. .) nrer ma? conduct such insetigarions ac he deemns C('otractor. ngineer , ill identify those portions of the Con- necciarx to assist in the esalualion of anr, Bid and to estab- tract Documentl not full\ signed by Owner and Contractor 1Ihl the resCponsibilr . quahlitcadions and financial ability ot and such idcnlification shall be hindinc on all parties. the Bidders. proposed Subcontractors and other persons and organizatiols to do the Work in accordance uith the Con- 19. Special I.egal Requirements. tract Documents to Ouner's satisfaction Aithin the prc- linsert provisions as applicable re (a) slatemelrts required by federal. state or local lan% or regulation or 16.5. c O, ner reserves the right to reject the Bid of any Bid- funding agenc! or appropriate reference thereto: der vho does not pass any such evaluation to Ou ner's satis- (h) Bid pricing requirements on base bid alternatives. cash allou- faction. I ances (see paragraph 11.10 of General Conditions). unit prices and acceptable combinations;: 16.6. If the contract is to be awarded it will be awarded to the losest Bidder whose exaluation by Ossner indicates order to Contractor: to Owner that the assard uill be in the best interests of the Project. (d) Owner's special tax exemption: (e) detailed description of 'ork with cross-reference to General 16.7. If the contract is to be as arded. Ousner will give the Requirements; and Successful Bidder a Notice of Award ithin sixty days after (f division of W'ork into separate parts %%ith cross-reference to Gen- the day of the Bid opening. eral Requirements.l I SECTION 00020 REHABILITATION OF THE PRESCOTT PARK SEAWALL To the City of Portsmouth, herein called the Owner, for the Rehabilitation of the Prescott Park Seawall at Prescott Park, Portsmouth, New Hampshire. The Undersigned, as Bidder, herein referred to as singular and masculine, declares as follows: (1) The only parties interested in the BID as Principals are named herein; (2) this BID is made without collusion with any other person, firm, or corporation; (3) no officer, agent, or employee of the Owner is directly or indirectly interested in this BID; (4) he has carefully examined the site of the proposed work and fully informed and satisfied himself as to the conditions therv existing, the character and requirements of the proposed Work, the difficul- ties attendant upon its execution and the accuracy of all estimated quantities stated in this BID, and he has carefully read and exam- ined the Drawings, the annexed proposed AGREEMENT and the Specifi- cations and other Contract Documents therein referred to and knows and understands the terms and provisions thereof; (5) he understands that information relative to subsurface and other conditions, natural phenomena, existing pipes and other structures (surface and/or subsurface) has been furnished only for his informa= tion and convenience without any warranty or guarantee, expressed or implied, that the subsurface and/or other conditions, natural pheno- mena, existing pipes and other structures (surface and/or subsur- face) actually encountered will be the same as those shown on the Drawings or in any of the other Contract Documents and he agrees that he shall not use or be entitled to use such information made available to him through the Contract Documents or otherwise ob- tained by him in his own examination of the site, as a basis of or ground for any claim against the Owner or Engineer arising from or by reasons of any variance which may exist between the aforesaid information made available to or acquired by him and the subsurface and/or other conditions, natural phenomena, existing pipes and other structures (surface and/or subsurface) actually encountered during the construction work, and he has made due allowance therefore in the BID; (6) he understands that all reports of investigations and tests of subsurface and latent physical conditions at the site and other information affecting the performance of the Work which have been relied upon by the Engineer in preparation of the Drawings and Specifications are not guaranteed as to accuracy or completeness and are not part of the Contract Drawings; (7) and he understands that the quantities of work tabulated in this BID and indicated on the Drawings and in the Specifications and other Contract Documents are only approximate and are subject to increase or decrease as deemed necessary by the Engineer. The undersigned agrees that for extra work, if any, performed in accordance with the terms and provision of the annexed form of AGREEMENT, he will accept compensation as stipulated therein in full payment for such extra work. If this BID is accepted by the Owner, the undersigned agrees to substantially complete the entire work provided to be done under the Contract within 140 calendar days from the date of signing the Contract, except as otherwise expressly provided in the AGREEMENT. As provided in the INSTRUCTIONS TO BIDDERS, the Bidder hereby agrees that he will not withdraw this BID within 60 days of Bid Opening, and that if the Owner shall accept this Bid, the Bidder will duly execute and acknowledge the AGREEMENT CONTRACI BONDS within ten (10) days after notification that the AGREEMENI and other Contract Documents are ready for signature. Should the Bidder fail to fulfill any of his agreements as hereinabove set forth, the Owner shall have the right to retain as liquidated damages the amount of the bid security which shall become the Owner's property. This BID includes Addends number * **To be filled in by Bidder if Addenda are issued. The Bidder, by submittal of this BID, agrees with the Owner that the amount of the bid security deposited with this BID fairly and reasonably represents the amount of damages the Owner will suffer due to the failure of the Bidder to fulfill his agreements as above provided. I ~~~~~~~~~~~SECTION 00022 PROPOSAL Proposal of: Name * ~~~~~~~~Address to furnish and deliver all materials to perform all work in accordance with I ~ ~the Contract Documents for the construction of NOTE: This proposal shall be filled in by the Bidder, with the unit prices I ~ ~~~written in both words and numerals, and the extensions shall be made by the Bidder. I ~~ITEM UNIT PRICES AMOUNT NO. UNIT ITEMS AND UNIT PRICES BID Dollars Cents Dollars Cents 1 1~~ CY Disposal of Unsuitable Material and Supplying of Granular Backfill Material *Not Applicable 2 Lump Sum Rehabilitation of the Prescott Park Seawall * ~~~~~~~TOTAL: The amount of the above Total attributable to Performance and Payment Bonds is. I * ~~Unit price to be used Ascontingency item I I Page 2 Respectfully Submitted: I I Signature Address Title Date I (Seal, if Bid is by a Corporation) I I Attest:I I I 'I I I I -I I I SECTION 00025 I ~~~~~~~~EXPER IENCE STATEMENT 1. General Each Contractor will submit with his proposal a statement of prco- jects constructed within the past two years, possibly of compar- able size and character. Not over five projects need be listed. This information will be utilized by the Owner and Engineer in reviewing the bidders' qualifications and capabilities for per~- forming the work. U ~~2. Sbitl The Contractor will submit as a part of his statement the follow-* ing: 1. Location and dollar volume of the project. 2. Brief description. I ~~~~3. Length' of Contract. 4. Listing of equipment which bidder considers necessary for conducting the Contract, and its availability. I~~~~~~~~~~~~~01 SECTION 00030 NOTICE OF AWARD Dated ,19 TO: iBIDDi. R OWNER'S PROJECT NO. _ PROJECT OWNER'S CONTRACT NO. _ CONTRACT FOR ___ tinerr tmm of orfnfrut a, it ap rrrv, in the Bidding D0-urnenl You are notified that your Bid dated , 198 for the above Contract has been considered. You are the apparent successful bidder and have been awarded a contract for (Indicalc total Work. itenates or sections of Work awarded) The Contract Price of your contract is Dollars ($ Three copies of each of the proposed Contract Documents (except Drawings) accom- pany this Notice of Award. Three sets of the Drawings will be delivered separately or otherwise made available to you immediately. You must comply with the following conditions precedent within fifteen days of the date of this Notice of Award, that is by , 198_. 1. You must deliver to the OWNER three fully executed counterparts of the Agreement including all the Contract Documents. This includes the triplicate sets of Drawings. Each of the Contract Documents must bear your signature on (the cover) (every) page. 2. You must deliver with the executed Agreement the Contract Security (Bonds) as specified in the Instructions to Bidders (paragraph 17), General Conditions (para- graph 5.1) and Supplementary Conditions (paragraph SC-5. 1). 3. (List other conditions precedent). PuhbIshed bh [ingineers' Joint Conrmtet Docutment% Commitlec: ACI ('-AS('I.-NSP1.FPIPP 1910-22 (1980 Edition) N 9Ki. Nalwina.l Stcietty of titLfcnslnal I;ngpinecr Failure to comply with these conditions within the time specified will entitle OWNER to consider your bid abandoned, to annul this Notice of Award and to declare your Bid Security forfeited. Within ten days after you comply with those conditions, OWNER will return to you one fully signed counterpart of the Agreement with the Contract Documents attached. (OWNERI By 4AUITHORIZED SIGNATUREI (TITLE) Copy to ENGINEER (Use Certified Mail, Return Receipt Requested) SECTION 00040 NOTICE TO PROCEED Dated ,19 TO: tCONTRAC'lOR) OWNER'S PROJECT NO. PROJECT - OWNER'S CONTRACT NO. CONTRACT FOR You are notified that the Contract Time under the above contract will commence to run on , 198. By that date, you are to start performing the Work and your other obligations under the Contract Documents. The dates of Substantial Completion and Final Completion are set forth in the Agreement: they are , 198_ and , 198_ , respectively. Before you may start any Work at the site, you and OWNER must each deliver to the other (with copies to ENGINEER) certificates of insurance which each is required to purchase and maintain in accordance with the Contract Documents. Also before you may start any Work at the site, you must -3 t~(add other requirements) Work at the site must be started by , 198_ as indicated in the Contract Documents. (OW N ER) By I'AUTHORIZED SIGNATURF tTITLEI Copy to ENGINEER (Use Certified Mail, Return Receipt Requested) Published by Engincers.' Joint Contracl Documenlt% Committec: ACEC-ASCE.NSPEIPEPP 1910-23 (1980 Edition) (LF 191M. Natmnal Socic�V of Professional Engineer% SECTION 00100 This document has important legal consequences; consultation with an attorney is encouraged with respect to its completion or modification. STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR ON THE BASIS OF A STIPULATED PRICE Jointly lrued by PROFESSIONAL ENGINEERS IN PRIVATE PRACTICE A proctice division of tAe NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS and by AMERICAN CONSULTING ENGINEERS COUNCIL a nd by CONSTRUCTION SPECIFICATIONS INSTITUTE I 1978. NATIONAL SOCIETY OF PlOF�ss1INAL ENGENEXi 2029 K STREET, N.W., WASHINGTON, D.C. 20006 AMERICAN CONSULTING ENGIN.EERS COUNCI.L I 11S 15TH STREET, N.W., WASHINGTON, D.C. 20005 CoNSTmRUTION SPEC1FCATnONS INSTrTVUT 1150 17TH STREET, N.W., WAS1HNGTON, D.C. WASHINGTON. D.C. 20036 This Standard Form of Agreement has been prepared for use with the Standard Form of Instructions to Bidders (NSPE-ACEC Document 1910-12, CSI 56466, 1978 edition) and with the Standard General Condi. tions of the Construction Contract (NSPE-ACEC Document 1910o8, CSI 56465, 1978 edition). Their provisions are interrelated and a change in one may necessitate a change in the others. Comments concerning their usage are contained in the Commentary to the Documents, NSPE.ACEC 1910.9. 1978 edition. NSPE.ACEC 1910.I-A-I CSI 56467 Relmrinteut !1.78 iKM THIS AGREEMENT is dated as df the ..............................day of..............................in the year 19 ........ by and between 3 City of Portsmouth (hereinafter called OWNER) and (hereinafter called CONTRACTOR) OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows: Arlicle 1. WORK. CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follov, s: Rehabilitation of the Prescott Park Seawall The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows: Article 2. ENGINEER. Kimball Chase Company, Inc. The Project has been designed by 40 Bridge Street Portsmouth, NH 03801 who is hereinafter called ENGINEER and who will assume all duties and responsibilities and will have the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents. Article 3, CONTRACT TIME. 3.1. The Work will be substantially completed on of before .............. ; ....................... . 19 ...., and .5 completed and ready for final payment in accordance with paragraph 14.13 of the General Conditions on or before .1. . Wc... * an. S= 3. 1. The Work will be substantially completed within.days after the date when the Contract Time commen... to run as provided in paragraph 2.3 of the General Conditions, and completed and ready for final payment in accordance with a paragraph 14.13 of the General Conditions within .......... days after the date when the Contract Time commences to run 3.2. Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not substantially complete within the time specified in paragraph 3.1 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expense and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by OWNER if the Work is not substantially complete on time. Accordingly, instead of requiring any such proof, OWNER and CONTR.AC- TOR agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER C.l.ly ...o f.P.o..mo.. ................. dollars (S .................. ) for each day that expires after the time specified in paragraph 3.1 for substantial completion until the Work is substantially complete. Article 4. CONTRACT PRICE. 4.1. OWNER shall pay CONTRACTOR for performance of the Work in accordance with the Contract Documents in current funds as follows: See Section 00022, Proposal (here insert a lump sum, unit prrnc or both, attaching exhibits if necesaryl fCONTRACTOR's Bid may be attached as exhibit to avoid klngthy retyping of unit price schedules, formulae for escalation of prices, information as to alternatives, etc.) I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Article S. PAYMENT PROCEDURES. Contractor shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by ENGINEER as provided in the General Conditions. Pate I of .......... pages 5.1. ProRress Payments. OWNER shall make progress payments on account of the Contract Price on the basis of CON- TRACTOR's Applications for Payment as recommended by ENGINEER, on or about the ................... day of each month during construction as provided below. All progress payments will be on the basis of the progress of the Work measured by the schedule of values provided for in paragraph 14.1 of the General Conditions. 5.1.1. Prior to Substantial Completion progress payments will be in an amount equal to: .............. q of the Work completed, and I... .......... % of materials and equipment not incorporated in the Work but delivered and suitably stored, less in each case the aggregate of payments previously made. 5.1.2. Upon Substantial Completion,.OWNER shall pay an amount sufficient to increase total payments to CON- TRACTOR to ............. of the Contract Price, less such amounts as ENGINEER shall determine in accordance with paragraph 14.7 of the General Conditions. 5.2. Finaol Payment. Upon final completion and acceptance of the Work in accordance with paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the Contract Price as 'recommended by ENGINEER as provided in said paragraph 14.13. Article 6. INTEREST. All moneys not paid when due hereunder shall bear interest at the maximum rate allowed by law at the place of the Project. Article 7. CONTRACTOR'S REPRESENTATIONS. In order to induce OWNER to enter into this Agreement CONTRACTOR makes the following representations: 7. 1. CONTRACTOR has familiarized himself with the nature and extent of the Contract Documents, Work, locality, and with all local conditions and federal, state and local laws, ordinances, rules and regulations that in any manner may affect cost. progress or performance of the Work. 7.2. CONTRACTOR has studied carefully all reports of investigations and tests of subsurface and latent physical condi- tions at the site or otherwise affecting cost, progress or performance of the Work which were relied upon by ENGINEER in the preparation of the Drawings and Specifications and which have been identified in the Supplementary Conditions. 7.3. CONTRACTOR has made or caused to be made examinations, investigations and tests and studies of such reports and related data in addition to those referred to in paragraph 7.2 as he deems necessary for the performance of the Work at the Contract Price. within the Contract Time and in accordance with the other terms and conditions of the Contract Documents; and no additional examinations, investigations, tests, reports or similar data are or will be required by CONTRACTOR for such purposes. 7.4. CONTRACTOR has correlated the results of all such observations, examinations, investigations, tests, reports and data with the terms and conditions of the Contract Documents. 7.5. CONTRACTOR has given ENGINEER written notice of all conflicts, errors or discrepancies that he has discovered In the Contract Documents and the written resolution thereof by ENGINEER is acceptable to CONTRACTOR. 76 Article 8. CONTRACT DOCUMENTS. The Contract Documents which comprise the entire agreement between OWNER and CONTRACTOR are attached to this Agreement. made a part hereof and consists of the following: 8. 1. This Agreement (pages I to ...., inclusive). 8.2. Exhibits to this Agreement (pages ..., to ...., inclusive). 8.3. Performance and other Bonds, identified as exhibits ..................... and consisting of ... pages. 8.4. Notice of Award. 8.5. General Conditions (pages .... to ..... inclusive). 8.6. Supplementary Conditions (pages .... to ...., inclusive). Page 2 of .......... pages 8.7. Specifications bearing the title and consisting of .... divisions and .... pages, as listed in table of contents thereof. 8.8. Drawings, consisting of a cover sheet and sheets numbered .. through 2,.. inclusive with each sheet bearing the following general title: Prescott Park Seawall Rehabilitation 8.9. Addenda numbers .... to ...., inclusive. 8. 10. CONTRACTOR's Bid (pages .. to ....inclusive) marked exhibit ..... (Attach Bid Form only in special circum- stances). 8.11. Documentation submitted by CONTRACTOR prior to Notice of Award (pages .... to . inclusive). 8.12. Any Modification, including Change Orders, duly delivered after execution of Agreement. 8 .13. There are no Contract Documents other than those listed above in this Article 8. The Contract Documents may only be altered, amended or repealed by a Modification (as defined in Section I of the General Conditions). Article 9. MISCELLANEOUS. 9.1. Terms used in this Agreement whiqh are defined in Article I of the General Conditions shall have the meanings indicated in the General Conditions. 9.2. No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documenis. 9.3. OWNER and CONTRACTOR each binds himself, his partners, successors, assigns and legal representatives to the other party hereto, his partners, successors, assigns and legal representatives in respect to all covenants, agreements and obligations contained in the Contract Documents. Article 10. OTHER PROVISIONS. IN WITNESS WHEREOF, the parties hereto have signed this Agreement in triplicate. One counterpart each has been delivered to OWNER, CONTRACTOR and ENGINEER. All portions of the Contract Documents have been signed or identified by OWNER and CONTRACTOR or by ENGINEER on their behalf. This Agreement will be effective on ............................................ 19 . OWNER .... ................................ CONTRACTOR .............................. . By .. . ....... By ......................... [CORPORATE SEAL} ICORPORATE SEAL] Attest . ............ .... .................... Attest.......... Address for giving notices Address for giving notices (If OwNER is a purl-. boyv attach evidence of License No ....... ............. authority to sign and resolution or other document authorizing execution of Agreement.) Agent for service of process: ...... Page 3 of .......... pages Failure to comply with these conditions within the time specified will entitle OWNER to consider your bid abandoned, to annul this Notice of Award and to declare your Bid Security forfeited. Within ten days after you comply with those conditions, OWNER will return to you one fully signed counterpart of the Agreeme nt with the Contract Documents attached. (OWN ERI By B (AUTHORIZED SIGNATURE) (TITLEi Copy to ENGINEER (Use Certified Mail, Return Receipt Requested) SECTION 00110 PERFORMANCE BOND I ~~~~~~~~~~~~~~~~Bond Number KNOW ALL MEN BY THESE PRESENTS: That 3 ~~as Principal, hereinafter called Contractor, and (Surety Company) a corporation organized and existing under the laws of the State of as surety, hereinafter called Surety, are held and firmly bound unto the 7Ziff/City of Portsmouth, New Hampshire I ~~Obligee, hereinafter called Owner, in the amount of 3 ~~Dollars ($ ), for the payment whereo-f Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. I ~~WHEREAS, Contractor has by written agreement dated entered into a contract with Owner for Rehabilitation of Prescott Park Seawall U ~~in accordance with drawings and specifications prepared by Kimbell Chase 3 ~~Company, Inc., 40 Bridge Street, Portsmouth, New Hampshire 03801, which contract is by reference made a part hereof, and is hereinafter referred to as 3 ~~the Contract. I ~~NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if the * ~~Contractor shall well and faithfully do and perform the things agreed by him to be done and performed, according to the terms of said Contract and such 3 ~~alterations as may be made in said Contract during progress of the wo-rk, and shall further indemnify and save harmless the said Owner from any expense I ~~incurred through the failure of said Contractor to complete the work specified and for any damages growing out of the manner of performance of said Contract or any subcontractors or his or their agents, and shall remedy without cost to the Owner any defect which may develop within one year from the time of3 completion and acceptance of the work; provided said d-efects, in the judgement of the Owner or its assigns, are caused by defective or inferior materials3 and/or workmanship then this obligation to be void, otherwise to remain in full force and effect. The Surety hereby waives notice of any lateration in work or extension of time made by the Owner of Engineer. Whenever Contractor shall be, and declared by Owner to be, in default under3 the Contract, the Owner having performed Owner's obligations thereunder, the Surety may promptly remedy the default, or shall promptly:I (1) Complete the Contract in accordance with its terms and conditions, orI (2) Obtain a bid or bids for submission to the Owner for completing the Contract in accordance with its terms and conditions, and upon determination by Owner and Surety of the lowest responsible bidder, arrange for a contract between such bidder and Owner and make avail- able as work progresses (even though there should be a default or a succession of defaults under the contract of completion arranged I under this paragraph) sufficient funds to pay the cost of completion less the balance of the contract price; but not exceeding, including other costs and damages for which the Surety may be liable hereun- der, the amount set forth in the first paragraph hereof. The term "balance of the contract price", as used in this paragraph, shall mean the total amount payable by' the Owner to Contractor under the Contract and any amendments thereto, less the amount paid by Owner I to Contractor. Any suit under this bond must be instituted before the expiration of two (2) years from the date on which final payment under the contract falls due.I 00110-3 No right of action shall accrue on this bond to or for the use of any person or corporation other than the Owner named herein or the heirs, executors, I ~~administrators or successors of Owner. Signed and sealed this ___day of A.D., 19 in the presence of: By, I ~~~~(witness) (Principal) (seal) (Surety Company) By, (Witness)(4 I ~~~~~~~~~~SECTION 00120 LABOR AND MATERIAL PAYMENT BOND Bond Number____ KNOW BY ALL THESE MEN PRESENTS: That as Principal, hereinafter called Principal, and (surety Company) a corporation organized and existing under the laws of the I ~~State of hereinafter called Surety, are held firmly bound unto the CityIXTN'X of Portsmouth, New Hampshire as Obligee, herinaf ter called Owner, for the use and benefit of claimants as hereinbelow defined, in the amount of Dollars ($ ), for payment whereof Principal and Surety bind themselves, their heirs, executors, administrators, I ~~successors and assigns, jointly and severally, firmly by these presents. U ~~WHEREAS, Principal has by written agreement dated entered into a contract with Owner for Rehabilitation of Prescott Park Seawall in accordance with drawings and specifications prepared by Kimball Chase Company, Inc., 40 Bridge Street, Portsmouth, New Hampshire, which co'ntract is by reference made a part hereof, and is hereinafter referred to as the Contract. I ~~NOW,THEREFORE, THE CONDITION OF THIS OBLIGATION is such that the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of I ~ ~the Contract and for the hire of all equipment, tools, and all other things contracted for or used in connection therewith, then this obligation shall be void; otherwise it shall remain in full force and effect, subject however, to the following conditions: (1) A claimant is defined as one having a direct contract with the Principal or, with a subcontractor of the Principal for labor, material, equipment, or other things used or reasonably required for use in the performance of the contract. Labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment applicable to the Contract. 00 120-21 (2) The above named Principal and Surety hereby jointly and severally agree with the Owner that every claimant as herein defined, who has not been paid in full before expiration of a period of ninety (90) days after the date on which the last of such claimant's work or labor was done or performed, or materials were furnished by such a claimant, may sue on this bond for the use of such claimant, prosecute the suit by final judgement for such sum or sums as may be justly due claimant, and 'haveI execution thereon. The Owner shall not be liable for the payment of any costs or expenses of any such suit. (3) No suit or action shall be commenced hereunder by any claimant: (a) Unless Claimant, other than one having a direct contract with the Principal, shall have given notice to all the following:I The Principal, the Owner and the Surety above named, within six calendar months after such claimant did or performed the last of theI work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished, or for whom the work or labor was done or performed. Such notice shallI be served by mailing the same by registered mail or certified mail, postage prepaid, in an envelope addressed to the Principal, Owner,' and Surety, at any place where an office is regularly maintained forI the transaction of business, or served in any manner in which legal process may be served in the State of save that such service need not be made by a public officer. (b) After the expiration of one (1) year following the date on which Principal ceased all work on said contract, it being understood, however, that if any limitation embodied in this bond is prohibitedI by any law controlling the construction hereof,. such limitation shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law. (c) Other than in a State court of competent jurisdiction in and for the county or other political subdivision of the State in which the project, or any part thereof, is situated, or in the United StatesI District Court for the district in which the project, or any part thereof, is situated, and not elsewhere. (4) The amount of this bond may be reduced by and to the extent of anyI payment of payments made in good faith hereunder, inclusive of the pay- ment by Surety of mechanics' liens which may be filed on record against said improvement, whether or not claim for the amount of such lien beI presented under and against this bond. I I 00120-3 Signed and Sealed this day of A.Dov 19 In the presence of: I By: (Witness) (Principal) I (Witness) I (Seal) I I I I I I I I I I I Section 00200 CONTRACTOR' S AFFIDAVIT STATE OF I ~~COUNTY OF Before me, the undersigned, a I ~ ~~~~~~~~~~~(Notary Public, Justice of the Peace) in for said County and State personally appeared (Individual, Partner, or who being duly sworn I ~~Duly Authorized Representative of Corporate Contractor) according to law disposes and says that the cost of all the Work and outstanding claims and indebtedness of whatever nature arising out of the performance of the Contract between I ~~and of (contractor) dated for and necessary appurtenant installations have been paid in ful I (Individual, Partner, or Duly Authorized Representative of Corporate Contractor) Sworn to and subscribed before me this day of * ~~19. Section 00210 CONTRACTOR'S RELEASE KNOW BY ALL THESE MEN PRESENTS THAT of , County of and State of do hereby acknowledge that has this day had, and received of and from the sum of One Dollar and other valuable considerations in full and complete satisfaction and payment of all sums of money owed, payable and belonging to_____ I ~ ~~~~~~~~~~~~~(Contractor) by any means whatsoever, for on account of a Contract Agreement between and dated for NOW,THEREFORE, the said (Contractor) (for myself, my heirs, executors and administrators)(for itself, its succes- sors and assigns) do/does by these presents remise, release, quit-claim and forever discharge ,its successors and assigns of and from all claims and demands, arising from or in connection with the said Contract dated , and of and from all, and all manner of action and actions, cause and causes of action and actions, suits, debts, dues, duties, sum and sums of money, accounts, reckonings, bonds, bills, specialties, covenants, contracts, agreements. promises, variances, damages, judgements, extents, executions, claims and demand, whatsoever in law or equity, or otherwise, against , its successors and assigns, which (I, my heirs, execu:ors. or acmznisrrators)"it successors and assigns) hereafter can, shall or may have, for, upon or by reason of any matter, cause, or thing whatsoever; from the beginning of recorded time to the date of these presents. 00210-2 IN WITNESS WHEREOF, (Contractor) has caused these presents to be duly executed this day of 19 . Signed,sealed and delivered in the presence of: (Seal) (Individual - Contractor) (Seal) (Partnership-Contractor) By: (Seal) (Partner) _~~~~~~~~~~~~~~~~--------- Attested: (Corporation) By: (Secretary (President or Vice President) (Corporate Seal) SECTION 00300 No ..... CHANGE ORDER Dated ............... OWNER's Project No ....................... ENGINEER's Project No ........................ Project .......................................... CONTRACTOR ........................................................................ Contract For ............................... Contract Date .............................. To ..... You aredireted to make the chanps motedbelow i thie sutject Contract: OWNER By .............. ................. Dated ........................19 Nature of the Changes Enclosures The changes result in the following adjiustnen of Corniac: P.nc and Conwtra. Tmune Contract Price Prior to This Change Order S Net I Increase)(Decrease) Resulting from this Change Order S Current Contract Price Including This Change Order S NSPL.ACEC 1910.8.- B(1978 Edition) tr 1'7h %atlonal S()m�1y of Pwlesr,�rnal Engtenes O-,25 0-2 5 Contract Time Prior to This Change Order ....................................................... (Days or Date) Net (Increase) (Decreae) Resulting from This Change Order ........................................... (Days) Current Contract Time Including This Change Order ........................................... (Days or Date) The Above Changes Are Approved: .. . . ............................,...... ENGINEER By ,.o. ,. .....,,o ,o .......................... Date .............................19 ..... The Above Changes Are Accepted: .................................o...... CONTRACTOR By o~o...,. m...,.,o...oooe............... Date ............................ .19 0-26 SECTION 00400 CERTIFICATE OF SUBSTANTIAL COMPLETION OWNER's Project No .................... ENGINEER's Project No...... . . . Project .....- .... .... .... ..................... CONTRACTOR .................................................................... Contract For ....................... Contract Date ........................ This Certificate of Substantial Completion applies to all Work under the Contract Documents or to the followaing specified parts thereof: To .. ..... ................... .......... . ........ .............. ...... . . . OWNER AndTo . . ....................................................... CONT R ACTOR The Work to which this Certificate applies has been inspected by authorized representatives of OWNER, CONTRACTOR and ENGINEER, and that Work is hereby declared to be substantially complete in accordance with the Contract Documents on . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Date of Substantial Completion A tentative lis of items to be completed or corrected is attached hereto. This lit may not be all-inclusive. and the failure to include an item in it does not alter the responsibility of CONTRACTOR to complete all the Work in accordance with the Contract Documents. When this Certifcate applies to a specified par.t of the Work the items in the tentative hst sall be completed or corrected by CONTRACTOR within days of the above date of Subsmatal Completion NSPE-ACEC 1910-8.D(1978 Edition) C 1976 National Soctly of Profeional En�tneeis 0-27 The date of Substantial Completion is the date upon which all guarantees and warranties begin, except as follows - The responsibilities between OWNER and CONTRACTOR for security, operation. safety, maintenance, heat, utilities and insurance shall be as follows RESPONSIBILITIES OWNER CONTRACTOR: The following documents are attached to and made a part of this Certificate: Executed by ENGINEER on ....19 ENGINEER By ..... .... The CONTRACTOR accepts this Certificate of Substantia! Completion on. 19 ~~~~~~~~~. . . . . . . . . . . . . . . . . .... ... CONTRACTOP By 0-28 I ~~~~This document has important legal consequences: consultation with an attorney is encouraged with respect to its completion or modification. STANDARD I ~~~~GENERAL CONDITIONS 3 ~~~~~OF THE CONSTRUCTION CONTRACT U ~~~~~~~~~~~Prepared by 3 ~~~Engineers' Joint Contract Documents Committee and I ~~~~~~~~~Issued and Published Jointly By AEICA yp~ F A O CIVIL ~~~~~~~~~~~~~AIN PROFESSIONAL ENGINEERS IN PRIVATE PRACTICE A practice division of the 1 ~~~~~NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS 3 ~~~~~~AMERICAN CONSULTING ENGINEERS COUNCIL * ~~~~~~~AMERICAN SOCIETY OF CIVIL ENGINEERS CONSTRUCTION SPECIFICATIONS INSTITUTE This document has been approved and endorsed by The Associated G nrlContractors of America These General Conditions have been prepared for use with the Owner-Contractor Agreements (No. 1910-8-A-I or 1910-8-A-2, 1983 editions). Their provisions are interrelated and a change in one may I ~ ~~~necessitate a change in the others. Comments concerning their usage are contained in the Commentary on Agreements for Engineering Services and Contract Documents, No. 1910-9, 1981 edition. For guidance in the preparation of Supplementary Conditions, see Guide to the Preparation of Supple- mentary Conditions (No. 1910-17, 1983 edition). When bidding is involved, the Standard Form of Instructions to Bidders (No. 1910-12, 1983 edition) may be used. 3 ~~~~No. 1910-8 (1983 Edition) TABLE OF CONTENTS OF GENERAL CONDITIONS Arti~ h' Nwitwr Tiilc pa,t, I DEFINI''I(ONS ...................................................... 7 2 PRELIMINARY MATTERS ........................................ 8 3 CONTRACT DOCUMENTS: INTENT. AMENDING AND REUSE ...............................9 4 AVAILABILITY OF LANDS: PHYSICAL CONDITIONS: REFERENCE POINTS ..........................................10 5 BONDS AND INSURANCE .......................................11 6 CONTRACTOR'S RESPONSIBILITIES ...........................14 7 OTHER WORK ....................................................18 8 OWNER'S RESPONSIBILITIES .................................... 9 ENGINEER'S STATUS DURING CONSTRUCTION .......... 10 CHANGES IN T'HE WORK ......................................... 1 11 CHANGE OF CONTRACT PRICE ..................................21 12 CHANGE OF CONTRACT TIME ...................................2 13 W'ARRANTY AND GUARANTEE: TESTS AND INSPECTIONS: CORRECTION. REMO()VAL OR A('CEPTANCE OF DEFECTIVE WORK ....................2 14 PAYMIENTS T() CONTRACTOR AND COMPLETION .......... lS SUSPENSION OF WORK AND TERMINATION ................. 16 AARBIT'RATIO(N ...................................................3 17 MISCELLANE()OUS ................................................. . 1 ~~~~~~~~~~~~~~~~~~~~~~~~~~~3 INDEX TO GENERAL CONDITIONS Arlicl or Paragraph Numnber Acceptdnce of Insurance................5.13 Contractor's Warranty of Title .............14.3 Acce~ss to the Work ..................13-2 Contractors-othcr.................... 7 Addendau-derinicion ouhsee dehnition of ' Contractual Liability Insurance............. I. Specific:ations).....................I Coordinating Contractor-definition of ..........7.4 Agrcerment-definition of ..............I Coordination ......................7. 4 All Risk insurance .....................6 Copies of Documents...................2.2 Amnerndment. Wrilcicn.1.........3.1.1 Correction or Removal ol'Delectiis Work.......13.1 II Application lor Payniient-detinition of ...........I Correction Period. One Year ............ 13.12 Application lfo Payment. nindl............14.12 Correction. Removal or Acceptance of 1)etecto-c Application loi P1,ogress Pa% entci...........14.2 Work-in general.............. 13. I1-13. 14 AppliL~ation for Progress Pa1~ nent-reN ew of'.. 14.4-14.7 Cost-net decrease........ ..........I Lt).2 Arbitraton ... .... .... ......I...16 Cost ol'Work .......... .......11.4-1 I.5 Authoruied \'arwhton in Work .............9.5 Costs, Supplemental .................11.4.5 As ailability of Lands..................4.1I AwAard. Notice of'-defined ................I Day-definition of..................... I Bef'ore: Starting Construction ............2.5-2.7 Dejrczive Work, Acceptance of .1............I' 13 Bid--aefulmton Of ... ................I Deji'ciive Work, Correction or Removal of .......13.11I Bonds and Insurance-iti general .............S Dejrctive Work-in general.........13. 14.7. 14.11 Bonds-defintion of....................I Dcefrctive Work. Rejecting ..9..............6~ Bonds. DeliserB of . ...............2.1I. 5.1 Definitions ........................ Bonds. Perf'ormance and Other ...........5.1-5.2 Delivery of Bonds ....................2.1 I Determination for Unit Prices .............9.1U Cash Allowances .. ................. 1.8 Disputes, Decisions by Engineer .9.1-......... Change Order-.derinition of. ...............I Documents, Copies of..................2.2 Change Orders-to he executed.............10.4 Documents. Record ..................6.19 Changes in the Work ...................0I Documents, Reuse ...................3.6 Claims. Wai,.er of'-on Final Pay ment ........14.16 Drawings-d~etinition of ..................I Clarifications and Interpretations.............9.4I Cleaning........................6.17 Easements .......................4.1 Completion........................14 Effective date of Agreernent-detinition of ......... Completion. Substantial..............14.8-14.9 Emergencies......................6.22 Conference. Preconstruction1..............2.8 Engineer-definition ot ..................I Conflict, Error. Discrepank;~-Coniraclor Engineer's Decisions ...............9.10-9.12 to Report ....................2.5. 3.3 Engineer's-Notice Work is Acceptable........14.13 Construction N1achinvr~. I-quipment, etc ........6.4 Engineer's Recommendation of Payment ....14.4. 14.1 I' C ontinuinrg Work ...................6.29 Engineer's Responsibilities. Limitations C06ntraC:loinut-aidin and on ................... 6. II. . 16-.l -supplemnieitng -................3.4-3.5 ELngineer's Status IDui Mg Consti UL1t0on-in gener'al .L Contract Docunicnts-dcfinifioin tit.............I Eq~uipment. Labor. Materials and ~....... U CtjntraILI DoLuments-Intentt............3.1-3,3 Equivalent Materials, aiid Lquipmejut........67 Contraict Documnents-Reusec of ...........3.6 Explorations of physical conditions...................4.2 Contract Price. Change of.................I I Contract Price-delinition ................I Fee. Cuntractor's-Cosis Plus. .............I I.( Contract Tfime. Change of .................12 Field Order-definition of .................I Contrac~t lime. Conmmcnceucnt of ............2.3 Field Order-issued by Enginceer. ........ .. I 9. Contract Tuime-definition of1...............I Final Application for Payment ...... .... ..14.12 I Cuntractor-definition of. ................I Final Inspection....................14.11 Contractor may Stop Woik or lerouinate ..1.....I5.5 Final Payment and Acceptance ............14.13 Contractor'h Continuing Obligation ..........14.15 Final Payment. Recommendation ofl.......14.1l3-14.14 Countractor's, Duty it) Report DiscrepartcyI in Documcnts .................2.5. 3.2 General Provisions ................17.3-17.4 Contractor's Fec-Cost Plus I II .4.5.6, 11.5.1, 11.6-11.7 General Requirements-definition of ......... .. Contractoris Liability InsuranLc............. .3 General Requiretnient s-principalI Contrac:tor'N Responsibilities-in general .........6 references to..........2.6. 4.4. 6).4. ti.t-6.7. 6.23 4I Giving Notice ........................................ 17.1 Payments to Contractor-when due ........... 14.4, 14.13 Performance and other Bonds .................... . 5.1-5.2 Indemnification ............................. 6.30-6.32. 7.5 Permits ................ 6.13 Inspection. Final .................................... 14.11 Physical Conditions ...........................4.2 Inspection. Tests and ............................... 13.3 Physical Conditions-Engineer's review ............. 4.2.4 Insurance. Bonds and-in general ....................... 5 Physical Conditions-existing structures . ........... 4.2.2 Insurance. Certificates of ........................... 2.7, 5 Physical Conditions-explorations and reports ....... 4.2.1 Insurance-completed operations ...................... 5.3 Physical Conditions-possible document change ..... 4.2.5 Insurance, Contractor's Liability ...................... 5.3 Physical Conditions-price and time adjustments .... 4.2.5 Insurance. Contractual Liability ....................... 