[House Report 119-307]
[From the U.S. Government Publishing Office]


119th Congress }                                         { Report 
                        HOUSE OF REPRESENTATIVES
  1st Session  }                                         { 119-307
======================================================================
 
                  POWER PLANT RELIABILITY ACT OF 2025

                                _______
                                

 September 23, 2025.--Committed to the Committee of the Whole House on 
            the State of the Union and ordered to be printed

                                _______
                                

 Mr. Guthrie, from the Committee on Energy and Commerce, submitted the 
                               following

                              R E P O R T

                             together with

                             MINORITY VIEWS

                        [To accompany H.R. 3632]

    The Committee on Energy and Commerce, to whom was referred 
the bill (H.R. 3632) to amend the Federal Power Act to adjust 
the requirements for orders, rules, and regulations relating to 
furnishing adequate service, to require owners or operators of 
generating facilities to provide notice of planned retirements 
of certain electric generating units, and for other purposes, 
having considered the same, reports favorably thereon without 
amendment and recommends that the bill do pass.

                                CONTENTS

                                                                   Page
Purpose and Summary..............................................     2
Background and Need for Legislation..............................     2
Committee Action.................................................     4
Committee Votes..................................................     4
Oversight Findings and Recommendations...........................     7
New Budget Authority, Entitlement Authority, and Tax Expenditures     7
Congressional Budget Office Estimate.............................     7
Federal Mandates Statement.......................................     7
Statement of General Performance Goals and Objectives............     7
Duplication of Federal Programs..................................     7
Related Committee and Subcommittee Hearings......................     7
Committee Cost Estimate..........................................     9
Earmark, Limited Tax Benefits, and Limited Tariff Benefits.......     9
Advisory Committee Statement.....................................     9
Applicability to Legislative Branch..............................     9
Section-by-Section Analysis of the Legislation...................     9
Changes in Existing Law Made by the Bill, as Reported............     9
Minority, Additional, or Dissenting Views........................    13

                          Purpose and Summary

    H.R. 3632, the ``Power Plant Reliability Act of 2025'', was 
introduced by Representative Griffith on May 29, 2025, and 
referred to the Committee on Energy and Commerce on May 29, 
2025. H.R. 3632 enhances authority under Section 207 of the 
Federal Power Act to allow affected parties to contest the 
retirement of generation resources, for up to a 5-year period, 
in the event that a retirement causes harm to the reliability 
of the bulk power system. The bill would also require power 
plants to provide a 5-year advance notice of plans to retire.

