[House Report 119-302]
[From the U.S. Government Publishing Office]


119th Congress }                                              { Report
                        HOUSE OF REPRESENTATIVES
 1st Session   }                                              { 119-302

=======================================================================



 
                           RELIABLE POWER ACT

                            ----------------
                                
 September 17, 2025.--Committed to the Committee of the Whole House on 
            the State of the Union and ordered to be printed

                            ----------------
                                
          Mr. Guthrie, from the Committee on Energy and Commerce,
                         submitted the following


                              R E P O R T

                             together with

                             MINORITY VIEWS

                        [To accompany H.R. 3616]

      [Including cost estimate of the Congressional Budget Office]

    The Committee on Energy and Commerce, to whom was referred 
the bill (H.R. 3616) to require the Federal Energy Regulatory 
Commission to review regulations that may affect the reliable 
operation of the bulk-power system, having considered the same, 
reports favorably thereon with an amendment and recommends that 
the bill as amended do pass.

                                CONTENTS

                                                                   Page
Purpose and Summary..............................................     3
Background and Need for Legislation..............................     3
Committee Action.................................................     7
Committee Votes..................................................     7
Oversight Findings and Recommendations...........................    10
New Budget Authority, Entitlement Authority, and Tax Expenditures    10
Congressional Budget Office Estimate.............................    10
Federal Mandates Statement.......................................    11
Statement of General Performance Goals and Objectives............    11
Duplication of Federal Programs..................................    11
Related Committee and Subcommittee Hearings......................    12
Committee Cost Estimate..........................................    13
Earmark, Limited Tax Benefits, and Limited Tariff Benefits.......    13
Advisory Committee Statement.....................................    13
Applicability to Legislative Branch..............................    13
Section-by-Section Analysis of the Legislation...................    13
Changes in Existing Law Made by the Bill, as Reported............    15
Minority, Additional, or Dissenting Views........................    22

    The amendment is as follows:
  Striking all after the enacting clause and insert the 
following:

SECTION 1. SHORT TITLE.

  This Act may be cited as the ``Reliable Power Act''.

SEC. 2. COMMISSION REVIEW AND COMMENT FOR COVERED AGENCY ACTIONS.

  Section 215 of the Federal Power Act (16 U.S.C. 824o) is amended--
          (1) in subsection (g)--
                  (A) by striking ``The ERO'' and inserting the 
                following:
          ``(1) In general.--The ERO''; and
                  (B) by adding at the end the following:
          ``(2) Annual long-term assessment.--The assessments under 
        paragraph (1) shall include an annual long-term assessment, 
        which shall include--
                  ``(A) an analysis of the ability of the bulk-power 
                system to supply sufficient electric energy necessary 
                to maintain an adequate level of reliability, taking 
                into account generation resource mix, transmission 
                development, and electric energy demand trends;
                  ``(B) an analysis of the risk of future electric 
                energy supply shortfalls under normal and extreme 
                weather conditions, and the risk of any such shortfalls 
                within each region of the bulk-power system; and
                  ``(C) a determination of whether additional 
                generation resources are necessary to supply sufficient 
                electric energy to maintain an adequate level of 
                reliability during the assessment period.
          ``(3) Notice of generation inadequacy.--In conducting a long-
        term assessment under paragraph (2), if the ERO finds that the 
        bulk-power system is at risk of not having adequate generation 
        resources to supply sufficient electric energy to maintain an 
        adequate level of reliability, the ERO shall publicly notify 
        the Commission that the bulk-power system is in a state of 
        generation inadequacy.
          ``(4) Data collection.--To conduct a long-term assessment 
        under paragraph (2), the ERO may collect information and data 
        from users, owners, and operators of the bulk-power system.'';
          (2) by redesignating subsections (h) through (k) as 
        subsections (i) through (l), respectively; and
          (3) by inserting after subsection (g) the following:
  ``(h) Commission Review and Comment for Covered Agency Actions.--
          ``(1) Notice to federal agencies.--If the ERO notifies the 
        Commission under subsection (g)(3) that the bulk-power system 
        is in a state of generation inadequacy, the Commission shall 
        promptly notify the Department of Energy, the Environmental 
        Protection Agency, and any other Federal agency the Commission 
        determines appropriate of such state of generation inadequacy.
          ``(2) Submission.--Upon receiving notice under paragraph (1), 
        the head of each Federal agency that received such notice shall 
        provide to the Commission for review and comment any covered 
        agency action by the Federal agency--
                  ``(A) on the first date on which such covered agency 
                action is provided to the Office of Management and 
                Budget or any other Federal agency for review and 
                comment; or
                  ``(B) if such covered agency action is not provided 
                to the Office of Management and Budget or any other 
                Federal agency for review and comment, not later than 
                90 days before the date on which the covered agency 
                action is published in the Federal Register or is 
                otherwise made available for public inspection or 
                comment.
          ``(3) Commission comments.--The Commission, in consultation 
        with the ERO and transmission organizations, shall, by order, 
        provide to the agency head that provided to the Commission a 
        covered agency action under paragraph (2)--
                  ``(A) comments on such covered agency action, which 
                such comments may include an assessment of the effect 
                of the covered agency action on rates, terms, and 
                conditions for services pursuant to the authority of 
                the Commission under sections 201 and 206; and
                  ``(B) if applicable, recommendations for 
                modifications to the covered agency action to prevent a 
                significant negative impact on the ability of the bulk-
                power system to supply sufficient electric energy 
                necessary to maintain an adequate level of reliability.
          ``(4) Agency response.--The head of a Federal agency may not 
        finalize a covered agency action that is provided to the 
        Commission under paragraph (2) until--
                  ``(A) the agency head responds in writing to the 
                Commission with an explanation of how the agency head 
                modified, or why the agency head determined not to 
                modify, such covered agency action in response to any 
                comments and recommendations provided by the Commission 
                under paragraph (3); and
                  ``(B) the Commission finds that the covered agency 
                action will not be likely to have a significant 
                negative impact on the ability of the bulk-power system 
                to supply sufficient electric energy necessary to 
                maintain an adequate level of reliability.
          ``(5) Public availability of comments and responses.--An 
        agency head shall include any comments, recommendations, and 
        responses for the covered agency action when--
                  ``(A) submitting the covered agency action to the 
                Federal Register for publication; or
                  ``(B) otherwise making the covered agency action 
                available for public inspection or comment.
          ``(6) Definitions.--In this subsection:
                  ``(A) Covered agency action.--The term `covered 
                agency action' means a regulation that--
                          ``(i) relates to, or otherwise directly 
                        affects, any generation resource in the bulk-
                        power system; and
                          ``(ii) is under development to be proposed or 
                        otherwise under consideration in a rulemaking 
                        prior to finalization on the date on which the 
                        Federal agency receives notice from the 
                        Commission under paragraph (1).
                  ``(B) Federal agency.--The term `Federal agency' 
                means an Executive department (as that term is defined 
                in section 101 of title 5, United States Code) or any 
                other Executive agency that is in the President's 
                cabinet.''.

