'%@@ YA @v -7 L J Coastal Energy Transportation Study Phase 11, Volume I A Study of OCS Onshore.Support Bases and Coal Export Terminals Paul D. Cribbins N.C. State University c/o UNC Institute for Transportation Research and Education P.O. Box 12551 Research Triangle Park, NC 27709 COASTAL ZONE INFORMATION CENTER AAM& North Carolina Coastal Energy Impact Program Office of Coastal Management North Carolina Department of Natural Resources and Community Development HD 9567 CEIP EPORT NO. 2 .N8 C74 UGUST 1981 @ r"' All Jon CC E C' 1981 To order: Residents of North Carolina may receive a single copy of a publication free upon request. Non-residents may purchase publications for the prices listed. Because of the production costs involved, some of the publications carry a minimal charge regardless of residency. Prices for these are indicated in the price list as being "for all requests". When ordering publications please provide the publication number and title and enclose a check made payable to DNRCD. For a complete list of CEIP publications - or to place an order - contact: Coastal Energy Impact Program Office of Coastal Management N.C. Department of Natural Resources and Community Development Box 27687 Raleigh, NC 27611 Series Edited by James F. Smith Cover Design by Jill Miller Coastal Energy Transportation Study- Phase 11, Volurne@ 1 A Study of OCS Onshore Support Bases and Coal Export Terminals N by Paul D. Cribbins UNC Institute for Transportation Research and Education P.O. Box 12551 Research Triangle Park, NC 27709 The preparation of this report was financed through a Coastal Energy Impact Program grant provided by the North Carolina Coastal Management Program, through funds pro- vided by the Coastal Zone Management Act. of 1972, as amended, which is administered by the Office of Coastal Zone Management, National Oceanic and Atmospheric Ad- ministration. This CEIP grant wa's part of NOAA grant NA-80-AA-D-CZ149. Project No. 80-07 Contract No. C-6041 August 1981 U S DEPARTMENT OF COMMERCE NOAA COASTAL SERVICES CENTER Z 2234 SOUTH HOBSON AVENUE I% Z CHARLESTON SC 29405-2413 Property of CSC Library PREFACE This report summarizes work on the second phase of a three-phase study funded by the Coastal Energy Impact Program and conducted by the UNC Institute for Transportation Research and Education. Phase I of this study, conducted in 1980, identified and documented the transportation needs necessary to support a group of energy projects proposed for the coastal area of North Carolina. Following a series of interviews with industry representatives, key officials in coastal counties, and various State agencies in mid-1980, major facilities were identified, energy use scenarios were developed, and trans- portation needs were assessed. Concurrent with these tasks, an impact assess- ment methodology was developed for conducting certain Phase II tasks. The results of Phase I were documented in three reports: 1. A technical report entitled "Coastal Energy Transportation Study: An Analysis of Transportation Needs to Support Major Energy Projects in North Carolina's Coastal Zone," Phase I Report, December 1980 (180 pages); 2. A summary report entitled "Coastal Energy Transportation Study: An Analysis of Transportation Needs to Support Major Energy Projects in North Carolina's Coastal Zone," March 1981 (30 pages); and 3. An executive summary report issued by the Office of Coastal Manage- ment entitled "Special Report: First Inventory of Coastal Energy Facilities Reported," April 1981 (2 pages). All of these reports are available from The UNC Institute for Transportation Research and Education or the Office of Coastal Management in the North Carolina Department of Natural Resources and Community Development. Phase II (September 1980-August 1981) is divided into two distinct parts: 1. An assessment of impacts of the Outer Continental Shelf (OCS) oil and gas exploration and production activity with emphasis on the transportation requirements and alternative locations for on-shore support base(s) in'North Carolina, and 2. An assessment of impacts of coal exports from North Carolina with emphasis on the transportation requirements of alternative loca- tions and capacities of coal terminals. Phase III (September 1981-August 1982) is an assessment of impacts of transport and storage of all other energy feedstocks and products, including crude oil, refinery products, liquified petroleum gas, peat, wood, and biomass material. A more detailed analysis of coal transportation to North Carolina's ports will also be undertaken during Phase III. Other energy- related projects may be added at a later date. This report is one of three volumes documenting the results of Phase II as described above. These three volumes are entitled: 1. Coastal Energy Transportation Study: Volume 1, A Study of OCS Onshore Support Bases and Coal Export Terminals; 2. Coastal Energy Transportation Study: Volume 2, An Assessment of Potential Impacts of Energy-Related Transportation Developments on North Carolina's Coastal Zone; and 3. Coastal Energy Transportation Study: Volume 3, An Analysis of State and Federal Policies Affecting Major Energy Projects in North Carolina's Coastal Zone. Scheduling of tasks was designed to permit the study team to complete key activities in advance of certain critical dates. For example, many of the tasks related to OCS activity in Phase II have been completed so that state, regional, and local decisionmakers involved in the OCS program will have output prior to August 1981, the scheduled.date for OCS Lease Sale #56 by the Bureau of Land Management. The movement of export coal shipments through North Carolina is now underway. The contract with Alla-Ohio Coal Company to ship three million tons annually through the State Ports Authority (SPA) facilities in Morehead. City was announced in October 1980;. and the first shipment of export steam coal left Morehead City for Holland on May 13, 1981. Although the situation regarding the development of energy projects is constantly changing, this report is based on the most up-to-date information available at the time of printing. An additional, parallel task of this study has been the monitoring of the situation regarding all types of energy projects in the coastal zone. The dynamics of the other projects that will be included in Phase III, as well as those of the coal exports and OCS lease sale, are of interest. Since this research project began in January 1980, a significant amount of activity,has taken place in the North Carolina coastal zone with respect to proposals for new or expanded energy projects. These project proposals have been in response to changing economic conditions and dynamic corporate and private investment strategies. For example, since the Phase I report was written, the following captions from Raleigh and Wilmington newspapers reveal the "shifting attitudes" surrounding the development of the Brunswick Energy Company (BECO) refinery in Brunswick County, across-the Cape Fear from Wilmington: 11/18/80 "Building Refinery" 1/04/81 "Refinery, Smelter Debated" 1/28/81 "U.S. Agency Not Taking Stand on Refinery" 2/22/81 "BECO, E-nvironmentalists at Odds" 3/08/81 "Low Demand (for petroleum products) Closing Refineries" 4/28/81 "BECO to 'Re-evaluate' Brunswick Co. Refinery" 4/29/81 "BECO May Consider Selling Refinery Project" 5/15/81 "BECO Drops Plans to Build Oil Refinery" Contin,ued monitoring of the local, state, national, and international situations that affect the potential of energy developments in North Carolina will be continued throughout this study. iv CONTENTS Section Page Preface . . . . . . . . . . . . . . . . . . . . . . . . . Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Vi Tables . . . ... . . . . . . . . . . . . . . . . . . . . . . . . . . . vii Acknowledgments . . . . . . . . . . . . . . . . . . . . . . . . . . . viii Project Advisory Committee . . . . . . . . . . . . . . . . . . . . . . X Abstract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xii Summary and Conclusions . . . . . . . . . . . . . . . . . . . . . . . xiii 1.0 Industry Needs . . . . . . . . . . . . . . . . . . . . . . . . 1 1.1 Outer Continental Shelf Oil and Gas Development and Production . . . . . . . . . . . . . . . . . . . . . 1 .1.2 Coal Export . . . . . . . . . . . . . . . . . . . . . . . 3 2.0 Location Alternatives for OCS Support Bases . . . . . . . . . . 7 2.1 Shore Support Requirements . . . . . . . . . . . . . . . . 7 2.2 Service Bases . . . . . . . . . . . . . . . . . . . . . . 7 2.3 Siting Considerations . . . . . . . . . . . . . . . . . . 7 2.4 Site Specific Needs . . . . . . . . . . . . . . . . . . . 8 2.5 Optimal Number of Sites . . . . . . . . . . . . . . . . . 9 2.6 Identification of North Carolina Sites . . . . . . . . . . 9 2.6.1 Morehead City . . . . . . . . . . . . . . . . . . . 9 2.6.2 Wanchese . . . . . . . . . . . . . . . . . . . . . 15 2.6.3 Southport . . . . . . . . . . . . . . . . . . . . . 19 2.6.4 Wilmington . . . . . . . . . . . . . . . . . . . . 19 2.7 Site Recommendations . . . . . . . . . . . ; . . . . . . . 26 2.8 Needed Improvements . . . . . . . . . . . . . . . . . . . 29 3.0 Location Alternatives for Coal Export Terminals . . . . . . . . 31 3.1 Export Demand . . . . . . . . . . . . . . . . . . . . . . 31 3.1.1 Production and Export Projects . . . . . . . . . . 31 3.1.2 Export Constraints . . . . . . . . . .. . . . . . . 32 3.2 Alternative Development Scenarios for North Carolina Ports . . . . . . . . . . . . . . . ... . 32 3.2.1 Terminal Development--U.S. East Coast . . . . . . . 32 3.2.2 Potential for New Ports . . . . . . . . . . . . . . 34 3.2.3 Vessel Requirements . . . . . . . . . . . . . . . . 34 3.2.4 Export Scenarios . . . . . . . . . . . . . . . . . 36 3.3 Long-Range Needs . . . . . . . . . . . . . . . . . . . . . 38 3.4 North Carolina Sites . . . . . . . . . . . . . . . . . . . 38 3.4.1 Morehead City . . . . . . . . . . .. . . . . . . . . 38 3.4.2 Wilmington . . . . . . . . . . . . . . . . . . . . 43 3.5 Improvements Needed . . . . . . . . . . . . . . . . . . . 56 3.6 Summary . . . . . . . . . . . . . . . . . . . . . . . . . 58 Bibliography . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59 V FIGURES Number Paqe 1 Proximity of Support Base Sites to Lease Area No. 56 . . . . . . . . . . . . . . . . . . . . . . . . 2 2 Prospective OCS Sites--Morehead City . . . . . . . . . . . . . 1.3 3 Port of Morehead City SPA Terminal . . . . . . . . . . . . . . 1.4 4 Site 21--Radio Island . . . . . . . . . . . . . . . . . . . . 1.6 5 Prospective OCS Support Base Site-Wanchese . . . . . . . . . . . 1.8 110 6 Southport Sites . . . . . . . . . . . . . . . . . . . . . . . Z. 7 Sites 3 and 4 . . . . . . . . . . . . . . . . . . . . . . . . . 8 Sites 2 and C-8 . . . . . . . . . . . . . . . . . . . . . . . 213 9 Sites 1, 9 and C-17 . . . . . . . . . . . . . . . . . . . . . 25 10 OCS Sites 10 and 11 . . . . . . . . . . . . .. . . . . . . . . 217 11 Prospective Coal Export Terminal Sites Morehead City . . . . . . . . . . . . . . . . . . . . . . . A-1 12 Site C-12 . . . . . . . . . . . . . . . . . . . . . . . . . . 42 13 Site C-16 . . . . . . . . . . . . . . . . . . . . . . . . . . 44 14 Site C-14 . . . . . . . . . . . . . . . . . . . . . . . . . . 46 15 Site C-7 . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.8 16 American Coal Export Company Site, C-20 . . . . . . . . . . . 1 510 17 Hampstead/Scotts Hill--Site C-18 . . . . . . . . . . . . . . . 52 18 Site C-17 Phase I . . . . . . . . . . . . . . . . . . . . . . 53 19 Site C-17 Phase II . . . . . . . . . . . . . . . . ... . . . . 54 20 Port of Wilmington--SPA Terminal . . . . . . . . . . . . . . . 55 Vi TABLES Number Page 1 Estimated Resources and Offshore Infrastructure . . . . . . . 4 2 Estimated Recovery Rate for Offshore Infrastructure Development Timetable . . . . . . . . . . . . . . . . . . . . 4 3 Estimated Recovery Rate for Northern Tract Group Offshore Development Scenarios . . . . . . . . . . . . . . . 5 4 Port an d Marine Service Infrastructure Requirements for Temporary OCS Service Base . . . . . . . . . . . . . . . 10 5 Prospective OCS Support Base Sites . . . . . . . . . . . . . . 11 6 Checklist of Industry Needs OCS Support Base Sites . . . . . . 12 7 Analysis of OCS Support Base Sites . . . . . . . . . . . . . . 28 8 Coal Production and Export Projections . . . . . . . . . . . . 33 9 Capacities of Planned Coal Terminals--U.S. East Coast . . . . 35 10 Planned Coal Terminals-North Carolina . . . . . . . . . . . . 37 11 Coal Export Capacity Estimates . . . . ; . . . . . . . . . . . 39 12 Port and Marine Service Infrastructure Requirements for Coal Export Terminals . . . . . . . . . . . . . . . . . . . 40 13 Prospective Coal Terminal Sites . . . . . . . . . . . . . . . 40 14 Analysis of Coal Terminal Sites . . . . . . . . . . . . . . . 57 Vii ACKNOWLEDGMENTS SPONSOR COASTAL ENERGY IMPACT PROGRAM (CE1P) North Carolina Department of Natural Resources and Community Development Joseph W. Grimsley, Secretary Kenneth D. Stewart, Director, Office of Coastal Management James F. Smith, CEIP Coordinator RESEARCH ORGANIZATION INSTITUTE FOR TRANSPORTATION RESEARCH AND EDUCATION (ITRE) The University of North@Carolina Edwin W. Hauser, Project Manager and Chairman of Advisory Committee; Deputy Director, ITRE Paul D. Cribbins, Co-Principal Investigator Professor, Ci'vil Engtneering North Carolina State University Pau-1 D. Tschetter, Co-Principa] Investigator Associate Professor, Sociology East Carolina University John R. Maiolo,, Research Associate Chairman, Department of Sociology and Anthropology East Carolina University Mark Fisch, Research Associate Assistant Professor, Sociology East Carolina University R. Daniel Latta, P.E., Project Associate Graduate Student, Business Administration University of North Carolina at Chapel Hill Tom Marzilli, Project Associate Graduate Student, Sociology East Carolina University Viii Reba Lewis, Project Associate Graduate Student, Sociology East Carolina University Paul S. Cribbins, Project Associate Legal Consultant Institute for Transportation Research and Education Tom Messick, Project Assistant Student, Mechanical Engineering North Carolina State University Pamela L. Godwin Project Secretary Institute for Transportation Research and Education Zaneta G. Walker Research Assistant Institute for Transportation Research and Education ix PROJECT ADVISORY COMMITTEE Steven BeInton, Head, Technical Services Office of Coastal Management NC Department of Natural Resources and Community Development Jerry Ganey, Administrative Assistant to Executive Director State Ports Authority Ralph L. Godwin, Executive Director Wilmington Industrial Development, Inc. Billy Ray Hall, Assistant Director Division of Policy Development NC Department of Administration Edd Hauser, Deputy Director UNC Institute for Transportation Research and Education Sam Holcomb, Transportation Planner Systems Planning Division K Department of Transportation Mary Ellen Marsden, Research Associate Institute forResearch in Social Science University of North Carolina at Chapel Hill Bruce Muga, Professor of Civil Engineering Duke University Angela G. Skelton, Associate Director North Carolina Petroleum Council James F. Smith, CEIP Coordinator Office of Coastal Management NC Department of Natural Resources and Community Development (ex-officio member) Yates.Sorrell, Technical Director Alternative Energy Corporation Roy Stevens, Executive Director Carteret County Economic Development Council, Inc. X Eric A. Vernon, Coordinator OCS Task Force, Office of Marine Affairs NC Department of Administration John Warren, Senior Environmental Planner Operations Analysis Division Research Triangle Institute Paul Wilms, Head, Planning and Environmental Studies Environmental Management Division NC Department of Natural Resources and Community Development xi ABSTRACT Following an earlier study (Phase I) that focused on the identification and documentation of transportation facilities necessary to support major energy projects@ proposed.for the coastal area of North Carolina, this study concentrates- on two of the projects (1) on-shore support base.s for Outer Continental* Shelf (OCS) oil and gas exploration and (2) coal export terminals. In order to develop location alternatives for OCS support bases, shore support requi-rements are identified, 16 alternative sites are