5.4 Physical Conditions-report of differing ............. 4.2.3 Insurance, Owner's Liability ....................... 5.5 Physical Conditions-Underground Facilities .......... 4.3 Insurance, Property ............................. 5.6-5.13 Preconstruction Conference ........................... 2.8 Insurance-Waiver of Rights ......................... 5.1I 1 Preliminary Matters .................................... 2 Intent of Contract Documents ................... 3.3. 9.14 Premises, Use of . ........................ 6.16-6.18 Interpretations and Clarifications ...................... 9.4 Price, Change of Contract . ............................. 11 Investigations of physical conditions ................... 4.2 Price-Contract-definition of ........................... I Progress Payment, Applications for ................... 14.2 Labor. Materials and Equipment .................. 6.3-6.5 Progress Payment--retainage . ........................ 14.2 Laws and Regulations-definition of ..................... 1 Progress schedule ............... 2.6, 2.9. 6.6, 6.29, 15.2.6 Laws and Regulations-general ....................... 6.14 Project-definition of ................................... 1 Liability Insurance-Contractor's ..................... 5.3 Project Representation-provision for ................. 9.3 Liability Insurance-Owner's ......................... 5.5 Project Representative, Resident-definition of .......... 1 Liens-definitions of ................................ 14.2 Project, Starting the ................................... 2.4 Limitations on Engineer's Property Insurance .............................. 5.6-5.13 Responsibilities ..................... 6.6, 9.11, 9.13-9.16 Property Insurance-Partial Utilization ............... 5.15 Property Insurance-Receipt and Application Materials and equipment-furnished by Contractor .... 6.3 of Proceeds ......... .................. 5.12-5.13 Materials and equipment-not Protection, Safety and ................,.... 6.20-6.21 incorporated in Work ......... ................ 14.2 Punch list ....................... . 1411 Materials or equipment-equivalent ................... 6.7 Miscellaneous Provisions ............................... 17 Recommendation of Payment .................. 14.4. 14.13 Multi-prime contracts ................................... 7 Record Documents ................................... 6.19 Reference Points ...................................... 4.4 Notice. Giving of ..................................... 17.1 Regulations, Laws and ........................ 6.14 Notice of Acceptability of Project ................... 14.13 Rejecting Defective Work ............................. 9.6 Notice of Award-definition of .......................... I Related Work at Site .............................. 7.1-7.3 Notice to Proceed-definition of ......................... I Remedies Not Exclusive ............................. 17.4 Notice to Proceed-giving of .......................... 2.3 Removal or Correction of Defective Work . .......... 13.11 Resident Project Representative-definition of ........... 1 "O r-Equal" Items ..................................... 6.7 Resident Project Representative-provision for ........ 9.3 Other contractors ..................... 7 Responsibilities, Contractor's-in general ...............6 Other work ............................................. 7 Responsibilities. Engineer's-in general ................. 9 Overtime Work-prohibition of ........................ 6.3 Responsibilities, Owner's-in general ...................8. Owner-definition of .................................... I Retainage ............................................ 14.2 Owner May Correct Defective Work ................. 13.14 Reuse of Documents ......... .................. 3.5 Owner May Stop Work ......... ........... 13.10 Rights of Way ...................1..................... 4.1 Owner May Suspend Work. Terminate .......... 15.1-15.4 Royalties, Patent Fees and .........6........ 6.12 Owner's Duty to Execute Change Orders .. ........... 11.8 Owner's Liability Insurance ............................ 5.5 Safety and Protection ............................ 6.0 1 Owner's Representative-Engineer to serve as ........ 9.1 Samples ............................. 6.23-6.28 Owner's Responsibilities-in general .................... 8 Schedule of progress ........ 2.6. 2.8-2.9. 6.6. 6.29. 15.2.6 Owner's Separate Representative at site ............... 9.3 Schedule of Shop Drawing submissions ...................... 2.6. 2.8-2.9. 6.23. 14.1 Partial Utilization ............................ ...... 14.10 Schedule of values ...................... 2.6. 2.8-2.9, 14.1 Partial Utilization--definition of ......................... I Schedules, Finalizing .................................. 2.9 Partial Utilization-Property Insurance ............... 5.15 Shop Drawings and Samples ..................... 6.23-6.28 Patent Fees and Royalties ............................ 6.12 Shop Drawings-definition of ............................ 1 Payments, Recommendation of ........... 14.4-14.7, 14.13 Shop Drawings, use to approve Payments to Contractor-in general .................... 14 substitutions ....... ...............................3 I 5 Site, Visits to-by Engineer ........................... 9.2 Time, Computation of ................................ 17.2 Specifications-definition of ............................. I Time, Contract-definition of ............................ I Starting Construction. Before ...................... 2.5-2.8 Starting the Project .................................... 2.4 Uncovering Work ............................... 13.8-13.9 Stopping Work-by Contractor ....................... 15.5 Underground Facilities-definition of .................... I Stopping Work-by Owner .......................... 13.10 Underground Facilities-not shown or indicated ..... 4.3.2 Subcontractor-definition of ............................. I Underground Facilities-protection of ........... 4.3. 6.20 Subcontractors-in general ....................... 6.8-6.11 Underground Facilities-shown or indicated ......... 4.3.1 Subcontracts-required provisions ............5.11.1. 6.11 Unit Price Work-definition of .......................... I 11.4.3 Unit Price Work-general ................. 11.9. 14.1. 14.5 Substantial Completion-certification of .............. 14.8 Unit Prices ......................................... 11.3.1 Substantial Completion-definition of .................... I Unit Prices. Determinations for ....................... 9.10 Substitute or "Or-Equal" Items ....................... 6.7 Use of Premises ................................. 6.16-6.18 Subsurface Conditions ............................. 4.2-4.3 Utility owners .......................... 6.13. 6.20. 7.2-7.3 Supplemental costs ................................. 11.4.5 Supplementary Conditions-definition of ................ I Values, Schedule of ......................... 2.6. 2.9, 14.1 Supplementary Conditions-principal Variations in Work-Authorized ............ 6.25. 6.27. 9.5 references to .. 2.2, 4.2, 5.1. 5.3. 5.6-5.8. 6.3. 6.13. 6.23, Visits to Site-by Engineer ............................ 7.4, 9.3 Supplementing Contract Documents ............... 3.4-3.5 Supplier-definition of.... I ~Waiver of Claims-on Final Payment .........14.16 Supplier-definition of ................................... I Wie fRgt yisrdpris.......51.61 Waiver of Rights by insured parties . 5.10. 6.I11 Supplier-principal references to ... 3.6.6.5.6.7-6.9.6.20, Warranty and Guarantee-by Contractor ............ 6.24,.9.13.9.16,.11.8. 13.4.14.12 Warranty of Title, Contractor's ....................... 14.3 Surety-consent to payment .................. 14.12, 14.14 Surey-Eginer hs nodut to ................ .13Work-b othersso .........................................2 Surety-Engineer has no duty to 913..................13.2 Work--by others.7 Surety-notice to .......................... 10.1, 10.5, 15.2 i.....................29 Work Continuing During Disputes ...........6.29 Surety-qualification of ........................... 5.1-5.2 Work,Costof.11.4-11.5 Suspending Work. by Owner ................. ........1 Work-definition of. Suspension of Work and Termination--in general ......15 Suspensiontef Work and Terminat-on-intgeneralos ....... 1 Work Directive Change-definition of ................... I Superintendent--Contractor's ......................... 6.2 Work Directive Change--principal Supervision and Superintendence .................. 6.1-6,2 referece Ch ange-p0ca references to ............................ 3.4.3, 10.1-10.2 Taxes-Payment by Contractor ..... .................. 6.15 Work, Neglected by Contractor ..................... 13.14 Termination-by Contractor ....................... 15 Stopping by Contractor.. Work, Stopping by Owner ....................... 15.1-15.4 Termination-uby Owner ......................... 15.2-15.4 WitnAedetdfnto f........... Written Amendment--definition of ............ Termination. Suspension of Work and-in general ......15 Written Amendment-principal Tests and Inspections ..........................3-13.7 3.4.1. 10.1. 11.2, 12.I Time, Change of Contract ..............................12 6~~~~~~~ GENERAL CONDITIONS tClff-cctivc--An adjective which when modifying the word Work refers to Work that is unsatisfactory, faulty or deficient, or AKRIC'LE 1I-DEFINITIlONS - does not conform to the Contract Documents. or does not meet the requirements of any inspection, reference standard, test or approval referred to in the Contract Documents, or Wherever used in these General Conditions or in the other has been damaged prior to ENGINEER's recommendation ontract Documents the follow in g terms have the meaningsdamaged prior to ENGNEER's recommendation Induedat ic ar apliah l bththe singulu- and plural has been assumed by OWNER at Substantial Completion in accordance with paragraph 14.8 or 14. 10). I.Al J-eW-rit tIen or graph ic iinstru ments issued prior to the I)Drawings-The drawings which show the character and scope opcning of BidMs hich clarif%. corrcclt or changeof the bidding of the Work to be performed and which have been prepared dIo, uiimnts or the Contract 6hcuimlents. or approved by ENGINFER and are referred to in the Con- tract Documents. .4 c,ccn cnt-li-The v, ritten agreement between OWNER and CON()TRAC'TOR( covering the W.ork to he performed: other Efi'ctriiv Date of the Agreement-The date indicated in the C(ontr act Documents ar arttached to the Agreement and made Agreement on wvhich it becomes effective. but if no such date a p:irt thcreof as provided therein. is indicated it means the date on which the Agreement is signed and delis ered by the last of the ti o parties to sign and .4?phcart,,n . /bfi PauNment-The form accepted by ENGI- deliver. NEER w hich is to be used b} CONT'RACTOR in requesting progress or final pay!ments and which is to include such sup- ENGINEER-The person. firm or corporation named as such porting documentation as is required by the Contract in the Agreement. Documents. Field Order-A written order issued by ENGINEER which Bid-The offer or proposal of the bidder submitted on the orders minor changes in the Work in accordance with para- prescribed form setting forth the prices for the Work to be graph 9.5 but which does not involve a change in the Contract performed. Price or the Contract Time. Bands-Bid. performance and payment bonds and other General Requirements-Sections of Division I of the Speci- instruments of security. fications. Change Order-A document recommended by ENGINEER. Laws and Regulations: Laws or Regulations-Laws, rules, which is signed by CONTRACTOR and OWNER and autho- regulations, ordinances, codes and/or orders. rizes an addition. deletion or revision in the Work, or an adjustment in the Contract Price or the Contract Time, issued Notice of Awmard-The written notice by OWNER to the on or after the Effective Date of the Agreement. apparent successful bidder stating that upon compliance by the apparent successful bidder with the conditions precedent Contract )Dcilnents-The Agreement, Addenda (vwhich per- enumerated therein. within the time specified. OWNER will tain to the Contract Documents), CONTRACTOR's Bid sign and deliver the Agreement. (including documentation accompanying the Bid and any' post- Notice to Proceed--A written notice given by OWVNER to Bid documentation submitted prior to the Notice of Award) CNTRACTOR (with a copy to ENGINEERfixingtheda Iwhen attached as an exhibit to the Agreement. the Bonds, on which the Contract Time will commence to run and on these General Conditions, the Supplementary Conditions, the which CON TRACTOR shal l start to pe rform CONTRAC- Specifications and the Drawings as the same are more spe- TOR'S obligations under the Contract Documents. cifically identified in the Agreement, together with all amend- ments, modifications and supplements issued pursuant to OWNER-The public body or authority. corporation. asso- paragraphs 3.4 and 3.5 on or after the Effective Date of the ciation. firm or person withwhom CONTRACTOR has entered I Agreement. into the Agreement and for whom the Work is to be provided. Contract Pricce-The moneys payable by OWNER to CON- Partial Utili.zation-Placing a portion of the Work in service TRACTOR under the Contract Documents as stated in the for the purpose for which it is intended (or a related purpose) Agreement (subject to the provisions of paragraph 11.9.1 in before reaching Substantial Completion for all the Work. the case of Unit Price WorkJ. Project--The total construction of which the Work to be Contract Tinme-The number of days (computed as provided provided under the Contract Documents may be the whole, in paragraph 17.2) or the date stated in the Agreement for the or a part as indicated elsewhere in the Contract Documents. completion of the Work. Resident Project Representative-The authorized represen- CONTRACTOR--The person. firm or corporation with whom tative of ENGINEER who is assigned to the site or any part OWNER has entered into the Agreement. thereof. 7 Shop Drawings-All drawings, diagrams, illustrations, ordering an addition, deletion or revision in the Work, or schedules and oth er data which are specifically prepared by responding to differing or unforeseen physical conditions under or for CONTRACTOR to illustrate some portion of the Work which the Work is to be performed as provided in paragraph and all illustrations, brochures. standard schedules, perfor- 4.2 or 4.3 or to emergencies under paragraph 6.22. A Work mance charts, instructions, diagrams and other information Directive Change may not change the Contract Price or the prepared by a Supplier and submitted by CONTRACTOR to Contract Time, but is evidence that the parties expect that illustrate material or equipment for some portion of the Work. the change directed or documented by a Work Directive Change will be incorporated in a subsequently issued Change Spc t ijrwalio.,-Those portions of the Contract Documents Order following negotiations by the parties as to its effect, if consisting of written technical descriptions of' materials. any, on the Contract Price or Contract Time as provided in equipment. construction systems. standards and workman- paragraph 10.2. ship as applied to the Work and certain administrative details applicable thereto. Written Atnendment-A written amendment of the Contract Documents. signed by OWNER and CONTRACTOR on or Suh'contrclrtor-An individual. firm or corporation having a after the Effective Date of the Agreement and normally deal- direct contract with CONITRACTOR or with any other Sub- ing with the nonengineering or nontechnical rather than strictly contractor for the performance of a part of the Work at the Work-related aspects of the Contract Documents. bile. substacrtial Completiot n-The Work for a specified part thereof) has progressed to the point where, in the opinion of ENGI- ARTICLE 2-PRELIMINARY MATTERS NEER as evidenced by ENGINEER's definitive certificate of Substantial Completion, it is sufficiently complete, in o accordance with the Contract Documents, so that the Work for specified part) can be utilized for the purposes for which 2.1. When CONTRACTOR delivers the executed Agree- it is intended: or if there be no such certificate issued, when ments to OWNER, CONTRACTOR shall also deliver to final payment is due in accordance with paragraph 14.13. The OWNER such Bonds as CONTRACTOR may be required to terms "substantially complete" and "substantially com- furnish in accordance with paragraph 5.1. pleted" as applied to any Work refer to Substantial Comple- tion thereot'. Copies of Documents: Supplementary Conditions-The part of the Contract Docu- 2.2. OWNER shall furnish to CONTRACTOR up to ten copies (unless otherwise specified in the Supplementary Con- ments whi ch amends or supplements these General Condi- ditions) of the Contract Documents as are reasonably nec- essary for the execution of the Work. Additional copies will Supplier-A manufacturer. fabricator. supplier, distributor. be furnished upon request, at the cost of reproduction matenalman or vendor. Commencement of Contract Time; Notice to Proceed: U U'nderground Facilirie.-Ali pipelines. conduits. ducts, cables. 2.3. The Contract Time will commence to run on the w'ires, manholes, vaults, tanks. tunnels or other such facilities thirtieth day after the Effective Date of the Agreement. or. if or attachments, and any encasements containing such facil- a Notice to Proceed is given, on the day indicated in the itics which have been in.talled underground to furnish any of Notice to Proceed. A Notice to Proceed may be given at any the following services or materials: electricity, gases. steam, time within thirty days after the Effective Date of the Agree- liquid petroleum products. telephone or other communica- ment. In no event will the Contract Time commence to run tions. cable television. sewage and drainage removal. traffic later than the seventy-fifth day after the day of Bid opening | or other control systems or water. or the thirtieth day after the Effective Date ofthe Agreement. whichever date is earlier. Unit Price Work-Work to be paid for on the basis of' unit prices. Starting the Project: ;Work--The entire completed construction or the various sep- 2.4. CONTRACTOR shall start to perform the Work on arately identifiable parts thereof' required to be furnished the date when the Contract Time commences to run. but no under the Contract Documents. Work is the result of per- Work shall be done at the site prior to the date on which the forming services, furnishing labor and furnishing and incor- Contract T'ime commences to run. porating materials and equipment into the construction, all as required by the Contract Documents. i Before Starting Construction: Wlork Directive Change-A written directive to CONTRAC- 2.5. Before undertaking each part of the Work. CON- TOR. issued on or after the Effective Date of the Agreement TRACTOR shall carefully study and compare the Contract and signed by OWNER and recommended by ENGINEER. Documents and check and verify pertinent figure,, shown 8 1 thereon and all applicable field measurements. CONTRAC- graph 2.6. The finalized progress schedule will be acceptable TOR shall promptly report in writing to ENGINEER any to ENGINEER as providing an orderly progression of the conflict, error or discrepancy which CONTRACTOR may Work to completion within the Contract Time, but such discover and shall obtain a written interpretation or clarifi- acceptancewill neitherimpose on ENGINEER responsibility cation from ENGINEER before proceeding with any Work for the progress or scheduling of the Work nor relieve CON- affected thereby: however, CONTRACTOR shall not be lia- TRACTOR from full responsibility therefor. The finalized ble to OWNER or ENGINEER for failure to report any schedule of Shop Drawing submissions will be acceptable to conflict, error or discrepancy in the Contract Documents, ENGINEER as providing a workable arrangement for pro- unless CONTRACTOR had actual knowledge thereof or should cessing the submissions. The finalized schedule of values will reasonably have known thereof. be acceptable to ENGINEER as to form and substance. 2.6. Within ten days after the Effective Date of the Agree- ment (unless otherwise specified in the General Require- ARTICLE3-CONTRACT DOCUMENTS: INTENT ments). CONTRACTOR shall submit to ENGINEER for ARTICE CONMENTS 1 review�: AMENDING, REUSE review: 2.6.1. an estimated progress schedule indicating the Intent: starting and completion dates of the various stages of the 3.1. The Contract Documents comprise the entire agree- Work: ment between OWNER and CONTRACTOR concerning the Work. The Contract Documents are complementary: what is 2.6.2.missions; a preminary schedule of Shop Drawing sub- called for by one is as binding as if called for by all. The Contract Documents will be construed in accordance with the law of the place of the Project. 2.6.3. a preliminary schedule of values for all of the aggregating the Contract Price and will subdivide the Work a functionally complete Project (or part thereof) to be con- into component parts in sufficient detail to serve as the structed in accordance with the Contract Documents. Any basis for progress payments during construction. Such Work, materials or equipment that may reasonably be inferred prices will include an appropriate amount of overhead and from the Contract Documents as being required to produce profi t applicable to each item of Work which will be con- the intended result will be supplied whether or not specifically firmed in writing by CONTRACTOR at the time of sub- called for. When words which have a well-known technical mission. mission. or trade meaning are used to describe Work. materials or I2.7. Before any Work at the site is started, CONTRAC- equipment such words shall be interpreted in accordance with 2.7. Before anys Work at the site is started, CONTRAC- that meaning. Reference to standard specifications, manuals or codes of any technical society, organization or association, certificates (and other evidence of insurance requested by orto the Laws or Regulations of any governmental authority, maintain in accordance with paragraphs 5.3 and 5.4, and OWNER) which CONTRACTOR is required to purchase and whether such reference be specific or by implication, shall OWNER shall deliver to CONTRACTOR certificates and mean the latest standard specification, manual, code or Laws other evidence of insurance requested b ce CONTRACTOR) or Regulations in effect at the time of opening of Bids (or, on the Effective Date of the Agreement if there were no Bids), which OWNER is required to purchase and 7maintain i except as may be otherwise specifically stated. However, no provision of any referenced standard specification. manual or code (whether or not specifically incorporated by reference ~Preconstruction Conference: ~in the Contract Documents) shall be effective to change the duties and responsibilities of OWNER, CONTRACTOR or 2.8. Within twenty days after the Effective Date of the ENGINEER, or any of their consultants, agents or employ- Agreement, but before CONTRACTOR starts the Work at ees from those set forth in the Contract Documents, nor shall the site, a conference attended by CONTRACTOR, ENGI- it be effective to assign to ENGINEER or any of ENGI- NEER and others as appropriate will be held to discuss the NEER's consultants, agents or employees, any duty or schedules referred to in paragraph 2.6, to discuss procedures authority to supervise or direct the furnishing or performance for handling Shop Drawings and other submittals and othe Work or any duty or submthorittals andertake responsi- processingApplicationsforPayment,andtoestablishaworking bility contrary to the provisions of paragraph 9.15 or 9.16. understanding among the parties as to the Work. Clarifications and interpretations of the Contract Documents shall be issued by ENGINEER as provided in paragraph 9.4. Finalizing Schedules: 3.3. If, during the performance of the Work, CONTRAC- 2.9. At least ten days before submission of the first Appli- TOR finds a conflict, error or discrepancy in the Contract cation for Payment a conference attended by CONTRAC- Documents, CONTRACTOR shall so report to ENGINEER TOR, ENGINEER and others as appropriate will be held to in writing at once and before proceeding with the Work affected finalize the schedules submitted in accordance with para- thereby shall obtain a written interpretation or clarification 9 from ENGINEER; however. CONTRACTOR shall not be such other lands which are designated for the use of CON- liable to OWNER or ENGINEER for failure to report any TRACTOR. Easements for permanent structures or perma- conflict. error or discrepancy in the Contract Documents nent changes in existing facilities will be obtained and paid unless CONTRACTOR had actual knowledge thereof or should for by OWNER. unless otherwise provided in the Contract reasonably have known thereof. Documents. If CONTRACTOR believes that any delay in OWNER's furnishing these lands. rights-of-way or ease- ments entitles CONTRACTOR to an extension of the Con- Amending and Supplementing Contract Documents: tract Time. CONTRACTOR may make a claim therefor as 3.4. The Contract Documents may be amended to pro- provided in Article 12. CONTRACTOR shall provide for all vide for additions, deletions and revisions in the Work or to additional lands and access thereto that may be required for modify the terms and conditions thereof in one or more of temporary construction facilities or storage of materials and the following ways: equipment. 3.4.1. a formal Written Amendment, i 3.4.2. a Change Order (pursuant to paragraph 10.4). 4.2.1. Explorations and Reports: Reference is made or to the Supplementary Conditions for identification of those reports of explorations and tests of subsurface conditions 3.4.3. a Work Directive Change (pursuant to para- at the site that have been utilized by ENGINEER in prep- graph 10. 1). aration of the Contract Documents. CONTRACTOR may rely upon the accuracy of the technical data contained in As indicated in paragraphs 11.2 and 12.1. Contract Price and such reports. but not upon nontechnical data, interpreta- Contract Time may only be changed by a Change Order or a tions or opinions contained therein orforthe completeness Written Amendment. thereof for CONTRACTOR's purposes. Except as indi- cated in the immediately preceding sentence and in para- 3.5. In addition. the requirements of the Contract Docu- graph 4.2.6, CONTRACTOR shall have full responsibility ments may be supplemented. and minor variations and devia- with respect to subsurface conditions at the site. tions in the Work may be authorized, in one or more of the following ways: 4.2.2. Existing Structures: Reference is made to the Supplementary Conditions for identification of those 3.5.1. a Field Order (pursuant to paragraph 9.5), drawings of physical conditions in or relating to existing surface and subsurface structures (except Underground 3.5.2. ENGINEER's approval of a Shop Drawing or Facilities referred to in paragraph 4.3) which are at or sample (pursuant to paragraphs 6.26 and 6.27), or contiguous to the site that have been utilized by ENGI- NEER in preparation of the Contract Documents. CON- 3.5.3. ENGINEER's written interpretation or clarifi- TRACTOR may rely upon the accuracy of the technical cation (pursuant to paragraph 9.4). data contained in such drawings, but not for the complete- ness thereof for CONTRACTOR's purposes. Except as indicated in the immediately preceding sentence and in paragraph 4.2.6, CONTRACTOR shall have full respon- 3.6. Neither CONTRACTOR nor any Subcontractor or sibility with respect to physical conditions in or relating Supplier or other person or organization performing or fur- to such structures. nishing any of the Work under a direct or indirect contract with OWNER shall have or acquire any title to or ownership 4.2.3. Report of Differing Conditions: If CONTRAC- rights in any of the Drawings. Specifications or other docu- TOR believes that: ments (or copies of any thereof) prepared by or bearing the seal of ENGINEER: and they shall not reuse any of them on 4.2.3.1. any technical data on which CONTRAC- extensions of the Project or any other project without writ ten consent of OWNER and ENGINEER and specific written e nd to is inaragrte, or verification or adaptation by ENGINEER. 4.2.3.2. any physical condition uncovered or revealed at the site differs materially from that indi- ARTICLE 4-AVAILABILITY OF LANDS: PHYSICAL cated, reflected or referred to in the Contract Docu- CONDITIONS: REFERENCE POINTS ments, CONTRACTOR shall, promptly after becoming aware thereof and before performing any Work in connection 4.1. OWNER shall furnish, as indicated in the Contract therewith (except in an emergency as permitted by para- Documents, the lands upon which the Work is to be per- graph 6.22), notify OWNER and ENGINEER in writing formed, rights-of-way and easements for access thereto, and about the inaccuracy or difference. 10 4.2.4. ENGINEER's Review: ENGINEER will determine the extent to which the Contract Documents promptly review the pertinent conditions, determine the should be modified to reflect and document the conse- necessity of obtaining additional explorations or tests with quences of the existence of the Underground Facility, and respect thereto and advise OWNER in writing (with a copy the Contract Documents will be amended or supplemented to CONTRACTOR) of ENGINEER's findings and con- to the extent necessary. During such time, CONTRAC- clusions. TOR shall be responsible for the safety and protection of such Underground Facility as provided in paragraph 6.20. 4.2.5. Possih1eh Docutlnent Change: If ENGINEER CONTRACTOR shall be allowed an increase in the Con- concludes that there is a material error in the Contract tract Price or an extension of the Contract Time, or both, Documents or that because of newly discovered condi- to the extent that they are attributable to the existence of tions a change in the Contract Documents is required. a any Underground Facility that was not shown or indicated Work Directive Change or a Change Order will be issued in the Contract Documents and which CONTRACTOR as provided in Article 10 to reflect and document the could not reasonably have been expected to be aware of. consequences of the inaccuracy or difference. If the parties are unable to agree as to the amount or length thereof. CONTRACTOR may make a claim therefor as 4.2.6. Pos.'ibhl Prite eandt Time Adju.stmnient: In each provided in Articles 11 and 12. such case. an increase or decrease in the Contract Price or an extension or shortening of the Contract Time. or any combination thereof. vx ill be allowable to the extent that Reference Points: they are attributable to any such inaccuracy or difference. 4.4. OWNER shall provide engineering surveys to estab- If OWNER and CONTRACTOR are unable to agree as to lish reference points for construction which in ENGINEER's the amount or length thereof, a claim may be made therefor judgment are necessary to enable CONTRACTOR to proceed as provided in Articles 11 and 12. with the Work. CONTRACTOR shall be responsible for lay- ing out the Work (unless otherwise specified in the General Requirements), shall protect and preserve the established Physical Conditions-U'nderground Facilities: reference points and shall make no changes or relocations 4.3.1. Shown or Indicated: The information and data without the prior written approval of OWNER. CONTRAC- shown or indicated in the Contract Documents with respect TOR shall report to ENGINEER whenever any reference to existing Underground Facilities at or contiguous to the point is lost or destroyed or requires relocation because of site is based on information and data furnished to OWNER necessary changes in grades or locations, and shall be respon- or ENGINEER by the owners of such Underground Facil- sible for the accurate replacement or relocation of such ref- ities or by others. Unless it is otherwise expressly pro- erence points by professionally qualified personnel. vided in the Supplementary Conditions: 4.3.1.1. OWNER and ENGINEER shall not be ARTICLE 5--BONDS AND INSURANCE such information or data; and, Performance and Other Bonds: 4.3.1.2. CONTRACTOR shall have full responsi- 5.1. CONTRACTOR shall furnish performance and pay- bility for reviewing and checking all such information ment Bonds, each in an amount at least equal to the Contract and data. for locating all Underground Facilities shown Price as security for the faithful performance and payment of or indicated in the Contract Documents. for coordina- all CONTRACTOR's obligations under the Contract Docu- tion of the Work with the owners of such Underground ments. These Bonds shall remain in effect at least until one Facilities during construction, for the safety and pro- year after the date when final payment becomes due, except tection thereof as provided in paragraph 6.20 and as otherwise provided by Law or Regulation or by the Con- repairing any damage thereto resulting from the Work, tract Documents. CONTRACTOR shall also furnish such the cost of all of which will be considered as having other Bonds as are required by the Supplementary Condi- been included in the Contract Price. tions. All Bonds shall be in the forms prescribed by Law or Regulation or by the Contract Documents and be executed 4.3.2. Not Shown or Indicated. If an Underground by such sureties as are named in the current list of "Com- Facility is uncovered or revealed at or contiguous to the panies Holding Certificates of Authority as Acceptable Sure- site which was not shown or indicated in the Contract ties on Federal Bonds and as Acceptable Reinsuring Corn- Documents and which CONTRACTOR could not reason- panies" as published in Circular 570 (amended) by the Audit ably have been expected to be aware of, CONTRACTOR Staff Bureau of Accounts. U.S. Treasury Department. All shall, promptly after becoming aware thereof and before Bonds signed by an agent must be accompanied by a certified performing any Work affected thereby (except in an emer- copy of the authority to act. gency as permitted by paragraph 6.22), identify the owner of such Underground Facility and give written notice thereof 5.2. If the surety on any Bond furnished by CONTRAC- to that owner and to OWNER and ENGINEER. ENGI- TOR is declared a bankrupt or becomes insolvent or its right NEER will promptly review the Underground Facility to to do business is terminated in any state where any part of II the Project is located or it ceases to meet the requirements thirty days' prior written notice has been given to OWNER of paragraph 5. 1, CONTRACTOR shall within five days and ENGINEER by certified mail. All such insurance shall thereafter substitute another Bond and Surety, both of which remain in effect until final payment and at all times thereafter must be acceptable to OWNER. when CONTRACTOR may be correcting. removing or replacing defective Work in accordance with paragraph 13.12. In addition. CONTRACTOR shall maintain such completed Contractor's Liability Insurance: operations insurance for at least two years after final payment 5.3. CONTRACTOR shall purchase and maintain such and furnish OWNER with evidence of continuation of such comprehensive general liability and other insurance as is insurance at final payment and one year thereafter. appropriate for the Work being performed and furnished and as will provide protection from claims set forth below which may arise out of or result from CONTRACTOR's perfor- Contractual Liabilith Insurance: mance and furnishing of the Work and CONTRACTOR's 5.4. The comprehensive general liability insurance required other obligations under the Contract Documents. whether it by paragraph 5.3 ill include contractual liability insurance is to be performed or furnished by CONTRACTOR. by any applicabletoCONTRACTOR'sobligationsunderparagraphs applicable to CONTRACTOR's obligations under'paragraphs Subcontractor. by anyone directly or indirectly employed by 6.30 and 6.31. an! of them to perform or furnish any of the Work. or by anyone for whose acts any of them may be liable: Owner's Liability Insurance: 5.3.1. Claims under workers' or workmen's compen- sation. disability benefits and other similar employee ben- 5.5. OWNER shall be responsible for purchasing and OWNER's option, may purchase and maintain such insur- 5.3.2. Claims for damages because of bodily injury. ance as will protect OWNER against claims which may arise occupational sickness or disease. or death of CONTRAC- from operations under the Contract Documents. TOR's employees: | 5.3.3. Claims for damages because of bodily injury, Property Insurance: sickness or disease, or death of any person other than 5.6. Unless otherwise provided in the Supplementary CONTRACTOR's employees: Conditions, OWNER shall purchase and maintain property insurance upon the Work at the site to the full insurable value 5.3.4. Claims for damages insured by personal injury thereof (subject to such deductible amounts as may be pro- liability coverage which are sustained (a) by any person vided in the Supplementary Conditions or required by Laws as a result of an offense directly or indirectly related to and Regulations). This insurance shall include the interests the employment of such person by CONTRACTOR, or of OWNER, CONTRACTOR, Subcontractors. ENGINEER (b) by any other person for any other reason: and ENGINEER's consultants in the Work, all of whom shall be listed as insureds or additional insured parties. shall insure 5.3.5. Claims for damages. other than to the Work against the perils of fire and extended coverage and shall itself. because of injury to or destruction of tangible prop- include "all risk" insurance for physical loss and damage erty wherever located, including loss of use resulting including theft, vandalism and malicious mischief, collapse therefrom: and water damage. and such other perils as may be pro ided in the Supplementary Conditions. and shall include damages. 5.3.6. Claims arising out of operation of Laws or Reg- losses and expenses arising out of or resulting from any insured ulations for damages because of bodily injury or death of loss or incurred in the repair or replacement of any insured any person or for damage to property: and property (including but not limited to fees and charges of engineers, architects, attorneys and other professionals). If 5.3.7. Claims for damages because of bodily injury or not covered under the "all risk" insurance or otherwise pro- death of any person or property damage arising out of the vided in the Supplementary Conditions. CONTRACTOR shall ownership. maintenance or use of any motor vehicle. purchase and maintain similar property insurance on portions of the Work stored on and off the site or in transit when such The insurance required by this paragraph 5.3 shall include portions of the Work are to be included in an Application for the specific coverages and be written for not less than the Payment. limits of liability and coverages provided in the Supplemen- tary Conditions, or required by law. whichever is greater. 5.7. OWNERshallpurchaseandmaintainsuchboilerand The comprehensive general liability insurance shall include machinery insurance or additional property insurance as may completed operations insurance. All of the policies of insur- be required by the Supplementary Conditions or Laws and ance so required to be purchased and maintained (or the Regulations which will include the interests of OWNER, certificates or other evidence thereof) shall contain a provi- CONTRACTOR, Subcontractors, ENGINEER AND sion or endorsement that the coverage afforded will not be ENGINEER's consultants in the Work. all of whom shall be cancelled. materially changed or renewal refused until at least listed as insured or additional insured parties. 12 I 5.8. All the policies of insurance (or the certificates or such waiver forms are required of any Subcontractor, other evidence thereof) required to be purchased and main- CONTRACTOR will obtain the same. tained by OWNER in accordance with paragraphs 5.6 and 5.7 will contain a provision or endorsement that the coverage afforded will not be cancelled or materially changed or renewal Receipt and Application of Proceeds: refused until at least thirty days' prior written notice has been 5.12. Any insured loss under the policies of insurance given to CONTRACTOR by certified mail and will contain required by paragraphs 5.6 and 5.7 will be adjusted with waiver provisions in accordance with paragraph 5.11.2. OWNER and made payable to OWNER as trustee for the insureds, as their interests may appear, subject to the require- 5.9. OWNER shall not be responsible for purchasing and ments of any applicable mortgage clause and of paragraph maintaining any property insurance to protect the interests 5.13. OWNER shall deposit in a separate account any money of CONTRACTOR, Subcontractors or others in the Work to so received, and shall distribute it in accordance with such the extent of any deductible amounts that are provided in the agreement as the parties in interest may reach. If no other Supplementary Conditions. The risk of loss within the special agreement is reached the damaged Work shall be deductible amount. will be borne by CONTRACTOR. Sub- repaired or replaced, the moneys so received applied on contractor or others suffering any such loss and if any of them account thereof and the Work and the cost thereof covered wishes property insurance coverage within the limits of such by an appropriate Change Order or Written Amendment. amounts, each may purchase and maintain it at the purchas- er's own expense. 