                          Purpose and Summary

    H.R. 3616, the Reliable Power Act, would amend the Federal 
Power Act to provide for the Federal Regulatory Commission 
(FERC) review of certain federal regulations that may affect 
the reliable operation of the bulk-power system.
    The legislation would require the electric reliability 
organization (ERO) to conduct annual long-term reliability 
assessments of the bulk-power system. In the event the ERO 
determines during such assessments that the bulk-power system 
does not have sufficient electric generation to maintain 
reliability, FERC would review, provide comment, and as 
necessary recommend changes to modify federal regulations 
proposed or under development that affect generation resources 
in the bulk-power system. No regulation affecting such 
resources would be allowed to be finalized if FERC finds it 
would have a significant negative impact on the reliability of 
the bulk-power system.

                  Background and Need for Legislation

    Reliable delivery of electric power is essential for all 
aspects of modern life, and especially, public health and 
welfare. The nation's electric power grid is comprised of vast 
networks of high voltage transmission lines, generating 
resources, local distribution lines, and other critical 
infrastructure to ensure the delivery of adequate and reliable 
supplies of electricity. The backbone of the electric grid is 
the bulk-power system. This system includes the facilities and 
control systems necessary for operating the interconnected 
transmission network and the electric energy generation 
resources needed to maintain transmission system 
reliability.\1\
---------------------------------------------------------------------------
    \1\The bulk-power system does not include the local distribution of 
electric power.
---------------------------------------------------------------------------
    FERC and the North American Electric Reliability 
Corporation (NERC), each have important statutory roles in 
monitoring and assuring reliability across the bulk power 
system.FERC oversees and regulates the interstate transmission 
of natural gas, oil, and electricity through its authority 
under the Natural Gas Act and the Federal Power Act. Under 
section 215 of the Federal Power Act, NERC is the ERO certified 
to establish and enforce reliability standards for the bulk-
power system, or BPS, subject to FERC review and approval.
    The need for strengthened oversight of policies by FERC and 
NERC that impact reliability is increasing. The electric power 
system is undergoing an unprecedented period of transformation 
and uncertainty. This is driven by an accelerated rate of pre-
mature retirements of traditional, baseload and dispatchable 
electric generation resources, without adequate replacement 
resources, coupled with substantial increases in the demand for 
more electric power. This demand is driven by rapid growth of 
data centers, artificial intelligence, domestic manufacturing, 
and general electrification. Absent sufficient new generation 
resources, the new demand is exacerbating existing and growing 
risks to the reliable delivery of power in large regions of the 
nation.
    For the past decade, accelerated retirement of dispatchable 
generation resources, chiefly coal, natural gas, and nuclear, 
has been driven by state and federal policies that limit 
production from or increase environmental compliance costs of 
these traditional generation resources and, particularly in 
deregulated wholesale electricity markets, favor investment in 
intermittent solar and wind resources over traditional fossil 
generation resources.
    The consequences of premature retirements have been 
magnified by the operating limitations of replacement 
generation--chiefly intermittent wind and solar--that do not 
have the same attributes or provide the same level of 
reliability as dispatchable resources. Existing state and 
federal policies continue to produce powerful economic 
incentives for retirements of baseload and dispatchable power 
and the related services to balance and maintain electric grid 
reliability.
    ``Accelerated retirements of the existing coal, natural 
gas, and nuclear generators can have a profound and negative 
effect on the resource adequacy and reliability of the BPS in 
the next 10 years,'' according to the NERC's December 2024 
Long-Term Reliability Assessment.\2\ The report states further: 
``Environmental regulations and energy policies have the 
potential to influence generators to seek deactivation during 
the 10-year assessment period. . . . The lack of dispatchable 
resources and diverse generator fuel types in the 
interconnection processes makes the future resource mix look 
alarmingly unreliable. The potential for capacity and energy 
shortfalls and a higher-risk resource mix is heightened by 
economic and policy factors that place pressure on existing 
thermal generators.''\3\
---------------------------------------------------------------------------
    \2\North American Reliability Corp. (NERC), 2024 Long-Term 
Reliability Assessment (Dec. 2024, updated Jul. 15, 2025), https://
www.nerc.com/pa/RAPA/ra/Reliability%20
Assessments%20DL/NERC_Long%20Term%20Reliability%20Assessment_2024.pdf.
    \3\Id.
---------------------------------------------------------------------------
    Analysis by the Department of Energy found that increased 
demand combined with retirements of dispatchable generation 
would increase the risk of power outages 100-fold by 2030. Even 
assuming no retirements, the increased risk of power outages in 
2030 increased by a factor of 34 over current risks, 
underscoring the current reliability crisis.\4\
---------------------------------------------------------------------------
    \4\U.S. Dep't of Energy, Evaluating the Reliability and Security of 
the United States Electric Grid (Resource Adequacy Report), at 1 (Jul. 
2025), https://www.energy.gov/sites/default/files/2025-07/
DOE%20Final%20EO%20Report%20%28FINAL%20JULY%207%29_.0.pdf.
---------------------------------------------------------------------------
    The Committee held multiple hearings during the 118th and 
119th Congress on electric reliability and, through these 
hearings and testimony, the Committee has heard from utilities, 
states, grid operators, and FERC Commissioners that there is an 
increasing threat to grid reliability that could lead to 
extensive, system-wide outages.
    Increasingly, grid operators have warned of the potential 
for electricity disruptions and asked their customers to 
conserve power.\5\ PJM, the nation's largest grid operator, has 
warned that it could see a capacity shortage as early as 2026/
2027 and identified public policies, permitting constraints, 
and supply chain challenges as key trends that are tightening 
supply-demand balance within the system.\6\ PJM CEO, Manu 