                  Background and Need for Legislation

    During the 119th Congress, the Energy Subcommittee of 
Energy and Commerce has held several hearings to better 
understand the ongoing electric reliability crisis facing our 
nation. While record levels of baseload thermal generation are 
being retired from the bulk power system, our nation is 
experiencing an historic increase in electricity demand, 
largely driven by artificial intelligence (AI) data centers, 
domestic manufacturing, and general economy wide 
electrification. These increases follow several decades of 
relatively flat electricity demand growth. Data centers alone 
could consume upwards of 132 GW by 2028.\1\ The North American 
Electric Reliability Corporation (NERC) projects peak demand to 
grow by 151 GW by 2034.\2\ At the same time, NERC reports that 
as much as 115 GW of thermal generation has announced to retire 
within the same time period.\3\ NERC has stated that 
``[e]nvironmental regulations and energy policies that are 
overly rigid and lack provisions for electric grid reliability 
have the potential to influence generators to seek deactivation 
despite a projected resource adequacy or operating reliability 
risk; this can potentially jeopardize[e] the orderly transition 
of the resource mix.''\4\ The pace of retirements of baseload 
generation combined with the explosive growth of large loads 
could leave our nation's bulk power system at extreme risk of 
power outages over the next 5 years. A recent report from the 
Department of Energy finds that our current pace could increase 
the risk of power outages by 100 times by 2030.\5\
---------------------------------------------------------------------------
    \1\Arman Shehabi et al., 2024 United States Data Center Energy 
Usage Report, Lawrence Berkely National Laboratory (Dec. 20, 2024), 
[https://escholarship.org/uc/item/32d6m0d1].
    \2\North American Reliability Corp. (NERC), 2024 Long-Term 
Reliability Assessment (Dec. 2024, updated Jul. 15, 2025), https://
www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20 DL/
NERC_Long%20Term%20Reliability%20Assessment_2024.pdf.
    \3\Id.
    \4\NERC, 2023 Long-Term Reliability Assessment (Dec. 2023), https:/
/www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20DL/
NERC_LTRA_2023.pdf.
    \5\U.S. Dep't of Energy, Evaluating the Reliability and Security of 
the United States Electric Grid (Resource Adequacy Report) (Jul. 2025), 
https://www.energy.gov/sites/default/files/2025-07/
DOE%20Final%20EO%20Report%20%28FINAL%20JULY%207%290.pdf.
---------------------------------------------------------------------------
    The pre-mature retirements of baseload generating units 
have largely been driven by federal and state actions that 
prevent, limit, or otherwise discourage continued operation or 
new investments in fossil fuels. In particular, the 
Environmental Protection Agency's ``New Source Performance 
Standards for Greenhous Gas Emissions from New, Modified, and 
Reconstructed Fossil Fuel-Fired Electric Generating Units: 
Emission Guidelines for Greenhouse Gas Emissions from Existing 
Fossil Fuel-Fired Electric Generating Units''' would have 
significant adverse impacts on existing coal units and new 
natural gas units. In 2024, FERC Commissioner Mark Christie 
testified before the House Energy and Commerce Committee 
regarding the severe impact of the Biden administration EPA's 
power plant rule, commonly known as the Clean Power Plan 2.0, 
specifically stating, ``[i]f the EPA's new power plant rule 
survives court challenge, it will force the retirements of 
nearly all remaining coal generation plants and will prevent 
the construction of vitally needed new combined-cycle baseload 
gas generation. This loss of vitally needed dispatchable 
generation resources will be catastrophic.'' In 2023, fossil 
fuels contributed 60 percent of all electricity generation in 
the United States.\6\
---------------------------------------------------------------------------
    \6\U.S. Energy Info. Admin., FAQs: What is U.S. electricity 
generation by energy source?, (Feb. 29, 2024), https://www.eia.gov/
tools/faqs/faq.php?id=427&t=3.
---------------------------------------------------------------------------
    The historic rate of premature retirements is compounded by 
ongoing constraints for new natural gas turbines, backlogs in 