5.13. OWNER as trustee shall have power to adjust and settle any loss with the insurers unless one of the parties in 5.10. If CONTRACTOR requests in writing that other interest shall object in writing within fifteen days after the special insurance be included in the property insurance pol- occurrence of loss to OWNER's exercise of this power. If icy, OWNER shall, if possible, include such insurance, and such objection be made. OWNER as trustee shall make set- the cost thereof will be charged to CONTRACTOR by appro- tlement with the insurers in accordance with such agreement priate Change Order or Written Amendment. Prior to corn- as the parties in interest may reach. If required in writing by mencement of the Work at the site, OWNER shall in writing any party in interest, OWNER as trustee shall. upon the advise CONTRACTOR whether or not such other insurance occurrence of an insured loss, give bond for the proper per- has been procured by OWNER. formance of such duties. Waiver of Rights: Acceptance of Insurance: 5.11.1. OWNER and CONTRACTOR waive all rights 5.14. If OWNERhasany objection tothe coverage afforded against each other for all losses and damages caused by by or other provisions of the insurance required to be pur- any of the perils covered by the policies of insurance chased and maintained by CONTRACTOR in accordance provided in response to paragraphs 5.6 and 5.7 and any with paragraphs 5.3 and 5.4 on the basis of its not complying other property insurance applicable to the Work, and also with the Contract Documents, OWNER shall notify CON- waive all such rights against the Subcontractors, ENGI- TRACTOR in writing thereof within ten days of the date of NEER, ENGINEER's consultants and all other parties delivery of such certificates to OWNER in accordance with named as insureds in such policies for losses and damages paragraph 2.7. If CONTRACTOR has any objection to the so caused. As required by paragraph 6.11. each subcon- coverage afforded by or other provisions of the policies of tract between CONTRACTOR and a Subcontractor will insurance required to be purchased and maintained by OWNER contain similar waiver provisions by the Subcontractor in in accordance with paragraphs 5.6 and 5.7 on the basis of favorof OWNER, CONTRACTOR, ENGINEER, ENGI- their not complying with the Contract Documents, CON- NEER's consultants and all other parties named as insureds. TRACTOR shall notify OWNER in writing thereof within ten None of the above waivers shall extend to the rights that days of the date of delivery of such certificates to CON- any of the insured parties may have to the proceeds of TRACTOR in accordance with paragraph 2.7. OWNER and insurance held by OWNER as trustee or otherwise pay- CONTRACTOR shall each provide to the other such addi- able under any policy so issued. tional information in respect of insurance provided by each as the other may reasonably request. Failure by OWNER or 5. I 1.2. OWNER and CONTRACTOR intend that any CONTRACTOR to give any such notice of objection within policies provided in response to paragraphs 5.6 and 5.7 the time provided shall constitute acceptance of such insur- shall protect all of the parties insured and provide primary ance purchased by the other as complying with the Contract coverage for all losses and damages caused by the perils Documents. covered thereby. Accordingly, all such policies shall con- tain provisions to the effect that in the event of payment of any loss or damage the insurer will have no rights of Partial Utilization-Property Insurance: recovery against any of the parties named as insureds or 5.15. If OWNER finds it necessary to occupy or use a additional insureds. and if the insurers require separate portion or portions of the Work prior to Substantial Comple- waiver forms to be signed by ENGINEER or ENGI- tion of all the Work. such use or occupancy may be accom- NEER's consultant OWNER will obtain the same, and if plished in accordance with paragraph 14.10; provided that no 13 such use or occupancy shall commence before the insurers 6.5. All materials and equipment shall be of good quality providing the property insurance have acknowledged notice and new, except as otherwise provided in the Contract Doc- thereof and in writing effected the changes in coverage neces- uments. If required by ENGINEER. CONTRACTOR shall sitated thereby. The insurers providing the property insur- furnish satisfactory evidence (including reports of required ance shall consent by endorsement on the policy or policies, tests) as to the kind and quality of materials and equipment. but the property insurance shall not be cancelled or lapse on All materials and equipment shall be applied. installed. con- account of any such partial use or occupancy. nected. erected. used, cleaned and conditioned in accordance with the instructions of the applicable Supplier except as otherwise provided in the Contract Documents: but no pro- vision of any such instructions will be effective to assign to ARTICLE 6-CONTRACTOR'S RESPONSIBILITIES ENGINEER. or any of ENGINEER's consultants. agents or employees, any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or author- ity to undertake responsibility contrary to the provisions of 6.1 . CONTRACTOR shall supervise anddirect the Work paragraph 9.15 or 9.16. competently and efficiently. devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Doc- Adjusting Progress Schedule: uments. CONTRACTOR shall be solely responsible for the 6.6. CONTRACTOR shall submit to ENGINEER for means. methods, techniques. sequences and procedures of acceptance (to the extent indicated in paragraph 2.9) adjust- construction. but CONTRACTOR shall not be responsible ments in the progress schedule to reflect the impact thereon for the negligence of others in the design or selection of a of new developments: these will conform generally to the specific means. method, technique, sequence or procedure progress schedule then in effect and additionally will comply of construction which is indicated in and required by the with any provisions of the General Requirements applicable Contract Documents. CONTRACTOR shall be responsible thereto. to see that the finished Work complies accurately with the Contract Documents. Substitutes or "Or-Equal" Items: 6.2. CONTRACTOR shall keep on the Work at all times 6.7.1. Whenevermaterialsorequipmentare specified during its progress a competent resident superintendent, who, or described in the Contract Documents by using the name shall not be replaced without written notice to OWNER and ENGIN EER except under extraordinary circumstances. The the naming of the item is intended to establish the type. superintendent will be CONTRACTOR's representative at function and quality required. Unless the name is followed the site and shall have authority to act on behalf of CON- by words indicating that no substitution is permitted. TRACTOR. All communications given to the superintendent materials or equipment of other Suppliers may be accepted shall be as binding as if given to CONTRACTOR. by ENGINEER if sufficient information is submitted by CONTRACTOR to allow ENGINEER to determine that the material or equipment proposed is equivalent or equal to that named. The procedure for review by ENGINEER 6.3. CONTRACTOR shall provide competent, suitably will include the following as supplemented in the General 3 qualified personnel to survey and lay out the Work and per- Requirements. Requests for review of substitute items of form construction as required by the Contract Documents. material and equipment will not be accepted by ENGI- CONTRACTOR shall at all times maintain good discipline NEER from anyone other than CONTRACTOR. If CON- and order at the site. Except in connection with the safety or TRACTOR wishes to furnish or use a substitute item of protection of persons or the Work or property at the site or material or equipment. CONTRACTOR shall make writ- adjacent thereto. and except as otherwise indicated in the ten application to ENGINEER for acceptance thereof. Contract Documents, all Work at the site shall be performed certifying that the proposed substitute will perform ade- - during regular working hours, and CONTRACTOR will not quately the functions and achieve the results called for by permit overtime work or the performance of Work on Sat- the general design, be similar and of equal substance to urday, Sunday or any legal holiday without OWNER's writ- that specified and be suited to the same use as that spec- ten consent given after prior written notice to ENGINEER. ified. The application will state that the evaluation and acceptance of the proposed substitute will not prejudice 6.4. Unless otherwise specified in the General Require- CONTRACTOR's achievement of Substantial Comple- ments, CONTRACTOR shall furnish and assume full respon- tion on time, whether or not acceptance of the substitute sibility for all materials. equipment, labor. transportation. for use in the Work will require a change in any of the construction equipment and machinery, tools, appliances, Contract Documents (or in the provisions of any other fuel. power, light, heat, telephone, water, sanitary facilities, direct contract with OWNER for work on the Project) to temporary facilities and all other facilities and incidentals adapt the design to the proposed substitute and whether necessary for the furnishing, performance, testing. start-up or not incorporation or use of the substitute in connection and completion of the Work. with the Work is subject to payment of any license fee or 14 royalty. All variations of the proposed substitute from that OWNER and ENGINEER and if CONTRACTOR has specified will be identified in the application and available submitted a list thereof in accordance with the Supple- maintenance. repair and replacement service will be indi- mentary Conditions, OWNER's or ENGINEER's accept- cated. The application will also contain an itemized esti- ance (either in writing or by failing to make written objec- mate of all costs that will result directly or indirectly from tion thereto by the date indicated for acceptance or objec- acceptance of such substitute. including costs of redesign tion in the bidding documents or the Contract Documents) and claims of other contractors affected by the resulting of any such Subcontractor, Supplier or other person or change. all of which shall be considered by ENGINEER organization so identified may be revoked on the basis of in evaluating the proposed substitute. ENGINEER may reasonable objection after due investigation. in which case require CONTRACTOR to furnish at CONTRACTOR's CONTRACTOR shall submit an acceptable substitute, the expense additional data about the proposed substitute. Contract Price will be increased by the difference in the cost occasioned by such substitution and an appropriate 6.7.2. If a specific means. method. technique. sequence Change Order will be issued or Written Amendment signed. or procedure of construction is indicated in or required by No acceptance by OWNER or ENGINEER of any such the Contract Documents. CONTRACTOR may furnish or Subcontractor. Supplier or other person or organization utilize a substitute means. method. sequence. technique shall constitute awaiver of an y right of OWNER or ENGI- or procedure of construction acceptable to ENGINEER. NEER to reject dcj/i'ctivc Work. if CONTRACTOR submits sufficient information to allow ENGINEER to determine that the substitute proposed is 6.9. CONTRACTOR shall be fully responsible to OWNER equivalent to that indicated or required by the Contract and ENGINEER for all acts and omissions of the Subcon- Documents. The procedure for review by ENGINEER tractors, Suppliers and other persons and organizations per- will be similar to that trovided in paragraph 6.7.1 as applied forming or furnishing any of the Work under a direct or by ENGINEER and as may be supplemented in the Gen- indirect contract with CONTRACTOR just as CONTRAC- eral Requirements. TOR is responsible for CONTRACTOR's own acts and omis- sions. Nothing in the Contract Documents shall create any 6.7.3. ENGINEER will be allowed a reasonable time contractual relationship between OWNER or ENGINEER within which to evaluate each proposed substitute. ENGI- and any such Subcontractor. Supplier or other person or NEER will be the sole judge of acceptability, and no organization. nor shall it create any obligation on the part of substitute will be ordered, installed or utilized without OWNER or ENGINEER to pay or to see to the payment of ENGINEER's prior written acceptance which will be evi- any moneys due any such Subcontractor. Supplier or other denced by either a Change Order or an approved Shop person or organization except as may otherwise be required Drawing. OWNER may require CONTRACTOR to fur- by Laws and Regulations. nish at CONTRACTOR's expense a special performance guarantee or other surety with respect to any substitute. 6.10. The divisions and sections of the Specifications and ENGINEER will record time required by ENGINEER the identifications of any Drawings shall not control CON- and ENGINEER's consultants in evaluating substitutions TRACTOR in dividing the Work among Subcontractors or proposed by CONTRACTOR and in making changes in Suppliers or delineating the Work to be performed by any the Contract Documents occasioned thereby. Whether or specific trade. not ENGINEER accepts a proposed substitute. CON- TRACTOR shall reimburse OWNER for the charges of 6.11. All Work performed for CONTRACTOR by a Sub- ENGINEER and ENGINEER's consultants for evaluat- contractor will be pursuant to an appropriate agreement ing each proposed substitute. between CONTRACTOR and the Subcontractor which spe- cifically binds the Subcontractor to the applicable terms and conditions of the Contract Documents for the benefit of Concerning Subcontractors, Suppliers and Others: OWNER and ENGINEER and contains waiver provisions 6.8.1. CONTRACTOR shall not employ any Subcon- as required by paragraph 5.11. CONTRACTOR shall pay tractor, Supplierorotherperson ororganization (including each Subcontractor a just share of any insurance moneys those acceptable to OWNER and ENGINEER as indi- received by CONTRACTOR on account of losses under pol- cated in paragraph 6.8.21). whether initially or as a substi- icies issued pursuant to paragraphs 5.6 and 5.7. tute, against whom OWNER or ENGINEER may have reasonable objection. CONTRACTOR shall not be required to employ any Subcontractor, Supplier or other person or Patent Fees and Royalties: organization to furnish or perform any of the Work against 6.12. CONTRACTOR shall pay all license fees and roy- whom CONTRACTOR has reasonable objection. alties and assume all costs incident to the use in the perfor- 6.8.2. If the Supplementary Conditions require the mance of the Work or the incorporation in the Work of any identity of certain Subcontractors. Suppliers or other per- invention, design, process, product or device which is the sons or organizations (including those who are to furnish subject of patent rights or copyrights held by others. If a the principal items of materials and equipment) to be sub- particular invention, design, process. product or device is mitted to OWNER in advance of the specified date prior specified in the Contract Documents for use in the perfor- to the Effective Date of the Agreement for acceptance by mance of the Work and if to the actual knowledge of OWN ER 15 or ENGINEER its use is subject to patent rights or copyrights place of the Project which are applicable during the perfor- calling for the payment of any license fee or royalty to others, mance of the Work. the existence of such rights shall be disclosed by OWNER in the Contract Documents. CONTRACTOR shall indemnify and hold harmless OWNER and ENGINEER and anyone Use of Premises: directly or indirectly employed by either of them from and 6.16. CONTRACTOR shall confine construction equip- against all claims, damages, losses and expenses (including ment. the storage of materials and equipment and the oper- attorneys' fees and court and arbitration costs) arising out of ations of workers to the Project site and land and areas iden- any infringement of patent rights or copyrights incident to tified in and permitted by the Contract Documents and other the use in the performance of the Work or resulting from the land and areas permitted by Laws and Regulations, rights- incorporation in the Work of any invention, design. process, of-way, permits and easements. and shall not unreasonably product or device not specified in the Contract Documents, encumber the premises with construction equipment or other and shall defend all such claims in connection with any alleged materials or equipment. CONTRACTOR shall assume full infringement of such rights. responsibility for any damage to any such land or area, or to the owner or occupant thereof or of any land or areas contig- uous thereto, resulting from the performance of the Work. Permits: Should any claim be made against OWNER or ENGINEER 6. 13. Unless otherwise provided in the Supplementary by any such owner or occupant because of the performance Conditions. CONTRACTOR shall obtain and pay for all con- of the Work, CONTRACTOR shall promptly attempt to settle struction permits and licenses. OWNER shall assist CON- with such other party by agreement or otherwise resolve the TRACTOR. when necessary. in obtaining such permits and claim by arbitration or at law. CONTRACTOR shall, to the licenses. CONTRACTOR shall pay all governmental charges fullest extent permitted by Laws and Regulations, indemnify and inspection fees necessary for the prosecution of the Work, and hold OWNER and ENGINEER harmless from and against which are applicable at the time of opening of Bids. or if there all claims, damages, losses and expenses (including. but not are no Bids on the Effective Date of the Agreement. CON- limited to, fees of engineers, architects, attorneys and other TRACTOR shall pay all charges of utility owners for con- professionals and court and arbitration costs) arising directly, nections to the Work. and OWNER shall pay all charges of indirectly or consequentially out of any action. legal or equi- such utility owners for capital costs related thereto such as table, brought by any such other party against OWNER or plant investment fees. ENGINEER to the extent based on a claim arising out of CONTRACTOR's performance of the Work. Laws and Regulations: 6.17. During the progress of the Work. CONTRACTOR 6.14.1. CONTRACTOR shall give all notices and shall keep the premises free from accumulations of waste comply with all Laws and Regulations applicable to fur- materials, rubbish and other debris resulting from the Work. nishing and performance of the Work. Except where oth- At the completion of the Work CONTRACTOR shall remove erwise expressly required by applicable Laws and Regu- all waste materials, rubbish and debris from and about the lations, neither OWNER nor ENGINEER shall be respon- premises as well as all tools, appliances. construction equip- sible for monitoring CONTRACTOR's compliance with ment and machinery, and surplus materials. and shall leave any Laws or Regulations. the site clean and ready for occupancy by OWNER. CON- TRACTOR shall restore to original condition all property not 6.14.2. If CONTRACTOR observes that the Specifi- designated for alteration by the Contract Documents. cations or Drawings are at variance with any Laws or Regulations, CONTRACTOR shall give ENGINEER 6.18. CONTRACTOR shall not load nor permit any part prompt written notice thereof, and any necessary changes of any structure to be loaded in any manner that will endanger will be authorized by one of the methods indicated in the structure. nor shall CONTRACTOR subject any part of paragraph 3.4. If CONTRACTOR performs any Work the Work or adjacent property to stresses or pressures that knowing or having reason to know that it is contrary to will endanger it. such Laws or Regulations. and without such notice to ENGINEER. CONTRACTOR shall bear all costs arising therefrom: however. it shall not be CONTRACTOR's pri- Record Documents: mary responsibility to make certain that the Specifications 6.19. CONTRACTOR shall maintain in a safe place at and Drawings are in accordance with such Laws and the site one record copy of all Drawings. Specifications. Regulations. Addenda. Written Amendments. Change Orders. Work Directive Changes, Field Orders and written interpretations and clarifications (issued pursuant to paragraph 9.4) in good Taxes: order and annotated to show all changes made during con- 6.15. CONTRACTOR shall pay all sales. consumer. use struction.These record documents togetherwith all approved and other similar taxes required to be paid by CONTRAC- samples and a counterpart of all approved Shop Drawings TOR in accordance with the Laws and Regulations of the will be available to ENGINEER for reference. Upon com- 16 pletion of the Work. these record documents, samples and Emergencies: Shop Drawings will be delivered to ENGINEER for OWNER. 6.22. In emergencies affecting the safety or protection of persons or the Work or property at the site or adjacent thereto, CONTRACTOR. without special instruction or authorization Safety and Protection: from ENGINEER or OWNER, is obligated to act to prevent finitiating. threatened damage, injury or loss. CONTRACTOR shall give I6.20. CONTRACTOR shall be responsible for initiating. ENGINEER prompt written notice if CONTRACTOR believes maintaining and supervising all safety precautions and pro- that any significant changes in the Work or variations from tak e all neces sary pin conn ection ith th e Work CONTRACTOR shall th e Contract Documents have been caused thereby. If ENGI- take all necessary precautions for the safety of, and shall NEER determines that a change in the Contract Documents Iprovide the necessary protection to prevent damage. injury is required because of the action taken in response to an emergency. a Work Directive Change or Change Order will be issued to document the consequences of the changes or 6.20. 1. all employees on the Work and other persons variations and organizations who may be affected thereby; 6.20.2. all the Work and materials and equipment to Shop Drawings and Samples: be incorporated therein. whether in storage on or off the 6.23. Aftercheckingandverifyingallfieldmeasurements site: and and after complying with applicable procedures specified in the General Requirements, CONTRACTOR shall submit to 6.20.3. other property at the site or adjacent thereto, ENGINEER for review and approval in accordance wit t including trees, shrubs, lawns, walks, pavements, road- accepted schedule of Shop Drawing submissions (see para- ways, structures utilities and Underground Facilities not graph 2.9), or for other appropriate action if so indicated in designated for removal. relocation or replacement in the tgraph 2.9), or for other appro priate acti on if s o indicated in course of construction. the Supplementary Conditions. five copies (unless o therwise s p ecified in the General Requirements) of all Shop Draw ings, which will bear a stamp or specific written indication that CONTRACTOR shall comply with all applicable Laws and CONTRACTOR has satisfied CONTRACTOR's responsi- Regulations of any public body having jurisdiction for the bilities under the Contract Documents with respect to the safety of persons or property orto protect them from damage. review of the submission. All submissions will be identified injury or loss: and shall erect and maintain all necessary as ENGINEER may require. The data shown on the Shop safeguards for such safety and protection. CONTRACTOR Drawings will be complete with respect to quantities, dimen- shall notify owners of adjacent property and of Underground sions, specified performance and design criteria, materials Facilities and utility owners when prosecution of the Work and similar data to enable ENGINEER to review the infor- may affect them. and shall cooperate with them in the pro- mation as required. tection. removal. relocation and replacement of their prop- erty. All damage, injury or loss to any property referred to 6.24. CONTRACTOR shall also submit to ENGINEER in paragraph 6.20.2 or 6.20.3 caused. directly or indirectly, for review and approval with such promptness as to cause in whole or in part, by CONTRACTOR, any Subcontractor. no delay in Work, all samples required by the Contract Doc- Supplier or any other person or organization directly or indi- uments. All samples will have been checked by and accom- rectly employed by any of them to perform or furnish any of panied by a specific written indication that CONTRACTOR the Work or anyone for whose acts any of them may be liable. has satisfied CONTRACTOR's responsibilities under the shall be remedied by CONTRACTOR (except damage or loss Contract Documents with respect to the review of the sub- attributable to the fault of Drawings or Specifications or to mission and will be identified clearly as to material, Supplier, the acts or omissions of OWNER or ENGINEER or anyone pertinent data such as catalog numbers and the use for which employed by either of them or anyone for whose acts either intended. of them may be liable, and not attributable. directly or indi- rectly, in whole or in part. to the fault or negligence of CON- 6.25.1. Before submission of each Shop Drawing or TRACTOR). CONTRACTOR's duties and responsibilities sample CONTRACTOR shall have determined and veri- for the safety and protection of the Work shall continue until fied all quantities, dimensions. specified performance cri- such time as all the Work is completed and ENGINEER has teria. installation requirements, materials. catalog num- issued a notice to OWNER and CONTRACTOR in accord- bers and similar data with respect thereto and reviewed ance with paragraph 14.13 that the Work is acceptable (except or coordinated each Shop Drawing or sample with other as otherwise expressly provided in connection with Substan- Shop Drawings and samples and with the requirements of tial Completion). the Work and the Contract Documents. 6.21. CONTRACTOR shall designate a responsible rep- 6.25.2. At the time of each submission, CONTRAC- resentative at the site whose duty shall be the prevention of TOR shall give ENGINEER specific written notice of each accidents. This person shall be CONTRACTOR's superin- variation that the Shop Drawings or samples may have tendent unless otherwise designated in writing by CON- from the requirements of the Contract Documents. and. TRACTOR to OWNER. in addition. shall cause a specific notation to be made on 17 each Shop Drawing submitted to ENGINEER for review provided that any such claim, damage, loss or expense (a) is and approval of each such variation. attributable to bodily injury, sickness. disease or death. or to injury to or destruction of tangible property (other than the 6.26. ENGINEER will review and approve with reason- Work itself) including the loss of use resulting therefrom and able promptness Shop Drawings and samples. but ENGI- (b) is caused in whole or in part by any negligent act or NEER's review and approval will be only for conformance omission of CONTRACTOR, any Subcontractor. any person with the design concept of the Project and for compliance ororganizationdirectlyorindirectlyemployedbyany ofthem with the information given in the Contract Documents and to perform or furnish any of the Work or anyone for whose shall not extend to means. methods, techniques. sequences acts any of them may be liable, regardless of whether or not or procedures of construction (except where a specific means. it is caused in part by a party indemnified hereunder or arises method. technique. sequence or procedure of construction is by or is imposed by Law and Regulations regardless of the indicated in or required by the Contract Documents) or to negligence of any such party. safety precautions or programs incident thereto. The review and approval of a separate item as such will not indicate 6.31. In any and all claims against OWNER or ENGI- approval of the assembly in which the item functions. CON- NEER or any of their consultants. agents or employees by TRACTOR shall make corrections required by ENGINEER. any employee of CONTRACTOR. any Subcontractor. any and shall return the required number of corrected copies of person or organization directly or indirectly employed by any Shop Drawings and submit as required new samples for review of them to perform or furnish any of the Work or anyone for and approval. CONTRACTOR shall direct specific attention whose acts any of them may be liable. the indemnification in writing to revisions other than the corrections called for obligation under paragraph 6.30 shall not be limited in any by ENGINEER on previous submittals. way by any limitation on the amount or type of damages, compensation or benefits payable by or for CONTRACTOR 6.27. ENGINEER's review and approval of Shop Draw- or any such Subcontractor or other person or organization ings or samples shall not relieve CONTRACTOR from under workers' or workmen's compensation acts. disability responsibility for any variation from the requirements of the benefit acts or other employee benefit acts. Contract Documents unless CONTRACTOR has in writing called ENGINEER's attention to each such variation at the 6.32. The obligations of CONTRACTOR under para- time of submission as required by paragraph 6.25.2 and graph 6.30 shall not extend to the liability of ENGINEER, ENGINEER has given written approval of each such varia- ENGINEER's consultants, agents or employees arising out tion by a specific written notation thereof incorporated in or of the preparation or approval of maps, drawings. opinions. accompanying the Shop Drawing or sample approval; nor reports, surveys, Change Orders, designs or specifications. will any approval by ENGINEER relieve CONTRACTOR from responsibility for errors or omissions in the Shop Draw- ings or from responsibility for having complied with the pro- ARTICLE 7-OTHER WORK visions of paragraph 6.25. 1. 6.28. Where a Shop Drawing or sample is required by the Related Work at Site: Specifications. any related Work performed prior to ENGI- 7.1. OWNER may perform other work related to the Proj- NEER's review and approval of the pertinent submission will ect at the site by OWNER's own forces. have other work be the sole expense and responsibility, of CONTRACTOR. performed by utility owners or let otherdirect contracts therefor which shall contain General Conditions similar to these. If Continuing the Work: the fact that such other work is to be performed was not noted in the Contract Documents, written notice thereof will be 6.29. CONTRACTOR shall carry on the Work and adhere given to CONTRACTOR prior to starting any such other totheprogress schedule during all disputesor disagreemnts work; and. if CONTRACTOR believes that such perfor- with OWN ER. No Work shall be delayed or postponed pend- mance will involve additional expense to CONTRACTOR or ing resolution of any disputes or disagreements. except as requires additional time and the parties are unable to agree permitted by paragraph 15.5 or as CONTRACTOR and as to the extent thereof, CONTRACTOR may make a claim OWNER may otherwise agree in writing. therefor as provided in Articles 11 and 12. 7.2. CONTRACTOR shall afford each utility owner and Indemnification: other contractor who is a party to such a direct contract (or 6.30. To the fullest extent permitted by Laws and Regu- OWNER, if OWNER is performing the additional work with lations CONTRACTOR shall indemnify and hold harmless OWNER's employees) proper and safe access to the site and OWNER and ENGINEER and their consultants. agents and a reasonable opportunity for the introduction and storage of employees from and against all claims, damages. losses and materials and equipment and the execution of such work, and expenses. direct, indirect or consequential (including but not shall properly connect and coordinate the Work with theirs. limited to fees and charges of engineers, architects, attorneys CONTRACTOR shall do all cutting, fitting and patching of and other professionals and court and arbitration costs) aris- the Work that may be required to make its several parts come ing out of or resulting from the performance of the Work, together properly and integrate with such other work. CON- 18 TRACTOR shall not endanger any work of others by cutting. tures which have been utilized by ENGINEER in preparing excavating or otherwise altering their work and will only cut the Drawings and Specifications. or alter their work with the written consent of ENGINEER and the others whose work will be affected. The duties and 8.5. OWNER's responsibilities in respect of purchasing responsibilities of CONTRACTOR under this paragraph are and maintaining liability and property insurance are set forth for the benefit of such utility owners and other contractors in paragraphs 5.5 through 5.8. to the extent that there are comparable provisions for the benefit of CONTRACTOR in said direct contracts between 8.6. OWNER is obligated to execute Change Orders as OWNER and such utility owners and other contractors. indicated in paragraph 10.4. 7.3. If anv part of CONTR.ACTOR's W'ork depends for 8.7,. OWNER's responsibility in respect of certain proper execution or results upon the work of any such other inspections tests and approvals is set forth in paragraph 13.4. contractor or utility owner (or OWNER). CONTRACTOR shall inspect and promptly report to ENGINEER in writing 8.8. In connection with OWNERs right to stop Work or any delays. defects or deficiencies in such work that render suspend Work. seeparagraphs 13.10and 1. 1. Paragraph 15.2 deals with OWNER's right to terminate services of CON- it unavailable or unsuitable for such proper execution and deals with OWNER's right to terinate services results. CONTRACTOR's failure so to report will constitute an acceptance of the other v ork as fit and proper for integra- tion with CONTRACTOR's Work except for latent or non- apparent defects and deficiencies in the other work. ARTICLE 9-ENGINEER'S STATUS DURING CONSTRUCTION Coordination: CONSTRUCTION 7.4. If OWNER contracts with others for the perfor- Owner's Representative: mance of other work on the Project at the site. the person or 9.1. ENGINEER will be OWNER's representative dur- organization who will have authority and responsibility for ing the construction period. The duties and responsibilities coordination of the activities among the various prime con- and the limitations of authority of ENGINEER as OWNER's tractors will be identified in the Supplementary Conditions, representative during construction are set forth in the Con- and the specific matters to be covered by such authority) and tract Documents and shall not be extended without written responsibility will be itemized, and the extent of such author- consent of OWNER and E?'GINEER. ity and responsibilities will be provided, in the Supplementary Conditions. Unless otherwise provided in the Supplementary Conditions, neither OWNER nor ENGINEER shall have any authority or responsibility in respect of such coordination. 9.2. ENGINEER will make visits to the site at intervals appropriate to the various stages of construction to observe the progress and quality of the executed Work and to deter- ARTICLE 8-OWNER'S RESPONSIBILITIES mine, in general, if the Work is proceeding in accordance with the Contract Documents. ENGINEER will not be required to make exhaustive or continuous on-site inspections to check 8.1. OWNER shall issue all communications to CON- the quality or quantity of the Work. ENGINEER's efforts TRACTOR through ENGINEER. will be directed toward providing for OWNER a greater degree of confidence that the completed Work will conform to the 8.2. In case of termination of the employment of ENGI- Contract Documents. On the basis of such visits and on-site NEER, OWNER shall appoint an engineer against whom observations as an experienced and qualified design profes- CONTRACTOR makes no reasonable objection. whose sta- sional. ENGINEER will keep OWNER informed of the prog- tus under the Contract Documents shall be that of the former ress of the Work and will endeavor to guard OWNER against ENGINEER. Any dispute in connection with such appoint- defects and deficiencies in the Work. ment shall be subject to arbitration. 8.3. OWNER shall furnish the data required of OWNER Project Representation: ments to CONTRACTOR promptly after they are due as will furnish a Resident Project Representative to assist provided in paragraphs 14.4 and 14.13. ENGINEER in observing the performance of the Work. The duties, responsibilities and limitations of authority of any 8.4. OWNER's duties in respect of providing lands and such Resident Project Representative and assistants will be easements and providing engineering surveys to establish as provided in the Supplementary Conditions. If OWNER reference points are set forth in paragraphs 4.1 and 4.4. Para- designates another agent to represent OWNER at the site graph 4.2 refers to OWNER's identifying and making avail- who is not ENGINEER's agent or employee, the duties, able to CONTRACTOR copies of reports of explorations and responsibilities and limitations of authority of such other tests of subsurface conditions at the site and in existing struc- person will be as provided in the Supplementary Conditions. 19 Clarifications and Interpretations: to ENGINEER written notice of intention to appeal from 9.4. ENGINEER will issue with reasonable promptness such a decision. such written clarifications or interpretations of the require- ments of the Contract Documents (in the form of Drawings Decisions on Disputes: or otherwise) as ENGINEER may determine necessary, which shall be consistent with or reasonably inferable from the 9.11. ENGINEER will be the initial interpreter of the overall intent of the Contract Documents. If CONTRACTOR requirements of the Contract Documents and judge of the believes that a written clarification or interpretation justifies acceptability of the Work thereunder. Claims, disputes and an increase in the Contract Price or an extension of the other matters relating to the acceptability of the Work or the Contract Time and the parties are unable to agree to the interpretation of the requirements of the Contract Documents amount or extent thereof. CONTRACTOR may make a claim pertaining to the performance and furnishing of the Work and therefor as provided in Article II or Article 12. claims under Articles I and 12 in respect of changes in the Contract Price or Contract Time will be referred initially to ENGINEER in writing with a request for a formal decision Authorized Variations in Uork: in accordance with this paragraph, which ENGINEER will 9.5. ENGINEER may authorize minor variations in the render in writing within a reasonable time. Written notice of Work from the requirements of the Contract Documents which each such claim, dispute and other matter will be delivered do not involve an adjustment in the Contract Price or the by the claimant to ENGINEER and the other party to the Contract Time and are consistent with the overall intent of Agreement promptly (but in no event later than thirty days) the Contract Documents. These ma y be accomplished by a after the occurrence of the event giving rise thereto. and Field Order and will be binding on OWNER, and also on written supporting data will be submitted to ENGINEER and CONTRACTOR who shall perform the Work involved the other party within sixty days after such occurrence unless promptly. If CONTRACTOR believes that a Field Order ENGINEER allows an additional period of time to ascertain justifies an increase in the Contract Price or an extension of more accurate data in support of the claim. the Contract Time and the parties are unable to agree as to the amount or extent thereof. CONTRACTOR may make a 9.12. When functioning as interpreter and judge under claim therefor as provided in Article I1 or 12. paragraphs 9.10 and 9.11, ENGINEER will not show par- tiality to OWNER or CONTRACTOR and will not be liable in connection with any interpretation or decision rendered in Rejecting Defective Work: good faith in such capacity. The rendering of a decision by 9.6. ENGINEER will have authority to disapprove or ENGINEERpursuant to paragraphs 9.10 and 9.11 with respect reject Work which ENGINEER believes to be defective, and to any such claim, dispute or other matter (except any which will also have authority to require special inspection or testing have been waived by the making or acceptance of final pay- of the Work as provided in paragraph 13.9, whether or not ment as provided in paragraph 14.16) will be a condition the Work is fabricated, installed or completed. precedent to any exercise by OWNER or CONTRACTOR of such rights or remedies as either may otherwise have under the Contract Documents or by Laws or Regulations in respect Shop Drawings, Change Orders and Payments: of any such claim, dispute or other matter. 9.7. In connection with ENGINEER's responsibility for Shop Drawings and samples. see paragraphs 6.23 through 6.29 inclusive, Limitations on ENGINEER's Responsibilities: 9.13. Neither ENGINEER's authority to act under this 9.8. In connection with ENGINEER's responsibilities as Article 9 or elsewhere in the Contract Documents nor any to Change Orders, see Articles 10, 1 I and 12. decision made by ENGINEER in good faith either to exercise or not exercise such authority shall give rise to any duty or 9.9. In connection with ENGINEER's responsibilities in responsibility of ENGINEER to CONTRACTOR. any Sub- respect of Applications for Payment, etc., see Article 14. contractor, any Supplier. or any other person or organization performing any of the Work, or to any surety for any of them. Determinationsfor LUnit Prices: 9.14. Whenever in the Contract Documents the terms 'as 9.10. ENGINEER will determine the actual quantities ordered", "as directed". "as required". "as allowed", "as and classifications of Unit Price Work performed by CON- approved" or terms of like effect or import are used. or the TRACTOR. ENGINEER will review with CONTRACTOR adjectives "reasonable"., "suitable", "acceptable", "proper" ENGINEER's preliminary determinations on such matters or "satisfactory" or adjectives of like effect or import are before rendering a written decision thereon (by recommen- used to describe a requirement. direction. review orjudgment dation of an Application for Payment or otherwise). ENGI- of ENGINEER as to the Work, it is intended that such NEER's written decisions thereon will be final and binding requirement, direction, review or judgment will be solely to upon OWNER and CONTRACTOR. unless. within ten days evaluate the Work for compliance with the Contract Docu- after the date of any such decision. either OWNER or CON- ments (unless there is a specific statement indicating other- TRACTOR delivers to the other party to the Agreement and wise). The use of any such term or adjective shall not be 20 effective to assign to ENGINEER any duty or authority to 10.4.3. changesintheContractPriceorContractTime supervise or direct the furnishing or performance of the Work which embody the substance of any written decision ren- or any duty or authority to undertake responsibility contrary dered by ENGINEER pursuant to paragraph 9. 11; to the provisions of paragraph 9.15 or 9.16. provided that, in lieu of executing any such Change Order, an appeal may be taken from any such decision in accordance 9.15. ENGINEER will not be responsible for CON- with the provisions of the Contract Documents and applicable TRACTOR's means. methods, techniques, sequences or pro- Laws and Regulations, but during any such appeal. CON- cedures of construction, or the safety precautions and pro- TRACTOR shall carry on the Work and adhere to the prog- grams incident thereto, and ENGINEER will not be respon- ress schedule as provided in paragraph 6.29. sible for CONTRACTOR's failure to perform or furnish the 10.5. If notice of any change affecting the general scope of the Work or the provisions of the Contract Documents 9. 16. ENGINEjR will not be responsible for the acts or (including, but not limited to, Contract Price or Contract omissions of CONTRACTOR or of any Subcontractor, any Time) is required by the provisions of any Bond to be given Supplier. or of any other person or organization performing to a surety, the giving of any such notice will be CONTRAC- or furnishing any' of the Work. TOR's responsibility, and the amount of each applicable Bond will be adjusted accordingly. ARTICLE 10-CHANGES IN THE WORK ARTICLE 1I--CHANGE OF CONTRACT PRICE 10.1. Without invalidating the Agreement and without notice to any surety, OWNER may. at any time or from time to 11.1. The Contract Price constitutes the total compen- time, order additions, deletions or revisions in the Work: sation (subject to authorized adjustments) payable to CON- these will be authorized by a Written Amendment. a Change TRACTOR for performing the Work. All duties. responsibil- Order, or a Work Directive Change. Upon receiptofansuch iies and obligations assigned to or undertaken by CON- document, CONTRACTOR shall promptly proceed with the TRACTOR shall be at his expense without change in the Work involved which will be performed under the applicable Contract Price. conditions of the Contract Documents (except as otherwise specifically provided). 