Asthana also stated, ``PJM needs to slow down the pace of 
generation retirements to avoid reliability problems by the end 
of the decade.''\7\ In Committee hearings during the 119th 
Congress, grid operators continued to identify premature 
retirements of generation resources as a risk to reliability.
---------------------------------------------------------------------------
    \5\News Release, Electric Reliability Council of Texas, Inc. 
(ERCOT), ERCOT Has Initiated Energy Emergency Alert Level 2 (EEA 2), 
Conservation is Critical (Sept. 6, 2023), https://www.ercot.com/news/
release/2023-09-06-ercot-has-initiated.
    \6\Letter from Mark Takahashi, Chair, Board of Managers, PJM 
Interconnection to PJM Stakeholders (Dec. 9, 2024), https://
www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/
2024/20241209-board-letter-outlining-action-on-capacity-market-
adjustments-rri-and-sis.pdf.
    \7\Rich Heidorn, Jr., PJM Chief: Retirements Need to Slow Down, RTO 
INSIDER, (Mar. 27, 2023), https://www.rtoinsider.com/31899-pjm-chief-
retirements-need-to-slow-down/.
---------------------------------------------------------------------------
    Over the past decade, federal regulatory initiatives, 
particularly by the Environmental Protection Agency (EPA), have 
contributed to or threatened to contribute to the premature 
retirement of baseload and dispatchable generation resources. 
In large part, these regulatory initiatives reflected policies 
to transition the nation's electric system away from fossil 
based electric generation.
    The most notable example of these regulatory initiatives is 
the EPA's promulgation during the Biden Administration of 
greenhouse gas standards for fossil-fuel fired power plants.\8\ 
Twenty-seven states filed legal challenges to the rule in the 
D.C. Circuit Court of Appeals in September 2024.\9\ An amicus 
brief filed by four grid operators requested the court remand 
the final rule back to EPA ``with instructions for it to 
adequately consider the . . . grid adequacy issues [grid 
operators] previously raised,'' noting the rules would trigger 
an acceleration in the pace of premature retirements of 
resources ``that can have significant, negative consequences on 
reliability.''\10\
---------------------------------------------------------------------------
    \8\U.S. Env't. Prot. Agency (EPA) Final Rule, New Source 
Performance Standards from Greenhouse Gas Emissions From New, Modified, 
and Reconstructed Fossil Fuel-Fired Electric Generating Units, etc., 89 
Fed. Reg. 39798 (May 9, 2024) (where EPA's greenhouse gas rules were 
part of a larger, comprehensive suite of regulatory actions for power 
plants. EPA Administrator Regan announced this suite of actions, known 
as the EGU (for ``electric generating unit'') strategy, to address 
climate, health, and environmental burdens from power plants; and where 
these regulatory actions include the Interstate Transport Rule, 
Regional Haze, Risk and Technology Review for the Mercury Air Toxics 
Rule, effluent limitations, and a legacy coal combustion residue rule; 
and where these rules are impacting operations of existing baseload 
generation in the bulk power system, compelling, in many instances, 
retirements of generating sources earlier than had been planned).
    \9\State of West Virginia, et al. v. EPA, No. 24-1120, (D.C. Cir. 
2024).
    \10\Brief of Midcontinent Independent System Operator, Inc., PJM 
Interconnection L.L.C., Southwest Power Pool, Inc., and Electric 
Reliability Council of Texas, Inc. as Amici Curiae in Support of 
Petitioners, State of West Virginia, et al. v. EPA, No. 24-1120, (D.C. 
Cir. 2024).
---------------------------------------------------------------------------
    Although Congress, under the Federal Power Act, provided 
FERC responsibility for assuring reliability of the bulk-power 
system, EPA was under no legal obligation to address adequately 
the electric reliability risk created by its rules. This 
legislation establishes a statutory mechanism to provide 
accountability for and to align federal agency actions with the 
surpassing importance of ensuring electric power reliability.
    The legislation builds upon existing authorities, which 
provide FERC and NERC responsibility to examine reliability of 
the bulk-power system and to identify actions that ensure 
reliable operation of the grid. It requires a long-term 
reliability assessment of the bulk power system by NERC, which 
is the ERO, and to include in that assessment determination 
whether more generation resources are necessary to maintain an 
adequate level of reliability. The assessment requirements 
reflect the existing objective criteria used by NERC to ensure 
there is sufficient energy to maintain an adequate level of 
reliability under a range of circumstances. It directs NERC to 
take into account transmission development, the mix of 
generation resources, and energy demand trends.
    If NERC finds the bulk power system is at risk of not 
having adequate generation resources to supply sufficient 
energy to maintain an adequate level of reliability during the 
assessment period, it must notify FERC that the system is in a 
state of generation inadequacy. Upon such notification, FERC 
notifies DOE and EPA and any agency it determines appropriate 
of the state of generation inadequacy. Upon such notice, the 
notified agency sends any rules under development that impact 
generation resources to FERC for review and comment, and any 
recommendations necessary to prevent significant impacts on the 
ability of the grid to supply sufficient energy to maintain an 
adequate level of reliability.
    Given the engineering and analytical capacity necessary to 
assess reliability adequately, the Committee expects that FERC 
will consult with grid operators and NERC and its subsidiaries, 
which have expertise, information, and modeling tools to assist 
with assessments. The Committee also expects that FERC will 
also consider impacts of proposed rules on rates, terms, and 
conditions of service, pursuant to its authority under the 
Federal Power Act, in its assessments under this legislation.
    To ensure rules are crafted to avoid significant 
reliability impacts, the legislation provides that no rule that 
affects generation resources can be finalized if FERC 
determines the rule would have a significant negative impact on 
the ability of the grid to supply sufficient energy to maintain 
an adequate level of reliability. It is expected this will 
provide for future regulatory actions that balance the needs 
for regulatory action with the public interest needs for 
affordable, reliable delivery of electric power.
    The Committee finds this legislation is necessary to 
provide accountability for federal rules that affect generation 
resources, and to provide a mechanism for adjusting any such 
rules to ensure they do not significantly impact electric power 
reliability.