described,, and a parametric analysi's is utilized to select the most promising sites. Site- specific recommendations regarding infrastructure requirements and transpor- tation impacts are provided. In the case of coal exports, it is anticipated that overseas demand for steam-coal,_ whi,ch:exploded'in 1980, wi1l continue to grow during the decade. But congestion at maj.or coal ports along the eastern seaboard--Hampton Roads, Baltimore, and Philadel.phia--is not expected to be alleviated for several years. Recent estimates of delays to colliers desiring to load at Hampton Roads indicate that as many as 150 vessels are anchored and experiencing waiting periods of'50 to 60 days each. These delays and the resulting demurrage charges which average $15,.000 per day per ship are an understandable source of concern to the industry. In response to these problems, nearly two dozen U.S. ports have announced plans for new coal export facilities. This study explores plans for coal port expansion on.the east coast,. attempts to determine needed capacity, identifies.major bottlenecks including vessel size and channel depths, and seeks location alternatives for export terminals. It is evident that coal shippers are not only expanding existing export facilities in traditional eastern coal ports, but also turning to ports that have exported little or no coal in the past. Projected annual throughput of coa] exports from North Carolina's deepwater ports during the next decade are projected to be between 54 and 67 million tons by 1990. This report identifies eleven alternative terminal sites and assesses their potential impacts on the Coastal Study Area. Xii SUMMARY AND CONCLUSIONS Volume 1, A Study of OCS Onshore Support Bases and Coal Export Terminals, addresses two major projects: 1. Impacts of Outer Continental Shelf (OCS) oil and gas exploration activity; and 2. Impacts of coal export movement from North Carolina. Following an assessment of industry need s for each of these projects, transportation requirements and location alternatives for OCS on-shore support bases and coal export terminals were determined as follows. Location Alternatives for OCS Support Bases Sixteen prospective site locations for an OCS support base were identified and briefly described. Following field inspection, each of these sites (see Table 5) was reviewed to ascertain its compliance with a checklist of industry needs. Specific port and marine infrastructure requirements needed to establish temporary OCS service bases along the North Carolina coast were used as guide- lines in this process. It should be noted that four of the 16 sites under consideration (C-5, 'C-8, C-13, and C-17) are also evaluated in Chapter 3 as potential coal terminal locations. Sixteen measures of merit were used in an updated parametric analysis of the support base sites. A preliminary-analysis was presented in Table 3-4 of the Phase I report, but that analysis has been modified with respect to',sites and merit measures to reflect the most current information available as of April 1981. If all of the merit measures were equally weighted, a simple summation would reveal the best of the candidate sites. But this is obviously not the case, and engineering judgment is needed to narrow the list of candidates. Two outstanding sites were identified: Sites 17 and 23 (see Table 7). Because of their location in an existing SPA terminal at Wilmington and Morehead City, respectively, each is in the enviable position of having most of the necessary port and marine service infrastructure requirements already.provided. Having relatively little demand for capital expenditures and the ability to begin operation almost immediately will make each of these sites especially attractive to the oil and gas drilling companies. Each has at least 1,000 feet of wharf and 35 feet of channel depth available at the site. Each is in a port area previously zoned for industrial use; good rail and highway facilities are available; and storage areas, cranes, fresh water, and bunkering facilities are already provided. With the possible exception of Site 22, which has been earmarked as a bulk phosphate facility for the North Carolina Phosphate Company, all other sites would require substantial investments of time and capita] to acquire the necessary infrastructure. Xiii Although there is little to choose between the two sites, it is recom- mended that Site 23 be given top priority as a support base site because of its proximity to the Northern Tract Group in Lease Area No. 56. Both its air and water distances to the lease area are approximately half of those for Site 17, and Site 23 is much closer to the open ocean. It is further recommended that, if exploratory drilling for OCS oil and gas is undertaken in 1981 or soon thereafter, the State of North Carolina through its appropri- ate agencies should take the steps necessary to make five to ten acres of land at Site 23 on the SPA terminal property in Morehead City available for use as a temporary onshore support base site. If a second support base is needed, steps should be taken to make a similar amount of land available on the SPA terminal in Wilmington at or near Site 17. Location Alternatives for Coal Export Terminals Utilizing U.S. coal production and export projections from a series of recent national studies, estimates of East Coast coal terminal capacity were prepared. Export potential for the South Atlantic range of ports, with particular emphasis on North Carolina's two deepwater ports, was then explored. Firm commitments or announced plans to locate coal terminals in the State have been reported in the news media for five locations. If all of these plans materialize and if the announced tonnages are realistic, as much as 54 to 67 million tons of coal could be exported from North Carolina by the end of the decade. Finally, eleven prospective sites in the Coastal Study Area were described and analyzed to ascertain their suitability as future locations for coal export terminals. Specific recommendations for sites in Morehead City, along the Cape Fear River, and offshore were itemized. It is anticipated that, during Phase III of this study, alternative transportation modes or systems that could relieve anticipated bottlenecks in the coal-haul railroad network or other transportation networks will be investigated. Analysis of the coal sites was complicated by the fact that several of the sites, regardless of whether or not they are the best sites, have already been selected by coal companies as export terminal sites. As a result, Sites C-12 and C-16 in Morehead City and C-7 and C-20 in Wilmington have been pre-empted for coal terminals in the past six months. In fact., most of the better sites have either been purchased or are presently under option. With these constraints in evidence and considering the findings revealed in this chapter, the following tentative recommendations are proposed: Morehead City Sites 1. That because the planned throughput of the Alla-Ohio Valley (C-16) and Gulf Interstate (C-12) terminals will far exceed the practical capacity of the railroad line through Morehead City, future expan- sion of these terminals should be very carefully evaluated. Xiv 2. That no additional coal terminals be approved in the Morehead harbor until major changes are implemented in the land trans- portation link for coal inbound to the port. These changes could include a rail bypass, slurry pipeline, conveyor system, barge service, or some combination of systems. Cape Fear River Sites 3. That, other than a moderate-sized terminal on SPA property (Site C-17), no additional coal terminals should be sited on the east side of the Cape Fear River because of railroad grade crossing problems in Wilmington. 4. That, if additional throughput capacity is required along the Cape Fear River, Site C-5 (north of Pfizer Chemical Company) and Site C-8 (north of Town Creek) should be considered as the best of the remaining available sites. Offshore Sites 5. That, if any coal companies desire to develop an offshore export terminal complex to load coal in deep water (>60 feet), Site C-18 (Hampstead/Scotts Hill) and possibly Site C-14 (near U.S. 70 and N.C. 24 west of Morehead City) should be initially considered. XV 1.0 INDUSTRY NEEDS Seemingly endless increases in the price of imported crude oil coupled with recent political upheaval in the Middle East have underscored this nation's vulnerability in continuing to depend on foreign sources for a large part of our energy supply. The need to increase our domestic resource production and reduce our consumption of scarce fuels is well documented. Recent administrations have stressed the need for greater energy independence. The goal of reducing our oil imports in 1990 to one-half the current level has been suggested. One of the most desirable ways to attain this goal is to encourage domestic production of oil and gas--both onshore and offshore. On the demand side, the need for imported oil can be substantially reduced by converting oil-fired electric generating plants to coal-fired plants. Each of these means of attaining greater self sufficiency will impact different areas of the country in varying degrees. In the Southeast, the most promising location for increased domestic oil and gas production is the Proposed 1981 Outer Continental Shelf (OCS) Oil and Gas Lease Sale No. 56, where the U. S. Geological Survey (USGS) has estimated there are 1.4 billion barrels of oil and 2.5 trillion cubic feet of gas in the leasing area. It is assumed that production, which is expected to peak in 1993, will be gathered from the offshore production areas and transported ashore to landfalls in Georgia and North Carolina. The export of coal from the U.S. is currently increasing. Steam coal is already beginning to move out of several South Atlantic ports other than Hampton Roads, which has long been the world's leading coal port. Although some of these shipments may be destined for domestic generating plants in' New England and Florida, most of the initial demand for export steam coal is originating in Western Europe where conversion from oil to coal in the generation of electricity has taken place much more rapidly than it has in this country. Just how these two energy developments--OCS oil and gas production and coal exportation--will impact the Coastal Study Area of North Carolina and what specific concerns the State should address to mitigate their impacts, will be described in the following sections. 1.1 Outer Continental Shelf Oil and Gas Development and Production The Final Environmental Impact Statement prepared for proposed Lease Sale 56 by the Bureau of Land Management (BLM) indicates that 286 tracts totalling 1.6 million acres in Federal waters offshore North Carolina, South Carolina, Georgia, and Florida will be offered for sale in August 1981. These tracts, which are located from 16 to 111 nautical miles off the coast in water depths of 65 to 6,890 feet, are depicted in Figure 1. Sale 1 cln WANC14ESE OREHEA WILUINGTON 0 GEORGETOWN SOUTHPORT CHARLESTON SAVANNAH 00, BRUNSWICK* NORTHERN TRACT GROUP )ACKSO ILLE SOUTHERN RACT GR P LINITED s,rATES DEPARTMENT OF IN 41 BUREAU01' LAND MANA(;VMt:Nr Nr,w OR LF-ANq ol'MR CONTINLN14 L 'it ku irriuv 0 10 10 10 40 10 rROPOcU0 TRACTS FOR S.At E -Sfi ,)TATIJTL MILES FIGURE 1 PROXIMITY OF SUPPORT 6ASe SITES TO LEASE AREA No. 56 tracts are divided into two geographic groups according to their proximity to likely shore-based services. The Northern Tract Group includes 130 tracts off the North Carolina coast while the Southern Tract Group encompasses 156 tracts off the coasts of north Florida, Georgia, and South Carolina. Existing commercial ports in the South Atlantic region are also shown. Resource and offshore infrastructure estimates for proposed Sale 56, which were furnished to BLM by the Conservation District, Eastern Region, provide an insight into industry requirements. Tables 1 and 2 summarize estimates for resources and offshore infrastructure and provide an estimated timetable for development utilizing low (5% probability), mean, and high (95% probability) recovery estimates. These estimates in turn provide the basis for Northern Tract Group Offshore Development Scenarios (Table 3) which help predict the estimated number of wells and platforms as well as daily production of oil and gas. Because the Coastal Study Area of North Carolina will most likely be impacted only by exploration activities in the Northern Tract Group, estimates of industry needs in Phase II of this investigation will focus on the 130 tracts in the Northern Tract Group. OCS oil and gas development activities resulting from Lease Sale 56 could eventually produce a multiplicity of impacts on the quality of life in the Study Area Chapter 2 (Location Alternatives for OCS Support Bases) of this study will be concerned only with the requirements for and impacts created by onshore support facilities required during the exploratory drilling period. Support facility require- ments for the development drilling period will be addressed during Phase III of the study. 1.2 Coal Export Overseas demand for,steam coal, which exploded last year, is expected to continue to grow during 1981; but congestion at major coal ports along the eastern seaboard--Hampton Roads, Baltimore, and Philadelphia--is not expected to be alleviated for the next year or two. Recent estimates of delays to colliers desiring to load steam coal at Hampton Roads indicate that up to 150 vessels are anchored and experiencing waiting periods of 50 to 60 days each. Coal buyers are understandably concerned by the lengthy delays and resulting demurrage charges which industry sources indicate have been running at $18 per ton and higher. Not only are these demurrage charges passed along to buyers, but the congestion has also cost the U.S. coal industry about 8 to 10 million tons of lost sales over the past year.' There appears to be little doubt that the demand for export coal will increase drastically during the coming decade. According to a recent study published by a federal government coal export study group, port authorities, railroads, and coal products will provide the impetus for an order of magni- tude increase in U.S. coal exports in the next five years. The Interagency Coal Export Task Force projects that U.S. coal export terminal capacity could expand from the congested 94.4 million ton level of 1980 to as much "'Strong Demand for Steam Coal Expected Abroad," The Journal of Commerce, February 17, 1981. 3 TABLE 1. ESTIMATED RESOURCES AND OFFSHORE INFRASTRUCTURE Low(5%) Mean High(95%) A. Resources 1. Total Production a. Oil (billion barrels) 0.8 1.4 2.1 b. Gas (trillion cubic feet) 1.4 2.5 3.5 2. Daily Peak Production a. Oil (barrels) 216,700 326,800 490,100 b. Gas (million cubic feet) 384.9 617 841 B. Offshore Infrastructure 1. Wells Drilled a. Exploratory/Delineation 101 101 101 b. Development 360 1,299 1,299 2. Platforms Installed 13 56 56 3. Pipelines Constructed (miles)a 140 340 540 Sources: USGS, 1979and BLM, 1980. aBLM estimate. TABLE 2. ESTIMATED RECOVERY RATE FOR OFFSHORE INFRASTRUCTURE DEVELOPMENT TIMETABLE Wells Drilled Pipelines Constructed Exploration8 Developmentb Platforms Installed (miles)b Year Low Medium High Low Medium High Low Medium High Low Medium High 1982 15 15 15 1983 15 15 15 1984 15 15 15 1985 15 15 15 1986 15 15 15 1987 15 15 15 1988 21 96 96 3 12 12 40 60 90 1989 63 280 280 3 11 11 30 60 90 1990 84 264 264 3 11 11 20 60 90 1991 77 264 264 2 11 11 20 60 90 1992 62 264 264 2 11 11 20 60 90 1993 42 131 131 10 40 90 1994 12 0 0 TOTAL 101 101 101 360 1299 1299 13 56 56 140 340 540 Sources: USGA, 1979 and BLM, 1980. aDelineation wells are included with exploratory wells in this and all subsequent tables. bBLM estimate by year. 4 TABLE 3. ESTIMATED RECOVERY RATE FOR NORTHERN TRACT GROUP OFFSHORE DEVELOPMENT SCENARIOS Northern Tract Group Scenarios Wells Drilled Daily Production Exploratory Development Platforms Installed Oil (MBOPD) Gas (MMCFP) Year Low High Low High Low High Low High Low High 1982 1983 4 4 1985 9 9 1986 12 12 1987 12 12 1988 9 9 1989 0 16 0 2 0 6 0 10 1990 14 80 2 61 8 36 15 62 1991 42 160 2 8 34 96 60 165 1992 56 200 2 9 67 171 120 295 1993 42 124 92 218 165 378 1994 12 0 100 198 178 339 1995 90 179 160 307 2000 48 108 87 186 2005 30 66 53 113 TOTAL 46 46 166 580 6 25 Source: BLM, 1980. as 277.8 million tons annually by 1985.2 This projection is based on terminal 'expansion of 23 million tons already underway plus commitments for another 160.4 million tons. Even the most conservative estimates indicate a doubling of coal export capacity to 200 million tons by 1985 accompanied by a reduction in port congestion by that time. Nearly two dozen ports have announced plans for new coal export facili- ties.3 On the East Coast, expansion is underway not only at Norfolk, Newport News, and Baltimore--currently the most active coal ports--but also at Camden, New Jersey; Philadel.phia; Morehead City; Wilmington, North Carolina; Charleston; Savannah; and Brunswick, Georgia. In fact, if all the recently announced plans for export terminals materialize, coal could become the region's major export commodity during the 19801s. How the movement of these tonnages of export steam coal through North Carolina and its major ports will impact the Coastal Study Area will be explored in the chapter, "Location Alternatives for Coal Export Terminals." 