11.2. The Contract Price may only be changed by a Change Order or by a Written Amendment. Any claim for an increase 10.2. If OWNER and CONTRACTOR are unable to agree or decrease in the Contract Price shall be based on written 10.2. If OWNER and CONTRACTOR are unable to agree as to the extent, if any, of an increase or decrease in the notice delivered by the party making the claim to the other Contract Price or an extension or shortening of the Contract party and to ENGINEER promptly (but in no event later than Change, a claim may be made thearesfor as prov ided in Aicle the claim and stating the general nature of the claim. Notice T hang e, a c aima be a de thirty days) after the occurrence of the event giving rise to Change a claim may be made therefor as provided in Article 12. of the amount of the claim with supporting data shall be delivered within sixty days after such occurrence (unless ENGINEER allows an additional period of time to ascertain 10.3. CONTRACTOR shall not be entitled to an increase in 10.3. CONTRACTORsha l lxnotbeentittledtoanincrease more accurate data in support of the claim) and shall be in the Contract Price or an extension of the Contract Time accompanied by claimant's written statement that the amount with respect to any Work performed that is not required by claimed covers all known amounts (direct, indirect and con- the Contract Documents as amended. modified and supple- sequential) to which the claimant is entitled as a result of the mented as provided in paragraphs 3.4 and 3.5. except in the occurrence of said event. All claims for adjustment in the I case of an emergency as provided in paragraph 6.22 and Contract Price shall be determined by ENGINEER in accor- except in the case of uncovering Work as provided in para- dance with paragraph 9.11 if OWNER and CONTRACTOR graph 13.9. cannot otherwise agree on the amount involved. No claim for an adjustment in the Contract Price will be valid if not 10.4. OWNER and CONTRACTOR shall execute appro- submitted in accordance with this paragraph 11.2. priate Change Orders (or Written Amendments) covering: 11.3. The value of any Work covered by a Change Order 10.4.1. changes in the Work which are ordered by or of any claim for an increase or decrease in the Contract OWNER pursuant to paragraph 10. 1, are required because Price shall be determined in one of the following ways: of acceptance of defective Work under paragraph 13.13 or correcting defective Work under paragraph 13.14, or are 11.3.1. Where the Work involved is covered by unit agreed to by the parties: prices contained in the Contract Documents, by applica- tion of unit prices to the quantities of the items involved 10.4.2. changes in the Contract Price or Contract Time (subject' to the provisions of paragraphs 11.9. I. through which are agreed to by the parties: and 11.9.3, inclusive). 21 I 11.3.2. By mutual acceptance of a lump sum (which to the other provisions of the Contract Documents insofar may include an allowance for overhead and profit not as applicable. necessarily in accordance with paragraph 11.6.2. 1). 11.4.4. Costs of special consultants (including but not 11.3.3. On the basis of the Cost of the Work (deter- limited to engineers, architects, testing laboratories. sur- mined as provided in paragraphs 11.4 and 11.5) plus a veyors. attorneys and accountants) employed for services CONTRACTOR's Fee for overhead and profit (deter- specifically related to the Work. mined as provided in paragraphs 11.6 and 11.7). 11.4.5. Supplemental costs including the following: Cost of the a ork-: 11.4.5.1. The proportion of necessary transporta- | tion. travel and subsistence expenses of CONTRAC- 11.4. The term Cost of the Work means the sum of all TOR's employees incurred in discharge of duties con- costs necessarily incurred and paid by CONTRACTOR in nected with the Work. the proper performance of the Work. Except as otherwise may be agreed to in writing by OWNER. such costs shall be 11... Cost. including transportation and main- in amounts no higher than those prevailing in the locality of tenance. of all materials, supplies, equipment. machin- the Project. shall include only the following items and shall ery. appliances, office and temporary facilities at the not include any of the costs itemized in paragraph 11.5: site and hand tools not owned by the workers, which are consumed in the performance of the Work. and cost 11.4.1 . Payroll costs for employees in the direct employ less market value of such items used but not consumed of CONTRACTOR in the performance of the Work under which remain the property of CONTRACTOR. schedules of job classifications agreed upon by OWNER and CONTRACTOR. Payroll costs for employees not 11.4.5.3. Rentalsofall construction equipment and employed full time on the Work shall be apportioned on machinery and the parts thereof whether rented from the basis of their time spent on the Work, Payroll costs CONTRACTOR or others in accordance with rental shall include, but not be limited to. salaries and wages agreements approved by OWNER with the advice of plus the cost of fringe benefits which shall include social ENGINEER, and the costs of transportation, loading, security contributions. unemployment, excise and payroll unloading, installation, dismantling and removal taxes. workers' or workmen's compensation, health and thereof-all in accordance with terms of said rental retirement benefits, bonuses, sick leave, vacation and hol- agreements. The rental of any such equipment, machin- iday pay applicable thereto. Such employees shall include ery or parts shall cease when the use thereof is no longer superintendents and foremen at the site. The expenses of necessary for the Work. performing Work after regular working hours, on Satur- day. Sunday or legal holidays, shall be included in the 11.4.5.4. Sales, consumer, use or similar taxes above to the extent authorized by OWNER. related to the Work, and for which CONTRACTOR is liable, imposed by Laws and Regulations. 11.4.2. Cost of all materials and equipment furnished and incorporated in the Work. including costs of trans- 11.4.5.5. Deposits lost for causes other than negli- portation and storage thereof, and Suppliers' field services gence of CONTRACTOR, any Subcontractor or any- required in connection therewith. All cash discounts shall one directly or indirectly employed by any of them or accrue to CONTRACTOR unless OWNER deposits funds for whose acts any of them may be liable. and royalty with CONTRACTOR with which to make payments, in payments and fees for permits and licenses. which case the cash discounts shall accrue to OWNER. All trade discounts, rebates and refunds and all returns 11.4.5.6. Losses and damages (and related from sale of surplus materials and equipment shall accrue expenses). not compensated by insurance or otherwise. to OWNER, and CONTRACTOR shall make provisions to the Work or otherwise sustained by CONTRACTOR so that they may be obtained. in connection with the performance and furnishing of the Work (except losses and damages within the 11.4.3. Payments made by CONTRACTOR to the deductible amounts of property insurance established Subcontractors for Work performed by Subcontractors. by OWNER in accordance with paragraph 5.9). pro- If required by OWNER, CONTRACTOR shall obtain vided they have resulted from causes other than the competitive bids from Subcontractors acceptable to CON- negligence of CONTRACTOR, any Subcontractor, or TRACTOR and shall deliver such bids to OWNER who anyone directly or indirectly employed by any of them will then determine. with the advice of ENGINEER. which or for whose acts any of them may be liable. Such bids will be accepted. If a subcontract provides that the losses shall include settlements made with the written Subcontractor is to be paid on the basis of Cost of the consent and approval of OWNER. No such losses. Work Plus a Fee, the Subcontractor's Cost of the Work damages and expenses shall be included in the Cost of shall be determined in the same manner as CONTRAC- the Work for the purpose of determining CONTRAC- TOR's Cost of the Work. All subcontracts shall be subject TOR's Fee. If, however, any such loss or damage 22 I requires reconstruction and CONTRACTOR is placed CONTRACTOR's Fee: in charge thereof, CONTRACTOR shall be paid for 11.6. The CONTRACTOR's Fee allowed to CONTRAC- services a fee proportionate to that stated in paragraph TOR for overhead and profit shall be determined as follows: 1 1.6.2. . 11.6.1. a mutually acceptable fixed fee: or if none can 11.4.5.7. The cost of utilities. fuel and sanitary beagreedupon facilities at the site. be agreed upon, 11.4.5.8, Minor expenses such as telegrams. long 11.4.5.8. Min~or expenses such as telegrams, long 11.6.2. a fee based on the following percentages of the distance telephone calls. telephone service at the site. various portions of the Cost of the Work: expressage and similar petty cash items in connection *ith the Work. 11.6.2. 1. for costs incurred under paragraphs 11.4.1 and 11.4.2. the CONTRACTOR's Fee shall be fifteen 11.4.5.9. Cost of premiums for additional Bonds percent; and insurance required because of changes in the Work and premiums for property insurance coverage within 11.6.2.2. for costs incurred under paragraph 11.4.3. the limits of the deductible amounts established by the CONTRACTOR's Fee shall be five percent: and if OWNER in accordance with paragraph 5.9. a subcontract is on the basis of Cost of the Work Plus a Fee. the maximum allowable to CONTRACTOR on 11.5. The term Cost of the Work shall not include any of account of overhead and profit of all Subcontractors the following: shall be fifteen percent; 11.5.1. PyrolcostsandothercopensationofCON- 11.6.2.3. no fee shall be payable on the basis of TRACTOR's officers. executives. principals (of partner- costs itemized under paragraphs 11.4.4. 11.4.5 and 11.5: ship and sole proprietorships). general managers. engi- neers, architects. estimators. attorneys, auditors. accoun- 11.6.2.4. the amount of credit to be allowed by tants. purchasing and contracting agents. expeditors, CONTRACTOR toOWNERforanysuchchangewhic timekeepers. clerks and other personnel employed by results in a net decrease in cost will be the amount of CONTRACTOR whether at the site or in CONTRAC- the actual net decrease plus a deduction in CONTRAC- TOR's principal or a branch office for general administra- TOR's Fee by ar amount equal to ten percent of the tion of the Work and not specifically included in the agreed net decrease, and upon schedule of job classifications referred to in para- graph 11.4.1 or specifically covered by paragraph 11.4.4- 11.6.2.5. when both additions and credits are all of which are to be considered administrative costs involved in any one change, the adjustment in CON- covered by the CONTRACTOR's Fee. covered by the CONTRACTOR's Fee. TRACTOR's Fee shall be computed on the basis of the 11.5.2. Expenses of CONTRACTOR's principal and net change in accordance with paragraphs 11.6.2.1 1 1.5.2.Expenses of CONTRACTOR's principal and branch offices other than CONTRACTOR's office at the through 11.6.2.4. inclusive. I site. 11.7. Whenever the cost of any Work is to be determined 11.5.3. Any partofCONTRACTOR's capital expenses. pursuant to paragraph 11.4 or 11.5, CONTRACTOR will including interest on CONTRACTOR'S capital employed submit in form acceptable to ENGINEER an itemized cost for the Work and charges against CONTRACTOR for breakdown together with supporting data. delinquent payments. Cash Allowances: 11.5.4. Cost of premiums for all Bonds and for all insurance whether or not CONTRACTOR is required by 11.8. It is understood that CONTRACTOR has included the Contract Documents to purchase and maintain the in the Contract Price all allowances so named in the Contract same (except for the cost of premiums covered by sub- Documents and shall cause the Work so covered to be done paragraph 1 1.4.5.9 above). by such Subcontractors or Suppliers and for such sums within the limit of the allowances as may be acceptable to ENGI- 11.5.5. Costs due to the negligence of CONTRAC- NEER. CONTRACTOR agrees that: TOR. any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them 11.8.1. The allowances include the cost to CON- may be liable, including but not limited to. the correction TRACTOR (less any applicable trade discounts) of mate- of defictive Work, disposal of materials or equipment rials and equipment required by the allowances to be deliv- wrongly supplied and making good any damage to prop- ered at the site. and all applicable taxes: and erty. erty. 11.8.2. CONTRACTOR's costs for unloading and 11.5.6. Other overhead or general expense costs of handling on the site. labor, installation costs, overhead. any kind and the costs of any item not specifically and profit and other expenses contemplated for the allowances expressly included in paragraph 11.4. have been included in the Contract Price and not in the 23 I allowances. No demand for additional payment on account shall be determined by ENGINEER in accordance with para-I of any thereof will be valid. graph 9. 11 if OWNER and CONTRACTOR cannot otherwise agree. No claim for an adjustment in the Contract Time will Prior to final payment, an appropriate Change Order will be be valid if not submitted in accordance with the requirementsI issued as recommended by ENGINEER to reflect actual of this paragraph 12. I. amounts due CONTRACTOR on account of Work covered by allowances, and the Contract Price shall be correspond- 12.2. The Contract Time will be extended in an amount ingly adjusted. equal to time lost due to delays beyond the control of CON- TRACTOR if a claim is made therefor as provided in para- Unit Price Work: ~~~~~~~~graph 12.1I. Such delays shall include, but not be limited to, Unit Price 1i'ork: ~~~~~~acts or neglect by OWNER or others performing additional 1 1.9. 1. Where the Contract Documents provide that work as contemplated by Article 7, or to fires, floods, laborI all or part of the Work is to be Unit Price Work, initially disputes, epidemics, abnormal weather conditions or acts of the Contract Price will be deemed to include for all Unit God. Price Work an amount equal to the sum of the established unit prices for each separately identified item of Unit Price 12.3. All time limits stated in the Contract DocumentsI Work times the estimated quantity of each item as indi- are of the essence of the Agreement. The provisions of this cated in the Agreement. The estimated quantities of items Article 12 shall not exclude recovery for damages (including of Unit Price Work are not guaranteed and are solely for but not limited to fees and charges of engineers, architects,I the purpose of comparison of Bids and determining an attorneys and other professionals and court and arbitration initial Contract Price. Determinations of the actual quan- costs) for delay by either party. tities and classifications of Unit Price Work performed by CONTRACTOR will be made by ENGINEER in accor-I dance with Paragraph 9. 10. 11.9.2. Each unit price will be deemed to include an ARTICLE 13-WARRANTY AND GUARANTEE; amount considered by CONTRACTOR to be adequate to TESTS AND INSPECTIONS; cover CONTRACTOR's overhead and profit for each sep- CORRECTION, REMOVAL OR arately identified item. ACCEPTANCE OF DEFECTIVE WORK 11.9.3. Where the quantity of any item of Unit PriceI Work performed by CONTRACTOR differs materially Warranty and Guarantee: and significantly from the estimated quantity of such item 13. 1. CONTRACTOR warrants and guarantees to indicated in the Agreement and there is no corresponding OWNER and ENGINEER that all Work will be in accor-I adjustment with respect to any other item of Work and if dance with the Contract Documents and will not be defective. CONTRACTOR believes that CONTRACTOR has Prompt notice of all defects shall be given to CONTRAC- incurred additional expense as a result thereof, CON- TOR. All defective Work, whether or not in place, may be TRACTOR may make a claim for an increase in the Con- rejected, corrected or accepted as provided in this Article 13.I tract Price in accordance with Article I I if the parties are unable to agree as to the amount of any such increase. Access to Work: 13.2. ENGINEER and ENGINEER's representatives,I ARTICLE 12-CHANGE OF CONTRACT TIME other representatives of OWNER, testing agencies and gov- ernmental agencies with jurisdictional interests will have access to the Work at reasonable times for their observation, inspecting 12. 1. The Contract Time may only be changed by a Change and testing. CONTRACTOR shall provide proper and safe Order or a Written Amendment. Any claim for an extension conditions for such access. or shortening of the Contract Time shall be based on written notice delivered by the party making the claim to the other TssadInsetos party and to ENGINEER promptly (but in no event later than Tssadisetos thirty days) after the occurrence of the event giving rise to 13.3. CONTRACTORshalIgiveENGINEERtimelynotice the claim and stating the general nature of the claim. Notice of readiness of the Work for all required inspections, tests or of the extent of the claim with supporting data shall be deliv- approvals.I ered within sixty days after such occurrence (unless ENGI- NEER allows an additional period of time to ascertain more 13.4. If Laws or Regulations of any public body having accurate data in support of the claim) and shall be accom- jurisdiction require any Work (or part thereof) to specifically panied by the claimant's written statement that the adjust- be inspected, tested or approved, CONTRACTOR shallI ment claimed is the entire adjustment to which the claimant assume full responsibility therefor. pay all costs in connection has reason to believe it is entitled as a result of the occurrence therewith and furnish ENGINEER the required certificates of said event. All claims for adjustment in the Contract Time of inspection, testing or approval. CONTRACTOR shall alsoI 24 be responsible for and shall pay all costs in connection with thereof, CONTRACTOR may make a claim therefor as pro- any inspection or testing required in connection with OWN- vided in Articles 11 and 12. ER's or ENGINEER's acceptance of a Supplier of materials or equipment proposed to be incorporated in the Work, or of Owner May Stop the Work: materials or equipment submitted for approval prior to CON- 13.10. If the Work is defectiie, or CONTRACTOR fails TRACTOR's purchase thereof for incorporation in the Work. TRACTOR's purchase thereof for incorporation in the Work to supply sufficient skilled workers or suitable materials or The cost of all inspections, tests and approvals in addition to equipment, or fails to furnish or perform the Work in such a the above which are required by the Contract Documents way that the completed Work will conform to the Contract shall be paid by OWNER (unless otherwise specified). Documents. OWNER may order CONTRACTOR to stop the Work, or any portion thereof, until the cause for such order 13.5. All inspections. tests or approvals other than those has been eliminated; however, this right of OWNER to stop required by Laws or Regulations of any public body having the Work shall not give rise to any duty on the part of OWNER jurisdiction shall be performed by organizations acceptable to exercise this right for the benefit of CONTRACTOR or to OWNER and CONTRACTOR (or by ENGINEER if so any other party. specified). 13.6. If any Work (including the work of others) that is Correction or Removal ofDefective Work: to be inspected. tested or approved is covered without written 13.11. If required by ENGINEER, CONTRACTOR shall concurrence of ENGINEER. it must, if requested by ENGI- promptly, as directed, either correct all defiective Work, NEER, be uncovered for observation. Such uncovering shall whether or not fabricated, installed or completed. or, if the be at CONTRACTOR's expense unless CONTRACTOR has Work has been rejected by ENGINEER. remove it from the given ENGINEER timely notice of CONTRACTOR's inten- site and replace it with nondefective Work. CONTRACTOR tion to cover the same and ENGINEER has not acted with shall bear all direct, indirect and consequential costs of such reasonable promptness in response to such notice. correction or removal (including but not limited to fees and charges of engineers, architects, attorneys and other profes- 13.7. Neither observations by ENGINEER nor inspec- sionals) made necessary thereby. tions, tests or approvals by others shall relieve CONTRAC- TOR from CONTRACTOR's obligations to perform the Work in accordance with the Contract Documents. One Year Correcton Perod: 1 in accordance with the Contract Documents. 13.12. If within one year after the date of Substantial Completion or such longer period of time as may be pre- scribed by Laws or Regulations or by the terms of any appli- Uncovering Work: cable special guarantee required by the Contract Documents 13.8. If any Work is covered contrary to the written request or by any specific provision of the Contract Documents, any of ENGINEER, it must, if requested by ENGINEER, be Work is found to be defective. CONTRACTOR shall promptly, uncovered for ENGINEER's observation and replaced at without cost to OWNER and in accordance with OWNER's CONTRACTOR's expense. written instructions, either correct such defective Work, or, if it has been rejected by OWNER, remove it from the site 13.9. If ENGINEER considers it necessary or advisable and replace it with nondefective Work. If CONTRACTOR that covered Work be observed by ENGINEER or inspected does not promptly comply with the terms of such instructions, I or tested by others, CONTRACTOR. at ENGINEER's or in an emergency where delay would cause serious risk of request, shall uncover. expose or otherwise make available loss or damage, OWNER may have the defective Work cor- for observation, inspection or testing as ENGINEER may rected or the rejected Work removed and replaced. and all require. that portion of the Work in question, furnishing all direct, indirect and consequential costs of such removal and necessary labor. material and equipment. If it is found that replacement (including but not limited to fees and charges of such Work is defective. CONTRACTOR shall bear all direct, engineers, architects, attorneys and other professionals) will sure. observation. inspection and testing and of satisfactory a particular item of equipment is placed in continuous service reconstruction, (including but not limited to fees and charges before Substantial Completion of all the Work, the correction of engineers, architects. attorneys and other professionals), period for that item may start to run from an earlier date if and OWNER shall be entitled to an appropriate decrease in so provided in the Specifications or by Written Amendment. the Contract Price, and, if the parties are unable to agree as to the amount thereof, may make a claim therefor as provided in Article II. If, however. such Work is not found to be Acceptance of Defective Work: deJective, CONTRACTOR shall be allowed an increase in 13.13. If, instead of requiring correction or removal and the Contract Price or an extension of the Contract Time, or replacement of defective Work, OWNER land. prior to both, directly attributable to such uncovering. exposure, ENGINEER's recommendation of final payment. also observation, inspection. testing and reconstruction: and, if ENGINEER) prefers to accept it, OWNER may do so. CON- the parties are unable to agree as to the amount or extent TRACTOR shall bear all direct, indirect and consequential 25 costs attributable to OWNER's evaluation of and determi- ARTICLE 14-PAYMENTS TO CONTRACTOR AND nation to accept such defective Work (such costs to be approved COMPLETION by ENGINEER as to reasonableness and to include but not be limited to fees and charges of engineers, architects, attor- Schedule of Values: neys and other professionals). If any such acceptance occurs prior to ENGINEER's recommendation of final payment. a 14. 1. The schedule of values established as provided in Change Order will be issued incorporating the necessary revi- paragraph 2.9 will serve as the basis for progress payments sions in the Contract Documents ' ith respect to the Work; and will be incorporated into a form of Application for Pay- and OWNER shall be entitled to an appropriate decrease in ment acceptable to ENGINEER. Progress payments on the Contract Price. and. if the parties are unable to agree as account of Unit Price Work will be based on the number of to the amount thereof. OWNER may make a claim therefor units completed. as provided in Article I 1. If the acceptance occurs after such recommendation. an appropriate amount will be paid by Application for Progress Payment: CONTRACTOR to OWNER. 14.2. At least twenty days before each progress payment is scheduled (but not more often than once a month). CON- TRACTOR shall submit to ENGINEER for review an Appli- OWN}^:ER aMlay Correct Defective lWoork: cation for Payment filled out and signed by CONTRACTOR 13.14 If C(ONTRACTOR fails within a reasonable time coveringthe Work completed as of the date of the Application after written notice of ENGINEER to proceed to correct and required by the Contract D ocument ation s is required by the Contract Documents. If payment is requested to correct ds/ 'triv e Work or to remove and replace rejected on the basis of materials and equipment not incorporated in reWork as required by ENGI:N<.EER in accordance with para- the Work but delivered and suitably stored at the site or at graph 13.1 1. or if CONTRACTOR fail" to perform the Work another location agreed to in writing. the Application for in accordance with the Contract Documents, or if CON- Payment shall also be accompanied by a bill of sale. invoice TRACTOR fails to comply x ith any other p; ox ision of the or other documentation warranting that OWNER has received Contract Documents. OWNER may. after seven dabys' writ- the materials and equipment free and clear of all liens, charges. ten notice to CONTRACTOR. correct and rermedv any such security interests and encumbrances (which are hereinafter deficiency. In exercising the rights and remedies under this in these General Conditions referred to as 'Liens") and paragraph OWNER shall proceed expeditiously. To the extent evidence that the materials and equipment are covered by necessary to complete corrective and remedial action. OWNER appropriate property insurance and other arrangements to may exclude CONTRACTOR from all or part of the site, take protect OWNER's interest therein, all of which will be sat- possession of all or part of the Work, and suspend CON- isfactory to OWNER. The amount of retainage with respect TRACTOR's services related thereto, take possession of to progress payments will be as stipulated in the Agreement. CONTRACTOR's tools, appliances, construction equipment and machinery at the site and incorporate in the Work all materials and equipment stored at the site or for which OWNER CONTRACTOR's Warranty of Title: has paid CONTRACTOR but which are stored elsewhere. 14.3. CONTRACTOR warrants and guarantees that title CONTRACTOR shall allow OWNER, OWNER's represen- to all Work, materials and equipment covered by any Appli- tatives, agents and employees such access to the site as may cation for Payment, whether incorporated in the Project or be necessary to enable OWNER to exercise the rights and will pass to OWNER no later than the time of payment remedies under this paragraph. All direct, indirect and con- free and clear of all Liens. sequential costs of OWNER in exercising such rights and remedies will be charged against CONTRACTOR in an amount approved as to reasonableness by ENGINEER, and a Change Review of Applications for Progress Payment: Order will be issued incorporating the necessary revisions in 14.4. ENGINEER will, within ten days after receipt of the Contract Documents with respect to the Work: and each Application for Payment. either indicate in writing a OWNER shall be entitled to an appropriate decrease in the recommendation of payment and present the Application to Contract Price. and, if the parties are unable to agree as to OWNER, or return the Application to CONTRACTOR indi- the amount thereof. OWNER may make a claim therefor as cating in writing ENGINEER's reasons for refusing to rec- provided in Article I 1. Such direct. indirect and consequen- ommend payment. In the latter case. CONTRACTOR may tial costs will include but not be limited to fees and charges make the necessary corrections and resubmit the Applica- of engineers, architects, attorneys and other professionals, tion. Ten days after presentation of the Application for Pay- all court and arbitration costs and all costs of repair and ment with ENGINEER's recommendation, the amount rec- replacement of work of others destroyed or damaged by ommended will (subject to the provisions of the last sentence correction, removal or replacement of CONTRACTOR's of paragraph 14.7) become due and when due will be paid by defective Work. CONTRACTOR shall not be allowed an OWNER to CONTRACTOR. extension of the Contract Time because of any delay inper- formance ofthe Work attributable to the exercise by OWNER 14.5. ENGINEER's recommendation of any payment of OWNER's rights and remedies hereunder. requested in an Application for Payment will constitute a 26 I representation by ENGINEER to OWNER, based on ENGI- OWNER to a set-off against the amount recommended, but NEER's on-site observations of the Work in progress as an OWNER must give CONTRACTOR immediate written notice experienced and qualified design professional and on ENGI- (with a copy to ENGINEER) stating the reasons for such NEER's revieNw of the Application for Payment and the action. accompanying data and schedules that the Work has pro- gressed to the point indicated: that, to the best of ENGI- NEER's knowledge. information and belief. the quality of SubstantialCompletion: the Work is in accordance with the Contract Documents 14.8. When CONTRACTOR considers the entire Work (subject to an evaluation of the Work as a functioning whole ready for its intended use CONTRACTOR shall notify prior to or upon Substantial Completion, to the results of any OWNER and ENGINEER in writing that the entire Work is subsequent tests called for in the Contract Documents, to a substantially complete (except for items specifically listed by final determination of quantities and classifications for Unit CONTRACTOR as incomplete) and request that ENGI- Price Work under paragraph 9.10. and to any other qualifi- NEER issue a certificate of Substantial Completion. Within cations stated in the recommendation): and that CONTRAC- a reasonable time thereafter, OWNER. CONTRACTOR and TOR is entitled to payment of the amount recommended. ENGINEER shall make an inspection of the Work to deter- However. by recommending any such payment ENGINEER mine the status of completion. If ENGINEER does not con- will not thereby be deemed to have represented that exhaus- sider the Work substantially complete, ENGINEER will notify tive or continuous on-site inspections have been made to CONTRACTOR in writing giving the reasons therefor. If check the quality or the quantity of the Work beyond the ENGINEER considers the Work substantially complete, responsibilities specifically assigned to ENGINEER in the ENGINEER will prepare and deliver to OWNER a tentative Contract Documents or that there may not be other matters certificate of Substantial Completion which shall fix the date or issues between the parties that might entitle CONTRAC- of Substantial Completion. There shall be attached to the TOR to be paid additionally by OWNER or OWNER to certificate a tentative list of items to be completed or cor- withhold payment to CONTRACTOR. rected before final payment. OWNER shall have seven days after receipt of the tentative certificate during which to make 14.6. ENGINEER's recommendation of final payment written objection to ENGINEER as to any provisions of the will constitute an additional representation by ENGINEER certificate or attached list. If, after considering such objec- to OWNER that the conditions precedent to CONTRAC- tions, ENGINEER concludes that the Work is not substan- TOR's being entitled to final payment as set forth in paragraph tially complete, ENGINEER will within fourteen days after 14.13 have been fulfilled. submission of the tentative certificate to OWNER notify CONTRACTOR in writing, stating the reasons therefor. If, 14.7. ENGINEER may refuse to recommend the whole after consideration of OWNER's objections, ENGINEER or any part of any payment if, in ENGINEER's opinion. it considers the Work substantially complete, ENGINEER will would be incorrect to make such representations to OWNER. within said fourteen days execute and deliver to OWNER ENGINEER may also refuse to recommend any such pay- and CONTRACTOR a definitive certificate of Substantial ment, or, because of subsequently discovered evidence or Completion (with a revised tentative list of items to be com- the results of subsequent inspections or tests, nullify any such pleted or corrected) reflecting such changes from the tentative payment previously recommended, to such extent as may be certificate as ENGINEER believes justified after consider- necessary in ENGINEER's opinion to protect OWNER from ation of any objections from OWNER. At the time of delivery loss because: of the tentative certificate of Substantial Completion ENGI- NEER will deliver to OWNER and CONTRACTOR a written 14.7.1. the Work is defe(tie, or completed Work has recommendation as to division of responsibilities pending been damaged requiring correction or replacement, final payment between OWNER and CONTRACTOR with respect to security, operation, safety, maintenance. heat. 14.7.2. the Contract Price has been reduced by Writ- utilities, insurance and warranties. Unless OWNER and ten Amendment or Change Order. CONTRACTOR agree otherwise in writing and so inform ENGINEER prior to ENGINEER's issuing the definitive 14.7.3. OWNER has been required to correct defec- certificate of Substantial Completion, ENGINEER's afore- tive Work or complete Work in accordance with paragraph said recommendation will be binding on OWNER and CON- 13.14, or TRACTOR until final payment. 14.7.4. of ENGINEER's actual knowledge of the 14.9. OWNER shall have the right to exclude CON- occurrence of any of the events enumerated in paragraphs TRACTOR from the Work after the date of Substantial Com- 15.o2.1 through 15.2.9 inclusive. pletion, but OWNER shall allow CONTRACTOR reasonable access to complete or correct items on the tentative list. OWNER may refuse to make payment of the full amount recommended by ENGINEER because claims have been made against OWNER on account of CONTRACTOR's per- Partial Utilization: formance or furnishing of the Work or Liens have been filed 14.10. Use by OWNER of any finished part of the Work. in connection with the Work or there are other items entitling which has specifically been identified in the Contract Docu- 27 ments, or which OWNER, ENGINEER and CONTRAC- 14.10.3. No occupancy or separate operation of part TOR agree constitutes a separately functioning and useable of the Work will be accomplished prior to compliance with part of the Work that can be used by OWNER without sig- the requirements of paragraph 5.15 in respect of property nificant interference with CONTRACTOR's performance of insurance. the remainder of the Work. may be accomplished prior to Substantial Completion of all the Work subject to the follow- ing: Final Inspection: 14.11. Upon written notice from CONTRACTOR that the 14.10.1 . OWNER at any time may request CON- entire Work or an agreed portion thereof is complete, ENGI- TRACTOR in writing to permit OWNER to use any such NEER will make a final inspection with OWNER and CON- part of the Work which OWNER believes to be ready for TRACTOR and will notify CONTRACTOR in writing of all its intended use and substantially complete. If CON- particulars in which this inspection reveals that the Work is TRACTOR agrees. CONTRACTOR will certify to OWNER incomplete or defective. CONTRACTOR shall immediately and ENGINEER that said part of the Work is substantially take such measures as are necessary to remedy such defi- complete and request ENGINEER to issue a certificate of ciencies. Substantial Completion for that part of the Work. CON- TRACTOR at any time may notify OWNER and ENGI- N EER in writing that CONTRACTOR considers any such part of the Work ready for its intended use and substan- tially complete and request ENGINEER to issue a certif- 14.12. After CONTRACTOR has completed all such cor- icate of Substantial Completion for that part of the Work. rections to the satisfaction of ENGINEER and delivered all Within areasonable time aftereithersuch request, OWNER, maintenance and operating instructions, schedules, guaran- CONTRACTOR and ENGINEER shall make an inspec- tees, Bonds, certificates of inspection, marked-up record tion of that part of the Work to determine its status of documents (as provided in paragraph 6.19) and other docu- completion. If ENGINEER does not consider that part of ments-all as required by the Contract Documents, and after the Work to be substantially complete, ENGINEER will ENGINEER has indicated that the Work is acceptable (sub- notify OWNER and CONTRACTOR in writing giving the ject to the provisions of paragraph 14.16). CONTRACTOR reasons therefor. If ENGINEER considers that part of the may make application for final payment following the pro- Work to be substantially complete, the provisions of para- cedure for progress payments. The final Application for Pay- graphs 14.8 and 14.9 will apply with respect to certification ment shall be accompanied by all documentation called for of Substantial Completion of that part of the Work and the in the Contract Documents, together with complete and legally division of responsibility in respect thereof and access effective releases or waivers (satisfactory to OWNER) of all thereto. Liens arising out of or filed in connection with the Work. In lieu thereof and as approved by OWNER, CONTRACTOR 14.10.2. OWNER may at any time request CON- may furnish receipts or releases in full; an affidavit of CON- TRACTOR in writing to permit OWNER to take over TRACTOR that the releases and receipts include all labor. operation of any such part of the Work although it is not services, material and equipment for which a Lien could be substantially complete. A copy of such request will be filed. and that all payrolls, material and equipment bills, and sent to ENGINEER and within a reasonable time there- other indebtedness connected with the Work for which after OWNER, CONTRACTOR and ENGINEER shall OWNER or OWNER's property might in any way be respon- make an inspection of that part of the Work to determine sible. have been paid or otherwise satisfied: and consent of its status of completion and will prepare a list of the items the surety, if any. to final payment. If any Subcontractor or remaining to be completed or corrected thereon before Supplier fails to furnish a release or receipt in full, CON- final payment. If CONTRACTOR does not object in writ- TRACTOR may furnish a Bond or other collateral satisfac- ing to OWNER and ENGINEER that such part of the tory to OWNER to indemnify OWNER against any Lien. Work is not ready for separate operation by OWNER. ENGINEER will finalize the list of items to be completed or corrected and will deliver such list to OWNER and FinalPaymentandAcceptance: CONTRACTOR together with a written recommendation 14.13. If, on the basis of ENGINEER's observation of as to the division of responsibilities pending final payment the Work during construction and final inspection, and between OWNER and CONTRACTOR with respect to ENGINEER's review of the final Application for Payment security. operation, safety, maintenance, utilities. insur- and accompanying documentation-all as required by the ance. warranties and guarantees for that part of the Work Contract Documents, ENGINEER is satisfied that the Work which will become binding upon OWNER and CON- has been completed and CONTRACTOR's other obligations TRACTOR at the time when OWNER takes over such under the Contract Documents have been fulfilled, ENGI- operation (unless they shall have otherwise agreed in writ- NEER will, within ten days after receipt of the final Appli- ing and so informed ENGINEER). During such operation cation for Payment, indicate in writing ENGINEER's rec- and prior to Substantial Completion of such part of the ommendation of payment and present the Application to Work, OWNER shall allow CONTRACTOR reasonable OWNER for payment. Thereupon ENGINEER will give access to complete or correct items on said list and to written notice to OWNER and CONTRACTOR that the Work complete other related Work. is acceptable subject to the provisions of paragraph 14.16. 28 Otherwise. ENGINEER will return the Application to CON- CONTRACTOR's continuing obligations under the Con- TRACTOR, indicating in writing the reasons for refusing to tract Documents; and recommend final payment. in which case CONTRACTOR shall make the necessary corrections and resubmit the Appli- 14.16.2. a waiver of all claims by CONTRACTOR cation. Thirty days after presentation to OWNER of the against OWNER other than those previously made in writ- Application and accompanying documentation. in appropri- ing and still unsettled. ate form and substance. and with ENGINEER's recommen- dation and notice of acceptability. the amount recommended by ENGINEER will become due and will be paid by OWNER ARTICLE IS-SUSPENSION OF WORK AND TERMINATION 14.14. If. through no fault of CONTRACTOR. final com- pletion of the Work is significantly delayed and if ENGI- O"nerMaySuspend 'ork: NEER so confirms. OWNER shall. upon receipt of CON- 15.1. OWNER may. at any time and without cause. sus- TRACTOR's final Application for Payment and recommen- pend the Work or any. portion thereof for a period of not more dation of ENGINEER. and without terminating the Agree- than ninety days by notice in writing to CONTRACTOR and the Work fully completed and accepted. If the remaining resumed. CONTRACTOR shall resume the Work on the date balance to be held by OWNER for Work not fully completed so fixed. CONTRACTOR shall be allowed an increase in the or corrected is less than the retainage stipulated in the Agree- Contract Price or an extension of the Contract Time. or both. ment. and if Bonds have been furnished as required in para- directly attributable to any suspension if CONTRACTOR graph 5. 