                            Committee Action

    On April 30, 2025, the Subcommittee on Energy held a 
legislative hearing on 14 pieces of legislative, including H.R. 
3616. The Subcommittee received testimony from:
           Mike Goff, Acting Undersecretary of Energy, 
        U.S. Department of Energy;
           David L. Morenoff, Acting General Counsel, 
        Federal Energy Regulatory Commission;
           Terry Turpin, Director, Office of Energy 
        Projects, Federal Energy Regulatory Commission;
           Jim Matheson, Chief Executive Officer, 
        National Rural Electric Cooperative Association;
           Amy Andryszak, President and Chief Executive 
        Officer, Interstate Natural Gas Association of America;
           Todd A. Snitchler, President and Chief 
        Executive Officer, Electric Power Supply Association 
        and;
           Kim Smaczniak, Partner, Roselle LLP.
    On June 5, 2025, the Subcommittee on Energy met in open 
markup session and forwarded H.R. 3616, as amended, to the full 
Committee by a record vote of 16 yeas and 14 nays. On June 25, 
2025 the full Committee on Energy and Commerce met in open 
markup session and ordered H.R. 3616, without amendment, 
favorably reported to the House by a record vote of 28 yeas and 
23 nays.

                            Committee Votes

    Clause 3(b) of rule XIII requires the Committee to list the 
record votes on the motion to report legislation and amendments 
thereto. The following reflects the record votes taken during 
the Committee consideration:

[GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]

                 Oversight Findings and Recommendations

    Pursuant to clause 2(b)(1) of rule X and clause 3(c)(1) of 
rule XIII, the Committee held hearings and made findings that 
are reflected in this report.

             New Budget Authority, Entitlement Authority, 
                          and Tax Expenditures

    Pursuant to clause 3(c)(2) of rule XIII, the Committee 
finds that H.R. 3616 would result in no new or increased budget 
authority, entitlement authority, or tax expenditures or 
revenues.

                  Congressional Budget Office Estimate

    Pursuant to clause 3(c)(3) of rule XIII, the following is 
the cost estimate provided by the Congressional Budget Office 
pursuant to section 402 of the Congressional Budget Act of 
1974:

[GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]