21nteragency Coal Export Task Force, "Report on Ports and Ocean Transportation." December 1, 1980. -3"S.haping Up to Ship Out," Forbes, February 16, 1981. 6 2.0 LOCATION ALTERNATIVES FOR OCS SUPPORT BASES 2.1 Shore Support Requirements Three scenarios for OCS oil and gas development, which were prepared by the Bureau of Land Management in 1980, were identified in Chapter.l. Resources and offshore infrastructure needed for each scenario, as well as development timetables, were also provided. From these estimates, assump- tions can be made concerning the onshore facility requirements for proposed Lease Sale No. 56. As previously indicated, the principal concern for the Coastal Study Area is to determine the need for and potential location of onshore support facilities in the form of service bases and/or heliports. 2.2 Service Bases Previous exploration activities in this country, especially in the Gulf of Mexico, suggest that onshore support needs are met by establishing temporary service bases during initial exploration activities and permanent service bases once the oil companies have identified commercial quantities of oil or gas. Temporary service bases are usually established in existing harbors where adequate wharfage, storage, supply, and bunkering facilities are available. Ports that are congested by recreational boating or commercial shipping are generally avoided if more desirable port facilities are avail- able. Permanent service bases normally provide the same support services available at a temporary base, but more storage area is required to handle larger quantities or material associated with a higher level of offshore activity. If existing developed ports are located within 100 to 150 miles of the OCS activity, as they are in North Carolina, temporary bases will most likely be developed. 2.3 Siting Considerations Whether temporary or permanent, most service bases in the United States have been owned and operated by the energy exploration companies. Each company selects its service base sites independently, but there are certain trends in selection that facilitate the identification of optimum sites for development. During the initial stages of exploration, energy companies might logically establish a temporary service base in an existing port if adequate facilities are available and good service can be expected. The companies may prefer to lease or rent such facilities to reduce initial capital expenditures. Whether owned, leased, or rented to the exploration company, state officials have a responsibility to the citizens of North Carolina to see that the selected service base sites are those which promise the optimum combination of economic and social benefits and will have the least impact on the environment and quality of life in the Coastal Study Area. 7 Because exploration on the South Atlantic coast is not yet underway, it is reasonable to assume that one or more temporary service bases will be required in North Carolina to serve the Northern Tract leases. The following physical characteristics and facilitieS4 are usually required for a temporary service base to be located in an existing harbor: 1. Least feasible distance to offshore activity, 2. All weather harbor, 3. Channel depth of 15 to 20 feet, 4. 200 feet of available wharf, 5. 5 to 10 acres of adjacent flat (<2% slope) land, 6. Highway access, 7. Railroad access, and 8. Air access. From the Northern Tract Group Development Scenarios shown in Table 3 the following estimates of the required number of temporary service bases have been developed by BLM: 1984, 1; 1986, 1-3; 1988, 1-3. (Note: The number of service bases required would be the same for low, mean, and high resource recovery estimates.) The precise number of bases will be dependent upon such factors as the number and distribution of offshore holdings, the number of companies involved, the schedule of exploration activity, the availability of land and facilities, and the number of companies served from each lease. Thus, it appears that planning for a minimum of one temporary service base by 1984 and perhaps one or two additional bases by 1986 should be initiated. 2.4 Site Specific Needs A temporary service base should be able to provide the necessary shore support capability, including the transfer of workers, equipment, and supplies, for offshore drilling operations. A typical service base will provide berthage for crewboats and supply vessels, wharf space for trans- ferring supplies, warehouse and open storage areas, and office space. A heliport may also be provided at the support base, but there are strong arguments for establishing helicopter facilities at existing airports where air traffic control equipment already exists and where personnel can be transferred more rapidly from commdi@@ial aircraft to the drilling sites. Drilling companies will often seek service base sites in ports closest to the offshore activity if land can be leased on a short term basis. 4R. F. Weston, Inc. "Methodology for Assessing Onshore Impacts for Outer Continental Shelf Oil and Gas Development," Volume 11, 1980. 8 As a result, ports with easy access to the open ocean, adequate turning basis, and uncongested inner harbors are potentially attractive if they also contain the necessary port and marine service infrastructure. Such infra- structure includes water, utilities, transportation access, and medical, waste disposal, and communication facilities. Specific needs for temporary service bases in North Carolina, which are summarized in Table 4, are a modification of requirements previously identified in the Weston study and the Final Environmental Impact Statement (EIS) for Lease Sale 56. 2.5 Optimal Number of Sites A review of the geography of Lease Area 56 quickly reveals that the Southern Tract Group would best be served by support bases located in Jacksonville, Brunswick, Savannah, or Charleston while the Northern Tract Group most logically would be served by one or more bases in an existing North Carolina port. Tentative site locations in each of the four ports-- Morehead City, Wanchese, Southport, and Wilmington--were identified during the early-part of this study and were summarized in Table 2-1 of the Phase I Report.5 Prospective site locations, which have been updated to reflect certain changes in land use since late 1980, are listed in Table 5. Each of the 14 sites was visited by the project staff in July 1980, and again in March 1981 to ascertain its suitability for consideration as a future temporary support base location. Before an evaluation of alternative sites could be undertaken, it was necessary to attain greater specificity in the site requirements.' To this end the checklist of industry needs compiled in Table 6 enabled project personnel to gather and screen data that would subsequently assist them in reaching decisions relative to support base recommendations. 2.6 Identification of North Carolina Sites A brief description of each of the 16 prospective sites, along with its strength and limitations, is provided in the following paragraphs. 2.6.1 Morehead City--As indicated in Figure 2, the four prospective sites in the Morehead City area are located in an industrial area near the existing State Ports Authority terminal. Each is conveniently located with'respect to the 40-foot deep turning basin and ship channel and is only A miles from the open ocean. Sites preceded by a "C" designator indicate that the location is being considered both as a coal terminal and as an OCS supply base site. Site C-13: Marsh Island--Marsh Island, which is located just north' of the SPA terminal (extreme right side of Figure 3) is undeveloped and is presently being used as a spoil dumping ground by the U.S. Army Corps of Engineers. Some lightly wooded areas, along with some wetlands on the northern side of the island, make up most of the terrain. The e@st side 51TRE staff, "Coastal Energy Transportation Study," Phase I Report, .December 1980. 9 TABLE-4., PORT AND MARINE, SERVICE INFRASTRUCTURE REQUIREMENTS FOR TEMPORARY OCS SERVICE BASE 1. Land 5-10 acres of flat land (< 2% slope) on an all weather harbor 2. Waterfront 200-400 linear feet of wharf 3. Channel Depth 1'5-20 feet 4. Fuel 26,000 bbl/rig/year during drilling 5. Fresh Water 5.2 million gall'ons/rig/year during drilling & Solid Wastes Faci I ities to handle: up to 6 tons per day (including hazardous wastes) 7. Noise Up to 85 decibels, 24 hours/day 8. Communication Telephone and radio facilities 9. Medical; Hospital within 10-15 minutes of travel time 110. Highway Access Minimum two-lane: service road that will support truck loads, 11. Rail Access Spur line and storage tracks. 12. Air Access Helipad, on base or heliport at nearby airport (less than 30 minutes travel time)- 10 TABLE 5. PROSPECTIVE OCS SUPPORT BASE SITES Site Location Acreage. Morehead City C-13 Marsh Island 50 21 Radio Island 10 22 Existing SPA Terminal (NW corner) 10 23 Existing SPA Terminal (west side) 10 Wanchese 15 Adjacent to harbor 10 Southport C-5 North of Pfizer Chemical Co. 350 6 South of Pfizer Chemical Co. 200 Wilmington I Eagle Island 50 2 South of Barnards Creek 50 3 North of Snow's Cut 50-100 4 North of Snow's Cut 50-100 C-8 North of Town Creek 250 9 South of NC 133 on Brunswick R. 220 10 North of W. R. Grace Co. on NE 70 Cape Fear River 11 West of General Electric Co. on 50 NE Cape Fear River C-1 7 North end of existing SPA Terminal 10 TABLE6 CHECKLIST'OF- INDUSTRY NEEDS OC&SUPPORT BASE SITES Land Water Supplies@ 0- Area Channel Depth 0, Water w Topography Wharfr Length 9 Utilities 0 Land.;@Use 0: Access to Open Water 0: Fuel w Ownership Proximity to Channel 0 Solid Wastes Transportation Distance@ to Lease: Area Competition for Use Highway. Access 0: Air Distance Rail Access 0 Water Distance Air Access Employment, Ptrmittability e, Direct w Indirect 12 Bridge Ca I ico Creek le, a (F. Ig iL. A A bDI s 22 CONV A A a r I ne 0 IQ -------- cc U C_aj@_ , V. Towers Oil ChG 1. nk rt T minal 21' V. Beacon 0 Fag 110 1NrPACoASrAL Beacon ight 0 Light WA rEpWA y Dolphins oLight N1 0- So UND 9 7, C 'N, Money 181and r Bay Fish --------- mbstone Pt Money sland :j 0 Al Tar Landing .?q 14 q Kj Bay ro MA MN 40RT MACON\L-7 ,S.TATE PARK'' ;7zz' Paco m t er n 14oney '114ind, Wnfd a FIGURE 2 PROSPECTIVE OCS SITES--MOREHEAD CITY US Coast Gua,d tation -j Sit, @V, r@7 !Lj Z4 7m FIGURE 3 PORT OF MOREHEAD CITY SPA TERMINAL (Photo ColegooftN@ State Ports ut ri y of the island is approximately 500 feet from the 12-foot channel of the Atlantic Intracoastal Waterway. The 40-foot channel does not extend north of the parallel bridges (U.S. 70 and B&MRR). Each of these bridges provides a horizontal clearance of 80 feet for vessel traffic; the fixed highway bridge has a vertical clearance of 65 feet mean high water (MHW) while the bascule railroad bridge has a vertical clearance of 4.0 feet (MHW) when closed. As shown in Figure 2, there is no rail or highway access to Marsh Island. Site 21: Radio Island--A site encompassing approximately ten acres of land owned by SPA and located on the west side of Radio Island has been identified as a prospective supply base site. As depicted in Figure 4, this site is just north of the aviation fuel terminal on Radio Island and is close to the 40-foot channel. Good highway and rail access are available on Radio Island, but rail traffic may become congested when a planned coal terminal (C-12: Gulf Interstate Company Site) on Radio Island becomes operational. Site 22: Existing SPA Terminal (northwest corner)--Figure 3 reveals that there is little open land on the west side of :Eh-eMorehead City channel for expansion of the existing SPA terminal. The open area near the water tower in the center of the terminal has already been committed to Alla-Ohio Valley Coal Company for an export terminal. One remaining parcel of undevel- oped land still remains at the northwest corner of the SPA property, just west of the phosphate storage area. The site indicated in Figure 2 is adjacent to a relatively shallow access channel (Calico Creek) which serves a yacht basin and barges discharging phosphate from the Texasgulf Company facility on the Pamlico River. Because it is north of the bridges previously described, Site 22 would have the same access problems inherent in Site C-13, e.g., limited channel depths and bridge clearances. Site 23: Existing SPA Terminal (west side)--Just south of U.S. 70 and along the west side of the present State Ports Authority terminal is another prospective support base location--Site 23. This site is the only one identified so far that already meets most of the port and marine service infrastructure requirements listed in Table 4. It has over 1,000 lineal feet of wharf with a 35-foot channel alongside, good rail and highway facilities into the site, paved storage areas and nearby warehouses, and access to utilities and communications. Most importantly, it is ready for almost immediate occupancy without major capital expenditures and presumably would face less stringent permitting requirements because of the industrial nature of present port activity at the terminal. 2.6.2 Wanchese Site 15: Adjacent to Wanchese Boat Harbor--The general location of a prospective OCS supply base site adjaceFt to-the Wanchese boat harbor on Roanoke Island is illustrated in Figure 5. Site 15 is a 10-acre parcel of land on the north side of the harbor between Broad Creek and the boat harbor. Because of the relatively isolated location on Roanoke Island, the site would have no rail access and somewhat limited highway and air access. 15 NORTH N. c, S, P A. c tp C2 200 100 0 200 7 FIGURE 4 SITE 21--RADIO ISLAND ug Most of the prospective OCS support base sites in the Morehead City area are clustered around the State Ports Authority Terminal. Site 23 (above) along the west side of the terminal and Sites 22 and C-13 (below) along Calico Creek are shown. K31 @ I " @Ia@yii 17 8 14 714 14 12 16 'a 12 10 7 8-1 Isl du@ss S.,,d d.r." TANK Ise It ,ivn I do 3 2 3 2 3 d 00\t pi SO@d F/.,, o C) ,_v 71 45 3 2 9 3 2 -10-d Fl.t, R 0 A N 0 K S 0 U N D 1411 0 3 2 -7- PA 2 c:::p C '31 ZZZ PA cfeev Cfee 90-@@2 PIP ?'(0 2 \\\Shallolb. 0 say 9 64 $(CP 15 ? 