1. the written consent of the surety to the payment makes an approved claim therefor as provided in Articles 11 of the balance due for that portion of the Work fully com- and 12. pleted and accepted shall be submitted by CONTRACTOR to ENGINEER with the Application for such payment. Such payment shall be made under the terms and conditions gov- OwnerMay Terminate: erning final payment, except that it shall not constitute a 15.2. Upon the occurrence of any one or more of the waiver of claims. following events: 15.2.1. if CONTRACTOR commences a voluntary case under any chapter of the Bankruptcy Code (Title I 1. United 14.15. CONTRACTOR's obligation to perform and com- States Code), as now or hereafter in effect, or if CON- plete the Work in accordance with the Contract Documents TRACTOR takes any equivalent or similar action by filing shall be absolute. Neither recommendation of any progress a petition or otherwise under any other federal or state or final payment by ENGINEER, nor the issuance of a cer- law in effect at such time relating to the bankruptcy or tificate of Substantial Completion. nor any payment by insolvency: OWNER to CONTRACTOR under the Contract Documents. nor any use or occupancy of the Work or any part thereof by 15.2.2. if a petition is filed against CONTRACTOR OWNER. nor any act of acceptance by OWNER nor any under any chapter of the Bankruptcy Code as now or failure to do so. nor any review and approval of a Shop hereafter in effect at the time of filing. or if a petition is Drawing or sample submission. nor the issuance of a notice filed seeking any such equivalent or similar relief against of acceptability by ENGINEER pursuant to paragraph 14.13. CONTRACTOR under any other federal or state lax, in nor any correction of de lctive Work by OWNER will con- effect at the time relating to bankruptcy or insolvency: stitute an acceptance of Work not in accordance with the Contract Documents or a release of CONTRACTOR's obli- 15.2.3. if CONTRACTORmakesageneralassignmen' gation to perform the Work in accordance with the Contract for the benefit of creditors: Documents (except as provided in paragraph 14.161. 15.2.4. if a trustee. receiver. custodian or agent of W 9'cuaivhter of Claims: provided in paragraph 14.16)CONTRACTOR is appointed under applicable law or under contract. whose appointment or authority to take charge 14.16. The making and acceptance of final payment will of property of CONTRACTOR is for the purpose of constitute: enforcing a Lien against such property or for the purpose of general administration of such property for the benefit 14.16.1. a waiver of all claims by OWNER against of CONTRACTOR's creditors: CONTRACTOR. except claims arising from unsettled Liens. from dcelidctive Work appearing after final inspec- 15.2.5. if CONTRACTOR admits in writing an inabil- tion pursuant to paragraph 14.11 or from failure to comply ity to pay its debts generally as they become due: with the ('ontract Documents or the terms of any special guarantees specified therein: however. it will not consti- 15.2.6. ifCONTRACTOR persistently fails to perform tute ia a:iver Oy (WNER ofl any rights in respect of the Work in accordance with the Contract Documents 29 I 1including. but not limited to, failure to supply sufficient 15.3. Where CONTRACTOR's services have been so skilled workers or suitable materials or equipment or terminated by OWNER, the termination will not affect any failure to adhere to the progress schedule established under rights or remedies of OWNER against CONTRACTOR then paragraph 2.9 as revised from time to time); existing or which may thereafter accrue. Any retention or payment of moneys due CONTRACTOR by OWNER will 15.2.7. if CONTRACTOR disregards Laws or Regu- not release CONTRACTOR from liability. lations of any public body having jurisdiction; 15.4. Upon seven days' written notice to CONTRAC- 15.2.8. if CONTRACTOR disregards the authority of TOR and ENGINEER. OWNER may, without cause and ENGI NEER: or without prejudice to any other right or remedy. elect to aban- don the Work and terminate the Agreement. In such case, 15.2.9. if CONTRACTOR otherwise violates in any CONTRACTOR shall be paid for all Work executed and any substantial way any provisions of the Contract Docu- expense sustained plus reasonable termination expenses. which ments: will include, but not be limited to. direct, indirect and con- sequential costs (including. but not limited to. fees and charges OWNER may. after giving CONTRACTOR (and the surety, of engineers. architects. attorneys and other professionals if there be one) seven days' written notice and to the extent and court and arbitration costs). permitted by Laws and Regulations. terminate the services of CONTRACTOR. exclude CONTRACTOR from the site and take possession of the Work and of all CONTRACTOR's ContractorMay Stop Work or Terminate: tools. appliances, construction equipment and machinery at 15.5. If, through no act or fault of CONTRACTOR, the the site and use the same to the full extent they could be used Work is suspended for a period of more than ninety days by by CONTRACTOR (without liability to CONTRACTOR for OWNER or under an order of court or other public authority, trespass or conversion), incorporate in the Work all materials or ENGINEER fails to act on any Application for Payment and equipment stored at the site or for which OWNER has within thirty days after it is submitted, or OWNER fails for paid CONTRACTOR but which are stored elsewhere, and thirty days to pay CONTRACTOR any sum finally deter- finish the Work as OWNER may deem expedient. In such mined to be due, then CONTRACTOR may. upon seven case CONTRACTOR shall not be entitled to receive any days' written notice to OWNER and ENGINEER, terminate further payment until the Work is finished. If the unpaid the Agreement and recover from OWNER payment for all balance of the Contract Price exceeds the direct, indirect and Work executed and any expense sustained plus reasonable consequential costs of completing the Work (including but termination expenses. In addition and in lieu of terminating not limited to fees and charges of engineers, architects, attor- the Agreement, if ENGINEER has failed to act on an Appli- neys and other professionals and court and arbitration costs) cation for Payment or OWNER has failed to make any pay- such excess will be paid to CONTRACTOR. If such costs ment as aforesaid, CONTRACTOR may upon seven days' exceed such unpaid balance, CONTRACTOR shall pay the written notice to OWNER and ENGINEER stop the Work difference to OWNER. Such costs incurred by OWNER will until payment of all amounts then due. The provisions of this be approved as to reasonableness by ENGINEER and incor- paragraph shall not relieve CONTRACTOR ofthe obligations porated in a Change Order, but when exercising any rights under paragraph 6.29 to carry on the Work in accordance or remedies under this paragraph OWNER shall not be required with the progress schedule and without delay during disputes to obtain the lowest price for the Work performed, and disagreements with OWNER. [The remainder of this page was left blank intentionally.] 30 ARTICLE 16--ARBITRATION American Arbitration Association, and a copy will be sent to ENGINEER for information. The demand for arbitration will 16. 1. All claims, disputes and other matters in question be made within the thirty-day or ten-day period specified in bet-een OPWNER and CONTRACTOR arising out of. or paragraph 16.2 as applicable, and in all other cases within a relating to the Contract Documents or the breach thereof reasonable time after the claim, dispute or other matter in (except tor claims which have been waived by the making or question has arisen, and in no event shall any such demand acceptance of final payment as provided by paragraph 14. 16) be made after the date when institution of legal or equitable x ill be decided by arbitration in accordance with the Con- proceedings based on such claim. dispute or other matter in struction Indust Arbitration Rules of the American Arbi- ueson would be barred by the applicable statute of limi- tration Association then obtaining subject to the limitations tations. of this Article 16. This agreement so to arbitrate and any other agreement or consent to arbitrate entered into in accor- 16.4. No arbitration arising out of or relating to the Con- dance herewith as provided in this Article 16 will be specifi- tract Documents shall include by consolidation, joinder or in callv enforceable under the prevailing law of any court having any other manner any other person or entity (including jurisdiction. ENGINEER, ENGINEER's agents, employees or consul- tants) who is not a party to this contract unless: 16.2. No demand for arbitration of any claim. dispute or other matter that is required to be referred to ENGINEER 16.4,1. the inclusion of such other person or entity is initially for decision in accordance with paragraph 9.11 will necessary if complete relief is to be afforded among those be made until the earlier of (a) the date on which ENGINEER who are already parties to the arbitration has rendered a decision or (b) the tenth day after the parties have presented their evidence to ENGINEER if a written decision has not been rendered by ENGINEER before that 16.4.2. such other person or entity is substantially date. No demand for arbitration of any such claim, dispute involved in a question of law or fact which is common to or other matter will be made later than thirty days after the those who are already parties to the arbitration and which date on which ENGINEER has rendered a written decision will arise in such proceedings, and in respect thereof in accordance with paragraph 9.11: and the failure to demand arbitration within said thirty days' period shall result in ENGINEER's decision being final and binding16.4.3. the written consent of the other person or entity shall result in ENGINEER 's d ec isio n being final and binding sought to be included and of OWNER and CONTRAC sought to be included and of OWNER and CONTRAC- upon OWNER and CONTRACTOR. If ENGINEER renders TOR has been obtained for such inclusion, which consent a decision after arbitration proceedings have been initiated, shall make specific reference to this paragraph; but no such decision mav be entered as evidence but will not supersede such consent shall constitute consent to arbitration of any the arbitration proceedings, except where the decision is dispute not specifically described in such consent or to acceptable to the parties concerned. No demand for arbitra- arbitration with any party not specifically arbitration with any party not specifically identified in such tion of any written decision of ENGINEER rendered in accordance with paragraph 9.10 will be made later than ten days after the party making such demand has delivered writ- ten notice of intention to appeal as provided in paragraph 16.5. The award rendered by the arbitrators will be final, 9.10. judgment may be entered upon it in any court having juris- diction thereof, and will not be subject to modification or 16.3. Notice of the demand for arbitration will be filed in appeal except to the extent permitted by Sections 10 and It writing with the other party to the Agreement and with the of the Federal Arbitration Act (9 U.S.C. ��10.l 1). [The remainder of this page was left blank intentionally.] 31 I I I I I I I I I (This page was left blank intentionally.) I I I I I I I ~~~~~~~I I I ARTICLE 17--MISCELLANE()US sion or act of the other party or of any of the other party's employees or agents or others for whose acts the other party Giving Notice: is legally liable. claim will be made in vNriting to the other 17.1 . Wheneer any provision of the Con~trac-t Docui- ppiartyvithin areasonabletimeof thefirst observanceof such 17.1. Whenever any provision of the Contract Docu- ment requires the giv ing ot'f written notice, it will be deemedl injury or damage. The provisions of this paragraph 17.3 shall to hase been alidlv gien if deliclerled in preron to the di- lnot he construed as a substitute for or a xai cer of the pro- vidual or to a member of the firm or to an o'ticer of theof an! applicahle statute of limitations or repose corporation for whom it is intended. or if delivered at or sent b! registered or certified mail. postage prepaid. to the last 17.4. The duties and obligations imposed b! these Gen- business address knov n to the gi,.er of the notice. eral Conditions and the rights and remedies available here- under to the parties hereto. and. in particular but without Coniputation of Time: limitation. the sarranties. guarantees and obligations imposed 17.2.1. When an! period of time is referred to in the upon CONTRACIOR by paragraphs 6.30. 13.1. 13. 12. 13.14. Contract Documents by days. it Nw-ill be computed to exclude 14.3 and 15.2 and all of the rights and remedies av ailable to the first and include the last day of such period. Iftthe last OWNER and ENGINEER thereunder. are in addition to. day of any such period f'alls on a Saturda! or SundI!L or and are not to be construed in an.s sN a! as a limitation of. any on a day made a legal holidab by the law of the applicable rights and remedies available to any or all of them which are jurisdiction. such day Vill be omitted fromn the computa- othersise imposed or available b Las\ s or Regulations. by tion. special w.arranty or guarantee or by other provisions of the Contract Documents. and the provisions of this paragraph 17.2.2. A calendar day ot ts enty-ftour hours measured will be as effective as if repeated specifically in the Contract from midnight to the next midnight shall constitute a day. Documents in connection with each particular duty. obliga- tion. right and remedy to which they apply. All representa- General: tions. sarranties and guarantees made in the Contract Doc- 17.3. Should OWNER or CONTRACTOR suffer injury uments will survxie final payment and termination or corn- or damage to person or propert. because of any error. omis- pletion of the Agreement. SECTION 00510 SUPPLEMENTARY CONDITIONS General Conditions The "Standard General Conditions of the Construction Contract" National Society of Professional Engineers, NSPE 1910-8 (1978 Edition), Articles 1 through 17 inclusive, is a part of this contract, and is incorporated herein as fully as if here setforth. Supplements The following supplements modify, change, delete, or add to the "Standard General Conditions of the Construction Contract". Where any part of the General Conditions is modified or voided by these Sections, the unaltered provisions of that part remain in effect. Where the language of the Supple- mentary Conditions conflicts with that of the Standard General Conditions, the Supplementary Conditions shall take precedence. Contents of Supplementary Conditions Section No. Section Title SC-1 General SC-2 Insurance SC-3 Performance & Materials SC-4 Extra Work/Change Order SC-5 Compliance with Air and Water Acts SECTION SC-i GENERAL I ~ ~~~ c oveie ofrfrne the Specifications are separated into titled Divisions and Sections. Such separations shall not, however, U ~ ~~operate to make the Owner or the Engineer an arbiter to establish limits to the contracts between the Contractor and Sub-Contractors. I ~ ~B. Copies of the Contract: In addition to Contract Documents furnished to Contractor by Owner for the Contractor's use during construction, there shall be at least three (3) executed copies of the Contract Documents to be distributed by the Owner as follows: a) One (1) copy to the Owner. b) One (1) copy to the Engineer. c) One (1) copy to the Contractor. C. Default & Annulment of Contract: In addition to the provisions contained in the General Conditions of the Construction Contract, the Owner may give notice in writing to the Contractor and his surety and may suspend Work upon the occurrence of any I ~ ~~one or more of the following events: a. If the Contractor is adjudged bankrupt or insolvent; b. If the Contractor makes a general assignment for the benefit of I ~ ~~~~creditors; C. If a tr-ustee or receiver is appointed for the Contractor or for any of the Contractor's property; N ~ ~~d. If the Contractor files a petition to take advantage of any debtor's act, or to recognize under the bankruptcy or similar laws; e. If the Contractor repeatedly fails to supply sufficient skilled workmen or suitable materials or equipment; f. If the Contractor repeatedly fails to make prompt payments to Sub- Contractors or for labor, materials, or equipment; g. If the Contractor disregards laws, ordinances, rules, regulations, I. ~ ~~~or orders of any public body having jurisdiction; h. If the Contractor disregards the authority of the Engineer; i. If the Contractor otherwise viloates in any substantial way any I ~ ~~~~provisions of the Contract Documents; j. If the Contractor fails to begin the Work within the time stated in the Notice to Commence Work and completion of phases of the Work in accordance with schedules approved by the Owner: I ~ ~~k. If the Contractor discontinues the Work or fail's to resume the Work when directed by the Owner, or; i. f th.e Contractor does not perform! the Work in a manner acceptable I ~ ~~~~to the Owner. D. Non-Resident Contractors: The successful bidder, if a corporation established under laws other than the State in which the proposed construction is located, shall file, at the time of the execution of the contract, with the Owner, notice of the name of its resident attorney, appointed as required by the laws of the State in which the proposed construction is located. The successfulI bidder, if a resident of another State other than that in which the proposed construction is located and not a corporation, shall file, at the time of execution of the contract, with the Owner, a written appointment of a resident of the State in which the construction is located, having an office or place of business therein, to be his true and lawful attorney upon whom all lawful processes in any actions or proceedings against him may be served; and in such writing, which shallI set forth said attorney's place of residence, shall agree that any same legal force and validity as if served on him, and that the authority shall continue in force so long as any liability remains outstanding against him in said State. The power of attorney shall be filed in the office of the Secretary of State if required, and copies certified by the Secretary shall be sufficient evidence thereof. Such appointment shall continue in force until revoked by an instrument in writing,I designating in a like manner some other person upon whom such processes may be served, which instrument shall be filed in the manner provided herein for the original appointment.I A Non-Resident Contractor shall be deemed to be: a. A person who is not a resident in the State where the proposed I construction is to be located. b. Any partnership that has no member thereof resident in the State where the proposed construction is to be located.I C. Any corporation established under laws other than those of the State .cn which the proposed construction is located. E. Duties, Responsibilities and Limitations of the Authority of Resident Project Representative: a. General: Resident Project Representative is ENGINEER'S Agent and I shall act as directed by and under the supervision of ENGINEER. He sahll confer with ENGINEER regarding his actions. His dealings in matters pertaining to the on-site Work will in general be only with ENGINEER and CONTRACTOR. His dealings with Sub-Contractors will only be through or with 'the full knowledge of CONTRACTOR or his superintendent. He shall generally communicate with OWNER only through or as directed by ENGINEER.I b. Duties and Responsibilities! Resident Project Representative shall: 1. Schedules: Review the progress schedule, schedule of Shop Drawing submissions, schedule of values and other schedules I prepared by CONTRACTOR and consult with ENGINEER concerning their acceptability. 2, Conferences: Attend preconstruction conferences. Arrange a schedule of progress meetings and other job conferences as I ~~~~~required in consultation with ENGINEER and notify in advance those expected to attend. Attend meetings, and maintain and circulate copies of minutes thereof. SECTION SC-2 INSURANCE A. General: The Contractor shall purchase and maintain, until Final Acceptance of the work, insurance of the limits and types stated in the General Conditions of the Construction Contract and as stated below, from an insurance company acceptable to the Owners. B. Evidence of Insurance: As evidence of insurance coverage, the Owner may, in lieu of actual policies, accept official written statements from the insurance company certifying that all the insurance policies specified below are in force for the specified period. The Contractor shall submit evidence of insurance to the Owner at the time of executing the Agreement. C. Form of Insurance: Insurance shall be in such form as will protect the Contractor and Owner from all claims and liabilities for damages for bodily injury, including accidental death and for property damage, which may arise from operations under this contract, whether such operation be by himself or by anyone directly or indirectly employed by him. D. Amount of Insurance Except when otherwise stated. the amount of insurance for each policy shall be not less than: 1. Liability for bodily injury, including accidental death: a. $1,000,000 for any one person. b. $1,000,000 for each accident. 2. Liability for Property Damage: a. $500,000 for any accident b. $500,000 for all accidents E. Types of Insurance: Purchase and maintain the following types of insurance: 1. Full Workmen's Compensation insurance coverage for all persons employed by the Contractor to perform work on this project. This insurance shall be in strict accordance with the requirements of the most current laws of the State. Section SC-2-2 U ~~~~2. Bodily Injury insurance and Contractor's Protective Property Damage insurance, each including coverage for blasting explosion and injury to, or destruction of, wires, pipes, I ~~~~~conduits and similar property, appurtenant apparatus, whether public or private and collapse of, or structural injury to, any building or structure, except those on which work under this Contract is being performed. 3. Bodily Injury and Property Damage insurance covering the operation of all motor vehicles and equipment, whether or not owned by the Contractor, being operated in connection with the prosecution of the work under this Contract. 4. Contractural Liability insurance coverage in the amounts specified above. 5. An Owner's Protective Liability insurance issued to the Owner I ~~~~~~at the expense of the Contractor. 6. Property insurance including "all risk" insurance as outlined I ~~~~~~in paragraph 5.6 of the General Conditions. SECTION SC-3 PERFORMANCE & MATERIALS A. OSHA Regulations: This pro ject is subject to all of the safety and health regulations as promulgated by the U. S. Department of Labor. Contractors are urged to make themselves familiar with the requirements of these regulations. B. Fire Hydrants: Fire hydrants on or adjacent to the work area shall be kept accessible to fire apparatus at all time. C. Use of Explosives: When the use of explosives is necessary for the prosecution of the Work, exercise the utmost care not to endanger life or property. The Contractor shall be responsible for any and all damage resulting from the use of explosives. Store all explosives in a secure manner, in compliance with all State and local laws and ordinances, and legally mark all such storage places. Storage shall be limited to such quantity as may be needed for the work underway. Designate as a BLASTING AREA all sites where electric blasting caps are located and where explosive charges are being placed. Mark all blastingI areas with signs are required by law. Please signs as required by law at each end of the blasting area and3 leave in place while the above conditions prevail. Immediately remove signs after blasting operations or the storage of caps is over. Nofity each property owner and public utility company having structuresI in proximity to the site of the work sufficiently in advance to enable the companies to take such steps as they may deem necessary to protect their property. Such notice shall not relieve the Contractor of any ofI his responsibility for damage resulting from his blasting operation. Warn. all persons within the danger zone of blasting operations and do not perform blasting work until the area is cleared. Provide sufficient flagmen outside the danger zone to- stop all approaching traffic and pedestrians. Provide watchmen during the loading period and until charges have been exploded. Please adequate protective covering over allI charges before being exploded. Section SC-3 - 2 Public Utilities: I ~~~Any elevations and locations of public utilities shown on the Drawings are approximate. It shall be the responsibility of the Contractor to make final and exact determination of the locations and extend of all I ~ ~~utilities. The Contractor shall be liable for any expense resulting from any damage to any public utility. It shall be the responsibility of the Contractor to notify all utility companies and pipe line owners, whether public or private and other parties affected, of his intention to perform work in the are where such utilities are located and to endeavor to have all necessary adjustments I ~ ~~of the public or private utility fixtures, pipe lines and other uction, made as appurtenances within or adjacent to the limits of constr soon as practicable and if at all possible before work contemplated is started in the area. In general, water lines, sewer lines, gas lines, service connections, water and gas meter boxes, water and gas valve boxes, light standards, cableways, signals and other utility appurtenances within the limits of the proposed construction shall be moved by the utility involved and the Owner shall bear the full expense, if any, of this work, unless otherwise specifically stated, or if otherwise noted on the plans. Any work done upon or within the right-of-way of a railroad company shall be done under the supervision and control of said railroad company to the extend considered necessary by said company. Any additional conditions or requirements for doing work within the railroad right-of-way will be I ~ ~~set forth in the special provision. The Contractor shall bear the full expense of any charges made by said railroad company during the course of construction within the railroad right-of-way, insofar as inspectors, flagmen, etc., are concerned. E. Substitute Materials and Equipment: U ~ ~~Section 01640, "Substitutions and Product Options" is in addition to the requirements stated in the "Equivalent Materials and Equipment" part of the Standard General Conditions of the Construction Contract. I ~~F. Standards: Whenever standards and standard specifications are referred to in these I ~ ~~Specifications, they shall be the latest edition. G. Cleaning Up: I ~~~Delete Standard General Conditions of the Construction Contract paragraph 6.17 in its entirety and substitute Section 01710, "Project Cleaning" in Division I of these Specifications. All references to Standard General I ~ ~~Conditions of the Construction Contract paragraph 6.17 elsewhere in the Contract Documents shall read as referring to Section 01710 of these * ~~~Specification. EXTRA WORK/CHANGE ORDER S- A. Amount of Compensation: The Engineer may at any time by written order and without notice to the sureties require the performance of such extra work or changes in the work as may be found necessary or desirable. The amount of compensationI to be paid to the Contractor for any extra work so ordered shall be made in accordance with whichever of the following plans the Engineer elects. a. A price agreed upon between the parties and stipulated in the orderI for the extra work, b. A price based on the unit prices of the contract, or C. A price determined by adding 15% to the "reasonable cost" of theU extra work performed, sc"raobl cost" to be determined by the Engineer in accordance with the following. 1. In arriving st the "reasonable cost" for the purposes of the above, the Engineer shall include the reasonable cost to the Contractor of all materials used, of all labor common and skilled, of foreman, trucks and the fair-market rental rate forI all machinery and equipment for the period employed directly on the work. The reasonable cost for extra work shall include the cost to the Contractor of any additional insurance that may be required covering public liability for injury to persons and property, the cost of Workman's Compensation Insurance, Federal Social Security and any other costs based on payrolls and required by law. 2. The cost of extra work shall not include any cost or rental of small tools, buildings, *or any portion of the time of theI Contractor, his project supervisor or his superintendent, or any allowance for use of capital or the premium on the bond as assessed upon the amount of extra work, these items being considered covered by the fifteen percent (15%) added to theI B. Subcontractors: In the case of extra work which is done by subcontractors, whether these are under the specific contract items provided herein, or otherwise if so approved by the Engineer, the 15% added to the reasonable cost of theI work will be allowed only to the subcontractor. On such work an additional 5% of the reasonable cost (before addition of the 15%) will be paid to the Contractor for his work in directing the oper ations of theU subcontractor and for any overhead involved. SECTION SC-5 I ~~~~~~~CERTIFICATION OF NONSEGREGATED FACILITIES AND COMPLIANCE WITH AIR AND WATER ACTS A. Certification of Nonsegregated Facilities By the submission of this bid, the bidder, offeror, applicant or subcon- tractor certifies that s/he does not maintain or provide for his/her employees any segregated facility at any of his/her establishments, and that s/he does not permit employees to perform their services at any I ~ ~~location, under his/her control, where segregated facilities are main- tained. S/He certifies further that s/he willnot maintainor provide for employees any segregated facilities at any of his/her establishments, I ~ ~~ands/hewill not permit employees to perform theirservicesat any loca- tion under his/her control where segregated facilities are maintained. The bidder, offeror, applicant or subcontractor agrees that a breach of this certification is a violation of the Equal Opportunity Clause of this contract. As used in this certification, the term "segregated facili- ties" means any waiting rooms, work areas, rest rooms and wash rooms, restaurants and other eating areas, time clocks, locker rooms, and other storage or dressing areas, *transportation and housing facilities provided for employees which are segregated by explicit directive or are in fact segregated on the basis of race, color, religion, or national origin, because of habit, local custom, or otherwise. S/He further agrees that (except where s/he has obtained identical certifications from proposed subcontractors for specific time periods) s/he will obtain identical certification from proposed subcontractors prior to the award I ~ ~~of subcontracts exceeding $10,000 which are not exempt from the provi- sions of the Equal Opportunity Clause; that s/he will retain such certi- fications in his/her files; and that s/he will forward the following notice to such proposed subcontractors (except where proposed subcontrac- tors have submitted identical certifications for specific time periods). *Parking lots, drinking fountains, recreation or entertainment areas. B. Civil R ihsAct of 1964 Under Title VI of the Civil Rights Act of 1964, no person shall, on the grounds of race, color, or national origin, be excluded from participa- tion in, be denied the benefits of, or be subjected to discrimination * ~~~under any program or activity receiving Federal financial assistance. C. Section 109 of the Housing~ and Community Development Act of 1974. (a) No person in the United States shall on the ground of race, color, national origin, or sex be excluded from participation in, be denied the benefits of. or be subjected to discrimination under any program or activity funded in whole or in part with funds made available under this title. D. "Section 3" Compliance in the Provision of Training, Employment and Business Opportunities a. The work to be performed under this contract is on a project assis- ted under a program providing direct Federal financial assistance from the Department of Housing and Urban Development and is subjectI to the requirements of Section 3 of the Housing and Urban Develop- ment Act of 1968, as amended, 12 U.S.C. 1701u. Section 3 requires that to the greatest extent feasible opportunities for training and employment be given lower income residents of the project area andI contracts for work in connection with the project be awarded to business concerns which are located in. or owned in substantial part by persons residing in the area of the project.I b. The parties to this contract will comply with the provisions of said Section 3 and the regulations issued pursuant thereto by the Secre- Itary of Housing and Urban Development set forth in 24 CFR 135, and all applicable rules and orders of the Department issued thereunder prior to the execution of this contract. The parties to this con- tract certify and agree that they are under no contractual or otherI disability which would prevent them from complying with these re- quirements. c. The contractor will send to each labor organization or representa- tive of workers with which he has a collective bargaining agreement or other contract or understanding, if any, a notice advising the said labor organization or worker' representative of his commitmentsI under this Section 3 clause and shall post copies of the notice in conspicuous places available to employees and applicants for employ- ment or training. d. The contractor will include this Section 3 clause in every subcon- tract for work in connection with the project and will, at the direction of the applicant for or recipient of Federal financialI assistance, take appropriate action pursuant to the subcontraczt up on a finding that the subcontractor is in violation of regulations issued by the Secretary of Housing and Urban Development, 24 CFRI Part 135. The contractor will not subcontract with any subcontrac- tor where it has notice of knowledge that the latter has been found in violation of regulations under 24 CFR Part 135 and will not let any subcontract unless the subcontractor has first provided it withI a preliminary statement of ability to comply with the requirements of these regulations. e. Compliance with the provisions of Section 3, the regulations set forth in 24 CFR Part 135, and all applicable rules and orders of the Department issued hereunder prior to the execution of the contract, shall be a condition of the federal financial assistance provided to the project, binding upon the applicant or recipient for such assis- tance, its successors or assigns. Failure to fulfill these require- ments shall subject the applicant or recipient, its contractors andI subcontractors, its successors and assigns to those sanctions speci- fied by the grant or loan agreement or contract through which fed- eral assistance is provided, and to such sanctions as are specifiedI by 24 CFR Part 135. SAMPLE I ~~~~~~CERTIFICATION OF BIDDER REGARDING SECTION 3 AND SEGREGATED FACILITIES * ~~~Name of Prime Contractor Project Name and Number The undersigned hereby certifies that: (a) Section 3 provisions are included in the Contract. I ~~~(b) A written Section 3 plan was prepared and submitted as part of the bid proceedings (if bid equals or exceeds $1O,OOO). (c) No segregated facilities will be maintained. Name and Title of Signer (Print or Type) Signature Date E. Certification of Compliance with Air and Water Acts (Applicable to Federally assisted construction contracts and relatedI subcontracts exceeding $100,000) During the performance of -this contract, the contractor and all subcontractors shall comply with the requirements of the Clean Air Act, as amended, 42 USC 1857 et seq., the Federal Water Pollution Control Act, as amended, 33 USC 1251 et seq., and the regulations of the Environmental Protection Agency with respect thereto, at 40 CFR Part 15, as amended. In addition to the foregoing requirements, all nonexempt contractors and subcontractors shall furnish to the owner, the following: (1) A stipulation by the Contractor or subcontractors, that any facility to be utilized in the performance of any nonexempt contract orI subcontract, is not listed on the List of Violating Facilities issued by the Environmental Protection Agency (EPA) pursuant to 40 CFR 15.20. (2) Agreement by the contractor to comply with all the requirements of Section 114 of the Clean Air Act, as amended, (42 USC 1857c-8) and Section 308 of the Federal Water Pollution Control Act, as amended,I (33 USC 1318) relating to inspection, monitoring, entry, reports and information, as well as all other requirements specified in said Section 114 and Section 308, and all regulations and guidelines issued thereunder. (3) A stipulation that as a condition for the award of the contract, prompt notice will be given of any notification received from theI Director, Office of Federal Activities, EPA, indicating thata facility utilized, or to be utilized for the contract, is under consideration to be listed on the EPA List of Violating Facilities. (4) Agreement by the contractor that he will include, or cause to be included, the criteria and requirements in paragraph (1) through (4) of this sect ion in every nonexempt subcontract and requiring thatI the Contractor will take such action as the Government may direct as a means of enforcing such provisions. (5) The contractor shall permit th'e City/Town of U the Department of Housing and Urban Development, the Comptroller General of the United States, or any of their duly authorized representatives, to have access to any books, documents, papers, andI records, of the contractor which are directly pertinent to this contract for the purpose of making audit, examination, excerpts, and transcriptions. DIVISION 1 GENERAL REQUIREMENTS Scope The scope of this Division covers the general administration requirements and the general work related provisions of the Construction Contract. Contents of Division Section No. Section Title 01010 Summary of Work 01020 Coordination 01090 Abbreviations and Symbols 01150 Measurement and Payment 01310 Construction Schedules 01510 Temporary Utilities 01630 Substitutions and Product Options 01710 Project Cleaning 01810 Project Record Documents SECTION 01010 I ~~~~~~~~~SUMMARY OF WORK U Location of Work The work of this Contract is located in Portsmouth, New Hampshire at Prescott 3Park, a waterfront park along the Piscataqua River. * Work to be Done The Contractor shall furnish all materials, labor, and equipment to perform the following: I ~~Rehabilitation of approximately 120 linear feet of granite seawall. Work to include, but not be limited to, resetting of top 3 courses of granite block, installation of subsurface drainage system, and I ~ ~the construction of a concrete diaphragm wall. All brick walls, lawns, lights, fences, and other site fixtures/features disturbed during construction shall be reinstalled. See Sheets I and 2 and Prescott Park Seawall Assessment done in January, 1986 (Exhibit O 10 1 A). EXHIBIT OIOIOA City of Portsmouth New Hampshire PRESCOTT PARK SEAWALL ASSESSMENT JANUARY 1986 Prepared By: Kimball Chase Company, Inc. 40 Bridge Street Portsmouth, New Hampshire 85-1227 PRESCOTT PARK SEAWALL ASSESSMENT Prepared for: N ~~~~~~~~City of Portsmouth, New Hampshire * ~~~~~~~~~~~Prepared by: Kimball Chase Company, Inc. 40 Bridge Street I ~ ~~~~~~~~Portsmouth, NH 03801 January, 1986 TABLE OF CONTENTS Page Summary of Findings and Recommendations Location Plan I Site Plan 2 1. Description 3 2. Observed Conditions 4 3. Assessment 9 4. Conceptual Rehabilitation 10 Photograph Location Plan 11 Photographs SUMMARY OF FINDINGS AND RECOMMENDATIONS 1 1. ~~Visual and measured observation of the 106' granite seawall indicates that, since its construction in 1975, that the top 3 granite block courses have moved horizontally up to 7.8" towards the water. 2. The movement of the wall, in addition to possible drainage problems I ~ ~~~behind the wall, has caused settlement in the abutting brick walk of up to 8"1. 3. The cause of the movement and settlement appears to be a combination of poor drainage, frost heaving, failure of granite fragment between courses and/or poor construction. I ~~4. While the wall is not in eminent danger of collapse or failure, correction of the condition should be undertaken to stop any further deterioration and to decrease maintenance and improve the aesthetic quality of the area. 5. Corrective measure should include relayering of the top 3 courses of granite stone, establishing structural connections between stones, and the construction of a perimeter drainage system along the wall. .- , .' V~~~~~~~~~~~~~~~~~~~~ iS < ~~~~~~~~~N '> >-jiY\ Granite Seawall , . "- '..- -~ ~." . ,z.- ~ '~\ :'..~... ,'~< - )a,::~:\ F- OUR TREE ~~~~~~~~~~~~~~~~~~~ISLN ~~~~ -~~~~~~~~~~ ~~ISLAND 4'IL - r-\- \. H ciii -- S a '~, " i , -'i- : - - - ~ ,'/ 'r !~~ ~ S L. - -' >; S ? ,gst\SCALE: I"= .' '" t ) __-- company, inc. 40 Bridge Street Civil Portsmouth Environmental New Hampshire 03801 Engineers 603-431-2520 -)~~~~.. <.j/.... ) ~ ~ ~ ~ ~ ~ ~ ~ ~ > \\\) .. LO^TO PIERC L ~~~~I M BALL HAS company, inc. 40 Bridge Street Civil Portsmouth Environmental New Hampshire 03801 Engineers 603-431-2520 I N , PI CATAQUA GRANITE SEAWALL CHASE Engineers 603-431-2520 -2- 7 -, PORTSMOUTH PARK SEAWALL ASSESSMENT 1. DESCRIPTION The granite seawall being assessed is made up of three sections; 31' section from STA 1.5, 58.91'+ LT to STA 1.5, 27.91'; 106' section from STA 3.1, 29.59' LT to STA 109.2, 30.12' LT; and a 20' section from STA 107.7, 28.52' LT to STA 107.5, 8.6' LT. See Kimball Chase Company Existing Condition Survey of Prescott Park Seawall completed on December 19, 1985 (in folder on back cover). This section of granite seawall is a portion of a land reclaimation project completed in 1975 for the Trustees of the Trust Funds. Based on original W.P.B. & W. design plans for project 4157, the following description has been summarized: The land project involved three types of soil retaining structures; a 63'+ section of sheet pile wall with a tie-back system; a 58'+ section of rip rap embankment and a 157'+ section of granite block gravity retaining wall. All retaining structures are capped with granite cap stone to elevation +10.0' and chain link fence except for approximately 35'+ on the southerly most section of sheet pile wall which is capped with steel channel. The granite block gravity walls are abutted on the land side by an 8' brick walk at elevation +9.75. This walk pitches down from the granite wall to the land side of the walk (8' away) at a 1.0% slope. The brick walk is underlayed by a 3" concrete slab (fc' = 2500 psi, w/6x6 #10 wire). The remainder of the retaining walls are abutted by gardens and shrubs. The granite block wall is made up of 3' wide by 1'-6" deep granite cap stones underlayed by two courses of 3' wide wide by 2'-6" deep granite blocks, followed by four courses of 3' x 4' wide by 2'-6" deep granite blocks supported on a concrete pile cap foundation. All blocks are laid dry with granite fragments being used to level stone courses. The back side of the top three joints have 4"+ of cement mortar filler. A 12" concrete diaphragm wall is located behind the bottom four courses. Vertical and horizontal joints between capstones and adjacent stones are cement mortar joints with minimum thickness of 1". The foundation for the granite seawall is made up of an 8' wide by 3' deep concrete pile cap with 12" timber piles placed in two rows; the front row being batter piles (3:1) @ 3'+ O.C. and the rear row being bearing piles @ 6'+ O.C.. Pile tip elevations vary from elevation -25.0 to -32�0. The top of the concrete pile cap is at elevation -7.4. All piles were to be driven to a safe bearing load of 30 tons. Backfill material is specified as granular material behind this portion of the seawall. The actual specification for this project required that the granular backfill be porous and free of injurious amounts of organic material. --3- Compaction was to be accomplished in 8" lifts being wet and compacted to 95% density relative to ASSHTO 99. See Typical Seawall Section on Page 5. 