    H.R. 3616 would require the Federal Energy Regulatory 
Commission (FERC), in consultation with the Electric 
Reliability Organization (ERO), to review regulations proposed 
by other federal agencies that could affect the reliability of 
the bulk-power system, under conditions specified in the bill. 
Agencies could not finalize those actions until they respond to 
any concerns raised by FERC as part of that review.
    Using information from FERC, CBO expects that the agency 
would need additional staff and would need to acquire new data 
to fulfill the bill's requirements. CBO estimates that 
implementing those requirements would cost FERC less than $10 
million each year. However, because FERC is authorized to 
recover 100 percent of its costs through user fees, any change 
in agency costs (which are controlled through annual 
appropriation acts) would be offset by an equal change in fees 
that the commission charges. Accordingly, CBO estimates that 
implementing those provisions would result in no net change in 
discretionary spending for FERC.
    CBO further estimates that the costs for other agencies 
(primarily the Department of Energy) to coordinate with FERC on 
those reviews would total $1 million over the 2025-2030 period; 
that spending would be subject to the availability of 
appropriated funds.
    Finally, enacting H.R. 3616 would increase direct spending 
and revenues because spending by the ERO is recorded on the 
budget as direct spending, and the organization assesses fees, 
which are recorded as revenues, to cover its costs. CBO 
estimates that consulting with FERC would increase costs for 
the ERO by less than $500,000 over the 2025-2035 period. 
Because any amounts collected would be spent soon thereafter, 
CBO estimates that the net effect on the deficit would be 
negligible.
    Implementing the bill could result in some regulations 
being delayed because of the procedures specified in the bill. 
Those delays could result in budgetary effects; however, CBO 
has no basis to estimate which regulations could be affected, 
nor the direction or magnitude of any such effects.
    If FERC and the ERO increase their fees to offset the costs 
of implementing the bill, H.R. 3616 would increase the cost of 
an existing mandate on public and private entities, such as 
electric utilities, that are required to pay those fees. CBO 
estimates that the incremental cost of the mandates would be 
small and fall well below the annual threshold established in 
the Unfunded Mandates Reform Act for intergovernmental and 
private-sector mandates ($103 million and $206 million in 2025, 
respectively, adjusted annually for inflation).
    The CBO staff contacts for this estimate are Aaron Krupkin 
(for federal costs) and Brandon Lever (for mandates). The 
estimate was reviewed by H. Samuel Papenfuss, Deputy Director 
of Budget Analysis.
                                         Phillip L. Swagel,
                             Director, Congressional Budget Office.

                       Federal Mandates Statement

    The Committee adopts as its own the estimate of Federal 
mandates prepared by the Director of the Congressional Budget 
Office pursuant to section 423 of the Unfunded Mandates Reform 
Act.

         Statement of General Performance Goals and Objectives

    Pursuant to clause 3(c)(4) of rule XIII, the general 
performance goal or objective of this legislation is to provide 
accountability for federal rules that affect generation 
resources, and to provide a mechanism for adjusting any such 
rules to ensure they do not significantly impact electric power 
reliability.

                    Duplication of Federal Programs

    Pursuant to clause 3(c)(5) of rule XIII, no provision of 
H.R. 3616 is known to be duplicative of another Federal 
program, including any program that was included in a report to 
Congress pursuant to section 21 of Public Law 111-139 or the 
most recent Catalog of Federal Domestic Assistance.

              Related Committee and Subcommittee Hearings

    On February 5, 2025, the Subcommittee on Energy held a 
hearing that covered issues related to HR 3616. The title of 
the hearing was ``Powering America's Future: Unleashing 
American Energy.'' The Subcommittee received testimony from:
           Amanda Eversole, Executive Vice President 
        and Chief Advocacy Officer, American Petroleum 
        Institute;
           Brigham McCown, Senior Fellow and Director, 
        Initiative on American Energy Security, The Hudson 
        Institute;
           Gary Arnold, Business Manager, Denver 
        Pipefitters Local 208 and;
           Tyler O'Connor, Partner, Crowell & Moring 
        LLP.
    On March 5, 2025, the Subcommittee on Energy held a hearing 
that covered issues relating to HR 3616. The title of the 
hearing was ``Scaling for Growth: Meeting the Demand for 
Reliable, Affordable Electricity.'' The Subcommittee received 
testimony from:
           Todd Brickhouse, CEO and General Manager, 
        Basin Electric Power Cooperative;
           Asim Haque, Senior Vice President for 
        Governmental and Member Services, PJM;
           Noel W. Black, Senior VP of Regulatory 
        Affairs, Southern Company and;
           Tyler H. Norris, James B. Duke Fellow, Duke 
        University.
    On March 25, 2025, the Subcommittee on Energy held a 
hearing that covered issues relating to HR 3616. The title of 
the hearing was ``Keeping the Lights On: Examining the State of 
Regional Grid Reliability.'' The Subcommittee received 
testimony from:
           Gordon van Welie, President and Chief 
        Executive Officer, ISO New England;
           Richard J. Dewey, President and Chief 
        Executive Officer, New York Independent System 
        Operator;
           Manu Asthana, President and Chief Executive 
        Officer, PJM Interconnection LLC;
           Jennifer Curran, Senior Vice President for 
        Planning and Operations, Midcontinent ISO;
           Lanny Nickell, Chief Operating Officer, 
        Southwest Power Pool;
           Elliot Mainzer, President and Chief 
        Executive Officer, California Independent System 
        Operator and;
           Pablo Vegas, President and Chief Executive 
        Officer, Electric Reliability Council of Texas, Inc.
    On April 9, 2025, the Committee on Energy and Commerce held 
a full committee hearing that covered issues relating to HR 
3616. The title of the hearing was ``The Energy Needs for 
Advancing American Technological Leadership.'' The Committee 
received testimony from:
           Eric Schmidt, Chair, Special Competitive 
        Studies Project;
           Manish Bhatia, Executive Vice President of 
        Global Operations, Micron Technology;
           Alexander Wang, Founder and Chief Executive 
        Officer, Scale AI, and;
           David Turk, Distinguished Visiting Fellow, 
        Center on Global Energy Policy, Columbia University.
    On April 30, 2025, the Subcommittee on Energy held a 
legislative hearing on H.R. 3616. The title of the hearing was 
``Assuring Abundant, Reliable American Energy to Power 
Innovation.'' The Subcommittee received testimony from:
           Mike Goff, Acting Undersecretary of Energy, 
        U.S. Department of Energy;
           David L. Morenoff, Acting General Counsel, 
        Federal Energy Regulatory Commission;
           Terry Turpin, Director, Office of Energy 
        Projects, Federal Energy Regulatory Commission;
           Jim Matheson, Chief Executive Officer, 
        National Rural Electric Cooperative Association;
           Amy Andryszak, President and Chief Executive 
        Officer, Interstate Natural Gas Association of America;
           Todd A. Snitchler, President and Chief 
        Executive Officer, Electric Power Supply Association 
        and;
           Kim Smaczniak, Partner, Roselle LLP.