2 4 00 812 ql' ROANOKE ISLAND C)TOWER \t mc ID x 0- nteo,,,., 0 TANK 0 K R 0 A N 0 To STATUTE MILES 0 1 2 10 10 FIGURE 5 PROSPECTIVE OCS SUPPORT BASE SITE-Wanchese Due to its proximity to the northernmost tracts in the Northern Tract Group, Site 15 is closer to the Lease Area than most of the other prospec- tive sites. However, this advantage is offset by the fact that supply vessels would have to negotiate a relatively unstable channel from the oce 'an at Oregon Inlet and then face draft limitations caused by the 8h-foot channel restriction. Several miles of dredging would be required to deepen the channel into Wanchese to the desired 15-20 feet. 2.6.3 Southport Site C-5: North of Pfizer Chemical Company--A 350-acre site just north of Pfizer Chemir'c"-al Company on the west banks of the Cape Fear River (Figure 6) has been identified as a prospective OCS supply base or coal terminal site. Due to its size and a combination of location factors,'Site C-5 might be especially attractive as a coal terminal location but will also be discussed in this section. Most of the site is on relatively high ground (farmland and woods) but is bordered along the river by marshlands and tidal flats and along its northern boundary by the intake canal for Carolina Power and Light Company's nuclear power plant. No wharf or pier facilities are available. The site is approximately 1,500 feet from the 38-foot ship channel and is only five miles from the mouth of the Cape Fear River. Highway access to N.C. 133 is provided by a good two-lane road into the site. The nearest rail access is the U.S. government-owned line serving the Sunny Point Army terminal north of the site. A spur line almost five miles in length and permission to use the federal rail link would be required. If used as a coal site, a tressle over the wetlands and a 1,700-foot T-head pier to the shipping channel would also be required. Site 6: South of Pfizer Chemical Company--A 200-acre site next to the ferry landing south of Pfizer Chemical Company (Figure 7) was identified in the Phase I report as a tentative OCS support base site; however, it has been learned that this parcel of land, which is owned by Pfizer, is not available for sale. It will therefore not receive further consideration as a potential site for a temporary support base. 2.6.4. Wilmington Sites 3 and 4: North of Snow's Cut--Two similar, 50 to 100 acre sites just north of the Snow's Cut section of the Atlantic Intracoastal Waterway (Figure 7) were identified in Phase I as prospective OCS support base sites. The sites are located between the 12-foot Atlantic Intracoastal Waterway (AIWW) channel and the U.S. Coast Guard Station. Good highway service is provided by River Road which connects to U.S. 421. The nearest rail service is about seven miles away. These sites are currently without wharf facilities and lie almost a mile from the 38-foot ship channel in the Cape Fear River. Site 2: South of Barnard's Creek--Site 2 encompases, about 50 acres on the east side of the Cape Fear River just south of Barnard's Creek (Figure 8). The site is in a larger 2,000-acre area surrounded by residential development and by the Echo Farms and Country Club Property. Rail service ends about one mile north of the site, but River Road provides good highway 19 @x 21 SIVOKli-, PT Bm 3762 !A 57'30" @.4 Al p 4 37fil ol c 5 3760 OUGHT hl c 01-IGHT 6 3758 PT FIGURE 6 SOUTHPORT SITES 20 a -F)T FIFiqE'R PCOQ@@iT-R YCLU&-'r A 17- t cl 4'AD110 @7bWEPS"-, @_ISLE A 7@_ BR8E b- co L Tto, L 1@-, 01 I_op c 04' LIGHTC Nq tA C, IBM' CAR L 1511- JND Ire, V 71 7: f Q Y Nil, -7 4.1 P/ R6 -A.Vk- 0 CAROLINA A;;, BEACH AROLINA 5 KE L FIGURE 7 SITES 3 & 4 21 Several of the potential OCS support base sites are located along the Cape Fear River. Sites 3 and 4 (above) along the Intracoastal Waterway at Snow's Cut and Site 10 (below) on the Northeast Cape Fear River are shown. ..... ..... .... ee -ee@ M mum NIP 00, NO M 22 LIGHT LIGHT N) LIG 0 1 OUGHT OL FIGURE 8 SITES 2 & C-8 access. Site 2 is approximately 20 miles from the ocean and would require extensive dredging to reach the ship channel a1most 3,000 feet away. Primary nursery ground in the Cape Fear River may restrict dredging activities. Site C-8: North of Town Creek-A 250-acre site on the west side of the Cape Fear River that might serve as either a coal terminal or an OCS support base is identified in Figure 8. The site is mostly on high ground with marsh areas and tidal flats bordering the site on the north and south sides. Land in this area has not yet been developed there is no rail or highway access into the site although the government-owned railroad is about three miles west and N.C. 133 borders the site on the west. River frontage totals 3,000 feet and distance to the deepwater channel is also about 3,000 feet. Site 1: Eagle Island--Relatively undeveloped Eagle Island (Figure 9) includes over 1,000 acres of land that have been created by spoil disposal from the Cape Fear River. This area has been used by the Corps of Engineers for many years, and new dredge disposal areas would have to be found if Eagle Island were to be utilized for other purposes. Its strategic location across the river from the existing State Ports Authority terminal actually makes it an extremely attractive site for future expansion of Wilmington public port faci1ities. U.S. 17, 74, and 76 provide excellent highway access at the north end of the island, and nearby rail access from the Seaboard Coastline Railroad is possible. The east side of Eagle Island is very close to the ship channel. Even if the island were designated for future development of the SPA terminal, there also appears to be adequate space for possible location of a temporary OCS supply base. Site 9: South of N.C. 133 on Brunswick River--Just west of Eagle Is1and across the Brunswick River (Figure 9), the SPA owns approximately 220 acres of 1and, a portion of which might be considered as a prospective support base site. Near the community of Old Towne, the site has good access to N.C. 133 but would require a two-mile rail spur. Also, the Brunswick River would require extensive,dredging because of silting in much of the lower portion of the river. No wharf facilities are presently available, and the site is almost 3,000 feet from the ship channel in the Cape Fear River. Significant environmental problems would have to be addressed at this location. Site C-17: North End of Existing SPA Terminal--In the next chapter, Site C-17 will be described in terms of its potential as a coal terminal site. If present p1ans of the Carolina Coal Export Corporation to utilize this location for an export terminal faiI to materialize, it should receive serious consideration as an OCS support base site. For the same reasons documented in the discussion of Site 23 in Morehead City--the existence of most of the necessary port and marine service infrastructure requirements-- this site should receive serious consideration. It has more than 1,000 lineal feet of wharf along the 38-foot channel of the Cape Fear River as well as good storage, service, and transportation access. Port officials have indicated that, should the site be developed as a coal terminal , other open areas at the SPA terminal could be designated for support base activities. 24 a La 0 I RTH 113 im K4 F tun Co te C 71brM WAS @@WCK; 10. I --T ZA 17 rl A CA r A AU Ll A All FIGURE 9 SITES 1, 9 & C-17 25 Site 10: North of W. R. Grace Company on Northeast Cape Fear River-- Situated,on high ground along the westbank of the Northeast Cape Fear River, Site 10 is located just north.of W. R. Grace Company (Figure .10). It contains 70 to 80 acres of undeveloped land and has excellent highway and rail access to U.S. 421 and the SCLRR whic.h border the site on the west. Although no wharf facilities-exist,, the site is only about 3,000 feet from the -upstream limit of the federal dredging.project and the nearby ship turning basin where a 25-foot channel is maintained. An important concern in considering Sites 10 and 11 for,prospective OCS supply bases is their excessive distance (30 to 35 miles) from the open ocean. Site 11: West of General Electric Company on Northeast Cape Fear River--Just upstream from Site 10 and located on the east side of the Cape Fe-ar River (Figure 10) Site 11 is the final OCS support-base.site under consideration at this time. It contains approximately 50 acres of,high -ground that would have to be provided with about two miles of access roadto reach N.C. 133 and about three miles of rail spur to cannect-with Seaboard Coa,st Line Rail-road (SCLRR) tracks. It isalso two miles further upstream from the existing dredged channel and turning:basin. 2.7 Site Recommendations Sixteen pros 'pective site locations were listed in Table 5 and briefly described in the preceding s,ecti,on of this chapter. Following field i.nspec- tion, each of the sites was revi.ewed to ascertain its compliance-with the checklist of industry,needs. shown in Table 6. Specific port and mari-ne infrastructure requirements (Table 4) needed to establis-h temporary OCS servicebases along the North Carolina coast were used as guidelines in this process. It should be noted that four of the 16 sites under.consideration (C-5, C-8, C-13, and C-17) will also beevaluated in Chapter 3 as.potential coal terminal locations. Table 7 utilizes 16 measures of merit in an updated parametric analysis of the support base sites. A preliminary analysis was.presented in Table 3- 4 of the Phase I report, but that analysis has been modified with respect to sites and merit measures to reflect the most cur-rent information available in April 1981. If all of the merit measures were equally weighted., a simple summation would reveal the best of the candidate sites. But this is obviously not the case,and engineering judgment is.needed to narrow the list of.candidates. Clearly the two outstanding sites i.n.,,Table 7 are Sites 17.and 23. Because of their location on an existing SPA terminal at Wilmington andMorehead City respectively, each is in the enviable position of having most of the necessary port and marine service infrastructure requirements already provided. Having relatively little demand for capital expenditures and the ability tobegin operation al.most immediately will make each of these sites especially attractive to the oil and gas drilling companies. Each has at least 1,.000 feet ofwharf and 35 feet of channel depth available at the site. Each is in a port area previously zoned for industrial use; good rail and highway facilities are available; and storage areas, cranes,.fresh 26 Ply V TIDAL ;agd 7 Ac' rn FIGURE 10 OCS SITES 10 & 11 27 TABLE 7. ANALYSIS OF OCS SUPPORT BASE SITES Wilmington Southport Morehead Wanchese 1 2 3 4 8 9 10 11 17 5 6 21 22 13 23 15 Acreage 1 1 2 3 2 1 1 1 2 2 1 3 3 2 2 3 Topography 3 1 1 1 2 2 1 1 1 2 1 1 1 2 1 1 Land Use 2 3 1 1 2 2 1 1 1 1 2 1 1 1 1 2 Rail Access 3 2 3 3 2 2 1 2 1 2 2 1 2 3 1 3 Access to Open Water 2 2 2 2 2 3 3 1 i 1 2 3 1 3 Proximity to Channel 1 3 1 1 2 1 1 1 3 1 1 8 .3 1 1 Channel Depth 1. 2 2 3 2 3 3 1 i 1 1 3 2 1 2 (feet) (38) (3) (12) (12) (1) (16) (5) (5) (38) (38) (38) (46) (6) (12) -1136) (81/2) Highway Access 1 2 2 2 2 1 1 2 1 3 1 2 Environmental Sensitivity 3 3 2 2 2 2 1 1 1 1 2 1 1 3 1 00 A@cheological or Historical Site 1 1 1 1 3 1 1 1 1 1 1 1 3 Competing Energy Use 2 1 1 1 2 2 2 2 3 1 3 3 2 3 2 1 Distance to Lease Area Air 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2. (miles) do (120) *0 10 0 26) --w- (58) (113) Water 3 3 3 3 3 3 3 3 8 2 2 1 1 2 (miles) (155) (150) (144) (144) (150) (155) (160) (168) (156)(136)(136) (62) (62) (62) (62) (181) Proximity to Airport 1 1 1 1 1 1 1 1 1 2 2 1 1 1 1 3 Proximity to Amenities 1 1 1 1 2 1 1 1 1 1 1 1 1 1 1 2 Permittability 3 3 2 2 3 3 2 2 1 3 2 1 1 3 1 2 water, and bunkering facilities are already provided. With the possible exception of Site 22 which has been earmarked as an $18 million bulk phosphate facility for the North Carolina Phosphate Company,6 all other sites in Table 7 would require substantial investments of time and capital to acquire the necessary infrastructure. Although there is little to choose between the two sites, it is recom- mended that Site 23 be given top priority as a support base site because of its proximity to the Northern Tract Group in Lease Area No. 56. Both its air and water distances to the lease area are approximately half of those for Site 17, and Site 23 is much closer to the open,ocean. It is further recommended that, if exploratory drilling for OCS oil and gas is undertaken in 1981 or soon thereafter, the State of North Carolina, through its appro- priate agencies, should take the steps necessary to make five to ten acres of land at Site 23 on the SPA terminal property in Morehead City available for use as a temporary onshore support base site. If a second support,base is needed, steps should also be taken to make a similar amount of land available on the SPA terminal in Wilmington at or near Site 17. 2.8 Needed Improvements If Sites 23 and 17 are selected, little in the way of transportation and other improvements will be required to make either of the sites viable support bases. As previously stated, most of the required infrastructure is already in place, but minor changes in access roads, rail spurs, utility and communication lines, waste treatment facilities, etc., may be needed to serve the expected crew and supply boats and helicopters. Detailed engineer- ing plans for the support bases have not been prepared at this phase of the study, and no cost estimates have been developed. It does appear, however, that no additional publicly financed transportation facilities will be needed to serve either of these sites. 6"Carolina Cargo," January 1981, p. 24. 29 3.0 LOCATION ALTERNATIVES FOR COAL EXPORT TERMINALS 3.1 Export Demand World demand for United States,steam coal has mushroomed since late 1979. Seaborne coal exports increased from 45 million tons in 1979 to 67 million tons in 1980, resulting in a backup of ships waiting to load at major U.S. coal ports. Especially at east coast coal facilities in Hampton Roads and Baltimore, vessel delays have become a way of life. Average demurrage in March 1981 was quoted at $15,000 per day per shi P. 7 Thus, a collier loading 75,000 long tons, waiting 40 days, and paying $15,000 per day in demurrage charges (total = $600,000) would add an $8 charge to each long ton of coal delivered. It is not surprising that a major Japanese coal user (Nippon Steel) recently announced that its demurrage bills for 1980 exceeded $40 million.8 Unfortunately, coal export terminals along the east coast of the U.S. are not only inadequate in terms of throughput capacity but also in terms of adequate channel depths. Vessel draft restrictions, created by channel depths of less than 45 feet, generally limit bulk carriers to Panamax-sized vessels (ships that can be accommodated fully loaded in the Panama Canal) of approximately 70,000 deadweight tons (dwt). These size restrictions add additional dollars to the delivered price per ton when compared with economy of scale advantages accruing to competitive colliers in the 120,000 to 150,000 dwt class that can be accommodated at deeper ports. 3.1.1 Production and Export Projections In an effort to determine the coal export potential for the South Atlantic range of ports, projections of coal demand will be reviewed against a background of U.S. coal reserves and production capacity. Recent projections indicate that if U.S. coal production continues the 5% compounded annual growth rate it has experienced since 1973, production by year 2000 should approach 2.2 billion tons annually.9 This production level would more than satisfy a 1.1 billion ton domestic demand for steam and metallurgical coal and a 350 million ton export demand. With actual 7R. Peckham, "United States Coal Ports--Time for a New Beginning," International Bulk Journal, April 1981. 8Ibid. 1R. L. Major, "U.S. Coal Reserves and Production Capabilities," paper presented at AAPA Conference on Coal and Ports, Mobile, Ala., February 17, 1981. 31 U.S. production in 1980 at 830 million tons, most observers foresee little restriction in supply potential although concern has been expressed over U.S. supply stability during periods of labor negotiations. A range of recently published production and export projections are summarized in Table 8. These have been extracted from the following major studies: 1. C. L. Wilson, Coal Bridge to the Future, Report of the World Coal Study (WOCOL), 1980. 2. "Interagency Coal Export Task Force Report on Ports and Ocean Transportation" (ICE), December 1980. 3. Forecasts by Economic Committee of the National Coal Association (NCA), 1980. 4. "The United States in the World Coal Market," distributed by Coal Exporters Association, 1979. Despite the variability in those projections, it is readily apparent-that coal exports, especially steam coal., will rise dramatically in the years ahead. 3.1.2 Export Constraints Production projections in Table 8 indicate that the United States could become the world's leading coal producer since it is unlikely that supply will be a future problem. Other factors, such as delivered cost and the impact of federal policy towards exports and market competition, could develop into major constraints. Delivered cost can be enhanced by the elimination of demurrage and the accommodation of larger vessels. Federal policy is more elusive, but certainly the posture of U.S. coal exports will be dependent in large measure on governments' response to two sensitive issues: channel dredging and the need to streamline environmental permitting. 