interconnection queues, and permitting delays at the federal 
and state level. Given the urgency of addressing the ongoing 
reliability crisis, the Commission requires additional tools to 
address reliability and potential electricity supply 
shortfalls. Increasingly, states have taken it upon themselves 
to push more stringent environmental standards and implemented 
intermittent energy standards that seek to increase the share 
of a utility's generation mix coming from renewable sources. 
These standards have contributed to pre-mature closures of 
fossil generating units that provide necessary baseload power 
and a growing reliance on states that are maintaining these 
resources. As an example, Pennsylvania is the only net exporter 
of electricity in 13 states and Washington, D.C. membership of 
PJM.\7\
---------------------------------------------------------------------------
    \7\Kim Riley, IFO report shows state still is top electricity 
exporter, Pa. Bus. Rep. (Feb.
4, 2025), https://pennbizreport.com/news/30128-ifo-report-shows-state-
still-is-top-electricity-
exporter/.
---------------------------------------------------------------------------
    Under current law, section 207 of the Federal Power Act 
provides FERC with authority to determine proper, adequate, or 
sufficient service to be furnished in the event that the 
Commission, upon a complaint from a state Commission, finds 
that any interstate service of a public utility is inadequate 
or insufficient. This authority of the Commission to address 
electric reliability has been used sparingly over its statutory 
history. When the authority has been invoked, it has been 
predominantly centered on the impacts of neighboring states to 
close generating stations that provide interstate service. Most 
recently, the District of Columbia Public Service Commission 
petitioned FERC under section 207 following the closure of the 
Potomac River Generating Station in Alexandria, Virginia. FERC 
found that the closure of the power plant in Virginia would 
result in electricity shortages in the Washington, D.C. area 
and would violate NERC reliability standards, endangering the 
transmission system.\8\ As part of these findings, FERC issued 
an order under section 207 requiring the grid operator and 
utility develop short-term and long-term solutions to 
reliability in the affected area, which resulted in new 
transmission lines and ultimate closure of the generation 
facility.\9\
---------------------------------------------------------------------------
    \8\Order on Petition and Complaint of the D.C. Pub. Serv. Comm'n., 
U.S. Fed. Energy Reg. Comm'n., Docket. No. EL05-145-000 (Issued Jan. 9, 
2006), [https://www.ferc.gov/sites/default/files/2020-05/
20060109190229-EL05-145-000.pdf].
    \9\Id.
---------------------------------------------------------------------------
    The Power Plant Reliability Act would enhance section 207 
of the Federal Power Act by standardizing the process by which 
FERC may issue orders, including flexibility for orders issued 
up to a 5-year time frame with the ability for reissuance if 
necessary. The legislation also includes transmission 
organizations, in addition to state Commissions, as parties 
authorized to file complaints with FERC to initiate a 
proceeding under this provision. The legislation also sets out 
cost allocation and compensation for service to be furnished 
pursuant to any order under section 207. This legislation would 
also address the competing interests of emission requirements 
of state and federal authorities that are weighed against 
reliability requirements implemented by NERC through the 
Federal Power Act by waiving violations of environmental 
standards that are required as part of any order under section 
207.
    Additionally, the legislation would require power plant 
owners to provide a 5-year advance notice to FERC of plans to 
retire operations. In the event the plant requires deactivation 
due to an emergency, catastrophe or similar event that renders 
a facility inoperable, plant owners are provided an opportunity 
to petition the commission for an earlier retirement. 
Currently, states and grid operators uniquely implement 
retirement notices, which must comply with NERC reliability 
standards implemented through the Federal Power Act. This 
legislation does not make any changes to the existing NERC 
reliability standards.