2. OBSERVED CONDITIONS Site visLts have been made to Prescott Park in Portsmouth, New Hampshire on December 8, and 23, 1985 at high tides, and on January 9, and 10, 1986 at low tides. It should be noted that all the following observed relationships assume that the wall was constructed according to the original design plans unless otherwise noted. Vertical: The brick walk that abuts the granite seawall appears to be intact at STA 0.0, 58.91'+ LT. Unless bricks have been replaced and/or reseated, the first granite block that was placed in 1975 was slightly offset of existing block wall. The brick walk has subsided vertically relative to the top of the granite wall (assuming that the brick walk was 3" below top of wall initially) as follows: STA Lt. Offset Vertical Subsidence 0 58.91 0.00"1 0 27.90 2.00" 10 28.40 2.75" 30 28.76 5.64" 50 28.79 5.64" 70 28.82 5.64" 90 28.86 4.80" 100 28.91 5.16" 106.2 28.68 8.04" 106.2 8.60 2.00" The brick walk presently pitches up from the granite wall to the land side of the walk (8' away). This pitch varies from 0.6% to 5.0%. The granite cap stones on the 106' section are rotating about a horizontal axis parallel to the 106' section. The river side of the cap stones are dropping in elevation relative to the land side of the cap stone. Elevations on the top of the granite wall are as follows: STA Land Side River Side 10 9.65' 9.57' 30 9.69' 9.50' 50 9.65' 9.46' 70 9.65' 9.52' 90 9.62' 9.48' 100 9.62' 9.51' -4-- j-',z'CJHAIN U NK FE-NCE- - 5E~~~( DTAIL M SO - ~0.C 3 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~~~~~IDEWALK I~ ~ ~~~~~33 ZkhTTER .- ~ ~ dK~ A 4 (rTEM ~~~~~~~~~ CE.~~~~~A~~~NT ~~MOR-A PlLLeR.-Aj t Wo 5r='ry%/SE-* OM-L 5rrO,~Com~ I iI~~~~~~~~-~~~~1~~~ F ~~~~AE50vr= COMCRQTF. IAC W.I Ar Qrn3uARCD STONF, ~MAK NT, I N PLACg~ MASONRY(GRANITPQ ~~~~~~(ITEM 912 G- RANiJLAR BACKCF"~~ - -c~~~R~d'~~T F%*HWEj%,b TO 2,Q PL E 6 Al$ S4OaN a ~ ~ -~- PAXMENT UMiIT FOR 14~ ~~~~~~~~1 Om-2'%'A'M CRUSHED UCAVANE I~~'M~~W E P 40I5iTELMIT 90a7)<r- iTM-M ~ 11112 I 61-~ ~ ~ ~ ~~~~ - PLS7 -7- (usDRIVE TO ITE 9K)5 WMEWT ~ ~~~~~~~~~~~~~~RN LIA(TD OPCFO O TYPICAL SEAWALL SEC)TION I I ? 3'*t 5 ~~~~~~~~~~~~~101 3 ~ ~ ~ ~ ~ ~ RA~~~~~~1~~~~~ ~Se-LIS It does not appear that the granite wall has subsided vertically by anyI appreciable amount. It does appear that the wall constructed in 1975 was placed vertically to match the existing wall which is at elevation 9.61+. Horizontal: Two smaller sections of seawall (31' & 20') appear to be in approximately original position relatixe to secztions of wall which have exhibited noI movement and therefore assessed to be of no immediate concerti. Visual inspection and extensive survey of the 106' section of granite seawall indicates the exaggerated deflected shapes shown in figures I & 2 on page 8. The table on page 9 summarizes the horizontal data collected and reduced. It should be noted that there does not appear to be any mortar between the top cap stones and the first granite block course below. We were not able to determine if top 3 joints have 4" of cement mortar as specified.I Numerically, there is an indication that the fifth course has moved approximately 3" outward towards the river, but it is felt that this is not the case. The numerical values for the fifth course are fairly close inI magnitude which we feel indicates that the wall was either initially constructed with (a) a 6" batter or with (b) a 3" flat bow in it horizontally at the top and a 3" batter.I Based on the above two scenarios, the top cap stone has been laterally displaced either 6.5 with scenario (a) or 3.5" with scenario (b). The top of the first 2'-6" course has been laterally displaced either 7.8" with (a) or 4.8" with (b). Visual observations showed that the second 21-6" granite course has not displaced laterally as much as the first 2'-6" course and by the fourth 2'-6" course it appears the block is in approximately the correct location relativeI to the bottom courses. Drainage: On January 9 & 10, 1986, site visits were made at a low tide. The older wall to the northwest which appears to be intact has a drain pipe coming out of it at elevation +4.0+. This drain had fairly large amounts of water flowing out of it-. The newer granite wall which we are assessing did not appear to have any water flowing out of its open joints. The entire reclaimed area of land (1600+ sq. ft.) pitches slightly to theI center where there is one catch basin. Piles: No pile driving logs have been located which could indicate actual pile capacities, length, and/or tip data. -6- RIVER REFERENCE LINE IG EXAGGERATED PLAN I ~~~~~~~~~~~~~~N.TS 3 U~~~~~~~~~~~~~~ FIG, 2 I-I EXAGGERATEP SECTION N .T:7S. I~~~~~~~~~s STATION AND OFFSET DATA Top of Cap Stone .Top of First 3' Course * Top of Fifth 3' Course Estimated : Estimated : Estimated Original Original Present Movement : Original Present Movement : Original Present Movement Station 7/75 7/75 11/85 (inches) : Station 7/75 11/85 (inches) : Station 7/75 11/85 (inches) 3.10 30.92 30.92 31.09 2.0 : 3.10 30.94 : 3.10 31.09 11.80 30.97 31.25 3.3 : 11.80 30.99 : 11.80 31.14 23.60 31.04 31.53 5.9 : 23.60 31.06 31.45 4.7 : 23.60 31.21 31.53 3.9 34.00 31.10 31.64 6.5 : 34.00 31.12 31.39 3.2 : 34.00 31.27 31.39 1.5 44.70 31.16 31.66 6.0 : 44.70 31.18 31.49 3.7 : 44.70 31.33 31.49 1.9 55.20 31.22 31.69 5.6 : 55.20 31.25 31.90 7.8 : 55.20 31.39 31.61 2.6 65.60 31.29 31.68 4.7 : 65.60 31.31 31.89 7.0 : 65.60 31.45 31.68 2.8 76.20 31.35 31.75 4.8 : 76.20 31.37 31.91 6.5 : 76.20 31.51 31.83 3.8 86.70 31.41 31.75 4.1 : 86.70 31.43 31.67 2.9 : 86.70 31.57 31.75 2.1 97.30 31.47 31.81 4.1 : 97.30 31.49 31.98 5.9 : 97.30 31.64 31.98 4.1 109.20 31.54 31.54 31.62 1.0 : 109.20 31.56 : 109.20 31.71 * Based on relationship to granite block that appears to not have moved. *~ Based on offsets @ stations 3.1 & 109.2 and assumption that wall was straight initially. *** Based on estimated original offset of cap stone and a 3 inch batter. Note: Present 11/85 data for the top of the first and fifth courses at stations 23.6,34.0, and 44.7 are estimated values I ~~~3. ASSESSMENT The cause for the elevation of the top of the wall to be .4' below the design I ~ ~~plans is some combination of the following: 1. Wall was actually constructed to match existing wall which was at some elevation below +10.0'. 2. Wall has uniformly settled up to .4' due to normal consolidation and * ~~~~~additional consolidation from overloaded rear piles. If as-built pile driving logs and data could be made available, then a more exact analysis and assessment could be made of the foundation system, but it appears that this data is not available. In situ testing is very complicated, expensive, and of questionable reliability. Considering all the above, I feel the foundation system currently in place is a sufficiently stable system but * ~~should be monitored in the future for indications of future movements. The cause for the lateral displacement of the cap stones and first two 2'-6"' courses of granite block appears to be some combination of the following: 1. Improper backfill material and compaction thereof, causing moisture retention and frost heaving action over the past 10 years. This would also explain some of the subsidence of the brick walk. If I ~ ~~~~thi-s backfill contained a large amount of fine material, it could also be washing out through the open joints; also causing subsidence of the brick walk. 2. The rear row of bearing piles is moderately overloaded. This could cause rotations about the longitudinal axis of the sea wall. The bottom four courses of granite block are tied together with a 12" I ~ ~~~~concrete diaphragm wall which will keep them together during this rotation. The top 2 courses plus cap stone are not tied together, and would not rotate with the wall, therefore effectively displacing I ~ ~~~~them relative to the bottom four courses. It should be noted that the front row of piles is underloaded and is therefore taking up the overload an the rear piles. * ~~~~3. Vehicle wheel loading. 4. Any movement of the top cap and first two 2'-6" granite courses would I ~ ~~~~cause the granite fragments (used to level blocks) to also move. If some of the front fragments were actually dislodged, this would promote further lateral movements and cause apparent rotation of the * ~~~~~top cap. The 106' section of granite seawall has clearly exhibited lateral movements to an extent that remedial action is necessary to solve the structural problems I ~ ~~and return the wall to a proper level of esthetic serviceability and stability. I ~~~~~~~~~~~~-9- 4. CONCEPTUAL REHABILITATION The top cap stone and the first two 2'-6" granite block courses should be reseated to maintain original continuous wall batter and level elevation. The cap stone and first two 2'-6" courses should be tied together and then tied into the bottom courses or to an independent tie back system. A perimeter drain system should be installed into compacted free draining backfill behlfn the granite wall to relieve hydrostatic pressures and prevent further subsidence due to migration of fines in the backfill soil mass. Benchmarks should be clearly established and a monitoring system developed to establish the as-built condition of the rehabilitation and measure its performance in the future. This step must be taken due to lack of available data on the existing pile foundation. -10- PI SCATAQUA RIVER 4%' , , A. A>X /' I . \%\ �, 2 K' M BALL CHASE company, inc. 40 Bndge Street Civil Portsmouth Environmental New Hampsnire 03801 Engineers 603 431-2520 -]- -~~~~~~~~~~~~~~~~~~~~~~~~~'~~~~~~- ~~~~~~ - - -~~~~~~~f U~~~~~~~~~~~~~~~~Lm -, 4. Ri~~~~~~~~~~~~~~~~~~~~~~~~~~gn - I i~~ ~Ama U~~~~~~~~~~~~~~~~~~f-1- ~- I- , -~:- 7;A *i4 7 ~ ~ =2 71~ ~ 7ii IIa W.-~~~~~- Ni.~~~~~~~~~~~~~~~~~~~~~~~~~~~~.9 -- ran~~~~~~~ -~~~~~~~~~~~~~~~~~~~~~~0 I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~V TO - --- I ~~~~~~~~~~~~~~~~~~A- 3',.~ ~ ~~~~~~~s ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~--4 ZA a~~~~~~~~~~~~~~~~~ t _____ -r - rrI.%hQ, II .4 'p - tvI .4 -44.-.At 4 V' W t. *S V - - - -- k O.i.43tttt5% - - tt' r 4 -' z54 - I  - '-1-- -- ( rjgjr*rr..   r .. -. 5Z, -t�0- j afl .0 - - - -. - - - V - _ - - 0   -r   _ _ S tr -j)- -. --r - -. ii 4 -. --- r _ rt -  - - U .1 - I ___4 -9----- I .- __ S - Cr V - -=  - __ :91 .- ___ S   - -t  4 -. .44 4 t-r Z* ' r 4 w -4 -  4 r h - "'d-  - - I - - 4 -r - _ s;.- -- - ?)-" -s6---- - - ->;'-k - A---- -i - , ytC *949fl   *3 t 4.-' _ TI I ~~~~~~~~~SECTION 01020 COORD INATITON I PART I - GENERAL 1.1 Description A. Contractor shall coordinate all work with the Trustees of the Prescott Park I ~ ~Trust Fund and the City of Portsmouth. ~~~~~~~~~~ENOFSCIO SECTION 01090 ABBREVIATIONS AND SYMBOLS PART 1 - GENERAL 1.1 DESCRIPTION A. Where any of the following abbreviations are used in these Specifications, they shall have the meaning set forth opposite each. AASHTO American Association of State Highway and Transporta- tion Officials AC Alternating Current ACI American Concrete Institute ACP Asbestos Cement Pipe AGA American Gas Association AIC Ampere Interrupting Capacity AGMA American Gear Manufacturers Association AIEE (IEEE) American Institute of Electrical Engineers (Institute of Electrical and Electronics Engineers, Inc.) AISC American Institute of Steel Construction amp Ampere 125-16 Amer. Std. American Standard for Cast Iron Pipe Flanges and Flanged Fittings, Class 125 (ASA B16 11960) ANSI American National Standards Institute API American Petroleum Institute ASA American Standards Association ASCE American Society of Civil Engineers ASH & AE American Society of Heating and Air Conditioning Engineers ASME American Society of Mechanical Engineers ASTM American Society of Testing and Materials AWG American or Brown and Sharpe Wire Gauge AWWA American Water Works Association BOD Biochemical Oxygen Demand c.f. Cubic foot c.fom. Cubic Foot per Minute C.f.s. Cubic Foot per Second CI Cast Iron CIPRA Cast Iron Pipe Research Association CSI Construction Specifications Institute c.y. Cubic Yards DC Direct Current DEP Department of Environmental Protection DI Ductile Iron DOT Department of Transportatior. EDR Equivalent Directional Radiation EPA U.S. Environmental Protection Agency Fed. Spec. Federal Specifications issued by the Federal Supply Service of the General Service Administration, Washington, D.C. FmHA Farmers Home Administration fps Feet per Second ft. Feet 01090-2 gal. Gallons gpd Gallons per Day gpm Gallons per Minute HP Horsepower IBR Institute of Boiler and Radiator Manufacturers in. Inches inter. Interlock ISA Instrument Society of America kva Kilovolt-ampere kw Kilowatt lb. Pound max. Maximum MCB Master Car Builders MGD Million Gallons per Day Min. Minimum NBS National Bureau of Standards~ NEC National Electrical Code (Latest Edition) NEMA National Electrical Manufacturers Association NEWWA New England Water Works Association NPT National Pipe Thread OS&Y Outside Screw and Yoke PCA Portland Cement Association ppm Parts per Million % Percent psi Pounds per Square Inch psig Pounds per Square Inch Guage PVC Polyvinyl Chloride rpm Revolutions per Minute s.f. Square Foot SSPC Steel Structures Painting Council STL. W.G. U.S. Steel Wire, Washburn and Moen, American Steel and Wire Cos., or Roebling Guage Soy. Sqare Yard TDH Total Dynamic Head USAS Standards of the United States of America Standards Institute (formerly American Standards Association) USS GUAGE United States Standard Guage VC Vitrified Clay WSP Working Steam Pressure END OF SECTION SECTION 01150 MEASUREMENT AND PAYMENT PART 1 GENERAL 1.1 DESCRIPTION A. For all items other than those to be paid for by lump sum amounts, after the work is completed and before final payment is made there- fore;. the Owner's Inspector shall make final measurements to deter- mine the quantities of various items of work accepted as the basis for final settlement. The Contractor, in case of unit price items, will be paid for the actual amount of work accepted and for the actual amount of materials in place, as shown by the final measure- ments. B. All units of measurement shall be standard United States convention as applied to the specific items of work by tradition and as inter- preted by the Engineer. C. At the end of each day's work, the Contractor's Superintendent or other authorized representative of the Contractor shall meet with the Owner's Inspector and determine and agree upon quantities of unit price work accomplished and/or completed during the work day. D. The Inspector will then prepare a "Daily Progress Report" which shall be signed by both the Inspector and Contractor's Representative indicating complete agreement and approval of the quantities listed. E. Once each month the Inspector will prepare a "Monthly Progress Summation" form from the month's accumulation of "Daily Progress Reports" which shall also be signed by both the Inspector and Con- tractor's Representative indicating complete agreement and approval of quantities listed. F. These completed forms will provide the basis of the Engineer's monthly quantity estimate upon which payment will be made. Items not appearing on both the "Daily Progress Reports" and "Monthly Progress Summation" will not be included for payment. Items appear- ing on forms not properly signed by the Contractor will not be included for payment. 1.2 SCOPE OF PAYMENT A. Payments to the Contractor will be made for the actual quantities of contract items performed and accepted in accordance with the plans and specifications. Upon completion of the construction, if these actual quantities show either an increase or decrease from the quantities given in the Proposal Form, the contract unit prices will still prevail, except as provided hereinafter. B. The Contractor shall accept in compensation, as herein provided, in full payment for furnishing all materials, labor, tools, equipment, and incidentals necessary to the completed work and for performing all work contemplated and embraced by the contract, also for all loss or damage arising from the nature of the work, or from the action of the elements, or from any unforeseen difficulties which may be encountered during the prosecution of the work and until its final acceptance by the Engineer, and for all risks of every de- scription connected with the prosecution of the work, except as provided herein, also for all expenses incurred in consequence of the suspension of the work as herein authorized. 01150-2 C. The payment of any partial estimate or of any retained percentage except by and under the approved final invoice in no way shall affect the obligation of the Contractor to repair or renew any defective parts of the construction or to be responsible for all damage due to such defects. 1.3 PAYMENT FOR INCREASED OR DECREASED QUANTITIES: When alterations in the quantities of work not requiring supplemental agreements, as here- inafter provided for, are ordered and performed, the Contractor shall accept payment in full at the contract price for the actual quantities of work done. No allowance will be made for anticipated profits. Increased or decreased work involving supplemental agree- ments will be paid for as stipulated in such agreements. 1.4 ELIMINATED ITEMS: Should any items contained in the proposal form be found unnecessary for the proper completion of the work contracted, the Engineer may eliminate such items from the contract, and such action shall in no way invalidate the contract, and no allowance will be made for items so eliminated in making final payment to the Contractor. 1.5 PARTIAL PAYMENT A. Partial Payments shall be made monthly as the work progresses. All partial invoices and payments shall be subject to correction in the final quantity invoice and payment. B. No monthly payment shall be required to be made when, in the judge- ment of the Engineer, the work is not proceeding in accordance with the provisions of the contract, or when, in his judgement, the total value of the work done since the last payment amounts to less than $1,000.00. 1.6 PAYMENT FOR MATERIAL DELIVERED ON LUMP SUM PROJECTS A. At the discretion of the Engineer, acting upon the request of the Contractor, an invoice, accompanied by receipted bills, may be made for payment of all or part of the value of acceptable, non-perish- able materials and equipment which are to be incorporated into lump sum type contracts, and which have been delivered to the site of the work or in acceptable storage places, and not used at the time of such invoice. Materials, when so paid for by the Owner, shall become the property of the Owner, and in the event of default on the part of the Contractor, the Owner may use, or cause to be used, these materials in the construction of the work provided for in the contract. The Contractor shall be responsible for any damage to, or loss of, these materials. The amount thus paid by the Owner shall go to reduce estimated amounts due the Contractor as the material is used in the work. B. No partial payment shall be made upon fuels, supplies, lumber, false work, or other materials, or on temporary structures of any kind which are not a permanent part of the contract. 1.7 FINAL PAYMENT: The Engineer shall make, as soon as practicable after the completion of the project, a final quantity invoice of the amount of work performed under the Contract and the value of such work and the Owner shall then pay the entire sum found to be due, after deducting therefrom all previous payments. All amounts to be retained or deducted under the provisions of the Contract may be held by the Owner for a period of sixty (60) days after the completion of the final quantity invoice, or until such time as the Contractor submits satisfactory evidence that all bills for labor and materials used under this Contract have been paid and all required documents sub- mitted to the Engineer. 1.8 SUBSIDIARY WORK: Incidential work items for which separate payment is not measured includes the following items. A. Mobilization/Demobilization. B. Construction Signs. C. Plugging Existing Sewers and Drains. D. Restoration of Property. E. Cooperation with Other Contractors and Others. F. Utility Crossing, unless Otherwise Paid For. G. Minor Items, such as Replacement of Fences, Guard Rails, Rock Walls, etc. E. Temporary Pavement and Trench Patch. I. Clean Up. J. Temporary Access to Businesses. K. Pre Construction Videotape. 1.9 DESCRIPTION OF PAY ITEMS: The following sections describe the measure- ment and payment for Items of Work not specified in the New Hampshire Department of PUblic Works and Highway Specifications or Division II herein. END OF SECTION SECTION 01310 CONSTRUCTION SCHEDULES Submission to Engineer The Contractor shall be responsible for submitting to the Engineer, at least seven (7) days before the start of construction, a detailed construction schedule on a weekly basis, showing how he intends to approach the project and what be expects to have completed at the end of the work. The schedule should be in bar graph form and list the various tasks required to complete the 3 ~project and the dates which these tasks will be done. Section 01510 TEMPORARY UTILITIES PART I GENERAL 1.1 DESCRIPTION A. Work Included: 1. Provide and pay for all temporary applicable utilities required to properly perform the Work at no additional cost to the Owner including the placement and removal of the utilities. 2. Completely remove all temporary equipment and materials upon completion of the Work and repair all damage caused by the installation of temporary utilities.I 3. Make all necessary applications and arrangements for electric power, light, water, telephone and other utilities with the local utility companies. Notify the local electric power com- I pany if unusually heavy loads, such as welders, will be con- nected. 1.2 QUALITY ASSURANCEI A. Requirements of Regulatory Agencies: 1. Obtain permits as required by local governmental authorities. 2. Obtain easements, when required, across private property other I than that of the Owner for temporary power service. 3. Comply with the latest National Electrical Code. 4. Comply with all local, State, and Federal codes. laws, and regulations. B. All temporary utilities are subject to the approval of the Engineer. PART 2 PRODUCTS 2.1 MATERIALS A. Electrical:I 1. Provide all required facilities, including but not limited to, transformers, conductors, poles, conduits, raceways, fuses, switches, fixtures and lamps.I 2. Use new or used materials adequate in capacity for the purposes intended. 3. Materials must not create unsafe conditions or violate the requirements of applicable codes. 4. Conductors: a. Wire, cable or busses of appropriate type, sized in accor- dance with the latest -National Electrical Code for the applied loads. b. Use only UL approved wire. 5. Conduit: a. Rigid steel, galvanized: ANSI C80.l. b. Electrical metallic tubing: ANSI C80.3. C. Other material approved by NEC.I 6. Equipment: Provide appropriate enclosures for the environment in which used in compliance with NEMA Standards. 01510-2 H B, HB eating: 1I When heat is required for the protection of the work, provide and install a non-hazardous type of heating apparatus, and I ~~~~~provide adequate and proper fuel. 2. Beating equipment and materials in proper condition. C. Water, Provide drinking water equipment and material that will prevent contamination and health hazards. D. Sanitary Accommodations: Shall comply with all local, State and Federal codes, laws and regulations. PART 3 EXECUTION 3.1 PERFORMANCE I ~~~A. Electrical: 1. Provide electrical energy to: a. All necessary points on the construction site so that I ~ ~~~~~power can be obtained at any desired point with extension cords no longer than 100 feet. b. Construction site offices. * ~~~~~C. Lighting as required for safe working conditions at any location on the construction site. d. Night security light. e. When applicable, Owner's present facilities during the change over of electrical equipment. 2. Maintain electrical energy throughout the entire construction period. I ~~~~3. Capacity: Provide and maintain adequate electrical service for construction use by all trades during the construction period at the locations necessary. I ~~~~4. Installation: a. Install all work with a neat and orderly appearance. b. Have all installations performed by a qualified electrician. I ~ ~~~~C. Modify service as job progress requires. d. Locate all installations to avoid interference with cranes and materials handling equipment, storage areas, traffic I ~ ~~~~~~areas and other work. B. Heating: 1. Maintain a heated environment for the work at the temperature I ~ ~~~~and for the length of time specified or as directed by the Engineer. 2, Precaution: a. Operate temporary heating apparatus in such a manner that finished work will not be damaged. b. Repair all damage caused by temporary heating operations to the complete satisfaction of the Engineer. I ~~~C. Water. Provide and maintain water for drinking and construction purposes as required for the proper execution of the Work. D. Sanitary Accommodations: 1. Provide and maintain sanitary accommodations for the use of the employees of the Contractor, subcontractors, and Engineer. 2. Sanitary accommodations shall meet the requirements of all local, State and Federal health codes, laws and regulations. END OF SECTION SECTION 01630 SUBSTITUTIONS AND PRODUCT OPTIONS PART I - GENERAL 1 ~101 DESCRIPTION A. If stated in these Specifications that the Contractor may furnish or use a substitute that is equal to any material or equipment speci- I ~ ~~~fied, he shall, promptly after the award of the Contract, apply to the Engineer for approval of such a substitute. B. No substitute shall be ordered or installed without the written approval of the Engineer who shall be the judge of equality. 1.2 SUBMITTALS A. Submit a written application for approval completely describing the I ~ ~~~proposed substitution. B. Submit, when requested by the Engineer: 1. Manufacturer's catalog data. I ~ ~~~2. Illustrations. 3. Specifications. 4. Samples. 5. Other material that may be required to determine equality. 1.3 CRITERIA A. The following criteria will be used by the Engineer in determining I ~ ~~~the equality of proposed substitutions: 1. Adaptability to the design. 2. Functional performance. I ~ ~~~3. Appearance when applicable. 4. Quality of materials. 5. Strength of materials. I ~ ~~~6. Complexity, frequency and cost of maintenance. 1.4 RESULTING CHANGES A. If proposed substitutions are judges as being acceptable, make all I ~ ~~~changes to structures, buildings, piping, electrical, and other items necessary to accommodate the substitutions, at no additional cost to the Owner. I ~ ~~B. Whenever it may be written that an equipment manufacturer must have a specified period of experience with his product, equipment which does not meet the specified experience period can be considered if * ~~~~the equipment supplier or manufacturer is willing to provide a bond or cash deposit for the duration of the specified time period which will guarantee replacement of that equipment in the event of failure. I 1.L5 ENGINEERING SERVICES A. If Contractor requests substitutions which require design. or other engineering services, the services will be provided by the Engineer. B. The cost of engineering services for substitutions shall be at the expense of the Contractor. * ~~~~~~~~~~END OF SECTION SECTION 01710 PROJECT CLEANING PART I GENERAL 1.1 DESCRIPTION A. Work Included: 1. Maintain premises and public properties free from accumulations of waste, debris, and rubbish caused by operations. 2. At completion of work, remove waste materials, and clean allI sight-exposed surfaces. Leave project clean and ready for use. 1.2 QUALITY ASSURANCE A. Requirements of Regulatory Agencies: Conduct cleaning and disposal operations in accordance with all applicable local and state laws, ordinances, and code requirements.I PART 2 PRODUCTS 2.1 MATERIALSI A. Use only cleaning materials recommended by manufacturer of surfaces to be cleaned. B. Use cleaning materials only on surfaces recommended by cleaningI material manufacturers. PART 3 EXECUTION 3.1 PERFORMANCE A. Cleaning during construction: 1. Execute cleaning operation to ensure that buildings, grounds, I and public properties are maintained free from accumulations of waste materials and rubbish. 2. Entirely remove and dispose of material or debris during the I progress of the work that has washed into or has been placed in watercourses, ditches, gutters, drains, catch basins, or else- where as a result of the Contractor's operations.I 3. Wet down dry materials and rubbish to lay dust and prevent blowing dust. 4. At reasonable intervals during the progress of work, clean the site and dispose of waste materials, debris, and rubbish.I 5. Clean interiors of buildings, when applicable, prior to finish painting, and continue to clean on an as--needed basis until buildings are ready for occupancy.I 6. Handle materials in a controlled manner with as few handlings as possible. Do not drop or throw material from heights. 7. When applicable, schedule cleaning operations so that dust and I other contaminants resulting from the cleaning process will not fall on wet, newly painted surfaces. I ~~~~~~~~~~SECTION 01810 PROJECT RECORD DOCUMENTS Part I -General 1.1 Description A. Work Included: 1. Keep accurate record documents for all additions, substitutions of material, variations of work and any other additions or revisions to the Contract. B. Related Work Specified Elsewhere: 1. Shop Drawings, Project Data and Samples are specified in "General Conditions". I ~~1.2 Maintenance Of Documents A. Maintain at job site, one copy of: 1. Contract Drawings 2. Specifications 3. Addenda 4. Reviewed Shop I ~ ~~~5. Change Orders 6. Any other modifications to the Contract 7. Field Test Reports I ~ ~~B. Store documents in approved files and racks apart from documents used for construction. C. File documents in a logical manner indexed for easy reference. I ~ ~~D. Maintain documents in clean, dry, legible condition. E. Do not use record documents for construction purposes. F. Make documents available at all times for inspection by the Architect/Engineer and Owner. 1.3 Recording I ~~~A. Label each document "PROJECT RECORD" in large high printed letters. B. Keep record documents current and do not permanently conceal any work until required information has been recorded. I ~ ~~C. Contract Drawings Legibly mark to record actual construction: 1. Depths of various elements of foundation in relation to survey data. 2. Horizontal and vertical locations of underground utilities and appurtenances referenced to permanent surface improvements. a. Include all water, sewer, steam, air, instrumentation and fuel piping systems and all electrical and communications I ~ ~~~~~~circuits including all direct burial cables. b. Whenever any existing utility line is uncovered in the course of excavation for new utility installation, record I ~ ~~~~~~location dimensions for such lines. C. Method of location and recording shall have prior approval of the Architect/Engineer. 01810-2 3. Location of house service connection points (when applicable) with any utility (water, sewer, electrical, telephone, etc.) and the location of capped or plugged ends of these same house service lines.I a. Locations shall be recorded by accurate "swing ties" or other methods approved by the Architect/Engineer. b. Method of location and recording shall have prior approvalI of the Architect/Engineer. 4. Location of internal utilities and appurtenances concealed in construction referenced to visible and accessible features of structure. a. Electrical equipment such as conduits, piping, instrumentation located in slabs, walls and ceilings and to include approximate locations and routing.I b. Schematic diagram of actual electric conduit or instrument tubing routing between equipment and supply. 5. Field changes of dimension and detail and changes made byI Change Order of Field Order. 6. Details not on original Contract Drawings. D. Specifications and Addenda - Legibly mark up each section to record:I 1. Manufacturer, trade name, catalog number and supplier of each product and item of equipment actually installed. 2. Changes made by Change Order or Field Order. 1.4 Submittals A. At the completion of the project, deliver record documents to the Architect/Engineer. B.Accompany submittal with transmittal letter, in duplicate, contain- B. ing: 1. Date, project title and number. 2. Contractor's name and address. 3. Title and number of each record document with certification that each document is completed and accurate.I 4. Signature of Contractor, or his authorized representative. C. Failure to record these locations on the Project Record Drawings shall result in non-approval of the final payment of the ContractI and/or if contract time (as specified in accordance with the Stand- ard General Conditions of the Construction Contract) has elapsed, this shall be grounds for the enactment of the liquidated damages asI specified. END OF SECTIONI DIVISION 2 I ~~~~~~~~~~~SITE WORK Scope I ~ ~The scope of this Division covers the general site work and related provisions of the Contract. Contents of Division I ~~Section No. Section Title 02201 Excavation, Filling, and Grading 02223 Trench Excavation - Earth 02401 Dewatering 02648 Lawns 02653 Filter Fabric 02660 Erosion Control 02694 Footing Drains 02701 Sidewalks - Brick 02901 Granite Blocks SECTION 02201 EXCAVATION, FILLING & GRADING PART I - GENERAL * ~~101 References Particular attention is drawn to Division I., General Requirements, all provisions of which are as fully applicable to work done under this Section as if repeated herein. * ~~1.2 Description A. Provide all labor, materials, equipment and supervision necessary to complete the work specified in this Section as shown on the * ~~~~~Contract Drawings or both but not limited to the following. 1. Excavation, filling, backfilling, grading and subgrade * ~~~~~~preparation for concrete work. * ~~1.2 Quality Assurance A. Soil testing and inspection service: 1. Owner will provide soil testing and field observation of I ~ ~~~~earthwork procedures for quality control testing during earthwork operations. 1.4 Submittals A. Contractor shall submit a 25 pound sample to an approved testing laboratory for each type of material to be brought in from off site for grain size distribution analysis. Test results shall be submitted at least two (2) weeks prior to anticipated use. All materials shall conform with the appropriate section of the State of New Hampshire Department of Public Works & Highways Standard Specifications and Paragraph 2.2 of this Section. * ~~1.5 Job Conditions A. Site information: Borings done prior to initial construction in 1975 have been supplied (Exhibit 02201A). Data on indicated subsurface I ~ ~~~conditions are not intended as representations or warrants of continuity of such conditions between soil borings. It is expressly understood that the Owner will not be responsible for interpretations of conclusions drawn therefrom by Contractor. Data are made available for the convenience of Contractor. 1. Additional test borings and other exploratory operations may I ~ ~~~~~be made by Contractor at not cost to owner. 0220 1-2 B. Existing utilities: Locate existing underground utilities in the areas of work. If utilities are to remain in place, provide adequate means of protection during earthwork operations. 1. Should uncharted or incorrectly charted piping or other utilities be encountered during excavation, consul t the Engineer immediately for directions as to procedure. CooperateI with Owner and-utility companies in keeping respective services and facilities in operation. Repair damaged utilities to satisfaction of utility owner.3 2. Do not interrupt existing utilities serving facilities occupied and used by Owner or others, except when permitted in writing by Engineer and then only after acceptable temporary utilityI services have been provided. C. Use of explosives:3 1. No explosives shall be used for any purpose. D. Protection of persons and property: Barricade open excavations occurring as part of this work and post with warning lights and signs. Operate warning lights during hours from dusk to dawn to each day and as otherwise required. 1. Protect structures, utilities, sidewalks, pavements and other facilities from damage caused by settlement, lateral movement, undermining, washout and other hazards created by earthworkI 1.6 Disturbance Of Excavated And Filled Areas During Construction3 A. The Contractor shall take the necessary steps to avoid disturbance of subgrade during excavation and filling operations. Methods of excavation and filling operations shall be revised as necessary toI avoid disturbance of the subgrade, including restricting the use of rubber tired vehicles or other equipment in areas where subgrade is above optimum moisture level and will become disturbed due toI movement of vehicles. B. All excavated or filled areas disturbed during construction that will not meet compaction and material requirements as specified herein shall be removed and replaced with granular backfill (see item 2.2A). Costs of removal of disturbed material and recompaction with granular backfill shall be borne by the Contractor. ContractorI shall be compensated for the cost of disposal of unsuitable material and supplying of granular backfill material on a unit cost basis (See Item No. I Section 00022).3 02201-3 PART 2 - PRODUCTS 2.1 Definitions A. All sieve analysis for conformance of on-site and off-site fill materials to be used in the Work shall conform to ASTM D-422. In addition to the requirements of this ASTM designation all materials beyond the #60 sieve shall be done by means of a mechanical wet sieve analysis. 2.2 Solid Materials A. Granular Backfill: Material for Granular Backfill base shall be a sandy gravel, free of organic material, trash, snow, ice, frozen soil and other objectionable material and shall be well graded within the following limits. SIEVE SIZE PERCENT FINER BY WEIGHT 3" 100 1/2" 50-85 #4 40-75 #40 10-35 #200 0-10 On-site material may be used for granular backfill provided the material conforms to the requirements of the specifications for this type of backfill. B. Coarse gravel: Material for coarse gravel shall be free of organic material, trash, snow, ice, frozen soil, and other objectional material and shall fall within the following limits: SEIVE SIZE PERCENT FINER BY WEIGHT 2" 100 1/2" 75 - 90 #4 0 PART 3 - EXECUTION 3.1 Inspection A. Examine the areas and conditions under which excavating, filling and grading are to be performed and notify the Engineer in writing of conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected in an acceptable manner. 02201-4 3.2 Excavation A. Excavation consists of removal and temporary storage of materials encountered when establishing required grade elevations.I B. Perform all excavation of every description and of whatever substances encountered to the depths and extent indicated for theU proper installation of the work. C. Excavate to the exact depth required for all drainage systems. Drainage trenches shall be over excavated to accommodate pipe beddingI as specified hereinafter. D. Unauthorized excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without specific direction of Engineer. 1. Backfill and compact unauthorized excavations with materials as specified for authorized excavation of same classification, unless otherwise directed by Engineer. This work shall be completed at no additional cost to the Owner. E. Stability of excavation: Slope sides of excavation to comply with local codes and ordinances having jurisdiction. Shore and brace where sloping is not possible either because of space restrictions or stability of material excavated. 1. Maintain side and slopes of excavation in a safe conditionI until completion of backfilling. 2. Contractor is responsible for assessing influence of tidal fluctuations on excavations. P. Shoring and bracing: Provide adequate shoring and bracing, such as sheet piling, uprights, stringers and cross-braces, in goodI serviceable condition. 1. Trench shoring and bracing shall comply with local codes and3 authorities having jurisdiction. 02 201-5 2. Maintain sharing and bracing in excavations regardless of time period excavations will be open. Carry down shoring and * ~~~~~~bracing as excavation progresses. G. Dewatering: Prevent surface water and subsurface or ground water from flowing into excavations or onto any work and from flooding I ~ ~~~~project site and surrounding area. 1. Do not allow water to accumulate in excavations. Remove water to prevent softening of subgrades and soil changes detrimental to stability of subgrades. Provide and maintain pumps, sumps, suction and discharge lines and other dewatering system * ~~~~~~components necessary to convey water away from excavations. H. Material storage: Stockpile satisfactory excavated materials and granite blocks until required for backfill and resetting near edge of stockpile shall be a minimum of 30' from granite wall. Place, grade and shape stockpiles for proper drainage. I. Excavation for structures: Conform to elevations and dimensions 0.10' and extending a sufficient distance from footings and foundations to permit placing and removal of concrete formwork, installation of services, other construction required and for I ~ ~~~~inspection. 1. in excavating for footings and foundations, take care not to disturb bottom of excavation. Excavate by hand to final grade just before concrete is placed. Trim bottoms to required lines and grades to leave solid base to receive concrete. 