3.2 Alternative Development Scenarios for North Carolina Ports Detailed estimates of total U.S. coal export terminal capacity, which were compiled by the Interagency Coal Task Force, were presented in Chapter 1. Expected increases in terminal capacity on the East Coast that are either planned or underway will be reviewed before alternative-development .scenarios for the North Carolina ports are determined. 3.2.1 Terminal Developments-U.S. East Coast Planned coal port expansion on the east coast is a dynamic process and much of the information related to these plans is necessarily proprietary. Significant uncertainties concerning timing, capital expenditures, and land acquisition make any compilation of future terminal capacity a risky endeavor; however, some attempt to determine present terminal commitments, especially 32 TABLE8. COAL PRODUCTION AND EXPORT PROJECTIONS Exports (million tons annually) Year Production (million tons annually) Metallurgical Steam Total 1980 830 90 1985 971-1118 (5) 55.2 (avg. of 9) 39.1 (avg. of 12) 94.3 1990 1223-1620 (4) 62.4 (avg. of 9) 68.8 (avg. of 12) 131.3 2000 1905-3077 (4) 74.4 (avg. of 4) 173.2 (avg. of 7) 247.6 Sources: WOCOL, ICE, NCA, and "International Bulk Journal" Note: Number of forecasts are in parentheses. 33 in competing east coast ports, is essential to the development of export pap acity scenarios for Wilmington and Morehead City. According to a review of east coast coal ports, the 1980 annual capacity was 51 million tons for Hampton Roads, 14 million tons for Philadelphia, and 25 million tons for New York. But expansion of existing ports is underway, and new terminals are planned along the entire coast. As illustrated in Table 9, specific plans for new coal terminals along the east coast are well developed and, if only a portion of them become a reality, the impact on local area economies and life styles may be substantial. 3.2.2 Potential for New Ports Bulk handling experience has shown that optimum effective capacity of a coal export terminal is about 65% of its maximum capacity.10 Above this level, vessel waiting time increases and congestion occurs. This is the present situation at Hampton Roads where loading facilities have been operating at about 90% of capacity. Part of the problem at Hampton Roads is that the loading system was designed to meet the multi-grade standards of the metal- lurgical coal trade where the required blends of coal are transferred from rail cars directly to the loading vessel. Practically all of the new coal terminals will be designed to handle steam coal, which,only requires ground storage and permits much faster rail car turnaround. It might be inferred from Table 9 that the east coast is rapidly moving from an undercapacity candition in 1980 to one of overcapacity by the late 1980's. Indeed, if all proposals were implemented, this could be a risk. But coal. port developments are a function of opportunity and market timing, and many of the new terminal facilities are being implemented only after firm, long-term contracts with importers have been signed. 3.2.3 Vessel Requirements Channel depths of 38 feet in the Cape Fear River and 40 feet in the Morehead City harbor somewhat restrict the size of ships that presently utilize North Carolina's two deepwater ports. This same criticism can be leveled at most U.S. ports where restricted channels limit the draft and therefore the deadweight capacity of entering vessels. Although the United States has the greatest number of coal export terminals, most are restricted to ships of the 50,000 to 70,000 dwt (Panamax) size. Few major coal-loading facilities for ships of 100,000 dwt and over exist anywhere in the world, and these are located in Western Canada, Australia, and South Africa. Most of the discharging terminals accessible to these bulk carriers over 100,000 dwt are concentrated in Western Europe and Japan. The share of these large vessels in world coal trade is steadily increasing (from 21% in 1980 to a 10J. Bowersmith, "Overview of U.S. Coal Port Capabilities and Deficiencies," Proceedings, AAPA Coal and Ports Seminar, February 17-19, 1981. 34 TABLE 9. CAPACITIES OF PLANNED COAL TERMINALS-U.S. EAST COAST Existing Throughput Planned Throughput Terminal (million toni annually) (million tons annually) New York-New Jersey 0 Jersey City 0 Stapelton, Staten Island 0 Port Reading 0.25 3-7 Port Camden 0 Alla-Ohio Valley 3 Philadelphia 0 Greenwich 0 Pier 124 3.5 10 0 Port Richmond 0 Northern Shipping Co. 1-5 Baltimore � Marley Neck (SOROS) 15-35 � Curtis Bay (Ky-Ohio Transp. Co.) 14 12 � Canton Marine Terminal (Consol.) 10-20 � Hawkins Point 10 Hampton Roads � Newport News (Chessie) 27 � Lamberts Point (N.&W) 34 � Newport News (A.T. Massey) 12 � Newport News (Utah I nt., et al.) 15 � Craney Island (VPA) 20 Morehead City � SPA (Alla-Ohio Valley) 3-12 � Radio Isiand (Gulf Interstate) 15-20 Wilmington 0 American Coal Export 6 0 Utah International 5 0 SPA Charleston 0 A.T. Massey 8-12 Savannah Elk River Resources-SCL 12-15 Brunswick Colonel's Island (SOROS) - Sources: "Marine Engineering/Lot," March 1981, "Journal of Commerce," February 17, 1981. W. White, Remarks summarizing "Atlantic Coast Port Potential" at Coal and Ports Conference, Mobile, Ala., February 18, 1981. 35 projected 36% in 1990 and 43% in 2000),11 and herein lies a basic problem for those concerned with coal termi,nal location. As vessel sizes increase, a large percentage of the bulk carriers loading in U.S. ports can-not be fully loaded. The maritime industry will be faced with either partially loading the larger vessels and "topping" them off at deeper ports, dredging deeper channels, or building new deepwater terminals offshore. This is the dilemma faced by North Carolina's ports, and its resolution to a large degree will control the number and location of future coal term- inals. Since several companies have already made commitments to export steam coal from Wilmington and Morehead City, it is apparent that they have opted, at least temporarily, to utilize smaller ships. The possibility of constructing a terminal with a submarine pipeline to deliver coal in slurry form to larger vessels at an offshore loading buoy is also being explored. 3.2.4 Export Scenarios It is evidence from Table 9 that traditional eastern coal ports-- Hampton Roads, Baltimore, and Philadephia--have plans to expand existing facilities and build new terminals. It is also evident that coal shippers are turning to ports that have exported little or no coal in the past (e.g., New York, Morehead City, Wilmington, Charleston, Savannah, and Brunswick) as potential locations for new terminals. Although it is beyond the scope of this study, it should be noted that similar plans for increasing export capacity are underway on the Gulf, Pacific, and Great Lakes coasts. Develop- ments at the ports of Mobile, New Orleans, Galveston, and Long Beach in particular suggest that the problem of increased export capacity is not unique to the east coast or to Appalachian coal. As world demand expands, growing amounts of western coal--6specially from the Powder River Basin-- will be produced and most likely exported from noneast coast ports. In the meantime, because of a well developed rail infrastructure for handling Appalchian coal, additional port capacity will be required along the Atlantic Coast. Since June 1980, numerous coal shippers, railroad officials, and consul- tants have explored the possibility of exporting coal from one or both of North Carolina's deepwater ports. Firm commitments or announced plans to locate in North Carolina have been reported by the news media for the loca- tions shown in Table 10. In addition to these five sites, an official of Wheelabrator-Frye Company announced at a recent coal conference that his firm is considering Alabama and/or North Carolina sites for a future coal slurry export terminal with offshore loading facilities to handle 12 to 15 million tons per year.12 If all of these plans materialize and no additional site selections are announced, it appears that as much as 54 to 67 million tons of coal could be exported from the state when all terminals are onstream. It should be ""Interagency Coal Export Task Force Report on Ports and Ocean Trans- portation," December 1980. 12W. McDonough, "A Slurry Export Terminal Concept," paper presented at AAPA Coal and Ports Conference, Mobile, Alabama, February 18, 1981. 36 TABLE 10. PLANNED COAL TERMINALS - NORTH CAROLINA Initial Ultimate Startup Capacity Capacity Date Terminal Site (Company) (mta) (mta) Morehead City April 1981 1. State Ports Authority Terminal (Alla-Ohio Valley Coal Co.)a 3.0 10-12 April 1984 2. Radio Island (Gulf Interstate, Inc.)b 15.0 15-20 Wilmington April 1982 3. Northeast Cape Fear River (American Coal Export Co.)c 1.5 6 4. Pleasant Oaks Plantation Brunswick Co. (Utah International)d 5 5. State Ports Authority Terminal (no contract announced)e 6-9 a Estimates announced by "Journal of Commerce," February 17, 1981. bEstimates announced by "Journal of Commerce," April 3, 1981 and "Engineering New Record," March 12, 1981. cEstimates announced by "Wilmington Morning Star," February 25, 1981 and February 28, 1981. dEstimates announced by "Wilmington Morning Star," March 12, 1981 and March 21, 1981. e Estimates announced by "Wilmington Morning Star," January 20, 1981. 37 noted that 54 to 67 million tons represent a maximum capacity and the effective capacity would probably be about 65 percent of this total. A summary of these estimates arranged in logical time frames has been assembled in Table 11. Obviously, delays in environmental permitting, financingi or construction of one or more of the projects could significantly reduce these estimates, and the totals for the decade probably represent an optimistic scenario of coal exports. 3.3 Long-Range Needs As of May 1981, only the three sites identi fied in Table 10 with fixed startup dates have announced specific intentions to begin exporting coal. Alla-Ohio Valley Coal Company loaded its first vessel in early May 1981,. while American Coal Export Company and Gulf Interstate, Inc. expect to be operational in 1982 and 1984 respectively. Detailed plans for the other firms in Table 10, plus any plans of companies yet to make public announce- ments, suggest the need for a delineation of long-range needs in terms of land, port facilities, channel depths, utilities, transportation links, easements, and other peripheral facilities. In the Phase I Report, a throughput of 6 to 10 million tons of coal annually was assumed for the prospective terminal(s) in Morehead City and a similar amount for the Wilmington terminal(s). In light of more recent data, these estimates will have to be increased and the infrastructure requirements modified. Table 12 presents recommended long-range requirements for coal export terminals. 3.4 North Carolina Sites Prospective coal terminal sites listed in Table 13 are numbered so as to provide consistency with the OCS support base sites listed in Table 5. Four of the sites (C-5, C-8, C-13, and C-17), which were identified both as potential support base and coal terminal sites, have already been described in Chapter 2. The remaining 7 coal terminal sites will be described in the following paragraphs. 3.4.1 Morehead City (Figure 11) Site C-12: Gulf Interstate Engineering Company Site on Radio Island: The Phase I Report indicated that Gulf Interstate Engineering Company had announced plans for a liquified petroleum gas terminal on this site in 1978. However, in February 1981, the Houston-based company made public plans to construct a $60 to 70 million coal export facility on Site C-12. The company intends to develop a privately-owned 74-acre parcel (Figure 12) on Radio Island with storage and loading facilities capable of handling 15 to 20 million tons of coal annually. A T-head loading pier would be constructed on the west side of the site parallel to the 40-foot ship channel. Excellent rail and good highway access is available on Radio Island. Following the issuance of environmental permits, construction would take 18 to 24 months with the first coal shipment expected in 1984. 38 TABLE 11. COAL EXPORT CAPACITY ESTIMATES (million tons annually). Morehead City Sites Wilmington Sites . Gulf American Utah SPA Date Alla-Ohio Interstate Coal International Terminal Off shore Total 1981 1.5 - - - 1.5 1982 3.0 1.5 5 3 - 7.5 1983 3.0 - 1.5 5 6 6 21.5 1984 6.0 15 6.0 5 6 12 45.5 1985 7.0 15 6.0 5 6 12 51.0 1986 8.0 15 6.0 5 7 12 63.0 1987 9.0 15 6.0 5 8 12 55.0 1988 10.0 15 6.0 5 9 13 58.0 1989 11.0 20 6.0 5 9 14 65,0 1990 12.0 20 6.0 5 9 15 67.0 39 TABLE 12. PORT AND MARINE SERVICE INFRASTRUCTURE REQUIREMENTS FOR COAL EXPORT TERMINALS 1. Land 100 to 200 acres of relatively flat land for ground storage of steam coal. 2. Wharf length 1,000 linear feet per berth. 3. Channel depth 38-40 feet. 4. Turning basin Accommodate vessels up to 60,000 dwt. 5. Reclaiming and loading capacity 6,000 net tons per hour. 6. Rail facilities Accommodate 100-car unit trains dumping 10,000 tons each into hopper. Coal can be conveyed either to stockpile or directly to shiploader. 7. Vehicular traffic Internal roads should be paved, curbed, and guttered to facilitate routine cleaning and dust suppression. B. Drainage Settling ponds sized to accept runoff from entire site. 9. Noise levels Maximum allowable noise emissions should assure that combined operational noise will not be a nuisance to near- by residents. 10. Coal dust suppression System to suppress coal dust at transfer points, including enclosed conveyors and equipment for washdown. ---- --- --- - --------- TABLE 13. PROSPECTIVE COAL TERMINAL SITES Site Location Acreage Morehead City C-13 Marsh Island 50 C-16 Alla-Ohio Valley Coal Co. site in existing SPA terminal 5 C-1 2 Gulf Interstate Engineering Co. Site on Radio Island 74 C-19 Brant Island 50 C-14 Near junction of US 70 and NC 24 200 Southport C-05 North of Pfizer Chemical Co. 350 Wilmington C-07 Utah International Site-South of Sand Hill Creek 350 C-17 North end of existing SPA terminal 58 C-18 Hampstead/Scotts Hill 100 C-20 American Coal Export Co. site on Northeast Cape Fear River 85 C-08 North of Town Creek 250 40 B0 ge C-reek Calico "ew 7- ar vy Al R, Ig f CONV SP Ia 1-J no 0 ta ------- 16 v- T@ 11agb0'r Port minal J"VrR-4C04SrA1. Beacon 0 -7@ 10 Boom 0 Beacon ight 0 Light WA rCRWAe co-o@ Jo Dolphins Aw ol-Ight N' S U N D /C \L9 Jv. Money Island Uh Bay 7- ombstone Pt Tfa money der ark Island in g Tar Land Bay 0 N11 oRr @.FOP@T MAC �TATE PAKK- V@, J. M Money' 1@)tiihd- r FIGURE 11 PROSPECTIVE COAL EXPORT TERMINAL SITES . ... .... US Coast Guard MOREHEAD CITY Station ............ 9.7 20. 