                            Committee Action

    On April 30, 2025, the Subcommittee on Energy held a 
legislative hearing on 14 pieces of legislation, including H.R. 
3632. The Subcommittee received testimony from:
           Mike Goff, Acting Undersecretary of Energy, 
        U.S. Department of Energy;
           David L. Morenoff, Acting General Counsel, 
        Federal Energy Regulatory Commission;
           Terry Turpin, Director, Office of Energy 
        Projects, Federal Energy Regulatory Commission;
           Jim Matheson, Chief Executive Officer, 
        National Rural Electric Cooperative Association;
           Amy Andryszak, President and Chief Executive 
        Officer, Interstate Natural Gas Association of America;
           Todd A. Snitchler, President and Chief 
        Executive Officer, Electric Power Supply Association 
        and;
           Kim Smaczniak, Partner, Roselle LLP.
    On June 5, 2025, the Subcommittee on Energy met in open 
markup session and forwarded H.R. 3632, without amendment, to 
the full Committee by a record vote of 15 yeas and 14 nays. On 
June 25, 2025, the full Committee on Energy and Commerce met in 
open markup session and ordered H.R. 3632, without amendment, 
favorably reported to the House by a record vote of 25 yeas and 
21 nays.

                            Committee Votes

    Clause 3(b) of rule XIII requires the Committee to list the 
record votes on the motion to report legislation and amendments 
thereto. The following reflects the record votes taken during 
the Committee consideration:



                 Oversight Findings and Recommendations

    Pursuant to clause 2(b)(1) of rule X and clause 3(c)(1) of 
rule XIII, the Committee held hearings and made findings that 
are reflected in this report.

             New Budget Authority, Entitlement Authority, 
                          and Tax Expenditures

    Pursuant to clause 3(c)(2) of rule XIII, the Committee 
finds that H.R. 3632 would result in no new or increased budget 
authority, entitlement authority, or tax expenditures or 
revenues.

                  Congressional Budget Office Estimate

    Pursuant to clause 3(c)(3) of rule XIII, at the time this 
report was filed, the cost estimate prepared by the Director of 
the Congressional Budget Office pursuant to section 402 of the 
Congressional Budget Act of 1974 was not available.