2. If requested by the Engineer, the Contractor shall overexcavate approximately 6" for footings and place a working mat ofcrush- ed stone to prevent subgrade disturbance of material in place * ~~~~~~or in fill material. J. Excavation for pavements: Cut surface under pavements to comply with cross-sections, elevations and grades as shown. K. Excavation for ditches: Cut ditches to cross-sections and grades as shown. Deposit excavated materials to prevent cave-ins or material falling or sliding into ditch. Keep ditches free of debris until final acceptance of the work. L. Excavation for utilities: The trench for the pipe shall be I ~ ~~~excavated to the required line and grade and of sufficient width to permit thorough compacting and tamping of the fill material under the haunches and around the pipe. In general, utility trenches 02201-6 shall be excavated to a point 6 inches below the bottom of the utility line to accommodate bedding material as specif ied hereinafter. Soft or unsuitable material encountered below the normal bedding line of the pipe shall be removed as directed, replaced with selected material, gravel or crushed stone andI thoroughly compacted. The bottom of the trench shall be shaped to conform to the curvature of the pipe. This bed shall also be excavated to accommodate the bells of pipes.I M. Removal of unsatisfactory soil materials: Excavate unsatisfactory soil materials encountered that extend below required elevations and beyond required excavation to additional depth directed by the Engineer. 1. Costs of such additional excavation, shall be borne by theI Contractor. 2. Material that is above or below optimum moisture for compaction of the particular material on place as determined by the Soils Representative and is disturbed by the Contractor duri ng construction operations so that proper compaction cannot be reached shall not be construed as unsuitable bearing materials or unsatisfactory soil materials. This material shall be removed and replaced with lean concrete or compacted gravel fill at no additional charge.I N. Cold weather protection: Protect excavation bottoms against freezing when atomspheric temperature is less than 35 degrees P. 3.3 COMPACTION A. General: Control soil compaction during construction providing minimum percentage of density specified for each area classification. B. Percentage of maximum density requirements: Provide not less than following percentages of maximum density of soil material as determined by ASTM Test D1557 Method C, latest revision (modifiedI proctor). 1. Lawn or Unpaved Areas: Compact top 6" of subgrade and each layer or backfill or fill material to a density approximating that of the adjacent undisturbed material but to a minimum of 90%.I 2. Walkways: Compact top 6" of subgrade to 96% and each layer of backfill material to 96% maximum density. I ~~~~~~~~~~~~~~~02 20 1-7 C. Moisture control: Where subgrade or layer of soil material must be moisture conditioned before compaction, uniformly apply water to surface of subgrade, or layer of soil material, to obtain optimum moisture content. I I~~~~1 Remove and replace or scarify and air dry, soil material that is too wet to permit compaction to specified density. a. Soil material that has been removed because it is to wet I ~ ~~~~~to permit compaction may be stockpiled or spread and allowed to dry. Assist drying by discing, harrowing or pulverizing, until moisture content is reduced by a satisfactory value, as determined by moisture-density relation tests. 3.4 Backfi'll A. General: Place acceptable soil material in layers to required subgrade elevations for each area classification listed below. 1 ~~~~1. Adjacent to granite seawall and under walkways, and landscaped areas, fill material shall be granular backfill. B. Backfill excavations as promptly as work permits, but not until completion of the following. 1. Acceptance by Engineer of construction below finish grade, including, but not limited to: - Concrete has reach 75% of 20 day strength. - Subsurface drainage system installed to manufacturer's recommendations. - Granite blocks are properly grouted into place to be level and plumb with proper batter. 2. Inspection, testing, approval and recording locations of * ~~~~~~underground utilities. 3. Removal of concrete framework. 4. Removal of shoring and bracing and backfilling of voids with satisfactory materials. Cut off temporary sheet piling driven below bottom of structures and remove in manner to prevent settlement of the structure or utilities or leave in place if required. * ~~~~5. Removal of trash and debris. C. Ground surface preparation: Remove vegetation, debris, unsatisfactory soil materials, obstructions and deleterious * ~~~~materials from ground surface prior to placement of fills. 02201-8 D. Placement and compaction: All compacted fill shall be placed in layers having a maximum loose layer thickness of 18 inches. Each layer shall be systematically compacted to the density specified here inbe fore. 1. Compaction equipment in confined areas shall be accomplished by hand operated vibratory equipment or mechanical tampers asI approved by the Soils Inspector. 2. Fill layers shall not be left in an uncompacted state at the close of a day's operations. Prior to terminating operationsI for the day, the final layer of fill, after compaction, shall be rolled with a smooth-wheeled roller to eliminate ridges of soil left by tractors, trucks and compaction equipment. SlopeI all fill to drain at termination of work day. 3. The Contractor shall not place a layer of compacted fill on snow, ice or soil that was permitted to freeze prior toI compaction. Removal of these unsatisfactory materials will be required as direct by the Soils Representative. 4. Each lift of placed and compacted material shall be tested by the Soils Representative. Do not proceed with additional lifts until authorized by the Soils Representative. See paragraph 3.7 for requirements. 3.4 Grading A. General: Uniformly grade areas within limits of grading under this section, including adjacent transition areas. Smooth finished surface within specified tolerances, compact with uniform levels orI slopes between points where elevations are shown, or between such points and existing grades. B. Grading Under Walkways: Grade areas under walkways to slope awayI from granite wall at 1/16" per foot. Finish surface shall be free from irregular surface changes. C. Grading Outside Walkways: Grade are-as outside walkways to slope away from walkways and towards catch basin at station 53 offset 17.9' right. D. Compaction: After grading, compact subgrade surfaces to the depth and percentage of maximum density for each area classification. 0220 1-9 3.5 Field Quality Control A. All operations under this Section of the Specification will be sub- ject to the continuous observation of the Engineer and of a soils testing laboratory, engaged and paid directly by the Owner except as described herein. The Engineer or the laboratory will determine I ~ ~~~conformance of materials and workmenship, particularly compaction, to the requirements of this Specification. 1. The laboratory shall make such tests of materials and I ~ ~~~~~compaction as the Engineer directs. Costs of such test shall be borne by the Contractor only when they indicate noncompliances of materials or compaction to the requirements of this Specification. Cost of tests shall be borne by the Owner when they indicate compliance of materials or compaction to the requirement of the Specification. I ~ ~~~2. The laboratory will defer testing of an area until the Contractor states that he has reached the specified compaction on the particular area. The laboratory will make a reasonable I ~ ~~~~number of tests or visual examinations of materials proposed for fill at no charge to the Contractor, but the Owner reserves the right to make charges for such tests where Contractor repeatedly proposed marginal materials for test or examination. 3. Areas for which tests indicate insufficient compaction shall be re-compacted andretested until the areas conform to the requirement of Specification. * ~~3.6 Maintenance A. Protection of graded areas: Protect newly graded areas from traffic and erosion and keep free of trash and debris. I ~~~~1. Repair and re-establish grades in settled, eroded, and rutted areas to specified tolerance. B. Reconditioning compacted areas: Where completed compacted areas are disturbed by subsequent construction operations or adverse weather, scarify surface, re-shape, and compact to required density prior to * ~~~~~further construction. 02201-10 3.7 DisPosal Of Excess And Waste Materials A. Removal to designated areas on Owners's property: 1. Remove excess materials, including excavated backfill material and unsuitable material from the Owner's property and legally dispose of it. END OF SECTION ~~~~~~~~~~~~~- -------- - ----- I~~~~~~~~~~~~~~~g ~~~~~ ~ M I+. ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~- )I -f-GO 3'-,------- 4., UNE ~0N )Jv 3 ~ ~ ~ ~ ~ ~ ~ ~ ~~~' ___ ~~ G - . - ____________ V~IN ,Act?~~~~~~~~~~~~~~~~~~~~~~~~- Ila~ - LA~~~~~~g c~-. O+C"P. ~ ~ ~ ~ - B A~LN B*C - P- 00O M0.E ?)2To- .F+ S - +E -GRD. EL. 0.3 GRO. EL. -1.1 GRD, SL. -j-.4I 'S. I 1 CLAl 0 BACKMC S70NES0 1'co is - :71~~~~~~~~ 0 ~~~~~~~~~~~~SILT CL. CL.16 24 ~ ~ ~ ~ ~~~~~I ~~~~1(SIL.T 4 C L" 6~~~~~~~~~~~~~57 103 ~ ~ ~ ~ ~ ~~~7 129 ~~~~~~~~~~~FINE SA,[46 114 Z4 $CTTCM~~~~~~~~~~o OF HOLE3$z2 WIGUFLES ~ ~ ~ ~ 2. 'fq C__ IP10CLM NIAT NUMBER OF BLOW% ;r~EQUIREED TO DRIVM k WEIGHT r-A.LLIFINE SAND 114 III I~~~~~~~~~~~~~LC I~~~~~~~~~~~~~OD I ~~~~~~~~~~~~~~~~~~~~~~~~~7 I~~~~~~~~~~~~~~~~5L 0,Ck 43 I~~~~~~~~~~~~~o - 9� 50'TOMOF OL-A SECTION 022231 TRENCH EXCAVATION - EARTH PART I - GENERALI 1.1 Description A. Work Included: 1. Trench excavation work in earth includes the removal of sand, gravel, existing sewers and manholes, ashes, loam, clay, swamp muck, trolley tracks, soft or disintegrated rock or hard pan, stumps,I existing sewers and manholes which can be removed with a backhoe, or a combination of such materials, and boulders measuring less than one cubic yard for the installation of pipes and appurtenant structures. 2. All trench excavation shall be classed as earth or ledge. B. Related Work Specified Elsewhere (When Applicable): 1. Traffic regulation is specified in Division 1.I 2. Clearing, removal and replacement of paving, trench excavation- ledge, material, manholes, an d catch basins, when applicable, are specified in the appropriate Sections in this Division. 3. Pipe and pipe fittings, valves, gates, and hydrants, when applic- able, are specified in this Division. 1.2 Job Conditions A. Utilities: I. The locations of known buried water lines, sewer lines, telephoneI cables, storm drains, culverts, gas mains, electric conduits, and other utilities are shown on the Drawings. No guarantee is made as to the correctness of the locations shown and to the completeness of the information given.I 2. Discontinue excavation bv machinery when the excavation approaches pipes, conduits, or other underground structures of which the approximate locations are known. Use manual excavation methods toI locate the obstructions. B. Existing Structures; 1. Perform excavation in such a manner that will prevent any pos- sibility of undermining and disturbing the foundations of any exist-I ing structures and any work previously completed under this Contract. 2. Where existing buildings and other structures are in close proximityI to the proposed construction, exercise extreme caution and utilize sheeting, bracing, and whatever other precautionary measures that may be required. C. Repairing Damage: Repair, or have repaired, all damage to existing utilities, structures, lawns, other public and private property which results from construction operations, at no additional expense to the Owner. to the complete satisfaction of the Engineer, the utility companyI and the property owner. 0222 3-2 * ~~PART 2 -PRODUCTS 2.1 Materials A. The Contractor shall not have any right of property in any suitable I ~ ~~materials taken from any excavation. Do not remove any such materials fornfi the construction site without the approval of the Engineer. This provision shall in no way relieve the Contractor of his obligations to I ~~~remove and dispose of any material determined by the Engineer to be unsuitable for backfilling. B~. Unsuitable Material: 1. If, in the opinion of the Engineer, the material encountered above I ~ ~~~the indicated grade shown on the Drawings for excavation is unsuit- able material, remove the material to the widths and depths as directed by the Engineer. Replace this material as specified in the "Backfilling, Compaction, Control and Testing" Section of this 2. If, in the opinion of the Engineer, the material encountered at or blwthe indicated grade shown on the Drawings for excavation is unstable material, remove the material to the full width of the trench and to a minimum depth of 12-inches below the pipe. Replace this material with thoroughly compacted, suitably screened gravel or I ~ ~~~~crushed stone bedding material. 3. All excavated materials designated by the Engineer as unsuitable shall become the property of the Contractor and disposed of at locations acceptable to or designated by the Owner, at no additional cost to the Owner. C. Embankment Material: Obtain prior approval and instructions from the Engineer prior to undertaking the excavation for pipe placement of any fill material that has been in an embankment less than one year. PART 3 - EXECUTION 3.1 Performance A. General: 1. Unless otherwise specifically directed or permitted by the Engineer, I ~ ~~~~begin excavation at the low end of sewer lines and proceed upgrade. 2. Perform excavation for sewers and drains in a logical sequence. B. Amount of Excavation: I ~ ~~~1. Trench Width: As shown on the Drawings. 2. Trench Depth: As shown on the Drawings. 3. Open Excavation: a) The extent of open excavation shall be controlled by prevailing I ~ ~~~~~conditions. b) Open excavation shall, at all times, be confined to the limits prescribed by the Engineer. I ~ ~~~4. Unauthorized Excavation: a) Backfill to the specified grade any excavation beyond the limits stated above and as shown on the Dr-awings (unless speci- fically ordered by the Engineer) with thoroughly compacted I ~ ~~~~~crushed stone or screened gravel. b) Backfilling unauthorized excavation shall be at no additional cost to the Owner. 02223-3 Part 3 -Execution (Continued)I C. Shoring and Bracing: As the excavation progresses, install such shoring and bracing necessary to prevent caving and sliding and to meet theI requirements of the State and OSHA safety standards. END OF SECTION SECTION 02401 DEWATERING PART I - GENERAL 1.1 Description I ~~~A. Work Included: Furnish, operate and maintain dewatering equipment for the control, collection and disposal of ground and surface water entering trenches and excavations. I ~~~B. Related Work Specified Elsewhere (When Applicable)., Trench excavation - earth, trench excavation - ledge, structural excavation, and backfilling, compaction, control and testing are specified in the appropriate Sections in this Division. PART 2 - PRODUCTS * ~~2.1 Materials A. Provide, operate, and maintain a dewatering system to remove all water from excavations and trenches containing pumps, drains, wellpoints, piping and any other facilities necessary to keep the excavations and trenches free of water, including spare units I ~~~~~available for immediate use in the event of equipment breakdowns. PART 3 - EXECUTION 3.1 Performance A. General: 1. Keep excavations and trenches dry until the structures, pipes, I ~~~~~~and appurtenances to be build therein have been completed to such an extent that they will not be damaged. 2. Perform dewatering work when necessary at no additional cost to the Owner. B. Disposal of Water: 1. Dispose of water pumped or drained from the construction site in a suitable manner to avoid public nuisance, injury to public I ~~~~~~health, damage to public and private property, and damage to the work completed or in progress. 2. Provide suitable temporary channels for water that may flow I ~~~~~~along or across the construction site. C. Damage: 1. All damage resulting from the dewatering operations, or the failure of the Contractor to maintain the work in a suitable I ~~~~~dry condition shall be repaired by the Contractor, to the satisfaction of the Engineer, at no additional cost to the * ~~~~~~Owner. 02401-2 D. Cofferdams: 1. Design, construct, maintain, and remove cofferdams where necessary for the dewatering, control, and diversion of water to keep excavations and trenches free of water. 2. Design and construct cofferdams to withstand all imposed loads to prevent injury to persons and property. Construct cofferdams to depths to permit a reasonable change in depths of the work, of sufficient height to prevent flooding, and of such dimensions to give sufficient clearance for construction and inspection. 3. Remove cofferdams, including all sheeting and bracing, after the completion or permanent construction. E. Temporary Underdrains: 1. When necessary, lay temporary underdrains in the excavation. 2. Excavate trenches to suitable dimensions to provide space for the underdrains and surrounding gravel. 3. Install underdrains a distance of at least 3 inches below the bottom of the pipe or structure and the top of the bells of the underdrain pipes, unless otherwise permitted by the Engineer. 4. Underdrain pipe shall be vitrified clay, concrete or P.V.C. pipe of standard thickness. Sewer pipe of the qualify known as "seconds" will be acceptable. 5. Entirely surround the underdrain and fill the space between the underdrain and the pipe or structure with screened gravel or crushed stone. 6. Compact the gravel or crushed stone, if necessary, and leave the surface suitable for laying the pipe or building the structure. F. Wellpoint System: 1. If required, dewater the excavations and trenches by an efficient drainage wellpoint system to drain the soil and prevent saturated soil from flowing into the excavated area. 2. Use wellpoints designed for dewatering work. 3. Use pumping units designed to be used with wellpoints, capable of maintaining high vacuums, and capable of handling large volumes of air and water at the same time. End Of Section U ~~~~~~~~~SECTION 02648 LAWNS I ~~~PART I - GENERAL 1. 1 Description A. Work Included - Perform the following items of work required to complete the work of this Section, as shown on the Drawings and specified herein. I I~~~~~. Spread loam and establish lawns in all areas where excavation or temporary stockpiles have destroyed lawns. B. Related Work Specified Elsewhere: U I~~~~~. Contractor shall coordinate this work with all work in related Sections of this specification. 3 ~~1.2 Scope A. The work of this Section consists of all Lawn and Fine Grading work and related items as indicated on the Drawings and/or as specified I ~ ~~~~herein and includes, but is not limited to, the following: 1. Fine grading and Loaming 2. Fertilizer and seeding 3. Maintenance and protection I ~~1.3 Samples A. Prior to ordering the below listed materials, submit representative samples of Architect for selection and approval, in accordance with requirements of General Conditions and Supplementary General Conditions as follows. Do not order materials until Architect's approval has been obtained. Delivered materials shall closely match * ~~~~~the approved samples. 1. Loam Borrow: The Contractor shall provide representative samplesfor testing and approval as directed by the Architect. Contractor shall deliver samples to testing laboratory, having testing report sent directly to the Architect and pay all costs. a. Mechanical and chemical (pH soluble salts) analysis shall I ~ ~~~~~be by a public extension service agency or a certified private testing laboratory in accordance with the curen"standards" of the Association of Official Agriculture Chemists". b. Report shall be submitted at least one month before any loaming is done. Soil tests shall be tested for Nitrate Nitrogen, Aumomium Nitrogen, Phosphorus, Potassium, Calcium Aluminum, Soluble Salts and show acidity of the Soil. 02 648-2 2. Seed: Submit a manufacturer's Certificate of Compliance to the Specifications with each shipment of each type of seed. These certificates shall include the guaranteed percentage of purity, weed content and germination of the seed and also the net weight and date of shipment. No seed may be sown until theI Contractor has submitted the certificates. 1.4 Certificate Of AcceptanceI A. The Architect will inspect all work upon the written request of the Contractor received at least ten days before the anticipated date of inspection. B. Seeded fine lawns shall be maintained until all areas have a close stand of grass which has received three mowings, have no bare spots greater four inches in diameter and at least 80% of the grassI established is permanent grass species. Seeded field grass areas shall be mowed to height of 4 inches following one(l) full growing season prior to acceptance. C. Furnish full and complete written instructions for maintenance ofI the lawns to the Owner at the time of acceptance. D. Architect's inspection shall determine whether maintenance shall continue in any part.I E. After all necessary corrective work and clean-up has been completed and maintenance instructions have been received by the Owner, the Architect will certify in writing the acceptance of the lawns. The contractor's responsibility for maintenance of lawns or parts ofI lawns shall cease on receipt of the Certificates of Acceptance. 1.5 InspectionI A. All areas to be fine graded and seeded shall be inspected by the Contractor before starting work. Any defects such as incorrectI grading, etc., shall be reported to the Architect prior to beginning this work. The commencement of work by the Contractor shall indicate his acceptance of the areas to be fine graded and seeded and he shall assume full responsibility for the work of thisU Section. PART 2 -PRODUCTS 2.1 Loam A. Loam shall be a "fine sandy loam" or a "sandy loam" determined by mechanical analysis and based on the"U.S.D.A. classificationI system". - It shall be of uniform composition, without a mixture of subsoil. It shall be free of stones greater than one inch, lumps, plants and their roots, debris and other extraneous matter over oneI inch in diameter or excess quantities of smaller pieces of the same materials as determined by the Architect. It shall not contain toxic substances harmful to plant growth. It shall be obtained from naturally well drained areas which have never been stripped before and have a history of satisfactory vegetative growth. 02648-3 B. Loam shall have an acidity range of pH 5.8 to pH 7.0 and shall I ~ ~~~contain not less than 4% nor more than 20% organic matter as determined by the loss of ignition of oven-dried samples. Test samples shall be oven-dried to a constant weight at a temperature of I ~~~~~2300F. plus or minus 90. C. The topsoil stripped and stockpiled on the site may be used provided that, after testing and addition of necessary additives, it meets the above specification. The Contractor shall provide additional loam as required to obtain the volume called for on the Drawings. * ~~2,2 Soil Additives A. Commercial fertilizer, peat, humus or other additives shall be used to counteract soil deficiencies as recommended by the soil analysis I ~~~~~and as directed by the Architect. a. Commercial fertilizer shall be a product complying with the State and United States fertilizer laws. Deliver to the site in the original unopened containers which shall bear the I ~~~~~manufacturer's certificate of compliance covering analysis which shall be furnished to the Architect. At least 50% by weight of the nitrogen content shall be derived from organic I ~~~~~materials. Fertilizer shall contain not less than the percentages of weight of ingredients as follows or as recommended by the soil analysis: I ~~~~~~~~Nitrogen Phosphorus Potash 10% 6% 4% B. Humus shall be natural humus, reed peat or sedge peat. It shall be free from excessive amounts of zinc, low in wood content, free from hard lumps and in a shredded or granular form. According to the methods of testing of A.O.A.C., latest edition. The acidity range shall be approximately 5.5 pH to 7.5 pH and the organic matter shall be not less than 85% as determined by loss on ignition. The minimum water absorbing ability shall be 200% by weight on an. oven-dry I ~~~~~basis. C. Limestone 1. Cround limestone shall be an approved agricultural limestone containing not less than 85% of total calcium or magnesium carbonates. Limestone shall be ground to such fineness that 50% will pass a 100 mesh sieve and 95% will pass through a 20 mesh sieve. I ~~~D. Superphospate 1. Superphospate shall be composed of fine ground phosphate rock as commonly used for agricultural purposes containing not less I ~~~~~~than 18% available phosphoric acid. 02648-4 2.3 Seeds A. Seed mixture shall be fresh, clean, new crop seed. Grass shall be of the previous year's crop and in no case shall the weed seed content exceed 1% by weight. The seed shall be furnished and delivered in the proportion specified below in new, clean, sealed and properly labeled containers. All seed shall comply with State and Federal seed laws. Submit manufacturer's Certificates of Compliance. Seed which has become wet, moldy or otherwise damaged shall not be acceptable. No seed shall be sown until the Contractor has submitted the certificates. B. Grass shall be of the previous year's crop and in no case shall the weed seed content exceed one percent (1%) by weight. Grass seed shall conform to the requirements of the following tables: Proportion Germination Purity Minimum Minimum For Fine Lawns Creeping Red Fescue 50% 85% 95% or Chewing's Fescue Kentucky Bluegrass 20% 85% 90% Manhattan Perennial Rye 20% 90% 90% Red Top 10% 85% 92% For Field Grass Creeping Red Fescue 40% 85% 95% or Chewing"s Fescue Kentucky Bluegrass 25% 85% 90% Kentucky 32 Fescue 20% 85% 95% Red Top 10% 85% 92% White Clover 5% 85% 96% C. Seed may be mixed by an approved method on the site or may be mixed by a dealer. If the seed is mixed on the site, each variety shall be delivered in the original containers which shall bear the dealer's guaranteed analysis. If the seed is mixed by a dealer, the Contractor shall furnish the Architect the dealer's guaranteed statement of the composition of the mixture. 02648-5 2.4 Equipment A. Suitable water, hose and other watering watering equipment required for the execution of this work and maintenance shall be provided by the Contractor. Water shall be free from impurities injurious to * ~~2.4 Mulch A. After the areas to be loamed have been brought to grade and immediately prior to dumping and spreading the loam, the subgrade I ~ ~~~shall be loosened by disking or rototilling to a depth of at least four inches to permit bonding of the loam to the subsoil. Remove all stones greater than two inches and all debris or rubbish. Such material shall be removed from the site. B. Loam shall be placed and spread over approved areas to a depth sufficiently greater than six inches so that after natural settlement and light rolling the completed work will conform to the I ~ ~~~~lines, grades and elevations indicated. Supply additional loam, after testing and approval, as may be needed to give the specified depths and finished grades under the contract without additional I ~ ~~~~cost to the Owner. C. Disturbed areas outside the limit of seeding shall be spread with six inches of loam to the finished grade. D. No subsoil or loam shall be handled in any way if it is in a wet or I ~ ~~~~frozen condition. E. Sufficient grade stakes shall be set for checking the finished grades. Stakes must be set in the bottom of swales and at the top of slopes. Grades shall be established which are accurate to 1/10th U ~~~~~of a foot either way. Connect contours and spot elevations with an even slope. F. After loam has been spread, it shall be carefully prepared by scarifying or harrowing and hand raking. All large stiff clods, lumps, brush, roots, stumps, litter and other foreign matter and stones over one inch in diameter shall be -removed from the loam. Loam shall also be free of smaller stones in excessive quantities as determined by the Architect. G. The whole surface shall then be rolled with a hand roller weighing not more than 100 lbs per foot of width. During the rolling, all depressions caused by settlement of rolling shall be filled with additional loam and the surface shall be regraded and rolled until presenting a smooth and even finish to the required grade. H. Contractor shall obtain Architect's written approval of fine grading and bed preparation before doing any seeding. * ~~3,2 Seeding A. Limit of work line shall be limit of seeding unless otherwise indicated on the Drawings. Areas on the plan are to be loamed and I ~ ~~~~seeded after written approval of the finished grading or as directed by the Architect. All disturbed areas outside the limit of seeding shall be seeded. 02648-6 B. Seeding shall be done only during the period from April 1 to June 1 or August 15 to October 15. The actual planting of seed shall be done, however, only during periods within this season which are normal for such work as determined by weather conditions and by accepted practice in this locality. At his option and on his responsibility, the Contractor may plant seed under unseasonable conditions without additional compensation, but subject to Architect's approval of time and methods. C. Soil additives shall be spread and thoroughly incorporated into the layer of loam and the upper one inch of the underlying subsoil by harrowing or other methods approved by the Architect. The following soil additives shall be incorporated: 1. Spread ground limestone as required by soil analysis to achieve a pH of 6.0 to 6.5, but the maximum amount applied shall be one pound per square yard. 2. Spread fertilizer at the rate of 25 lbs per 1,000 square feet, or more, as recommended by the soil analysis. 3. Spread superphospate at the rate of 20 lbs per 1,000 square feet. 4. Spread humus as required by soil analysis. D. Seed only when the bed is in a firable condition, not muddy or hard. E. Seeding shall be done in two directions at right angles to each other. Sow the seed with approved seeding device at the rate of five lbs per 1,000 square fee. No seeding shall be done in windy weather. F. If covering and rolling is not properly accomplished by the seeding machine, the seed shall be lightly raked into the ground, after which the ground shall be rolled with a five hundred pound roller andthoroughly and evenly watered with a fine spray to penetratethe soil to a depth of at least two inches. 3.3 Hydroseeding A. Limit of work line shall be limit of hydroseeding unless otherwise indicated on the Drawings. Areas on the plan are to be loamed and hydroseeded after written approval of the finished grading or as directed by the Architect. All disturbed areas outside the limit of hydroseeding shall be hydroseeded. B. Seeding shall be done only during the period from April 1 to June 1 or August 15 to October 15. The actual planting of seed shall be done, however, only during periods within this season which are normal for such work as determined by weather conditions and by accepted practice in this locality. At his option and on his responsibility, the Contractor may plant seed under unseasonable conditions without additional compensation but subject to Architect's approval of time and methods. C. For construction methods conform to Hydraulic Method requirements specified in the Standard Specifications for Road and Bridge Construction, State of New Hampshire, Section 644, Paragraph 3.5.2 and as specified herein. 02 648-7 D. Prior to the start of work, the Architect shall be furnished with a with a certified statement for approval as to the number of pounds of material to be used per 100 gallons of water. This statement shall also specify the number of square feet of seeding that can be covered with the quantity of solution in the hydroseeder. E. Fertilizer shall be added to the hydroseeding slurry at the rate of 25 pounds per 1,000 square feet, or more, as recommended by the soil I ~~~~~analysis. P. Limestone shall be added to the hydroseeding slurry as required by soil analysis to achieve a pH of 6.0 to 6.5, but at a maximum rate of one pound per square yard. C. Seed shall be added to the hydroseeding slurry at the rate of 5 pounds per 1,000 square feet. H. A mobile tank with a capacity of at least 500 gallons is to be I ~~~~~filled with water, seed, a fertilizer, in quantities so they may be sprayed in the specified proportions per unit of area to beseeded. The slurry must be thoroughly mixed by means of a centrificalpump using the turret or hose application technique from the mobile tank. The hose or turret shall be equipped with a seeding nozzzle ofa proper design to insure even distribution of the seed and fertilizer solution over the area to be seeded and shall be operated by a I ~~~~~person thoroughly familiar with this type of seeding operation. I. Straw mulch shall be applied within a minimum of (1/2) one half hour of hydroseeding at the rate of 2 tones per acre. 3.4 Maintenance And Protection A. Maintenance shall begin immediately after any area is seeded or hydroseeded and shall continue until acceptance. In the event that seeding operations are completed too late in the Fall for adequate germination and growth of grass, then maintenance shall continue into the following Spring until acceptance. B. Maintenance shall include reseeding, rehydroseeding, mowing, wateingweeding and fertilizing. C.Watering of Seeded Areas 1. First Week: The Contractor shall provide all labor and arrange for all watering necessary to establish an acceptable lawn. In the absence of adequate rainfall, watering shall be performed daily or as often as necessary during the first week and in sufficient quantities to maintain moist soil to a depth of at least two inches. 2. Second and Subsequent Weeks: The Contractor shall water the lawn as required to maintain adequate moisture, in the upper two inches of soil, necessary for the promotion of deep root growth. I ~~~~3. Watering shall be done in a manner which will provide uniform coverage, prevent erosion due to application of excessive quantities over small areas, and prevent damage to the finished I ~~~~~~surface by the watering equipment. The Contractor shall furnish sufficient watering equipment to apply one complete coverage to the seeded areas in an eight hour period. 02648-8I D. Protection 1. Seeded areas shall be protected by a three foot high barrier constructed of two by four stakes or iron pipes, set eighteenI inches in the ground at ten foot intervals and connected by #10 wire. Flags of white cloth shall be secured to the wire at center points between stakes. 2. Barriers must be raised immediately after seeding and shall'be maintained until acceptance. E. After the grass in seeded areas has appeared, all areas and parts of areas which, in the opinion of the Architect, fail to show a uniformI stand of grass, -for any reason whatsoever, shall be reseeded or rehydroseeded and such areas and parts of areas shall be seeded repeatedly until all areas are covered with a satisfactory growth of grass. Reseeding together with necessary grading, fertilizing and trimming shall be done at the expense of the Contractor who shall spread the seed by a method approved by the Architect and during an approved season. . F. Mowing 1. The Contractor shall keep fine lawn areas moved until acceptance of the contract by cutting to a height of 2 1/2 inches when growth reaches six inches or as directed by theI Architect. 2. The Contractor shall mow the field grass areas to a height of 4t1 at the end of the growing season or as directed by theI Architect. Fieldgrass areas shall be moved at least once prior to acceptance of the Contract. END OF SECTION I ~~~~~~~~~~SECTION 02653 FILTER FABRIC I ~~PART I - GENERAL A. Work Included: Furnish and install mira drain drainage panels with I ~ ~~Filter fabric on one side only of the type and in the location as shown on the Drawings and specified herein. B. Acceptable Manufacturers: 1. Mirafi Inc. 3 ~~PART 2 -PRODUCT A. Materials: * ~~~~1. The filter fabric shall consist of continuous filament fibers which are formed into a sheet by heat bonding. It shall be tear resistant and be capable of conducting water. I ~~~~2. The fabric shall retain its durability and strength when it is wet. 3. The fabric shall not decompose under all soil conditions such as high acidity, alkalinity, or salinity. 4. The drainage core shall have a minimum compressive strength of 4000 3 ~~~~~psf. PART 3 - EXECUTION * ~~~A. installation: 1. Trench shall be clean and free from sharp objects such as roots and 3 ~~~~~stones. 2. The filter fabric shall be lapped a minimum of 6-inches when joining 3 ~~~~~two pieces together. 3. Care shall be taken when dropping backfill into the trench. 4. Filter fabric damaged during or prior to installation shall be I ~ ~~~~removed and replaced at no additional cost to the Owner. * ~~~~5. Tips shall be cut off of core dimples to drain into weep holes. 6. Installation shall be according to manufacturers recommendations. END OF SECTION SECTION 026601 EROSION CONTROL Descript ion 1.1 This work shall consist of furnishing and placing mulch on surfaces prepared and seeded under other items, at locations shown on the plans orI Materials 2.1 Mulch shall consist of late cut, matured, and cured hay. When air-dried in the loose state for 24 hours, the contents of a representative bale shall lose not more than 15 percent of the original weight of the bale. It shall beI free from primary noxious weed seeds and rough or woody materials. Construction Requirements 3.1 Mulch 3.1.1 Mulching shall be done immediately after each area has been properlyI prepared. When seed for erosion control is sown prior to placing the mulch, the mulch shall be placed on the seeded areas within 48 hours after seeding. Hay that has been thoroughly fluffed shall be applied at approximately, butI not to exceed 3 tons per acre unless ordered. Blowing chopped mulch will be permitted when authorized. Authorization will be given when it can be determined that the mulch fibers will be of such length and applied in such a manner that there will be a minimum amount of matting that would retard theI growth of plants. Matted mulch or bunches shall be removed or otherwise taken care of to the satisfaction of the Engineer. 3.1.2 in order to prevent its being blown away, after the mulch has been spread to the required depth, a light covering of loose branches, a system of pegs and strings, or other approved method shall be employed. Unless otherwise ordered, such means of control shall be removed prior to the acceptance of the project. 3.2 Maintenance 3.4.1 The Contractor shall maintain areas mulched with no extra compensation, until the completion of the contract. END OF SECTION SECTION 02694 FOOTING DRAINS U ~~~PART I - GENERAL 1.01 DESCRIPTION A. Work included in this Section: Furnish and install PVC Footing Drain Pipe and fittings of type and U ~ ~~~~size specified herein. PART 2 - PRODUCTS 3 ~~~2.01 MATERIALS 3 ~~~~A. Pipe and Fittings I1. Heavy wall perforated PVC. All pipe to be 2" diameter. Couplings and fittings shall be of the same materials as the 3 ~~~~~~~pipes. 2. Filter fabric (surrounding the drainage panel) shall be 3 ~~~~~~recommended by drainage panel manufacturer. PART 3 - EXECUTION 3 ~~~3.01 PLACING OF PIPE A. Pipe shall be bedded in a 1 1/2" layer of mortar and shall pitch to drain to the river. Do not install defective pipe. Lay pipe in I ~ ~~~~accordance with manufacturer's recommendations as approved by the Architect/Engineer. U ~~~~~~~~~END OF SECTION SECTION 02701 SIDEWALKS - BRICK 1.1 This work shall consist of the construction of sidewalks as shown on the plans or ordered. Materials 2.1 Bricks shall conform to AASHO M114, Grade SW 2.2 Portland Cement Concrete shall be Class A conforming to 911. 2.3 Steel Mesh shall conform to AASHO M 55. 2.5 Cement Mortar shall conform to BOCA Section 1114 1984 Edition. Construction RequirementsI 3.1 Brick Sidewalk 3.1.1 Subgrade and base. The subgrade shall be carefully graded and compacted. The base concrete shall be poured to the cross-section shown on the plans. The surface shall be pitched at 1/16" per foot away from graniteI 3.1.2 Mortar. After concrete base has set spread 1/2 inch of mortar. The mortar shall be proportioned in accordance with BOCA Table 1114.2.1 For Type SI 3.1.3 Setting the brick. The brick shall be set in the wet mortar in a standard pattern. The bricks shall be wetted before use. Set the bricks firmly in place, leaving a 1/2" joint between them and tamp into them mortar. After the brick have been set for 24 hours, sweep fine sand into the joints. 3.2 Concrete Base 3.2.1 Excavation shall be made to the required depth and to a width that will permit the installation and bracing of the forms. The foundation shall be shaped and compacted to a firm, even surface conforming to the section shown on the plans. All soft and yielding material shall be removed and replaced with acceptable material. 3.2.2 Forms shall be of wood or metal and shall extend for the full depth of the concrete. All forms shall be straight, free from warp, and of sufficientI strength to resist the pressure of the-concrete without springing. Bracing and staking of forms shall be such that the forms remain in both horizontal and vertical alignment until their removal. 3.2.3 The foundation shall be thoroughly moistened immediately prior to the placing of the concrete. The proportioning, mixing, and placing of the concrete shall be in accordance with 3.2.4 Polypropylene fiber reinforcing shall be thoroughly mixed into the concrete in accordance with the manufacturers recommendations. 3.2.5 The concrete base shall be placed in alternate slabs 30 feet in length except as otherwise ordered. 3.2.6 Concrete shall be moisture :-ured for at least seven days. Curing shall be by means of moist burlap or mats or by other approved methods. During the curing period, all traffic, both pedestrian and vehicular, shall be excluded. Vehicular traffic shall be excluded for such additional time as the Engineer may direct. END OF SECTION SECTION 02901 GRANITE BLOCKS PART I1-GENERAL 1.1 Description Granite blocks are on site and are to be reset as shown and directed on theI plans. END OF SECTION DIVISION 3 CONCRETE Scope of Work Furnish, install, and test all concrete work and appurtenant work in complete I ~ ~accordance with the Drawings and Specifications. 3 ~~Contractor's Duties Except as specifically noted, provide and pay of all labor, materials, equipment, tools, machinery, water, heat, other facilities, and services necessary for proper execution and completion of the work. I ~~Contents of Division Section No. Section Title Page No. 03000 Concrete - General 03001-1 03300 Cast-in-Place Concrete 03300-1 03380 Cement Mortar 03380-1 I ~~~~~~~~~~~SECTION 03000 CONCRETE - GENERAL PART I - GENERAL 1 ~~1.1 Description A. Work Included: Furnish and install all concrete work of the type(s) and size(s) and in the locations shown on the Drawings and as I ~ ~~~~specified herein. B. Related Work Specified Elsewhere (When Applicable) 1. Cast-in-place concrete finishing and curing, construction and expansion joints, concrete formwork, concrete reinforcement, and concrete testing are specified in the appropriate Sections of this Division. 