2 oc, 100, 1.0 a RADIO ISLAND If 1/0L. 4 .7 C@ Scale: I"=400' a C. SITE C-12 0C. FIGURE 12 SITE C-12 Site C-16: All a-Ohio Valley Coal Company Site in Existing SPA Terminal-- In late T9-80,Alla-Ohio Valley Coal Company (AOV) of Washington, D.C. announced plans for construction of a $3 million coal handling facility on land owned by the State Ports Authority. A sketch of the stacker, reclaimer, conveyor, and coal storage area that comp,rises the AOV facility on Site C-16 is shown in Figure 13. A four--track addition to the existing rail lines permits the storage and dumping of rail cars at the terminal. Coal is stored on the ground, reclaimed, and transferred to the existing phosphate conveyor system for loading aboard ship. The existing ship berth on the east side of the SPA terminal will accommodate bulk carriers up to about 60,000 dwt. This berth and the existing conveyor belt will be shared with vessels loading phosphate for export. Initially, the AOV terminal will have an annual throughput capacity of three million tons, but the company hopes eventually to increase this level to 10 to 12 million tons. In order to achieve this magnitude of expansion, additional storage area and a new rail line bypassing Morehead City will probably be needed. Because of limited open area at the existing SPA terminal, any expansion of the AOV facility from 3 to 10 million tons throughput will almost certainly have to be provided for elsewh6re--perhaps on 38 acres of SPA-owned land on Radio Island. The possibility of a new rail line or alternative facility (slurry pipeline, conveyor belt, etc.) to relieve the present track located in the median of the main street of Morehead City is being addressed in a study performed by SOROS and Associates for Alla-Ohio Valley, the Southern Railroad, and the SPA. Site C-19: Brant Island--A low-level site within the Morehead City Harbor known as Brant Island is revealed in Figure 11. The island is presently uninhabited, has no highway or rail access, and is bounded on the south by Fort Macon State Park. Although it is conveniently located with respect to the deepwater channel, major environmental problems would have to be overcome, and it probably should be viewed only as a potential site for the long term future. Site C-14: Near Junction of U.S. 70 and N.C. 24--This site was identified in the Phase I Report as a 200-acre parcel of land just west of Morehead City and adjacent to the A&ECRR (Southern) at the junction of U.S. 70 and N.C. 24 (Figure 14). It would eliminate the movement of coal trains through the city but would require an offshore loading facility for large bulk carriers. It is identified here as a prospective site for ground storage of steam coal, but in order to be a viable undertaking, would require a slurry pipeline or similar technology to connect the storage area with the offshore loading facility. Excellent rail and highway access is available at the site. 3.4.2 Wilmington Site C-7: Utah International Site South of Sand Hill Creek--Utah International, a wholly owned subsidiary of General Electric Company, confirmed in March 1981, that it holds an 18-month renewable option to buy a 350-acre tract of land on the west bank of the Cape Fear River, where it 43 loll- AIWW NEWPORT RIVER loll L 0 %%%, 00 r cj 0 Zz- c C -16 C=3: 0 Q 'IK -0000 @0 z cr U) X/ fit ji I L ,ri SCALE: 1"=400* FIGURE 13 SITE C-16 44 P @HHHH M RM I'Ii N, Mg, IM, a Export coal bound for Western Europe began flowing out of North Carolina in May 1981. After moving through the State by unit train (above) Appalachian coal is loaded aboard the "S.S. CHIHAYA" (below) at the Alla-Ohio Valley Coal Company facility in Morehead City. K 45 0 Q\ /'c 14 St arks lal)il I v 77 BM j ne aybeacon o Light oDaybeacon INTRACOASTAL Foul, o Daybeacon WATERWAY FIGURE 14 SITE C-14 hopes to build a coal export terminal. This location was previously identified in the Phase I Report and is depicted in greater detail in Figure 15. The site is part of a larger 3,000 to 4,000 acre tract known as Pleasant Oaks Plantation. Entrance to the plantation is at the junction of N.C. 133 and S.R. 1518, roughly one-half mile south of Town Creek. The property is within a riverfront corridor largely zoned for industrial use in the Brunswick County Land Use Plan. Much of the tract is on high ground, but substantial wetlands are also present. Besides the Brunswick County site, the company is also considering sites in Baltimore and Newport News. If Site C-7 is selected for development by Utah International, the company would ship coal from their mines in Kentucky and West Virginia Via the Seaboard Coastline Railroad system to the export terminal. This presumably would require federal approval for the use of the rail spur leading to the Military Ocean Terminal at Sunny Point. The company anticipates exporting at least five million tons of coal a year through whichever site is chosen. Site C-20: American Coal Export Company Site on Northeast Cape Fear River--Preliminary plans for a coal exporting facility on an 85-acre tract on the Northeast Cape Fear River were submitted to government regulatory agencies in February 1981. American Coal Export Company plans to develop a $20 to $25 million facility at Site C-20, which is.bounded by U.S. 421 and the Seaboard Coastline Railroad tracks (Figure 16). The site is zoned for heavy industry, and the company's option to purchase is good until August 15, 1981. The company hopes to begin exporting 1.5 million tons of coal to Europe by early 1982* With completion of a second phase in 1983, the facility will be exporting about 6 million tons annually. The site has several obvious advantages with respect to location and transportation access. Excellent highway access is available from U.S. 421 which has a five-lane cross section. The main rail line linking Wilmington ..with the Seaboard yards at Navassa runs along the south side of Site C-20 and under U.S. 421. Thus, unit coal trains would not have to pass through Wilmington to reach the site. The major limitations of the site relate to constraints imposed upon shipping. The ship channel opposite the site is presently only 22 feet deep, the turning basin is almost a mile north of the site, and any ships loading at the site will have to pass through the restrictive Hilton Bridge (Bascule R.R.) after a 30-mile trip up the Cape Fear River. Relatively shallow channel depths will severely restrict @ vessel size unless further channel dredging is approved. The channel is now 38 feet deep upriver to the Cape Fear Memorial Bridge. From that point north to the turning basin (Figure 16), the project depth is 25 feet. Apparently, as part of an agrement with other industries upstream (W. R. Grace Company and Rumsey Marine and Drydock), the entire channel north of Cape Fear Memorial Bridge will soon be dredged to 25 feet. Site C-18: Hampstead/Scotts Hill--With a view towards the possibility of an offshore coal loading facility Seing constructed in the future, a 47 t@t I "I (n 0 NEW HANOVER NSWICK CO V4. TJ LJ f-lo - Zvi @q- ............. fun".. Plans to construct coal export terminals are being considered at several locations along the Cape Fear River. American Coal Export Company plans to develop Site C-20 (above) above the Hilton RR Bridge while Utah International holds an option on Site C-7 (below) south of Sound Hill Creek. OHE @N j @NHWH 49 44 Igd: j Q. RIVER IK @4f 311 1 iy. Et.: tentative site north of Wilmington has been identified for further study. Site C-18 (Figure 17) would be located on a portion of a 2,000 acre tract of land on the east side of U.S. 17 between the communities of Hampstead and Scotts Hill. The site is on relatively high ground overlooking the Atlantic Intracoastal Waterway, some low lying uninhabited islands, and the ocean to the east. If utilized for a coal terminal at some future date, coal would arrive by unit train on a rail spur from the SCL main line and be dumped at the site. A submarine pipeline from the storage area would then carry the coal in slurry form approximately six miles out into the ocean where an offshore loading terminal in 60 feet of water could accommodate bulk carriers up to 120,000 dwt. If larger vessels are contemplated, 90 feet of water is available about 22 miles offshore. Tradeoffs in cost of additional pipeline versus economy of scale provided by larger ships would have to be evaluated. It should be emphasized that, while no offshore coal terminals are in existence in the U.S. today, such a concept is receiving serious attention in the coal transportation community. In essence, the concept of an offshore coal terminal bypasses the existing bottlenecks at coal ports and results in new export ports without the need for conventional port infrastructure--new harbors, piers, ground transport, and expensive waterfront property. It can be implemented quickly, it may be more environmentally acceptable, it can accommodate larger ships and provide a lower ocean transport cost, and it can be readily expanded to meet growing demand. In the case of Site C-18, it offers the additional advantage of probable public acceptance in that both the coal storage area and the offshore loading facility could be designed and located so they would not be visible from or impact on inhabited areas. Site C-17: North End of Existing SPA Terminal--Although a description of Site C-17 in terms of a prospecti e OCS support base site was provided in Chapter 2, some additional remarks relative to its potential as a coal terminal are in order. An indicated in Figures 18 and 19 ' a two-phase project is envisioned that would utilize a portion of the north end ofthe SPA terminal (Figure 20) to construct a coal export terminal. Phase I (Figure 18) would include the development of a 6-acre tract east of Warehouse No. 3 to construct several 15,000 ton silos for storing coal. Coal would arrive by unit train on the SCL tracks, be stored in the silos, and then transferred by conveyor belt to Berth B for vessel load'i"ng. Annual throughput capacity of Phase I is expected to be about three million tons. Phase II would encompass plans for a 52-acre undeveloped area shown in Figure 19. Coal would arrive in the existing rail yard and be stored on the ground in 80,000 ton stockpiles. Initially, this coal would move south by conveyor belt to Berth B for shiploading. After a new loading pier, which could accommodate 65,000 dwt vessels, is constructed alongside the Phase II storage area (Berth C), the conveyor system would permit simultaneous loading of two ships. 51 25 uf] 4r LIGHTS 51 PE _77 P. U c @_@,NG A:w av. 0 ,t@,r P.@ A3 UNCIL is i_:;/ HT ..TIL)A t3; fs- GL I G'H T FIGURE 17 HAMPSTEAD/SCOTTS HILL--SITE C-18 wN 52 NZ, A 4,4 7 AREA OPEN '15 000 TON CAP"'. SILOS 4 np@ IV T-T 4N*v, STORAG, SE NO *AFIE"OUSE No 3 t!-t@ -S- TRANSIT SH D 101 TRANSIT SHED NO 2 CAPE FEAR RIVER SCALE IN FEET p 200 100 0 200 400 fg%o ow FIGURE 18 SITE C-17 PHASE I 53 A -BA L L PA L.E@CUE BASf is LITTLE T14 N El -4RT PIEDU -@7 rA L)C) Oo *s tt OF- OND x XN :.X. 6-11 000 7' v ulv S'SCL r 40 SC:ALE IN FEET 2 200 400 wo FIGURE 19 SITE C-17 PHASE II 54 Ln Ln _RF FIGURE 20 Port of Wilmington--SPA Terminal (Photo Courtesyof NC State Ports Authority) Total capacity of the entire project is estimated at nine to twelve million tons annually. Actual implementation of this project will depend upon negotiations with prospective coal shippers, since a firm contract does not presently exist. Many inherent advantages can be credit to this site as a potential coal export terminal--the SPA already owns the land, Berth B and the necessary rail facilities are in place, and of course, the SPA terminal is presently zoned and in use as an industrial entity.. Offsetting these advantages is the need to move the unit coal trains through the city of Wilmington where numerous grade crossings are encountered. 3.5 Improvements Needed Eleven prospective coal terminal sites were listed in Table 13 and described in Chapter 2 or in the preceding section of this chapter. After field inspection, each of the sites was evaluated to determine compliance with the infrastructure requirements listed in Table 12. As in the case of OCS support base sites, an updated parametric analysis for coal terminals was performed; and the results are summarized in Table 14. Analysis of the coal sites is complicated by the fact that several of the sites, regardless of whether or not they are the best sites, have already been selected by coal companies as export terminal sites. As a result, Sites C-12 and C-16 in Morehead City and C-7 and C-20 in Wilmington have been pre-empted for coal terminals in the past six months. In fact, most of the better sites have either been purchased or are presently under option. With these constraints in evidence and considering the findings revealed in this chapter, the following tentative recommendations are proposed: Morehead City Sites 1. That because the planned throughput of the Alla-Ohio Valley (C-16) and Gulf Interstate (C-12) terminals, which may total up to 32 million tons annually by 1990, will far exceed the practical capacity of the railroad line through Morehead City, future expansion of these terminals should be very carefully evaluated. 2. That no additional coal terminals be approved in the Morehead City Harbor until major changes are implemented in the land transportation link for coal inbound to the port. These changes could include a rail bypass, slurry pipeline, conveyor system, barge service, or some combi- nation of systems. Cape Fear River Sites 3. That, other than a moderate-sized coal terminal on SPA property (C-17), no additional coal terminals should be sited on the east side of the Cape Fear River because of railroad grade crossing problems in Wilmington. 56 TABLE 14. ANALYSIS OF COAL TERMINAL SITES Morehead City Southport Wilmington C-12 C43 C44 C-16 C49 C-5 C-7 C-8 C-17 C-18 C-20 Gulf Marsh- US 70 Alla- Brant Northof Utah Town SPA American Interstate Island I and NC 24 Ohio Island Pfizer I nt. Creek Terminal Hampstead Coal Acreage 2 2 1 3 2 1 1 1 2 1 2 Land Use 1 1 1 1 2 2 1 2 1 1 1 Rail Access 3 3 1 3 3 2 2 2 1 1 1 Access to Open Water 1 2 3 1 1 1 2 2 2 2 3 Proximity to Channel 1 3 3 1 1 3 3 3 1 3 1 Channel Depth 1 3 3 1 1 1 3 1 1 3 3 Highway Access 2 3 1 1 3 2 2 2 1 1 1 Environmental Sensitivity 1 3 1 1 3 2 2 3 1 2 1 Archeological or Historical Site 1 1 1 1 1 1 3 1 1 1 1 Competing Energy Use 3 2 1 2 1 2 2 3 2 1 1 Permittability 1 3 2 1 3 2 3 2 1 2 1 Legend: 1 - Good 2 - Fair 3 - Poor 4. That, if additional throughput capacity is required along the ,Cape Fear River, Site C-5 (north of Pfizer Chemical Company) and Site C-8 (north of Town Creek) should be considered as the best of the remaining available sites. Offshore Sites 5. That, if any coal companies desire to develop an offshore export terminal cpmpl,@ex to load coal in deep water (>60 feet), Site C-18 (Hampstead/Scotts Hill) and possibly Site C-14 (near U.S. 70 and N.C. 24 west of Morehead City) should be initially considered. 3.6 Summary Utilizing U.S. coal production and export projections from a series of recent national studies, estimates of East Coast coal terminal capacity were prepared. Export potential for the South Atlantic range of ports, with particular emphasis on North Carolina's two deepwater ports, was then explored. Firm commitments or announced plans to locate coal terminals in the State have been reported in the news media for five locations. If all of these plans materialize and if the announced tonnages are realistic, as much as 54 to 67 million tons of coal could be exported from North Carolina by the end of the decade. Finally, eleven prospective sites in the Coastal Study Area were described and analyzed to ascertain their suitability as future locations for coal export terminals. Specific recommendations for sites in Morehead City, along the Cape rear River, and offshore were itemized. It is anticipated that, during Phase III of this study, alternative transportation modes or systems that could relieve anticipated bottlenecks in the coal-haul railroad network or other transportation networks will be investigated. 58 BIBLIOGRAPHY The references cited in this bibliography are classified under the following topics: North Carolina Transportation Ports North Carolina State Ports OCS Impacts and Oil and Gas Studies Coal North Carolina Energy Statistics Environmental Assessments and Studies Water Resources Land Use Plans Bibliographies and Data Sources NORTH CAROLINA TRANSPORTATION Barton-Aschman Associates, Inc. 1976. Statewide Transportation Plan: Phase I Summary Report. Prepared for North Carolina Department of Transportation. Evanston, Illinois. Mulligan, Paul F. 1975. Executive Summary: Analysis of Transportation Services in North Carolina and Their Relationships to_Economic Growth Management. Prepared for North Carolina Department of Administration. Research Triangle Park, North Carolina: Research Triangle Institute. Mulligan, Paul F. 1975. Final Report: Analysis of Transportation Services in North Carolina and Their Relationships to Economic Growth, and Manage- ment. Prepared for North Carolina Department of Administration. Research Triangle Park, North Carolina: Research Triangle Institute. North Carolina Department of Transportation, Board of Transportation. 1979. North Carolina's Transportation Improvement Program, 1980-1986. Raleigh, North Carolina. 59 North Carolina Department of Transportation, Division of Highways. 1980. Highway and Road Mileage. Raleigh, North Carolina. North Carolina Department of Transportation, Office of the Assistant Secretary for Planning, Aviation Systems, Inc., and Research Triangle Institute. 1979. North Carolina Airport System Plan: Executive Summary. Raleigh, North Carolina. North Carolina Department of Transportation, Office of the Assistant Secretary for Planning, Aviation Systems, Inc., and Research Triangle Institute. 