                        Committee Cost Estimate

    Pursuant to clause 3(d)(1) of rule XIII, the Committee 
adopts as its own the cost estimate prepared by the Director of 
the Congressional Budget Office pursuant to section 402 of the 
Congressional Budget Act of 1974.

       Earmark, Limited Tax Benefits, and Limited Tariff Benefits

    Pursuant to clause 9(e), 9(f), and 9(g) of rule XXI, the 
Committee finds that H.R. 3616 contains no earmarks, limited 
tax benefits, or limited tariff benefits.

                      Advisory Committee Statement

    No advisory committees within the meaning of section 5(b) 
of the Federal Advisory Committee Act were created by this 
legislation.

                  Applicability to Legislative Branch

    The Committee finds that the legislation does not relate to 
the terms and conditions of employment or access to public 
services or accommodations within the meaning of section 
102(b)(3) of the Congressional Accountability Act.

             Section-by-Section Analysis of the Legislation


Section 1. Short title

    Section 1 provides that the Act may be cited as the 
``Reliable Power Act''.

Section 2. Commission review and comment for covered agency actions

    Paragraph (1) of Section 2 amends subsection (g) of Section 
215 of the Federal Power Act to require under a new subsection 
(g) (2) an annual long-term assessment of the reliability and 
adequacy of the bulk-power system by the Energy Reliability 
Organization (ERO). The paragraph provides for what analyses 
the assessment must include, considering generation resource 
mix, transmission development, and electric energy demand 
trends, to assess the risk of future electric energy supply 
shortfalls. It requires the ERO to make a determination whether 
additional generation resources are necessary to supply 
sufficient energy to maintain an adequate level of reliability 
during the assessment period.
    The new subsection (g) (3) requests that, if the ERO finds 
the bulk-power system is at risk of not having adequate 
generation, it shall notify the Federal Energy Regulatory 
Commission (Commission) that the bulk-power system is in a 
state of generation inadequacy.
    The new subsection (g) (4) provides that the ERO may 
collect information from users, owners, and operators of the 
bulk-power system to conduct its long-term assessments.
    Paragraph (2) of Section 2 redesignates subsections (h) 
through (k) of the Federal Power Act as subsections (i) through 
(l) respectively.
    Paragraph (3) of Section 2 inserts a new subsection (h) 
Commission Review and Comment for Covered Agency Actions. The 
new subsection (h) (1) provides that, if the ERO notifies the 
Commission that the bulk-power system is in a state of 
generation inadequacy, the Commission shall promptly notify the 
Department of Energy, the Environmental Protection Agency, and 
any other Federal agency the Commission determines appropriate 
of the state of generation inadequacy.
    The new subsection (h) (2) provides that the head of each 
Federal agency so notified shall provide for Commission review 
and comment any Covered Agency Action by the Federal agency not 
later than 90 days before the covered action is made available 
for public inspection.
    The new subsection (h) (3) provides that the Commission, in 
consultation with the ERO and transmission organizations, 
shall, by order, provide to the Federal agency comments on the 
Covered Agency Action, and, if applicable, recommendations for 
modification to the Covered Agency Action to prevent a 
significant negative impact on the ability of the bulk-power 
system to supply sufficient energy to maintain reliability. The 
Commission response may include assessment of the effects of 
the Covered Agency Action on rates, terms, and conditions for 
services, pursuant to Commission authority.
    The new subsection (h) (4) provides that the head of a 
Federal agency may not finalize a Covered Agency Action 
provided to the Commission under (h) (2) until the agency head 
responds in writing to the Commission how the agency head 
modified the action in response to Commission comments and 
recommendations and the Commission finds that the Covered 
Agency Action will not be likely to have a significant negative 
impact on the reliability of the bulk-power system.
    The new subsection (h) (5) provides for the Federal agency 
head to make public Commission comments, recommendations, and 
related responses for the Covered Agency Action.
    The new subsection (h) (6) provides definitions, including 
that a Covered Agency Action is a regulation that relates to or 
otherwise directly affects any generation resources in the 
bulk-power system and is under development or consideration by 
a federal agency.

         Changes in Existing Law Made by the Bill, as Reported

  In compliance with clause 3(e) of rule XIII of the Rules of 
the House of Representatives, changes in existing law made by 
the bill, as reported, are shown as follows (existing law 
proposed to be omitted is enclosed in black brackets, new 
matter is printed in italics, and existing law in which no 
change is proposed is shown in roman):

                           FEDERAL POWER ACT

           *       *       *       *       *       *       *

           PART II--REGULATION OF ELECTRIC UTILITY COMPANIES
                    ENGAGED IN INTERSTATE COMMERCE

           *       *       *       *       *       *       *

SEC. 215. ELECTRIC RELIABILITY.