2. Concrete accessories and grout are specified in the appropriate I ~ ~~~~~sections of this Division. C. Other Trades: Cooperate with all other trades whose work is to be * ~~~~~coordinated with concrete work. 1.2 Quality Assurance A. Testing I. Have tests conducted as specified in the Concrete Testing Section of this Division. 2. Perform all concrete work in accordance with the latest ACI I ~ ~~~~~~Code and Manual. 1.3 Submittals to the Engineer I ~~~~A. Shop Drawings 1. Submit shop drawings in accordance with the General Conditions of the Construction Contract. I ~ ~~~2. Submit schedules and detailed setting diagrams for all reinforcing steel. 3. Submit copies of test results on all aggregates and on all mix design proportions for concrete strengths specified in this B. Informational Data 1. Have informational data available on the site at all times as a standard of reference when applicable. 2. Informational data shall consist of: a. ACI Field Reference Manual SP-15. b. PCA Manual of Concrete Mix Design, latest edition. 03000-2I 1.4 Delivery, Storage, and HandlingI A. Deliver, store and handle materials to prevent damage of any nature. B . Store cement in undamaged condition with seals and labels intact as packaged by the manufacturer. C. Store cement in weathertight bins or buildings and keep cement dry at all times. D. Store aggregate in separate piles or bins and handle in a mannerU that will minimize segregation and prevent contamination. E. Protect anchors, ties, reinforcement, and other hardware from the elements. 1.5 Job Conditions A. Wet Weather ProtectionI 1. Do not place concrete during rain, sleet, or snow unless adequate protection is provided and/or approval is obtained from the Engineer.U 2. Do not allow rain water or other weather conditions to damage the surface finish. B. Cold Weather Protection 1. Do not place concrete in an ambient air temperature belowI 400F., except by written permission from the Engineer. 2. When work is permitted by the Engineer in temperatures below 400F., make approved provisions for heating materials and theI completed work in accordance with ACI 306 and the Concrete Finishing and Curing Section of this Division. 3. The minimum temperature of concrete as placed shall be 500F. C. Hot Weather ProtectionI 1. During hot weather conditions, place concrete in accordance with ACI 305 and the Concrete Finishing and Curing Section of this Division.I 2. Place concrete at a temperature which will not cause difficulty from loss of slump, flash set, or cold joints, usually somewhat less than 900F. D. Metal Protection: Metal in contact with mortar, concrete or otherI masonry materials shall be painted with alkali-resistant coatings such as heavy bodied bituminous paint. 1.6 Acceptance of Structure A. Work which meets all applicable requirements will be accepted without qualification. B. Work which fails to meet one or more requirements, but which has been repaired to bring it into compliance, will be accepted without qualification.I C. Work which fails to meet one or more requirements and which cannot be brought into compliance may be accepted or rejected as determined by the Engineer.I 03000-3 D. Concrete failing to meet the strength requirements as specified in the Concrete Testing Section of this Division, may require additional curing as directed by the Engineer. Modifications may be required in the concrete mix design for the remaining concrete work, at the Contractor's expense. I ~~1.6 Acceptance of Structure (Continued) E. Formed surfaces larger or smaller than dimensional tolerances specified in this Division may be rejected. If the Engineer permits the Contractor to correct the error, such correction shall be as directed and in such a manner as to maintain the strength, function, and appearance of the structure. I ~ ~~F. Concrete members cast in the wrong location may be rejected and shall be removed at the Contractor's expense if the strength, appearance or function of the structure is adversely affected. G. The strength of the structure in place will be considered potentially deficient if it fails to comply with any of the following requirements: 1. Low concrete strength as evaluated by the requirements of this I ~ ~~~~~~Divisiton. 2. Reinforcing steel size, quantity, strength, position, or arrangement at variance with the Drawings. I ~ ~~~3. Concrete which differs from the required dimensions or locations in such a manner as to reduce the strength. * ~~~PART 2 -PRODUCTS 2.1 Materials A. Materials are specified in the following Sections in this Division. END OF SECTION SECTION 03300 CAST-IN-PLACE CONCRETE PART - GENERAL 1.1 Description A. Work Included - Furnish and install the following, as shown on the Drawings and specified herein: 1. Cast-in-place concrete, including walls and slabs and other concrete work shown on the DRAWINGS. Refer to the Site Drawings for details of site improvement items fabricated from concrete. 2. Formwork for cast-in-place concrete. 3. Reinforcing steel for cast-in-place concrete. 4. Waterstops and moisture barriers. 5. Do all cutting, patching and repairing of concrete which may be required for proper completion of the work. 6. Control joints in slabs. 7. Expansion joint filler at perimeter and other locations of slabs. 8. Install the following items furnished under the designated SECTIONS: a. Sleeves, inserts and other items required to be built into the concrete: By trade requiring same. 1.2 Reference Specifications A. "Specifications for Structural Concrete for Building" by the American Concrete Institute (ACI-301 Specification for Structural Concrete for buildings. B. "Building Code Requirements for Reinforced Concrete" (ACI-318-83). 1.3 Shop Drawings A. Submit complete shop drawings as required by the GENERAL CONDITIONS and the SUPPLEMENTARY CONDITIONS. B. Provide shop drawings for fabricating and placing reinforcing steel. Show all required information for cutting, bending and placing reinforcing bars and show all accessories and support bars on placing drawings. Indicate suitable marks for placing bars. C. Fabrication of any material or performing of any work pcior to the final review of the shop drawings will be entirely at the risk of the Contractor. U ~~~~~~~~~~~~~~~~~03300-2 1.4 Testing And Control For Concrete A. The Contractor shall furnish copies of test results from the concrete supplier as listed below. Tests shall be at the expense of the concrete supplier by an independent testing laboratory and shall I ~ ~~~~have been made within the past six months. 1. Standard gradation analysis meeting these specifications. 2. Mix design proportions and additives used for concrete specified herein and for concrete of similar proportions types and strengths furnished Lo other projects. * ~~~B. Tests occasioned by changes or materials of mix proportions shall be at the expense of the Contractor. C. Tests for slump shall he made at place of deposit and in accordance with ASTM C143 by the General Contractor. Tests shall be made for I ~ ~~~~each 5 cu. yds., more or less, as approved by and in the presence of the Engineer or his representative. D. The Contractor shall ma~ke, in accordance with ASTM C31, four test I ~ ~~~cylinders for each 50 cu. yds., or one day's pour, whichever is less. Tests shall be made in accordance with method of "Test for Compressive Strength of Molded Concrete Cylinders -- ASTM C39". Cylinders shall be delivered by the General Contractor to the test-= I ~ ~~~~ing laboratory designated by the Engineer. The fourth cylinder shall be used for additional tests as necessary, being retained at laboratory for necessary period as approved by Engineer. E. Tests for air content will be made in accordance with ASTM C94, using ASTM C231 method of test. Intermediate Chase Meter tests will be made on each load of concrete or as considered necessary by the * ~~~~~Engineer's Office. 1. Results shall be sent to the Engineer's Office within three (3) days after tests are made; notify at once when tests show low test results. F. Additional Tests: Tests necessary to resolve disputes will be made by an Independent Testing Laboratory designated by the Engineer. if work is found to be deficient, testing cost shall be paid by the Contractor. If work is satisfactory, testing cost will 'De paid by 3 ~~~~~the Owner. 1.5 Notification Of Related Trades A. Notify all other trades responsible for installing inserts, sleeves, anchors, etc., when ready for such installation and for final checking immediately before concrete is placed. Cooperate with such trades to obtain proper installation. 03300-3 PART 2 - PRODUCTS 2.1 Materials For Concrete A. Cement - Portland Cement - ASTM Specification C-150, Type II, or Type II modified. B. Aggregates 1. Coarse aggregate shall be hard, durable, uncoated crushed stone or gravel conforming to ASTM Specification C-33. Coarse aggregate shall pass through sieves 1-1/2 inch. 2. Fine aggregate shall be sand, clean, hard, durable, uncoated grains free from silt, loam and clay, to meet ASTM Specification C33. C. Water - Water shall be from the local municipal supply. D. Admixtures 1. Water reducing agent: "Sonotard WR" by Sonneborn Building Products, "WRDA" by W. R. Grace & Company, "Pozzolith 100" by Master Builders Co. or equal as approved by the Engineer and conforming with ASTM 494 Type A. Water reducing agent must be by same manufacturer as air-entraining agent. 2. Air-entraining agent: "Aerolith" by Sonneborn Building Prod- ucts, "Darex" by W. R. Grace & Company, "MB-VR" by Master Builders Company, or equal approved by the Engineer conforming to ASTM C-260. To be used to obtain percent air-entrainment specified unless obtained by cement used. 3. Noother admixtures may be used without Engineer approval. Calcium chloride will not be permitted. E. Concrete Reinforcement l. Reinforcing steel shall conform to ASTM Specification A-615, Grade 60. 2. Welded wire fabric shall conform to ASTM Specification A-185. 3. Fiber reinforcement shall conform to manufacturer's recommendations. 4. Bar supports, metal accessories and other devices necessary for proper assembly of concrete reinforcing shall be of standarized factory made wire bar supports. Wire for tieing shall be 18 gauge black annealed wire conforming to ASTM Specification A- 82. F. Formwork 1. Forms - Concrete surfaces without sjecial finish shall be "plyform" Class 1, B-B. EXT-DFPA or as approved by the Architect. 2. Form Oil - Oil shall be of a non-staining type, specifically manufactured for concrete forms. 03300-4 3. Form Ties - Factory fabricated, removable or snap back of approved design. Wire shall be at least back 1 1/2 inch from the surface and leave a hole less than 1 inch in diameter after snapped. Furnish with removable wooden or plastic cones of approved sizes where called for on: the Drawings. G. Joint filler at slap perimeters - 1/4 inch thick asphalt impregnated board, of same depth as slab less 3/4 inch for sealer, by Burke, W. R. Meadows, Johns Manville or Hlohmaii a*id Barnard. 2.2 Storage Of Materials A. All materialsshall be stored to prevent damage from the elements and other caused. B. Cement and aggregates shall be stored in such a manner as to prevent deterioration or instruction of foreign matter. Any 1nqter;als which have deteriorated, or which have been damaged, shall not be used for concrete. C. Store reinforcement steel on wood skids to protect if from weather, or, earth and damage from trucking or other construction operations. Reinforcement shall be free from loose mill scale, rust, from oil, concrete spatter and other extraneous coating at the time it is embedded in the concrete. D. All forms shall be stored in a neat manner and orderly fashion. protected from the weather and abuse. E. Materials which are judged not acceptable for this project shall not be stored on the site, but shall be immediately removed from the site. 2.3 Proportioning and Design of Mixes A. Prepare design mixes for each type of concrete. Use an iadependent testing facility acceptable to the Engineer for preparing and reporting proposed mix designs. B. Proportion mixes by either laboratory trial batch or field experience methods, using materials to be employed on the project for each class of concrete required, complying with AC1 211.1 for normal weight concrete, and report to the Engineer the following data: 1. Complete identification of aggregate source of supply. 2. Tests of aggregates for compliance with specified requirements. 3. Scale weight of each aggregate. 4. Absorbed water in each aggregate. 5o Brand, type, and composition of cement. 6. Brand, type, and amount of each admixture. 7. Amounts of water used in trial mixes. 8. Proportions of each material per cu. yd. 03300-5 9. Gross weight and yield per cu. yd. of trial mixtures. 10. Measured slump.I 11. measured air content. 12. Compressive strength developed at 7 days and 28 days, from not less than 3 test cylinders cast for each 7- and 28-day test, and for each design mix. C. Submit written reports to the Engineer of each proposed mix for each class of concrete at least 15 days prior to start of work. Do not begin concrete production until mixes have been reviewed by the Engineer. D. Laboratory Trial Batches: When laboratory trial batches are used to3 select concrete proportions, prepare test specimens in accordance with ASTM C 192 and conduct strength tests in accordance with ASTM C 39, as specified in ACI 301.3 E. Field Experience Method: When field experience methods are used to select concrete proportions, establish proportions specified in ACI 301.3 F. Water-Cement Ratio Methods: If suitable data from field experience or laboratory trial batches cannot be obtained, concrete proportions may be established by use of the water-cement ratio limits table, and the limiting restrictions of ACI 301. G. Adjustments of Concrete Mixes: Mix design adjustments may be requested by the Contractor when characteristics of materials, job conditions, weather, test results, or other circumstances warrant; at no additional cost to the Owner and as accepted by the Architect. Laboratory test data for revised mix design and strength results must be submitted to andI accepted by the Architect before using in the work. H. Admixtures: 1. Use air-entraining admixture in all concrete, unless otherwise shown or specified. Add air-entraining admixture at the manufacturer's prescribed rate to result in concrete at the point of placement having air content within the following limits: a. Concrete structures and slabs exposed to freezing and thawing or subjected to hydraulic pressure:3 Nominal Max. Size of Coarse Aggregate Total Air Content 3/41" 4% to 8%3 1" ~~~~~~3.5% to 6.5% 1-1/2" ~~~~~3% to 6% b. All other concrete: 2% to 4% air.I 2. Use water-reducing admixtures in strict compliance with the manufacturer's directions. Admixtures to increase cement dispersion, or to provide increased workability for low-slump concrete, may be used at the Contractor's option subject to the Architect's acceptance. 03300-6 I. Classification of Concrete: Ultimate Regular Aggregate Strength Aggregate Size Slump Wall 3000 psi Stone 3/4"-1-1/2" 1" to 3" Gravel Slab 3000 psi Stone 3/4"-1" 3" to 4" Gravel 5. If a pumping process is utilized to convey concrete, established concrete mixtures may require increased proportion of cement and fine aggregate and a decreased proportion of coarse aggregate, but these mixtures may not be altered more than: Cement plus 20 lbs./cu. yd. Fine Aggregate plus 50 lbs./cu. yd. Coarse Aggregate minus 50 lbs./cu. yd PART 3 - EXECUTION 3o1 Forming A. Formwork shall conform to ACI 347. B. Forms shall be constructed to conform to shapes, lines and dimen- sions shown, plumb and straight and shall be maintained sufficiently rigid to prevent deformation under load. Forms shall be sufficient- ly tight to prevent the leakage of grout. Securely brace and shore forms to prevent displacement and to safely support the construction loads. C. Treat forms and form linings with a form release agent applied according to the manufacturer's instructions, by roller, brush or sprayto produce a uniform thin film without bubbles or streaks. Apply the release agent in two coats for the first use of the form and in one for each additional use. D. Removal: 1. Formwork for wall and slabs must remain a minimum of 3 days after the placement of the concrete. 3.2 Mixing Process: Use ready-mix process, ACI 301-72 Par. 7.1. 03300-7 3.3 Fabrication And Placing Reinforcing A. Fabricate rebars to the following requirements: I. Stirrups and ties +1I inchI 2. All other bends +1 inch B. Place bars to the following tolerances: 1. Concrete cover to formed surfaces + 1/4 inch 2. Minimum spacing between bars + 1/47inch 3. Top bars in slabs and beams a. Members 8 in. deep or less + 1/4 inch b. Crosswise of members - spac-ed evenly within 2 in overall. C. Lengthwise of members + 2 inch C. If the number of bars is shown on drawings the number given shall govern over the spacing.I D. Bars may be moved up to one bar diameter for conduits, pipes or embedded items. If moved more, the arrangement must be approved by the Architect/Engineer.I E. Splicing of bars and details not covered herein shall be in accordance with the recommendations of "Manual of Standard Practice for Detailing Reinforced Concrete Structures" ACI 315.I F. Supports on grade may be concrete brick or block. All other supports shall be specified in 2.lE.3 of this SECTION. G. Lap WWF mats not less than one full cross wire spacing. Use same type supports as for re-bars.I H. Obtain Engineer's approval of all splices not shown onthe project drawings. I. Do not bend reinforcement partially embedded in hardened concrete. 3.4 Embedded Items A. Comply with ACE 318, Chapter 6, Pipes Embedded in Concrete. B. Coordinate the installation of all inserts required by other trades.I Such inserts normally are to be in place prior to the placing of reinforcing steel. 3.5 Joints A. Provide construction and control joints as shown on the Drawings, but in any case limit the maximum dimensions for placement of concrete in any one pour as follows:I 1. Wall: 40 feet. Stagger section pours of all walls within minimum of 3-day delays. 2. Slabs-on-grade: 30 feet. Stagger section pours of all slabsI with minimum of 3 day delays between pours. 3. Tooled controlled joints in slabs: 15'. 03300-8 B. Constructionjoint shall be formed with keyed bulkheads. I ~ ~~~Reinforcement shall continue through the joint and additional reinforcement shall be place if indicated on the Drawings. I ~~3.6 Placing A. Notify Engineer at least 24 hours prior to each placement. B. Do not place concrete until soil bottoms, reinforcing steel and inserts, sleeves and other work to be built into the concrete have been inspected and approved by the Engineer and by all trades concerned. C. Conveying - Concrete shall be handled from the mixer to the place of I ~ ~~~final deposit as rapidly as practicable by methods which will prevent separation or loss of ingredients and in a manner which will assure that the required quality of the concrete is retained. D. Depositing - Delivery and placement of concrete shall be programmed so that the time lapse between batching and placement shall not exceed 1-1/2 hours. Concrete shall not be allowed a free fall of over 4 feet. Concrete shall be deposited as nearly as practicable I ~ ~~~in its final position to avoid segregation due to rehandling or flowing. T.". Concrete shall be deposited continuously, in horizontal layers of such thickness (not deeper than 18 inches) that no concrete will be deposited on concrete which has hardened sufficiently to cause the formation of seams or planes of weakness within the section. Placing shall be carried out at such a rate that the concrete which is being I ~ ~~~integrated with fresh concrete is still plastic. Concrete which has partially hardened or has been contaminated for foreign materials shall not be deposited. No horizontal construction joints will be I ~ ~~~~allowed in foundation walls. P. Concrete shall be compacted thoroughly by vibrating to producea dense, homogeneous mass without voids or pockets. Vibrators should be placed in concrete rapidly so as to penetrate approximately 3 inches to 4 inches into the preceding lift so as to blend the two layers. Vibrating techniques must assure that when the coarse aggregate reaches the form it stops and the matrix fills the voids. G. Place concrete as nearly as practicable to its final position to avoid segragation due to rehandling or flowing. Concrete should flow over no more than 10 feet in either direction from point of * ~~~~~discharge. 3.7 Floor And Other Flatwork Finishes A. Use a " t oed finish" * ACI 302, Sections 7.2.1 - 7.2.1-,except I ~ ~~~where notes otherwise, including tops of exposed walls. 03300-9 B. All floors shallI be screeded to the established elevations, then steel troweled level, with allowable tolerance not exceeding 1/8 inchin any direction when tested with a 10-foot long straightedge, where floors contain drains, in which case the floors shall beI pitched to drains as indicated. if either or both of the above requirements are not met, the Contractor shall, at his own expense, correct the conditions by grinding and filling, as direct by the Engineer, using materials and methods which will be compatible withI all finish and surfacing materials to be installed on floors. *Recommended Practice for Concrete Floor and Slab Construction ACI 302-69 3.8 Curing And Protection A. Protect newly placed concrete against low and high temperature effects and against rapid loss of moisture. Moist cure all concreteI for at least seven days at a temperature of at least 50 degrees F by curing methods approved by the Engineer. B. For vertical or near vertical surfaces, moist cure by keeping theI form in contact with the concrete, or by other effective means approved by the Architect/Engineer. Intermittent wetting and drying does not provide acceptable curing. Liquid curing compound as approved may be used.I C. Cure floor slabs if exposed to sun and warm weather by covering with sisal or other waterproof curing paper conforming to ASTM Specifications C 171, lapped 4 inches at edges and sealed with tapeI at least 3 inches wide. D. In hot weather, be adequately prepared to protect the concrete from the adverse influence of heat before the placement of anyconcrete. Take special precautions to avoid cracking of the concrete due to rapid drying during placement of concrete when the air temperature exceeds 70 degrees F, particularly when the work is exposed to direct sunlight. Follow "Recommended Practice for Hot WeatherI Concreting" (ACI 305-72) 1. Cool forms by fog spraying with water or by protecting them from the direct rays of the sun.I 2. If requested by the Contractor, deemed advisable by the Testing Engineer and approved by the Engineer, a retardant may be used to delay the initial set of the concrete. E. In cold weather, be adequately prepared to protect the concrete from the adverse influence of cold before placement of any concrete andI flow the "Recommended Practice for Cold Weather Concreting" (ACT- 306 latest edition)> 1. After placement, maintain all concrete at a temperature of atI least 50 degrees F for seven days. 03300-10 2. Where concrete it to be placed on hardened concrete, all laitance and foreign matter shall be removed and the surface saturated with water. A mortar cushion shall be provided against which the new concrete is to be placed. This mortar cushion shall be made with the same water content as the concrete with a slump of 6". Mortar shall be placed to a thickness of 1/2 to 1 inch and well worked into irregularities of the hard surface. 3.9 Surface Repairs A. Remove all honeycombed and other defective concrete down to sound concrete. Dampen area to be patched and area around it to prevent absorption of water from patching mortar. Areas concealed in the finished work may be filled with trowel. B. Make patching mixture of same sand and cement used in concrete. Mix not more than 1/2 to 1. Use white cement as necessary to match color of existing concrete as determined by trail patches in exposed areas. C. Limit amount of mixing water to that necessary for handling and placing. Mix mortar in advance, allow to stand with frequent manipulation with a trowel,without addition of water, until it has reached the stiffest consistency that will permit placing. D. After surface water has evaporated from the area to be patched, brush area with neat cement grout, let set until grout loses its sheen and apply the patching mortar. Pack mortar thoroughly into place, strike off to leave the patch slightly higher than surrounding surfaces to permit initial shrinkage. Leave undisturbed for at least 1 hour before finally finished. Keep patched area damp for 7 days. Finish exposed surfaces of patch to match adjacent surfaces. E. After cleaning and thoroughly dalnpening, fill tie holes with patch mortar. Finish off as above specified for all exposed areas. Tie holes not exposed in the finish work may be filled with asphalt roofing cement troweled into holes. 3.10 Cutting Of Holes A. Cut holes required by other trades in any cast-in-place concrete which did not receive sleeves. Use a core drilling process or sawing process which produces clean sharp edges and the minimum hole size which accommodates the piping,conduit, or equipment requiring the opening. B. Obtain approval of Architect/Engineer before cutting any holes for any trades. 3.11 Evaluation A. Strength: Strength of concrete shall be considered satisfactory if the average of any five consecutive strength tests of the laboratory cured specimens representing each strength of concrete is equal to or greater than the specified strength and if not more than 20 percent of the strength tests have values less than specified. 03300-11 B. Additional Tests 1. If concrete shown by laboratory strength tests is defective, the Contractor may, at his own expense, conduct such testing as he may deem uecessary. Test results so obtained, unless properly calibrated and correlated with other test data, shall not be used as a basis for acceptance or rejection. 2. If cores are taken for such determination they shall be in accordance with ASTM C42. Testing shall he by an independent laboratory approved by the Engineer. 3. At least three cores shall be taken from each potentially deficient area. Locations will be determined by the Engineer. Damaged cores may be replaced. 4. Strength of cores from each member or area shall he considered satisfactory if their average is equal to or greater than 90% of the specified strength. 5. Core holes shall be plugged solid with grout specified in this Specification. 3.12 Acceptance A. Work which meets all applicable requirements of 3.17 following will be accepted without qualification. B. Work which fails to meet one or more requirements of 3.17 following but which has been repaired to bring it into compliance will be accepted without qualification. C. Work which fails to meet one or more requirements and which cannot be brought into compliance may be accepted or rejected as determined by the Architect/Engineer. D. Concrete failing to meet the strength requirements of this Section may berequired to undergo additional curing as specified by.the Engineer. Modifications may be required to the concrete mix design for the remaining concrete work, at the expense of the Contractor. E. Formed surfaces that ave not within the tolerances specified may be rejected. If permission is granted to correct the error, such correction shall be directed and in such a manner as to maintain the strength, function and appearance of the structure. F. Concrete members cast in the wrong location may be rejected if the strength appearance or function of the structure is adversely affected. C. Inaccurately formed surfaces exposed to view may be rejected and shall be repaired or removed and replaced if required by the Engineer. H. Finished flatwork exceeding specified tolerances may be repaired by grinding high spots or by patching low spots with an approvedepoxy grout. I. Concrete exposed to view with defects which adversely affect the appearance of the structure may be repaired if possible. If, in the opinion of the Engineer, the defects cannot be repaired, the concrete may be accepted or rejected in accordance with the decision of the Engineer. 03300-12 3.13 Strength Of Structure A. The strengi:l of the structure in place will be considered potentially deficient if it fails to comply with any requirements which control the strength of the structure, as outlined below: 1. Low concrete strength as evaluated by the requirements of this Section. 2. Reinforcing steel size, quantity, strength, position or arrangement at variance with the project drawings. 3. Concrete which differed from the required dimension or locations in such a manner as to reduce the strength. B. The work will be accepted or rejected as the work is produced by the Engineer or his authorized representative. END OF SECTION SECTION 03380 CEMENT MORTAR PART 1 - DESCRIPTION 1.1 Cement mortar shall consist of either portland cement or masonry cement, mortar sand, and water. PART 2 - MATERIALS 2.1 PORTLAND CEMENT shall conform to 03300, 2.1A of these specifications. 2.2 MASONRY CEMENT shall be as portland-cement base cement meeting all the requirements of the AASHO M 150, Type II; with the additional requirement that final set shall be attained within 12 hours. 2.3 MORTAR SAND. Sand for mortar shall consist of hard, strong, durable uncoated mineral or rock particles, free firm injurious amounts of organic or other deleterious substances, and shall be uniformly graded from fine to coarse within the following limits: Sieve Size Percentage by Weight Passing No. 8 100 No. 16 60 - 100 No. 50 15 - 35 No. 100 2 - 15 No. 200 0 - 5 2.3.1 TEST FOR IMPURITIES. Mortar sand subjected to the test for organic impurities described in the AASHO T 21, and producing a color darker than the standard shall be rejected, except as provided below. 2.3.1.1 Sand for mortar failing in this test may be used, provided that, when tested for mortar making properties in the manner described in the AASHO T 71, the mortar develops a compressive strength at 7 and 28 days of not less than 95 percent of that developed by a similar mortar made from another portion of the same sample which has been washed in a 3 percent solution of sodium hydroxide followed by a thorough rinsing in water. The treatment shall be sufficient so that the washed material produces a color lighter than standard. 2.3.2 TEST FOR STRENGTH. Sand for mortar shall be of such quality that a mortar made up in a manner as described in AASHO, T 71 shall develop a compressive mortar specified in that method as the basis of comprison. 2.4 WATER shall meet the requirements of 03300, 2.1C of these specifications. 03380-2 PART 3 - PROPORTIONS AND PROCEDURES 3.1 Cement mortar shall be composed of I part, by volume, of either portland cement or masonry cement, (except as specified under 3.4) combined with not more than 2 parts, by volume, of damp loose mortar sand with water as * ~~~necessary to obtain the required consistency. 3.2 Within these above limits, the exact proportion may be determined by the mason for best workability. 3.3 Mixing shall be as follows: (a) To prepare a hand mixed mortar, the dry sand and cement shall be thoroughly mixed in a clean tight mortar box until the mixture is of uniform color. Water shall be added in such quantity as to form a * ~~~~~mortar of the consistency of stiff paste. (b) Machine mixed mortar shall be mixed in an approved mixer for not less than 3 minutes. The consistency shall be the same as (a). 3.4 The cement in cement mortar for ashlar or for mortar squared stone masonry shall consist of portland cement only. In mortar for brick or block masonry, hydrated lime may be substituted for 10 percent, by weight, of portland cement to obtain better workability, or masonry cement may be used instead of the portland cement-lime mixture. 3.5 Mortar shall be used within 2-1/2 hours after original mixing when the air temperature is 80OF or higher and within 3-1/2 hours when the air temperature is below 800F. Mortar not used within these time limits shall be * ~~~discarded. END OF SECTION Do Not Scan RepreD-Insert Do Not Scan Document Here Document ID: I Reoren-Insert Do Not Scan Document Here Document ID: A Page #: me, K amjo-a NORMANDEAU ASSOCIATES, INC. ENVIRONMENTAL SCIENTISTS, ENGINEERS & PLANNERS 25 NASHUA ROAD, BEDFORD, N.H. 03102 (603) 472-5191 May 15, 1986 Mr. Robert Snover Kimball Chase Company, Inc. 40 Bridge Street Portsmouth, NH 03801 Dear Mr. Snover: The enclosed represents our assessment of potential impacts related to rehabilitation of the granite seawall in Prescott Park for the City of Portsmouth. The assessment describes the action to be taken, the existing environment, the potential impacts, and mitigation suggested to lessen impacts related to this program. Sincerely, NORMANDEAU ASSOCIATES, INC. Peter C. Kinner Assistant Vice President Piscataqua Marine Laboratory 7 Pickering Avenue Portsmouth, NH 03801 603/431-5270 PCK:ksp 1.0 PROJECT PURPOSE AND NEED Prescott Park is an urban waterfront park located on the Piscataqua River in the City of Portsmouth, NH. This park is heavily utilized by city residents and tourists as a recreational area. In the summer, the Prescott Park Arts Festival brings thousands of people to the park for nightly performances. The park has various types of retaining walls along its river side (see attached location plans). The material behind these walls is fill material that is capped by grass and walkways. A 120-linear foot section (approximately) of seawall has exhibited excessive rotations and translations over the past ten years. This section is in the vicinity of the wooden fishing pier in the middle of the park. The movement of this section of wall has caused concern for its structural stability in addition to the aesthetic quality of this area of the park. The consulting firm of Kimball Chase Company, Inc. has performed an engineering assessment of the section of seawall and drawn up plans and specifications for the rehabilitation of the seawall. The construction, in summary, will require the first three courses of granite block to be removed and reset, the drainage system be rehabilitated, and a concrete diaphragm wall be installed. All work can be performed from land and with little disturbance to the marine or landside environment, if standard construction practices are followed. 2.0 PROJECT ALTERNATIVES The alternatives for this project are: 1) no action alternative; and 2) rehabilitate the section of granite seawall as proposed by Kimball Chase Company, Inc. The design shown under the preferred alternative represents the best solution that addresses the requirements of the City of Portsmouth. 2.1 NO ACTION ALTERNATIVE This action would leave the damaged seawall in place. Progressive rotations and translations are expected if no action is taken. At some point, the wall will become unstable and become a safety hazard. In addition, if no action is taken, local subsidence of abutting sidewalks is expected to continue causing unacceptable public walkways, and these walks will become a safety hazard. Under the no action alternative, there will be a greater chance for fill material behind the wall being released to the marine environment as the structure becomes less stable. 2.2 PREFERRED ALTERNATIVE Under the preferred alternative, the City of Portsmouth proposes to rehabilitate the section of seawall and the abutting walkways. Design plans and specifications have been developed by Kimball Chase Company, Inc. for the City (see attached drawings). These plans indicate that resetting the granite blocks in grout, constructing a concrete diaphragm wall, and rehabilitating the drainage system will restore the wall to its correct location and impede any future tendencies for the seawall to translate and rotate out of place. 3.0 EXISTING ENVIRONMENT Prescott Park is in the City of Portsmouth and is bordered to the north by the Piscataqua River. The Piscataqua River is 13 miles long and drains approximately 1,000 square miles. The river is tidal with a mean tidal range in the harbor of 8.4 feet (ACOE, 1984). The lower Piscataqua River and Portsmouth Harbor display one of the fastest tidal flows in the northeastern United States. The average velocity ranges from 2.6 to 4.0 knots. Water quality in the Piscataqua River meets New Hampshire Class B standards, suitable for bathing, recreation, and fish habitat. The Piscataqua River biotic communities are similar to other northeast estuaries (NAI, 1979). The system supports both a healthy benthic and plankton community. A number of fish species, such as winter flounder, Atlantic silversides. Atlantic tomcod, mummichog and killifish are nearshore resident species. Other anadromous species such as smelt, blueback herring, alewife and stocked coho salmon pass up the river to spawning areas in fresh water. Lobsters and Cancer crabs inhabit the river including areas off Prescott Park. Both lobsters and Cancer crabs are taken commercially throughout the river including areas near the project site (ACOE, 1984). The terrestrial habitat is consistent with other such recreational parks. Grass, flower beds and walkways are maintained for the enjoyment of visitors. Terrestrial animals consist of squirrels, small rodents, such as deer mice, meadow voles and Norway rats, along the shoreline. Songbirds utilize the areas and are generally acclimated to people and activity. 4.0 ENVIRONMENTAL IMPACTS ASSOCIATED WITH THE PROPOSED PROJECT 4.1 MARINE IMPACTS The impacts on the marine environment will be limited to turbidity caused by sediment being washed out while the granite wall is removed for repair. The potential for the impact will be limited to high tides exceeding +4.4' MHW. The increased turbidity will be of short duration. It is anticipated that the high flushing rate and current velocity will cause rapid dispersion of suspended and dissolved solids. Increased turbidity would be expected to impact zooplankton and fish'larvae most, by clogging feeding apparatus or gill structures. However, the local nature of this action and the dispersion capabilities of the river will make these effects negligible. Operational considerations will also further mitigate any effects of the construction. Filter fabric will be utilized to cover exposed sediments during operations. This will substantially reduce any loss of sediment to the water column. Proper engineering supervision and use of best engineering practices will eliminate any other disposal of material overboard. 4.2 TERRESTRIAL IM4PACTS The terrestrial environment will be impacted by the movement of machinery (cranes and trucks) to the project site as well as the placement and stockpiling of materials. The grass, flower beds and walkways will be replaced according to the engineering specifications in the rehabilitation plan (Kimball Chase Company, Inc. 1986). The construction activity will result in additional noise in the park as well as reduce the area for recreation. Both the noise and the reduced recreation area will be of short (1-2 mouth) duration and should not be a major problem. These impacts could be further mitigated if the construction activity is undertaken in the early spring or late fall; these are periods of much reduced activity in the park. The period of June-August would cause the greatest impact as this is the greatest period of utilization by tourists, fishermen and the Prescott Park Arts Festival. The disposal of any unacceptable fill material removed from behind the wall (see Kimball Chase Company, Inc., 1986) will be the responsibility of the contractor. This material should be removed from the site and disposed of in a proper manner in accordance with the type of material encountered. 5.0 REFERENCES CITED Kimball Chase Company, Inc. 1986. Project Manual for Rehabilitation of the Prescott Park Seawall. Prepared for the City of Portsmouth, New Hampshire. Normandeau Associates, Inc. 1979. Newington Generating Station 316 demonstration. Vol. I. 316(a) demonstration. Prepared for Public Service Co. of New Hampshire. 398 p. U.S. Army Corps of Engineers. 1984. Feasibility report for improvements to the existing federal deep-draft navigation project. April, 1983 (revised March, 1984). 75 MINUTE W-141ts FIOPMPAIIHIC) All Wh. Olt Mill 0 Pe Arm Simth Eliot 1.. I, T F 'R Y Do qu; Oil 0 06 Wentworth Mm x x, eze, -1Z Project Location Af. Q r P T 0 V T H Patina Manot. 21 KIMBALL CHA%1. company Erormwe 40 Snc*e Sirse Dvw*prmo C""U"ru Now manv"A am &21 -Oson 7 V~~~~~~~~~~~~~~~~~~~~~~~ s~~', - * Y. Granite Seawaill FOUR TREE ~ \~ r ~~~~~~~~~~PIERCE di, po~e /IIIA //i ISLAND oqC Ir SCALE' 10-1 --_0O'CATIN PLAN KIMBALL CHASE company, ifl 40 Bridge Street ClviI Portsm outh Enviroinmental New Hampshire 0:1 Engineers 403431-25M el~~~~~ - .'- .m..n a rr - P1ISCATAQUA * RIVER GRANITE SEAWALLI 7,~~~~~, -�3~~~~~~~~~~~~~Ol SCALE: Itoo SITE PLAN KIMBALL CHASE company, inc 40 Brlidge Streel Oivil Portsmouth EnvironrnenWa New Hmmpshire 038 Engineers 03-431-2S20 R~~E'F DLO4H.?, -i ~~~~~ CHIP OUjT EXISTIMP MORT^#* IN!-lP[ FACt COr 3.OC.tIt 7 JINT -T LAEC BLOCKS 11 0 1UCE. 5,HOUJJ 61W FLUSH 4 #1A socNID AE.5*tl -E ND FACEF Of BLOCKI or HENVD rSLC 1 -~_FYTCNT or NEW1 ~111CT WLK64 Ja~ WORKAN ITNT lIC A K MVIIN& SMLA I'D TO EWIT'114 PLAN NOTE' I ILA THE INSIDE FACES Of BLOCKS' 1-1I SHALL BE At IGNEP ALONC.G A STRAIGHNT LINEF "PrT%-Nf 57A 1.5 0.,.~'F AD STA./ wal, ". S2 LT-(SE-i SHEET 2) KIMBALL CHASE company, tnc. 40 Rridge Street Fivinmfti e P atmouthip011 IRFMOVF ARqD 0E FENCF GR.ANITe CAPS~TONF I lbP TW COURSES TO 13C R12.109ITIONED Al6J- Ce.-' NOTED 4 51-OV,/N MOM IT M *ff 1t1&VRT, EM13E G" INTO Apppox j1t" t EXI1ST W"HILTI HVA APHESIgVIE SATTF-R FR~OM *-ANCHOR 5Y5TErlM~j#ITI H-13P 3RD COUR.Nrt ~ ~APSULE' PR MANUrACTUIVERS TYP ALL IOINTS:(HORIZ 4 VrRfT) j'/j T-IlCk, ~.2i(IIKPAVI:Ft ON F'o 'IA &R0UTE~D. V'- ~V MoflTAI Oil 3#1 (GRANITE SPACERS MAY ~ CORbe colAVIL. CONC. 5LAS, StL0PI OF USED 'TO INSURE C-.'PACDS * AWAY FRI-It WVALtLt Kj 1iCINV, F. I 3lfrTb Yfit/ FT [SE.r PEI Al - r'~~~~-~~ A~~~ ~~OLLO~~~HI NWh CO*4C. WALL, FULL 1~.24 Or- IN~ VEIA-r JTLNGT- S0d ~4OO~ IN HORIJTS. -- ~ 100T RS a, O PVC a IO'-x -AGEN'r OR CQUAL FOR 1WEEP"VI-ES VA- 84 0- 1W M&M I O rwtvr &%tANIrC F ~ ABRIC Of% EQUAL Di-OCKC. -TO REMSAINI r- WEc VW(-IFILATIO0,5 4 NOTE ON A. It to the Cointractor'e r*6ponulbility 20 saaltaim stable *Xravations durieg all P6aafl of coanstruct ion. Care should be token to(7 locating equipment, w* ipnrary storage of - - graftite bjeink. and owcaveted Materials. ~ ' ,�, No A RCKPk$ 3. *Riault ing granular laer~ral sacavated for 170�A -.. ~ the laetollet ion of drainage systems, tencrote P CorrzRINF Id disphl-axw well 'Ind rese.tting of granite blocks ,sPtIDRM115" POLV ' amis bw Toplaeco in compacted lifts of not moto PROPYLENr FIFAER5 then to korhes each. At'v material axceavated PERt MANuIP. "FC-Orl *21-A 40.. Wm" Met 9kw ririffriA ix this dV~TifiC*- gif DATI(At.I! TYrP �.rs;IM growualo b0ackfill most be w."lmee with No 100eiiAl thaw dow Swet 2216 oprCifiCAtiaa. DETAIL A C. catractow will am gm"~ (WImiitimmal a pvad~to"mimed swig Cost &sis KIMBALLCHS company, inc 40 Aridqv Sir'eP'