                       Federal Mandates Statement

    The Committee adopts as its own the estimate of Federal 
mandates prepared by the Director of the Congressional Budget 
Office pursuant to section 423 of the Unfunded Mandates Reform 
Act.

         Statement of General Performance Goals and Objectives

    Pursuant to clause 3(c)(4) of rule XIII, the general 
performance goal or objective of this legislation is to amend 
section 207 of the Federal Power Act to enhance opportunities 
for state commissions or transmission organizations to file 
complaints with FERC to furnish adequate service in the event 
that interstate service is found to be inadequate. This 
legislation also amends section 207 to require generating 
facilities provide a 5-year advance notice on retirement plans.

                    Duplication of Federal Programs

    Pursuant to clause 3(c)(5) of rule XIII, no provision of 
H.R. 3632 is known to be duplicative of another Federal 
program, including any program that was included in a report to 
Congress pursuant to section 21 of Public Law 111-139 or the 
most recent Catalog of Federal Domestic Assistance.

              Related Committee and Subcommittee Hearings

    Pursuant to clause 3(c)(6) of rule XIII, the following 
related hearings were used to develop or consider H.R. 3632:
    On February 5, 2025, the Subcommittee on Energy held a 
hearing on H.R. 3632, titled ``Powering America's Future: 
Unleashing American Energy.'' The Subcommittee received 
testimony from:
           Amanda Eversole, Executive Vice President 
        and Chief Advocacy Officer, American Petroleum 
        Institute;
           Brigham McCown, Senior Fellow and Director, 
        Initiative on American Energy Security, The Hudson 
        Institute;
           Gary Arnold, Business Manager, Denver 
        Pipefitters Local 208 and;
           Tyler O'Connor, Partner, Crowell & Moring 
        LLP.
    On March 5, 2025, the Subcommittee on Energy held a hearing 
on H.R. 3632, titled ``Scaling for Growth: Meeting the Demand 
for Reliable, Affordable Electricity.'' The Subcommittee 
received testimony from:
           Todd Brickhouse, CEO and General Manager, 
        Basin Electric Power Cooperative;
           Asim Haque, Senior Vice President for 
        Governmental and Member Services, PJM;
           Noel W. Black, Senior VP of Regulatory 
        Affairs, Southern Company and;
           Tyler H. Norris, James B. Duke Fellow, Duke 
        University.
    On March 25, 2025, the Subcommittee on Energy held a 
hearing on H.R. 3632, titled ``Keeping the Lights On: Examining 
the State of Regional Grid Reliability.'' The Subcommittee 
received testimony from:
           Gordon van Welie, President and Chief 
        Executive Officer, ISO New England;
           Richard J. Dewey, President and Chief 
        Executive Officer, New York Independent System 
        Operator;
           Manu Asthana, President and Chief Executive 
        Officer, PJM Interconnection LLC;
           Jennifer Curran, Senior Vice President for 
        Planning and Operations, Midcontinent ISO;
           Lanny Nickell, Chief Operating Officer, 
        Southwest Power Pool;
           Elliot Mainzer, President and Chief 
        Executive Officer, California Independent System 
        Operator and;
           Pablo Vegas, President and Chief Executive 
        Officer, Electric Reliability Council of Texas, Inc.
    On April 9, 2025, the Committee on Energy and Commerce held 
a hearing on H.R. 3632, titled ``Converting Energy into 
Intelligence: The Future of AI Technology, Human Discovery, and 
American Global Competitiveness.'' The Committee received 
testimony from:
           Eric Schmidt, Chair, Special Competitive 
        Studies Project;
           Manish Bhatia, Executive Vice President of 
        Global Operations, Micron Technology;
           Alexander Wang, Founder and Chief Executive 
        Officer, Scale AI, and;
           David Turk, Distinguished Visiting Fellow, 
        Center on Global Energy Policy, Columbia University.
    On April 30, 2025, the Subcommittee on Energy held a 
legislative hearing on H.R. 3632, titled ``Assuring Abundant, 
Reliable American Energy to Power Innovation.'' The 
Subcommittee received testimony from:
           Mike Goff, Acting Undersecretary of Energy, 
        U.S. Department of Energy;
           David L. Morenoff, Acting General Counsel, 
        Federal Energy Regulatory Commission;
           Terry Turpin, Director, Office of Energy 
        Projects, Federal Energy Regulatory Commission;
           Jim Matheson, Chief Executive Officer, 
        National Rural Electric Cooperative Association;
           Amy Andryszak, President and Chief Executive 
        Officer, Interstate Natural Gas Association of America;
           Todd A. Snitchler, President and Chief 
        Executive Officer, Electric Power Supply Association 
        and;
           Kim Smaczniak, Partner, Roselle LLP.