1979. North Carolina Airport System Plan: Technical Report, Book 1. Raleigh, North Carolina. North,Carolina Department of Transportation, Office of the Assitant Secretary for Planning, Aviation Systems, Inc., and Research Triangle Institute. 19'79. North Carolina Airport System Plan: Technical ReRort, Book 2. Raleigh, North Carolina. Office of the Governor. 1981. "Hunt Pledges Cooperation with New Bern Officials." News Release of March 20, 1981. Raleigh, North Carolina. Smith, Wilbur, & Associates. 1979. North Carolina Rail Plan: 1979. Prepared for North Carolina Department of Transportation, Office of Assistant Secretary for Planning. Raleigh, North Carolina. Smith, Wilbur, & Associates. 1979. Report of Governor's Blue Ribbon Com- mission on Transportation Needs and Financing. Prepared for North Carolina Department of Transportation. Raleigh, North Carolina. Stone, John R. 1981. The Impacts of Coal Movements Through North Carolina." Presented at the North Carolina Urban Affairs Conference. Charlotte, North Carolina. United States Department of Transportation, Federal Highway Administration, and North Carolina Department of Transportation. 1979. Pro osed Primary Highway Extension from 1-40 Terminus (at 1-95) near enson to Wilmington, Johnston, Sampson, Duplin, Pender, and New Hanover Counties. Administrative Action Final Environmental Impact Statement. PORTS Architecture Research Center. 1972. Port and Harbor Development System: Phase 2-Planning Summary. Texas A&M University, College of Architecture and Environmental Design. College Station, Texas. American Association of Port Authorities. 1981. Coal and Ports Seminar. Proceedings of seminar. Mobile, Alabama. Bowersmith, J. 1981. "Overview for U.S. Coal Port Capabilities and Defi- ciencies." Proceedings of AAPA Coal and Ports Seminar. February 17- 19, 1981. 60 Coal Age. November 1980. pp. 66-84. (Port Traffic & Development Status). Goodman, A. C., and Hess, A. L. 1980. Middle Atlantic Region Port Handbook: Baltimore, Philadelphia, Hampton Roads. Paper prepared for the Trans- portation Freight Conference. Baltimore, Maryland. Harlow, E. H. 1975. Artificial Offshore Islands. Lecture for Department. of Civil Engineering, State University. Raleigh, North Carolina. Harris, Frederic R., Inc. 1975. An Evaluation, Multi-Purpose Offshore Industrial-Port Islands: Civ n2ineering Considerations. Prepared for NSF/RANN. Great Neck, New York. Interagency Coal Export Task Force. 1980. "Report on Ports and Ocean Transportation." A working paper. Maritime Administration. Washington, D.C. Mascerik, John, ed. Ports '80. Proceedings from Specialty Conference spon- sored by Committee on Ports and Harbors, Waterway, Port, Coastal and Ocean Division of ASCE. May 1980. Norfolk, Virginia. New York: ASCE. McDonough, W. 1981. "A Slurry Export Terminal Concept." Presented at AAPA Coal and Ports Conference. Mobile, Alabama. Office of the Assistant Secretary of Transportation for Policy and Inter- national Affairs. 1980. Landside Transportation at Ports: A Prelim inary Assessment of Transportation Connectivity Problems at United States Ports. Washington, D.C. Office of Technology Assessment, Congressional Board of the 97th Congress. 1981. "Coal Exports and Port Development: A Technical Memorandum." Washington, D.C. Peckham, R. "United States Coal Ports-Time for a New Beginning." 1981. International Bulk Journal. United States Army Corps of Engineers. 1978. Waterborne Commerce of the United States-1977. United States Army Corps of Engineers, Lower Mississippi Valley Division. 1973. Report on Gulf Coast Deepwater Port Facilities: Texas, Louisiana, Mississippi, Alabama, and Florida. Vicksburg, Mississippi. United States Army Corps of Engineers, Lower Mississippi Valley Division. 1973. Report on Gulf Coast Deepwater Port Facilities: Texas, Louisiana Mississippi, Alabama, and Florida. Appendix E: Transportation and Costs Analysis. Vicksburg, Mississippi. United States Army Corps of Engineers, Lower Mississippi Valley Division. 1973. Report on Gulf Coast Deepwater Port Facilit.ies: Texas, Louisi- ana, Mississippi, Alabama, and Florida. Appendix F: Environmental Assessment; Environmental Impact. Vicksburg, Mississippi. 61 United States Army Corps of Engineers, Philade lphia District. 1973. Ifterim Report: Atlantic Coast Deepwater Port Facilities Study. Eastport, Maine to Hampton Roads, Virginia. Philadelphia, Pennsylvania. United States Army Corps of Engineers, Philadelphia District. 1973. Atlantic Coast Deepwater Port Facilities Study. Eastport, Maine to Hampton Roads, Virginia: Economic Analysis. Philadelphia, Pennsylvania. United States Army Corps of Engineers, Philadelphia District.. 1973. Atlantic 'toast Deepwater Port Facilities Study. Eastport, Maine to Hampton Roads', Virginia: Econoif-cs -of Tanker Size Selection. Philadelphia, Pennsylvania. United States Army Corps of Engineers, Philadelphia District. 1973. Atlantic Coast Deepwater Port Facilities Study. Eastport, Maine to Hampton Roads, Virginia: Soc.io-Economic Considerations. Philadelphia, Penn- sylvania. United States Army Corps of Engineers, South Pacific and North Pacific Divisions. 1973. West Coast Deepwater Port Facilities Study: Summary Report. United States Army Corps of Engineers, South Pacific and North Pacific Division. 1973. West Coast Deepwater Port Facilities Study: Appendix C, Transportation Economics. United States Army Corps of Engineers, South Pacific and North Pacific Division. 1973. West Coast Deepwater Port Facilities Study. Appendix E, Environmental Assessment. U.S. Department of Commerce, National Oceanic and Atmospheric Administration and National Ocean Survey. 1979. United States Coast Pilot--Atlantic Coast: Cape Henry to Key West. 17th Edition. Washington, D.C. United States General Accounting Office, Comptroller General. 1979. Report to the Congress of the United States: American Seaports--Change Affect- ing Operations and Development. United States Department of the Interior. 1974. Final@Environmental Impac Statement--Deepwater Ports. 2 volumes. United States Department of Transportation, Office of University Research. 1977. Federal Port Policy in the United States. Final Report. Spring- field, Virginia: National Technical Information Service. NORTH CAROLINA PORTS A.. T. Kearney, Inc. 1980. Water Transportation Users: Element C of the National Waterways Study. Prepared for the Institute for Water Resources, Water Resources Support Center, United States Army Corps of Engineers, Fort Belvoir, Virginia. 62 Coastal Plains Center for Marine Development Services. The Marine News- letter. Vol. 2, No. 2 (March-April 1980). Wilmington, North-E-a-rolina. Coastal Plains Center for Marine Development Services. The Marine News- letter. Vol. 2, No. 3 (May-June 1980). Wilmington, North Carolina. Godwin, G. 1980. Coal Export Potential and North Carolina Ports, In-House Work Paper. North Carolina Ports Authority. Raleigh, North Carolina. Lockwood-Greene Architects and Engineers. 1979. North Carolina State Ports Authority, Port of Wilmington: Expansi6n -Development Study. Prepared for North Carolina State Ports Authority. Spartanburg, South Carolina. Mulligan, P. F., and Collins, R. L. 1975. Executive Summary: Report of Impact of the North Carolina Ports on the State EconoTy. Prepared for North Carolina Department of Transportation and Highway Safety. Mulligan, P. F., and Collins, R. L. 1975. Final Report: Impact of the North Carolina Ports on the North Carolina Economy. Prepared for North Carolina Department of Transport@@tionand Highway Safety. North Carolina State Department of Transportation. 1973. Report: Stu of Plans for Development of.North Carolina State Ports@ Raleigh, North Carolina. North Carolina State Ports Authority. 1980. North Carolina's Ports and Waterways. Raleigh, North Carolina. Robert R. Nathan Associates, Inc., and Coastal Zone Resources Corporation. 1975. The Coastal Plains Deepwater Terminal Study. Prepared for the Coastal Plain Regional Commission. Washington, D.C. Stover, William T., Jr., ed. Carolina Cargo, December 1979-January 1980. North Carolina State Ports Authority. Wilmington, North Carolina. Stover, William T., Jr., ed. Carolina Cargo, February-March 1980. North Carolina,State Ports Authority. Wilmington, North Carolina. Stover, William T., Jr., ed. 1981. Carolina Cargo, January 1981. North Carolina State Ports Authority. Wilming n, North Carolina. Stover, William T., Jr., ed. 1981. Carolina Cargo, February 1981. North Carolina State Ports Authority. Wilmington, North Carolina. Stover, William T., Jr., ed. 1981. Carolina Cargo, March 1981. North Carolina State Ports Authority. Wilmington, North Carolina. Water Resources Support Center. 1980. The Ports of Wilmington and Morehead City, North Carolina. Prepared for the United States Army Corps of Engineers. Washington, D.C. 63 OCS IMPACTS AND OIL AND'GAS STUDIES Centaur Associates. 1976. Mana2ing the Social & Economic Impacts of Energy Developments. Prepared for the United States Energy Research and Development Administration. Washington, D.C. Center for Natural Areas. 1979 A Summary and Analysis of Environmental Information on the Continental-Shelf and Blake Plateau from Cape Hatteras to Cape Canaviral. United States Department of Commerce. Washington, D.C. Clark, John. 1974. Coastal Ecosystems: Ecological Considerations for Management of.the Coastal Zone. The Conservation Foundation. Washington, D.C. Coastal Environments, Inc. 1976. A Process for Coastal Resource Manage- ment and Impact Assessment. Prepared for the Louisiana State Planning F_iana. Office, Baton Rouge, Louis Council on Environmental Quality. 1974. OCS Oil and Gas--An Environmental Assessment: A Report to the President. 5 volumes. Washington, D.C. Exxon Production Research Company, 1976. Deepwater Capabilities. New York, New York. Gillman, Katherine. 1977. Oil and Gas in Coastal Lands and Waters. Council on Environmental Quality. Washington, D.C. U.S. Government Printing Office. Kilpatrick, J. E. 1975. The Role of North Carolina in Regulating Offshore Petroleum Development, UNC Sea Grant Program, N.C. State University, Raleigh, North Carolina. Library of Congress. Congressional Research Service. 1976. Effects of Offshore Oil and Natural Gas Development in the Coastal Zone. Prepared for the Ad Hoc Select Committee on Outer Continental Shelf. Washington, D.C.: House of Representatives, 94th Congress, 2nd Session. Macpherson, G. S., and Bookman, C. A. 1979. Outer Continental Shelf Oil and Gas Activities in the Mid-Atlantic and Th-eir Onshore Impacts: A Summary Report. Prepared for U.S. Department of the Interior Geological Survey in Cooperation with Council on Environmental Quality. U.S. Geological Survey Open File Report 80-17. Philadelphia, Pennsylvania. Management Consultant Services. 1974. Construction Impact Study. Prepared for the Construction Impact Group. Seattle,* Washington. Marine Affairs Office, North Carolina Department of Administration. 1976. The North Carolina Petrocomplex Study. For the North Carolina Depart- ment of Natural and Economic Resources. Raleigh, North Carolina. 64 Marcus, Phillip; Smith, Ethan T.; Robertson, Sidney A.; Wong, Albert T. 1977. DEROCS: Development of Energy Resources on the Outer Continen- tal Shelf: A Computer Program to Simulate Offshore Energy Development Scenarios and Onshore Service Base Requirements. United States Geo- logical Survey Open File Report 77-130. Washington, D.C. Massachusetts Institute of Technology. 1974. Primary, Physical Impacts of Offshore Petroleum Developments. Prepared for the National Oceanic and Atmospheric Administration. Cambridge, Massachusetts. t National Supply Company. 1979. Oil and Gas Pocket Reference 1979. Houston, Texas.. New England River Basins Commission. 1976. Factbook. NERBC and U.S.G.S. Resource and Land Investigations. Boston, Massachusetts. North Carolina Department of Administration, Office of Marine Affairs. 1976. "Planning for North Carolina's OCS." Bibliographies with abstracts. Developed with U.S. Department of Commerce National Oceanic and Atmos- pheric Administration grant # 04-6-158-44095. Raleigh, North Carolina. North Carolina Department of Administration, Office of Marine Affairs. 1976. The North Carolina Petrocomplex. Study. Prepared for the North Carolina Department of Natural and Economic Resources. Raleigh, North Carolina. North Carolina Department of Military and Veterans Affairs, Energy Division, Allocations Section. 1975. North Carolina Petroleum Distribution. Raleigh, North Carolina. Petroleum Extension Service, The University of Texas. 1976. A Primer of Offshore Operations, First Edition. Austin, Texas. Pipeline Planning Committee, Pipeline Division of American Society of Civil Engineers. Final Report of the Task Committee on Pipeline in the Ocean. New York. Robert R. Nathan Associates and Coastal Zone Resources Commission. 1975 The Coastal Plains Deepwater Terminal Study. Wilmington, North Carolina. United States Department of the Interior. 1976. The Outer Continental Shelf Oil and Gas Development Process: A Background Paper for State Planners and Managers. Bureau of Land Management, United States Department of the Interior. United States Department of the Interior. 1978. ;Study Design for Resource I Management Decisions: OCS Oil and Gas Deve 1opment and the Environment. United States Department of the Interior, Bureau of Land Management. 1980. Draft EIS for Pr02Osed 1981 Outer Continental Shelf, Oil and Gas Lease Sale No. 56. New Orleans, Louisiana. 65 U.S.@Department of the Interior, Coastal Zone Management Office and Bureau of Land Management. 1977. State Information Needs Related to Onshore and Nearshore Effects of OCS Petroleum Development. Roy J. Weston, Inc. 1978. Methodoloqy for Assessing Onshore Impacts for O.C.S. Oil and Gas Devef-opment. West Chester, Pennsylvania. Williams, D. C. 1976. Rapid Growth from EnergX Projects: Ideas for State and Local Action. Prepared for the Office of Community FTanning and Development, Department of Housing and Urban Development. Washington, D.C. Williams, David C., and Hom, Kathleen B. 1979. Onshore Impacts of Offshore Oil: A User's Guide to Assessment Methods. Prepared for Department of the Interior, Office of Policy Analysis, Washington, D.C. Williams, David C., and Zinn, Jeffrey A. 1977. Sourcebook: Onshore Impacts of Outer Continental Shelf Oil and Gas DevelopTent. Pripared by the Conservation Foundation for the American Society of Planning Officials. COAL Alla-Ohio Valley Coals, Inc. 1980. "Proposed Coal Facility Development." Minutes,of Citizens' Meeting. Morehead City, North Carolina. Baker, C. R., and Hensley, C. 1981. "Financing Coal and Coal Handling Facilities." Prepared for the American Association of Port Authorities, Coal and Ports Seminar. Mobile, Alabama. Bessemer and Lake Erie Railroad. 1979. Bessemer Coal Manual, 1979. Pitts- burgh, Pennsylvania. Booz, Allen and Hamilton, Inc. 1976. A Procedures Manual for AssesESL'nj the Socioeconomic Impact of the ConstructioF and-operation of Coal Utilization Facilities in the Old West Region. Prepared for the Old West Regional Commission. Washington, D.C. Campbell, T. C. "Coming: New Coal Transportation Modes," Mechanical ,Engineering, Vol. 101, No. 9. September 1979. Coal: 1985 and Beyond. 1978. Published for the United Nations. New York: Fergamon Press. Coal Exporters Association. 1980. Report on Coal Export Port Capacity and Port Congestion. Washingt , D.C. Coal Exporters Association. 1980. The United States in the World Coal Market. Washington, D.C. 66 Ebling, K. 1979. Multi-Modal Analysis of the National Coal Transportation System. Paper prepared for the Conference on Coal Transportation, Arlington, Virginia. Exxon Corporation. 1977. Coal: Energy Bridge to the Future. New York, New York. Fettweis, Gunter B. 1979. World Coal Resources Methods of Assessment and Results. Elsevier Scientific Publishing Company. New York, New York. Forbes. "Shaping Up to Ship Out." February 16, 1981. Harvey, C. E. 1980. Revitalization of Port Capacity and the Foreign Demand for United States . Paper prepared for the Transportation Freight Conference. Baltimori, Maryland. Interagency Coal Export Task Force. "Report on Ports and Ocean Transpor- tation." December 1, 1980. Journal of Commerce. "Strong Demand for Steam Coal Expected Abroad." February 17, 1981. Lin, King. 1980. Coal Traffic Annual, 1979. National Coal Association. Washington, DC. Maritime Transportation Research Board, Commission on Sociotechnical Systems, National Research Council. 