  (a) Definitions.--For purposes of this section:
          (1) The term ``bulk-power system'' means--
                  (A) facilities and control systems necessary 
                for operating an interconnected electric energy 
                transmission network (or any portion thereof); 
                and
                  (B) electric energy from generation 
                facilities needed to maintain transmission 
                system reliability.
        The term does not include facilities used in the local 
        distribution of electric energy.
          (2) The terms ``Electric Reliability Organization'' 
        and ``ERO'' mean the organization certified by the 
        Commission under subsection (c) the purpose of which is 
        to establish and enforce reliability standards for the 
        bulk-power system, subject to Commission review.
          (3) The term ``reliability standard'' means a 
        requirement, approved by the Commission under this 
        section, to provide for reliable operation of the bulk-
        power system. The term includes requirements for the 
        operation of existing bulk-power system facilities, 
        including cybersecurity protection, and the design of 
        planned additions or modifications to such facilities 
        to the extent necessary to provide for reliable 
        operation of the bulk-power system, but the term does 
        not include any requirement to enlarge such facilities 
        or to construct new transmission capacity or generation 
        capacity.
          (4) The term ``reliable operation'' means operating 
        the elements of the bulk-power system within equipment 
        and electric system thermal, voltage, and stability 
        limits so that instability, uncontrolled separation, or 
        cascading failures of such system will not occur as a 
        result of a sudden disturbance, including a 
        cybersecurity incident, or unanticipated failure of 
        system elements.
          (5) The term ``Interconnection'' means a geographic 
        area in which the operation of bulk-power system 
        components is synchronized such that the failure of one 
        or more of such components may adversely affect the 
        ability of the operators of other components within the 
        system to maintain reliable operation of the facilities 
        within their control.
          (6) The term ``transmission organization'' means a 
        Regional Transmission Organization, Independent System 
        Operator, independent transmission provider, or other 
        transmission organization finally approved by the 
        Commission for the operation of transmission 
        facilities.
          (7) The term ``regional entity'' means an entity 
        having enforcement authority pursuant to subsection 
        (e)(4).
          (8) The term ``cybersecurity incident'' means a 
        malicious act or suspicious event that disrupts, or was 
        an attempt to disrupt, the operation of those 
        programmable electronic devices and communication 
        networks including hardware, software and data that are 
        essential to the reliable operation of the bulk power 
        system.
  (b) Jurisdiction and Applicability.--(1) The Commission shall 
have jurisdiction, within the United States, over the ERO 
certified by the Commission under subsection (c), any regional 
entities, and all users, owners and operators of the bulk-power 
system, including but not limited to the entities described in 
section 201(f), for purposes of approving reliability standards 
established under this section and enforcing compliance with 
this section. All users, owners and operators of the bulk-power 
system shall comply with reliability standards that take effect 
under this section.
  (2) The Commission shall issue a final rule to implement the 
requirements of this section not later than 180 days after the 
date of enactment of this section.
  (c) Certification.--Following the issuance of a Commission 
rule under subsection (b)(2), any person may submit an 
application to the Commission for certification as the Electric 
Reliability Organization. The Commission may certify one such 
ERO if the Commission determines that such ERO--
          (1) has the ability to develop and enforce, subject 
        to subsection (e)(2), reliability standards that 
        provide for an adequate level of reliability of the 
        bulk-power system; and
          (2) has established rules that--
                  (A) assure its independence of the users and 
                owners and operators of the bulk-power system, 
                while assuring fair stakeholder representation 
                in the selection of its directors and balanced 
                decisionmaking in any ERO committee or 
                subordinate organizational structure;
                  (B) allocate equitably reasonable dues, fees, 
                and other charges among end users for all 
                activities under this section;
                  (C) provide fair and impartial procedures for 
                enforcement of reliability standards through 
                the imposition of penalties in accordance with 
                subsection (e) (including limitations on 
                activities, functions, or operations, or other 
                appropriate sanctions);
                  (D) provide for reasonable notice and 
                opportunity for public comment, due process, 
                openness, and balance of interests in 
                developing reliability standards and otherwise 
                exercising its duties; and
                  (E) provide for taking, after certification, 
                appropriate steps to gain recognition in Canada 
                and Mexico.
  (d) Reliability Standards.--(1) The Electric Reliability 
Organization shall file each reliability standard or 
modification to a reliability standard that it proposes to be 
made effective under this section with the Commission.
  (2) The Commission may approve, by rule or order, a proposed 
reliability standard or modification to a reliability standard 
if it determines that the standard is just, reasonable, not 
unduly discriminatory or preferential, and in the public 
interest. The Commission shall give due weight to the technical 
expertise of the Electric Reliability Organization with respect 
to the content of a proposed standard or modification to a 
reliability standard and to the technical expertise of a 
regional entity organized on an Interconnection-wide basis with 
respect to a reliability standard to be applicable within that 
Interconnection, but shall not defer with respect to the effect 
of a standard on competition. A proposed standard or 
modification shall take effect upon approval by the Commission.
  (3) The Electric Reliability Organization shall rebuttably 
presume that a proposal from a regional entity organized on an 
Interconnection-wide basis for a reliability standard or 
modification to a reliability standard to be applicable on an 
Interconnection-wide basis is just, reasonable, and not unduly 
discriminatory or preferential, and in the public interest.