                        Committee Cost Estimate

    Pursuant to clause 3(d)(1) of rule XIII, the Committee 
adopts as its own the cost estimate prepared by the Director of 
the Congressional Budget Office pursuant to section 402 of the 
Congressional Budget Act of 1974. At the time this report was 
filed, the estimate was not available.

       Earmark, Limited Tax Benefits, and Limited Tariff Benefits

    Pursuant to clause 9(e), 9(f), and 9(g) of rule XXI, the 
Committee finds that H.R. 3632 contains no earmarks, limited 
tax benefits, or limited tariff benefits.

                      Advisory Committee Statement

    No advisory committees within the meaning of section 5(b) 
of the Federal Advisory Committee Act were created by this 
legislation.

                  Applicability to Legislative Branch

    The Committee finds that the legislation does not relate to 
the terms and conditions of employment or access to public 
services or accommodations within the meaning of section 
102(b)(3) of the Congressional Accountability Act.

             Section-by-Section Analysis of the Legislation


Section 1. Short title

    Section 1 provides that the Act may be cited as the ``Power 
Plant Reliability Act''.

Section 2. Furnishing of adequate service; advance notice of planned 
        retirements

    Section 2 amends section 207 of the Federal Power Act to 
clarify the process by which a state Commission or transmission 
organization can file a complaint with FERC to furnish adequate 
service in the event that interstate service of a public 
utility is found to be inadequate or insufficient. Generating 
facilities that may be ordered to operate pursuant to orders 
under section 207 may not extend longer than 5 years, with an 
opportunity for reissuance. This section also provides that any 
action taken by a generating facility to comply with orders 
issued under section 207 may not be considered a violation of 
any federal, state, or local environmental law. This section 
also requires generating facilities to provide 5-year advance 
notice on plans to retire.

         Changes in Existing Law Made by the Bill, as Reported

  In compliance with clause 3(e) of rule XIII of the Rules of 
the House of Representatives, changes in existing law made by 
the bill, as reported, are shown as follows (existing law 
proposed to be omitted is enclosed in black brackets, new 
matter is printed in italics, and existing law in which no 
change is proposed is shown in roman):

                           FEDERAL POWER ACT



           *       *       *       *       *       *       *
PART II--REGULATION OF ELECTRIC UTILITY COMPANIES ENGAGED IN INTERSTATE 
COMMERCE

           *       *       *       *       *       *       *


                    [furnishing of adequate service

  [Sec. 207. Whenever the Commission, upon complaint of a State 
commission, after notice to each State commission and public 
utility affected and after opportunity for hearing, shall find 
that any interstate service of any public utility is inadequate 
or insufficient, the Commission shall determine the proper, 
adequate, or sufficient service to be furnished, and shall fix 
the same by its order, rule, or regulation: Provided, That the 
Commission shall have no authority to compel the enlargement of 
generating facilities for such purposes, nor to compel the 
public utility to sell or exchange energy when to do so would 
impair its ability to render adequate service to its 
customers.]

SEC. 207. FURNISHING OF ADEQUATE SERVICE; ADVANCE NOTICE OF PLANNED 
                    RETIREMENTS.