1979. Critical Issues in Coal Transporta- tion Systems: Proceedings of Symposiu National Academy of Sciences. Washington, N-.C. McGraw-Hill Mining Information Services. 1980. 1980 Keystone Coal Industry Manual. New York: McGraw-Hill, Inc. Coal Age. "Port Traffic." November 1980. National Coal Association. 1975. Coal Facts 1974-1975. Washington, D.C. National Coal Association. 1979. Coal Facts, 1978-9. Washington, D.C. Noyes, Robert, ed. 1978. 'Coal Resources, Characteristics and Ownership in the U.S.A. Noyes Data Corporation. Park Ridge, New Jersey. Pelham, L. 1980. The Environmental Impact on Coal Transfer and Terminal Operations. U.S. Envfronmental Protection Agency. EPA-600/7-8T--169. Cincinnati, Ohio. Proceedings of the Conference on Coal Transportation. October 14-15, 1980. Arlington, Virginia. Proceedings, Transportation Freight Service Conference. October 15, 1980. Baltimore, Maryland. 67 Research Triangle Institute, North Carolina State University and Appalachian Regional Commission. 1977. An Assessment of the Effects of Coal Movement on the Highways in the Appalachian Region. Research Triangle Park, North Carolina. Schwartz, G. G. 1980. Economic Revitalization and Port Development. Paper prepared for the Transportation Freight Service Conference, October 15, 1980. Baltimore, Maryland. Szabo, M. F. 1978. Environmental Assessment of Coal Transportation. U..S. Environmental Protection Agency. EPA-600/7-78-081. Ci.ncinnati, Ohio. U.S. Army Corps of Engineers; Department of Commerce, Maritime Administration-; Department of Energy; Department of Transportation. 1980. Moving Coal to United States Export Markets: An Assessment of the Transpor- tation System's Capability to Handle Future Coal Traffic. Draft Report. Washington, D.C. U.S. Department of the Interior, Bureau of Mines. 1975. "Long Distance Coal Transport: Unit Trains or Slurry Pipelines." Bureau of Mines.. Circular No. 8690. U.S. Department of Transportation, Office of the Secretary, and U.S. Depart- ment of Energy, Office of the Secretary. 1980. National Energy Trans- portation Study. A Preliminary Report to the President. Washington, D.C. Wilson, C. L. 1980. Coal-Bridge to the Future: Report of the World Coal Study. Cambridge, Massachusetts. Ballinger Publis-hing Company.. NORTH CAROLINA ENERGY STATISTICS Enviro nmental Studies Council, University of North Carolina. 1978. Energy Technologies and Policies for North Carolina: Conference Proceedings. North Carolina Department of Administraton, Division of State Budget and Planning, Research*and Planning Services. North Carolina State Govern- ment Statistical Abstract; Fourth Edition. Raleigh, North Carolina. North Carolina Department of Commerce, North Carolina Energy Institute. 1979. Anuual Report-1979. Raleigh, North Carolina. North Carolina Department of Commerce. 1980. The North Carolina Industrial Data File. A Concise Presentation of North Carolina's Resources for TTant Location Decision Makers. Raleigh, North Carolina. North Carolina Utilities Commission. 1979. 1978 Report-Vol. XII. Statis- tical and Analytical Data Through 1976. Raleigh, North Carolina. Research and Planning Services Division of State Budget and Management. 1979. North Carolina State Government Statistical Abstract. Fourth Edition. Raleigh, North Carolina. 68 Research and Planning Services Office of State Budget and Management. 1980. 1980 North Carolina Statistical Guide. Raleigh, North Carolina. Researc h Triangle Institute, The Center for Development and Resource Planning, and North Carolina Department of Administration. 1974. Final Report. A State Energy.Management Plan for North Carolina.. Phase I: A Quanti- tative Description of the Current Situation and Analysis of the Determi- nants and Consequences of Future Energy Use. Research Triangle Park, North Carolina. ENVIRONMENTAL ASSESSMENTS AND STUDIES Council on Environmental Quality, Executive Office of the President. 1978. Regulations for Implementing the Procedural Provisions of the National Environmental_Policy Act. Great Lakes Basin Commission. 1980. Coastal Effects of Coal Trans2hip: ments in Michigan: An Evaluation Survey. Prepared for the Michigan Department Of Natural Resources. Little, Arthur D. and Co- 1973. Potential Onshore Effects of Deepwater Ports. NTIS (PB 224 018). Springfield, Virginia. For Council on Environmental Quality. Neal, Leon.. 1976. Impact of Continental Shelf Development. North Carolina Science and Technology Research. North Carolina Department of Natural Resources, North Carolina Sedimentation Control Commission. Rules and Regulations for Erosion and Sediment I Control. Promulgated Pursuant to Provisions contained in Sedimentation T-ol-1-u-t-iron Control Act of 1973. (GS chapter 113A, Article 4). North Carolina Department of Transportaton, Division'of Highways. 1978. Final Environmental Statement: Marine Maintenance Facility, Manns Harbor, Dare County. July 1978. North Carolina Department of Transportation, Environmental Unit. 1978. "Executive Order 11990-Protection of Wetlands-Revised Guidance and Prcedures.": December 21, 1978. Memo to Project Engineers. North Carolina Department of Transportation, Environmental Unit. 1979. "Coastal Area Management Act.": December 6, 1979. Memo to Project Engineers. North Carolina Department of Transportation, Environmental Unit. 1980. "Procedures to Follow to Comply with the Endangered Species Act-1978 Amendments.": February 18, 1980. Memo to Project Engineers. North Carolina Department of Transportation, Transportation Planning Division. 1981. "Coal Train Movements Through the City of New Bern." Working paper. 69 "Procedures for Considering Environmental Impacts; Policies and Procedures." Federal Register. Vol. 44, No. 191. Monday, October 1, 1979. Schoebaum, Thomas J., and Silliman, Kenneth G. 1976. Coastal Planning: The Designation and Management of Areas of Critical Environmental Concern. Raleigh, North Carolina: UNC Sea Grant Program. Shuldiner, P. W.; Cope, D. F.;. and Newton, R. B. 1979. National Coo era- tive Highway Research Program Report 218 B: Ecological Effects of Highway Fills on Wetlands, User's Manual. Transportation Research Board. Washington, D.C. United States Department of Commerce, National Oceanic and Atmospheric Administration, Office of Coastal Zone Management, and North Carolina Department of Natural Resources and Community Development, North Carolina Coastal Management Program. Final Environmental Impact Statement: Proposed Coastal Management Program for the State of North Carolina. United States Department of Commerce, National Oceanic and Atmospheric Administration, Office of Coastal Zone Management, and North Carolina Department of Natural Resources and Community Development, North Carolina Coastal Management Program. Final Environmental Impact State- ment: Proposed Costal Management-Program for the State of North Carolina. Appendices. United States Department of the Interior, Bureau of Land Management. 1977. Final Environmental Impact Statement, OCS Lease Sale No. 43. New Orleans, Lousiana. United States Department of the Interior, Bureau of Land Management, 1981. Final Environmental Impact Statement, OCS Lease Sale No. 56. New Orleans, Lousiana. WATER RESOURCES Howells, David H. 1976. Water Resource Problems and Research Needs of F-h, North Carolina: Water Resources Research North Carolina. Raleig Institute of ihe University of North Carolina. McJenkin, Frederick Eugene; Coe, Mary Jordan; and Knarr, Bruce Allen. 1968. Water Resources of North Carolina: An Inventory of Information and Data. Report #22. Raleigh, North Carolina: Water Resources Research Institute. National Association of Conservation Districts. 1979. The Role of Conserva- tion Districts in the Coastal Zone Management Program. Written and compiled under contract from the Office of Coastal Zone Management, National Oceanic and Atmospheric Administration, United States Department of Commerce. 70 North Carolina Department of Administration, North Carolina Marine Science Council. 1972. North Carolina's Coastal Resources: A Preliminary Planning Report for Marine and Coastal Resource Devil-opment in North Carolina. Raleigh, North Caroli-n-a. North Carolina Department of Natural Resources and Community Development. 1977. Public Water Supplies of North Carolina. North Coastal Region. South Coastal Region. North Carolina Department of Natural Resources and Community Development. Coastal Management. Subchapter 7J--Procedures for Handling Major Development Permits, Variance Requests, and Appeals from Minor Develop- ment Permi.t Decisions. Raleigh, North Carolina. Record of the First Annual Review Conference on Marine Resources Develop- ment. December 7-8, 1978. Charleston, South Carolina. Sponsored by the Coastal Plains Center for Marine Development Service. Report of the Conference on Marine Resources of the Coastal Plains States. December 6-7, 1979. Wilmington, North Carolina. Sponsored by the Coastal Plains Center for Marine Development Services. Report of the Conference on Marine Resources of the Coastal Plains States. December 9-10, 1976. Jacksonville, Florida. Sponsored by the Coastal Plains Center for Marine Development Services. Report of the Conference on Marine Resources of the Coastal Plains States. December 11-12, 1975. Savannah, Georgia. Sponsored by the Coastal Plains Center for Marine Development Services. Report of the Conference on Marine Resources of the Coastal Plains States. December 8-19, 1977. Williamsburg, Virginia. Sponsored by tFe -Coastal Plains Center for Marine Development Services. Stream Channelization and Wetland Drajn@. 1970. Proceedings of works.hop sponsored by North Carolina Department of Water and Air Resources and Water Resources Research Institute held at Rougemont, North Carolina. Raleigh, North Carolina. Report #45. United States Army Corps of Engineers. 1979. Water Resources Development. North Carolina. Virginia Institute of Marine Science. 1975. An Assessment of Estuarine and Nearshore Marine Environments. Gloucester Point, Virginia: Virginia Institute of Marine Science. Wurfel, Seymour W., Principal Investigaqtor. 1974. Emerging Ocean Oil and Mining Law. Raleigh, North Carolina. UNC Sea Grant Program, N.C. State University, Raleigh, North Carolina. 71 LAND USE PLANS Camden County Board of Commissioners. 1976. Camden County Land Use Plan 1975-1985. Camden County, North Carolina. Camden County Board of Commissioners. 1976. Camden County Land Use Plan Synopsis. Camden County, North Carolina. Dare County Board of Commissioners. 1976. Coastal Area Management Act: Dare County Land Development Plan. Manteo, North Carolina. Dare County Board of Commissioners. 1976. Dare County Land Use Plan: Summary. Manteo, North Carolina. Hyde County Board of Commissioners. 1976. Coastal Area Management Act: Land Development Plan for Hyde County, A. Swan Quarter, North Carolina. Hyde County Board of Commissioners. 1976. Hyde County Land.Use Plan: Summary. Swan Quarter, North Carolina. Mid-East Commission. 1976. Overall Economic Development Program Update. Washington, North Carolina. Neuse River Council of Governments, Division of Planning and Management. 1976. Craven County Land Development Plan. New Bern, North Carolina. North Carolina Coastal Resources Commission. 1978. Coastal Area Manage- ment Act: Land Use Plan, Carteret County, North arolina. Raleigh, North Carolina. North Carolina Outdoor Recreation Plan: Summary. 1970. Raleigh, North Carolina. Onslow County Board of Commissioners. 1976. Coastal Area Management Act: Land Use Plan. Onslow County, North Caro-lina. Jacksonville, North Carolina. Onslow County Planning Department. 1976. Onslow County Land Use Plan: Summary. Jacksonville, North Carolina. Pasquot'ank County Board of Commissioners. 1976. Pasquotank County Land Use Plan: Synopsis. Elizabeth City, North Carolina. Pasquotank County Board of Commissioners. 1976. Pasquotank County, North Carolina: Land Use Plan, 1975-1985. Elizabeth City, North Carolina. Reeves, Lenora, ed. 1979. The Mid-East Commission, Annual Report, 1978- 1979. Washington, North Carolina. 72 Tyrrell County Board of Commissioners. 1976. Coastal Area Management Act: Tyrrell CountyLand Development Plan. Columbia, North Carolina. Tyrrell County Board of Commissioners. 1976.' Tyrrell County Land Use Plan: Summary. Columbia, North Carolina. Washington County Board of Commissioners. 1976. Washington County Land Use Plan. Plymouth, North Carolina. Washington County Board of Commissioners. 1976' Washington County Land Use Plan: Summary. Plymouth, North Carolina. Wilmington-New Hanover Planning Department. 1976. Coastal Area Manage- ment Act: Land Use Plan V. Wilmington, North Carolina. Wilmington-New Hanover Planning Department. 1976. Wilmington-New Hanover County Land Use Plan: Summary. Wilmington, North Carolina. BIBLIOGRAPHIES AND DATA SOURCES American Waterways Operators, Inc. 1970. The Barge and Touring Industry Catalog of Publications, Films and Inf-ormation Resources. Washington, D.C. Clay, James W., Orr, Douglas M., and Stuart, Alfred W., eds. 1975. North Carolina Atlas: Portrait of a Changing Southern State. Chapel ffTTTT North Carolina: The U5'1versity of North Carolina,Press. Emmett, Robert C. 1978. The Trans2ortation of Energy Materials in the United States: A Bibliograp7hy. Evanston, Illinois: Northwestern Unversity Transportation Library. Prepared for Argonne Laboratory, Energy and Environmental Systems Division Transportation Energy Systems Section. Garrett, Wilbur E., ed. 1981. "Energy: Facing Up to the Problem, Getting Down to Solutions." National Geographic Special Report, February 1981. Washington, D.C. Savannah River Laboratory, E. I. du Pont de Nemours and Company. 1977. The North Carolina Costal Zone and Its Environment: A Compilation Of Resource Materials Covering the Costal Plain, Estuaries, and Offshore Waters. Prepared for the United States Department of Energy. UNC Sea Grant Program, 1980. Publications List. North Carolina State University, Raleigh, North Carolina. UNC-CH Center for Urban Studies, 1981. Outer Continental Shelf Development and the North Carolina Coast: A Guide for Local Planners, Annotated Bibliography, UNC-Chapel Hill. 73 CEIP Publications 1. Hauser, E. W., P. D. Cribbins, P. D. Tschetter, and R. D. Latta. Coastal Energy Transportation Needs to Support Major Energy Projects in North Carolina's Coastal Zone. CEIP Report #1. September 1981. $10. 2. P. D. Cribbins. A Study of OCS Onshore Support Bases and Coal Export Terminals. CEIP Report #2. September 1981. $10. 3. Tschetter, P. D., M. Fisch, and R. D. Latta. An Assessment of Potential Impacts of Energy-Related Transportation Developments on North Carolina's Coastal Zone. CEIP Report #3. September 1981. $10. (Available spring 1982) 4. Cribbins, P. S. An Analysis of State and Federal Policies Affecting Major Energy Projects in North Carolina's Coastal Zone. CEIP Report #4. September 1981. $10. 5. Brower, David, W. D. McElyea, D. R. Godschalk, and N. D. Lofaro. Outer Continental Shelf Development and the North Carolina Coast: A Guide for Local Planners. CEIP Report #5. August 1981. $10. 6. Rogers, Golden and Halpern, Inc., and Engineers for Energy and the Environment, .Inc. Mitigating the Impacts of Energy Facilities; A Local Air Quality Program for the Wilmington, N.C. Area. CEIP Report #6. September 1981. $10. 7. Richardson, C. J. (editor). Pocosin Wetlands: an Integrated Analysis of Coastal Plain Freshwater Bogs in North Carolina. Stroudsburg (Pa): Hutchinson Ross. 364 pp. $25. Available from School of Forestry, Duke University, Durham, N. C. 27709. (This proceedings volume is for a conference partially funded by N. C. CEIP. It replaces the N. C. Peat Sourcebook in this publication list.) 8. McDonald, C. B., and A. M. Ash. Natural Areas Inventory of Tyrrell County, N. C. CEIP Report #8. October 1981. $10 for all requests. 9. Fussell, J., and E. J. Wilson. Natural Areas Inventory of Carteret County, N. C. CEIP Report #9. October 1981. $10 for all requests. 10. Nyfong, T. D. Natural Areas Inventory of Brunswick County, N. C. CEIP Report #10. October 1981. $10 for all requests. 11. Leonard, S. W., and R. J. Davis. Natural Areas Inventory for Pender County, N. C. CEIP Report #11. October 1981. $10 for all requests. NOTE: Please note renumbering of reports 5-10. QATE- DUE, GAYLORD No. 2333 PRIWED IN U.S.A @@3 i66@6i8 @14106 1905 ri