  (a) Furnishing of Adequate Service.--
          (1) In general.--Whenever the Commission, upon 
        complaint of a State commission or a Transmission 
        Organization, after notice to each State commission and 
        public utility affected, and after opportunity for 
        hearing within 90 days of receipt of such complaint, 
        finds that any interstate service of any public utility 
        is inadequate or insufficient, or is likely to become 
        inadequate or insufficient within 5 years of receiving 
        such complaint, the Commission shall determine the 
        proper, adequate, or sufficient service to be 
        furnished, and shall fix the same by issuing an order, 
        rule, or regulation.
          (2) Requirements.--The Commission, in an order, rule, 
        or regulation issued under paragraph (1)--
                  (A) may not--
                          (i) compel the enlargement of 
                        generating facilities; or
                          (ii) compel the public utility to 
                        sell or exchange electric energy when 
                        to do so would impair its ability to 
                        render proper, adequate, or sufficient 
                        service to its customers;
                  (B) may require--
                          (i) continuing the operation of an 
                        electric generating unit; and
                          (ii) any affected State commission, 
                        Transmission Organization, or public 
                        utility to develop and implement a 
                        long-term plan for the planning, 
                        construction, and operation of 
                        interstate transmission facilities that 
                        may be necessary for the public utility 
                        to provide adequate and sufficient 
                        interstate service; and
                  (C) shall determine--
                          (i) any rate or charge necessary to 
                        provide compensation for the additional 
                        costs of the proper, adequate, or 
                        sufficient service to be furnished, 
                        including compensation to an owner or 
                        operator of an electric generating unit 
                        that is required to continue to operate 
                        under such order, rule, or regulation; 
                        and
                          (ii) the cost allocation of any rate 
                        or charge.
          (3) Term length.--Except as provided in paragraph 
        (4), an order, rule, or regulation issued under 
        paragraph (1) shall terminate on the date that the 
        Commission determines appropriate, which may not be 
        later than 5 years after the date on which the 
        Commission issues such order, rule, or regulation.
          (4) Extension.--
                  (A) Request for extension.--Not earlier than 
                the date that is 180 days prior to the date on 
                which an order, rule, or regulation terminates, 
                as determined under paragraph (3), and not 
                later than 60 days prior to such termination 
                date, any affected State commission, 
                Transmission Organization, or public utility 
                may submit to the Commission a request to 
                extend such order, rule, or regulation.
                  (B) Deadline.--With respect to a request 
                submitted under subparagraph (A), the 
                Commission shall--
                          (i) not later than 14 days after the 
                        date on which the Commission receives 
                        the request, notify each affected State 
                        commission, Transmission Organization, 
                        and public utility of the request;
                          (ii) provide an opportunity for a 
                        hearing on the request before accepting 
                        or denying the request under clause 
                        (iii); and
                          (iii) not later than 60 days after 
                        the date on which the Commission 
                        receives the request--
                                  (I) accept the request and 
                                extend the applicable order, 
                                rule, or regulation; or
                                  (II) deny the request.
                  (C) Term length.--An order, rule, or 
                regulation extended under subparagraph (B) 
                shall terminate on the date that the Commission 
                determines appropriate, which may not be later 
                than 5 years after the date on which the 
                Commission extended such order, rule, or 
                regulation.
          (5) Treatment of certain actions.--To the extent an 
        omission or action taken by a party, that is necessary 
        to comply with an order, rule, or regulation issued or 
        extended under this subsection, including any omission 
        or action taken to voluntarily comply with such order, 
        rule, or regulation, results in noncompliance with, or 
        causes such party to not comply with, any Federal, 
        State, or local environmental law or regulation, such 
        omission or action shall not be considered a violation 
        of such environmental law or regulation, or subject 
        such party to any requirement, civil or criminal 
        liability, or a citizen suit under such environmental 
        law or regulation.
  (b) Advance Notice of Planned Retirements.--
          (1) In general.--If an owner or operator of a 
        generating facility plans to retire an electric 
        generating unit that is a component of such facility, 
        such owner or operator shall submit to the Commission 
        and any affected State commission or Transmission 
        Organization a notice of such plan at least 5 years 
        before the date on which such owner or operator plans 
        to retire such electric generating unit.
          (2) Unplanned retirements.--An owner or operator of a 
        generating facility that retires an electric generating 
        unit due to an unplanned catastrophe, emergency, 
        disaster, or similar event that renders such electric 
        generating unit inoperable is not subject to the notice 
        requirement described in paragraph (1).
          (3) Publicly available.--The Commission shall make 
        publicly available each notice submitted under 
        paragraph (1).
  (c) Definitions.--In this section:
          (1) Bulk-power system.--The term ``bulk-power 
        system'' has the meaning given such term in section 
        215(a).
          (2) Electric generating unit.--The term ``electric 
        generating unit'' means an electric energy producing 
        unit that--
                  (A) is a component of a generating facility;
                  (B) has a power production capacity of not 
                less than 5 megawatts; and
                  (C) is interconnected to the bulk-power 
                system.
          (3) Retire.--The term ``retire'', with respect to an 
        electric generating unit, means to, for an indefinite 
        period of time--
                  (A) idle the electric generating unit;
                  (B) disconnect the electric generating unit 
                from the bulk-power system; or
                  (C) otherwise make unavailable for sale all 
                electric energy that is generated by the 
                electric generating unit.

           *       *       *       *       *       *       *


                             MINORITY VIEWS

    H.R. 3632, the Power Plant Reliability Act H.R. 3632, the 
Power Plant Reliability Act, would convey new powers upon the 
Federal Energy Regulatory Commission (FERC) to compel aging, 
outdated, and expensive power plants to stay online past their 
useful or economic life and would require retiring generation 
resources to give five years' notice to their grid operators 
and state utility regulatory commissions. This authority would 
drastically increase American families' utility bills and is 
unnecessary to address the issues identified by the majority's 
report.
    The bill also broadly represents a rejection of American 
innovation. As the Committee heard at a legislative hearing, 
long-term reliability concerns are best addressed by utility 
planning and market design--exactly what utilities and grid 
operators have been doing for over a century.\1\ Power markets 
have developed a number of constructs to acquire enough power 
to ensure reliability at the lowest cost. This bill presumes 
that government regulators know better. The Committee heard 
testimony that the bill ``. . . would impose astronomical new 
costs on Americans at a time when energy costs are already 
rising.''\2\ Americans are already paying $3 billion more on 
their power bills as utilities arbitrarily choose to run their 
own aging coal plants instead of cheaper or more efficient 
power plants.\3\ H.R. 3632 would severely worsen the problem.
---------------------------------------------------------------------------
    \1\House Committee on Energy and Commerce, Testimony of Kim 
Smaczniak, Partner, Roselle LLP, Hearing on Assuring Abundant, Reliable 
American Energy to Power Innovation, 119th Cong. (Apr. 30, 2024).
    \2\Id.
    \3\Rocky Mountain Institute, Economic Dispatch Dashboard (https://
utilitytransitionhub. rmi.org/economic-dispatch/) (accessed Sep. 11, 
2025).
---------------------------------------------------------------------------
    Recent actions by the Department of Energy (DOE) illustrate 
the negative outcomes we can expect if this bill is enacted. 
Earlier this summer, the Department ordered two fossil fuel 
power plants slated to retire to stay online: a coal plant in 
Michigan and a dual gas-and-oil-fired power plant in 
Pennsylvania.\4\ This was an unprecedented usage of DOE's 
authority under section 202(c) of the Federal Power Act.\5\ 
While the emergency underlying DOE's order is entirely made up, 
the costs that the order will impose on consumers are not. 
DOE's action came despite the fact that the retirement of the 
Michigan plant was slated to save ratepayers nearly $600 
million, and that same plant racked up costs of $29 million in 
its first five weeks of forced operation--costs that will be 
borne by ratepayers across the Midwest, even families that live 
hundreds of miles away from the facility itself.\6\ Undeterred 
by these skyrocketing energy bills, the Trump Administration 
has extended the two 90-day orders to keep the power plants 
online. One recent report found that if all retiring fossil 
fuel power plants were subject to indefinite similar orders, 
ratepayers would be on the hook for $6 billion in annual costs 
by the end of Trump's term.\7\
---------------------------------------------------------------------------
    \4\Department of Energy, Order No. 202-25-3 (May 23, 2025); 
Department of Energy, Order No. 202-25-4 (May 30, 2025).
    \5\16 U.S.C. Sec. 824a(c).
    \6\Settlement Reply Brief of Consumers Energy Company (May 27, 
2002), In the Matter of the Application of Consumers Energy Company for 
Approval of an Integrated Resource Plan under MCL 460.6t, certain 
accounting approvals, and for other relief, Michigan Public Service 
Commission (Case No. U-21090); Coal Plant Ordered to Stay Open Cost 
$29M to Run in 5 Weeks, E&E News (Aug. 1, 2025).
    \7\Grid Strategies, The Cost of Federal Mandates to Retain Fossil-
Burning Power Plants (Aug. 2025).
---------------------------------------------------------------------------
    While DOE's actions are egregious and illegal, H.R. 3632 
actually proposes a worse framework. The bill would not require 
any evidence of an emergency, just the hint of a supply--demand 
mismatch that could be a half-decade away. The bill would also 
enable FERC to issue orders for five years at a time, rather 
than the current 90 days that DOE is limited to. Under the 
bill, in one action, FERC could mandate massive increases in 
Americans power bills for five years without any evidence of an 
actual grid emergency. Furthermore, the bill contains no 
requirement that the rates assigned be just and reasonable, or 
that they follow cost-causation principles that FERC currently 
must abide by for assigning the costs of DOE's 202(c) orders. 
When Rep. Robin Kelly (D-IL) offered an amendment to add these 
guardrails to the bill at the Committee markup, her amendment 
was defeated in a party-line vote.
    Such a massive grant of power to a single agency requires 
significant evidence that the change is necessary. 
Unfortunately, several pieces of evidence cited by the majority 
in their report are misleading or are blatantly incorrect. The 
majority report cites a recent DOE report claiming that the 
risk of power outages could increase by 100 times by the end of 
the decade.\8\ But that report was rife with methodological 
errors, most notably by fundamentally biasing itself towards 
over-estimating load growth, over-estimating power plant 
retirements, and under-estimating new power plant construction 
by assuming that only projects with signed interconnection 
agreements in 2025 will manage to come online by 2030.\9\ The 
majority's report also states that ``Pennsylvania is the only 
net exporter of electricity in . . . PJM.'' This is simply 
untrue. The PJM-jurisdictional portions of Illinois, Indiana, 
Michigan, and West Virginia were all net-exporters of power in 
2024, in addition to Pennsylvania.\10\ The paltry evidence 
simply does not justify such a government intervention in the 
electricity sector.
---------------------------------------------------------------------------
    \8\Department of Energy, Evaluating the Reliability and Security of 
the United States Electric Grid (July 2025).
    \9\Motion to Intervene and Request for Rehearing of Natural 
Resources Defense Council, the Ecology Center, Environmental Defense 
Fund, Environmental Law and Policy Center, Public Citizen, Sierra Club, 
and Vote Solar (Aug. 8, 2025), Resource Adequacy Report Evaluating the 
Reliability and Security of the United States Electric Grid, Department 
of Energy.
    \10\PJM, 2024 Illinois State Infrastructure Report (June 2025); 
PJM, 2024 Indiana State Infrastructure Report (June 2025); PJM, 2024 
Michigan State Infrastructure Report (June 2025); PJM, 2024 West 
Virginia State Infrastructure Report (June 2025); PJM, 2024 
Pennsylvania State Infrastructure Report (June 2025).
---------------------------------------------------------------------------
    FERC and grid operators currently have a number of tools to 
fix short-term reliability issues, namely reliability-must-run 
agreements. Critically, those agreements are time-limited, 
designed only to act as a bridge until such time as a 
reliability constraint is relieved.\11\ They are not meant to 
be recurring without end. H.R. 3632 would meddle with a system 
that already has the tools it needs to ensure reliability, all 
at the cost of higher electricity bills.
---------------------------------------------------------------------------
    \11\See note 1.
---------------------------------------------------------------------------
    For the reasons stated above, I oppose this legislation.

                                        Frank Pallone, Jr.,
                                                    Ranking Member.

                                  [all]