  (4) The Commission shall remand to the Electric Reliability 
Organization for further consideration a proposed reliability 
standard or a modification to a reliability standard that the 
Commission disapproves in whole or in part.
  (5) The Commission, upon its own motion or upon complaint, 
may order the Electric Reliability Organization to submit to 
the Commission a proposed reliability standard or a 
modification to a reliability standard that addresses a 
specific matter if the Commission considers such a new or 
modified reliability standard appropriate to carry out this 
section.
  (6) The final rule adopted under subsection (b)(2) shall 
include fair processes for the identification and timely 
resolution of any conflict between a reliability standard and 
any function, rule, order, tariff, rate schedule, or agreement 
accepted, approved, or ordered by the Commission applicable to 
a transmission organization. Such transmission organization 
shall continue to comply with such function, rule, order, 
tariff, rate schedule or agreement accepted, approved, or 
ordered by the Commission until--
          (A) the Commission finds a conflict exists between a 
        reliability standard and any such provision;
          (B) the Commission orders a change to such provision 
        pursuant to section 206 of this part; and
          (C) the ordered change becomes effective under this 
        part.
If the Commission determines that a reliability standard needs 
to be changed as a result of such a conflict, it shall order 
the ERO to develop and file with the Commission a modified 
reliability standard under paragraph (4) or (5) of this 
subsection.
  (e) Enforcement.--(1) The ERO may impose, subject to 
paragraph (2), a penalty on a user or owner or operator of the 
bulk-power system for a violation of a reliability standard 
approved by the Commission under subsection (d) if the ERO, 
after notice and an opportunity for a hearing--
          (A) finds that the user or owner or operator has 
        violated a reliability standard approved by the 
        Commission under subsection (d); and
          (B) files notice and the record of the proceeding 
        with the Commission.
  (2) A penalty imposed under paragraph (1) may take effect not 
earlier than the 31st day after the ERO files with the 
Commission notice of the penalty and the record of proceedings. 
Such penalty shall be subject to review by the Commission, on 
its own motion or upon application by the user, owner or 
operator that is the subject of the penalty filed within 30 
days after the date such notice is filed with the Commission. 
Application to the Commission for review, or the initiation of 
review by the Commission on its own motion, shall not operate 
as a stay of such penalty unless the Commission otherwise 
orders upon its own motion or upon application by the user, 
owner or operator that is the subject of such penalty. In any 
proceeding to review a penalty imposed under paragraph (1), the 
Commission, after notice and opportunity for hearing (which 
hearing may consist solely of the record before the ERO and 
opportunity for the presentation of supporting reasons to 
affirm, modify, or set aside the penalty), shall by order 
affirm, set aside, reinstate, or modify the penalty, and, if 
appropriate, remand to the ERO for further proceedings. The 
Commission shall implement expedited procedures for such 
hearings.
  (3) On its own motion or upon complaint, the Commission may 
order compliance with a reliability standard and may impose a 
penalty against a user or owner or operator of the bulk-power 
system if the Commission finds, after notice and opportunity 
for a hearing, that the user or owner or operator of the bulk-
power system has engaged or is about to engage in any acts or 
practices that constitute or will constitute a violation of a 
reliability standard.
  (4) The Commission shall issue regulations authorizing the 
ERO to enter into an agreement to delegate authority to a 
regional entity for the purpose of proposing reliability 
standards to the ERO and enforcing reliability standards under 
paragraph (1) if--
          (A) the regional entity is governed by--
                  (i) an independent board;
                  (ii) a balanced stakeholder board; or
                  (iii) a combination independent and balanced 
                stakeholder board.
          (B) the regional entity otherwise satisfies the 
        provisions of subsection (c)(1) and (2); and
          (C) the agreement promotes effective and efficient 
        administration of bulk-power system reliability.
The Commission may modify such delegation. The ERO and the 
Commission shall rebuttably presume that a proposal for 
delegation to a regional entity organized on an 
Interconnection-wide basis promotes effective and efficient 
administration of bulk-power system reliability and should be 
approved. Such regulation may provide that the Commission may 
assign the ERO's authority to enforce reliability standards 
under paragraph (1) directly to a regional entity consistent 
with the requirements of this paragraph.
  (5) The Commission may take such action as is necessary or 
appropriate against the ERO or a regional entity to ensure 
compliance with a reliability standard or any Commission order 
affecting the ERO or a regional entity.
  (6) Any penalty imposed under this section shall bear a 
reasonable relation to the seriousness of the violation and 
shall take into consideration the efforts of such user, owner, 
or operator to remedy the violation in a timely manner.
  (f) Changes in Electric Reliability Organization Rules.--The 
Electric Reliability Organization shall file with the 
Commission for approval any proposed rule or proposed rule 
change, accompanied by an explanation of its basis and purpose. 
The Commission, upon its own motion or complaint, may propose a 
change to the rules of the ERO. A proposed rule or proposed 
rule change shall take effect upon a finding by the Commission, 
after notice and opportunity for comment, that the change is 
just, reasonable, not unduly discriminatory or preferential, is 
in the public interest, and satisfies the requirements of 
subsection (c).
  (g) Reliability Reports.--[The ERO]
          (1) In general._The ERO  shall conduct periodic 
        assessments of the reliability and adequacy of the 
        bulk-power system in North America.
          (2) Annual long-term assessment.--The assessments 
        under paragraph (1) shall include an annual long-term 
        assessment, which shall include--
                  (A) an analysis of the ability of the bulk-
                power system to supply sufficient electric 
                energy necessary to maintain an adequate level 
                of reliability, taking into account generation 
                resource mix, transmission development, and 
                electric energy demand trends;
                  (B) an analysis of the risk of future 
                electric energy supply shortfalls under normal 
                and extreme weather conditions, and the risk of 
                any such shortfalls within each region of the 
                bulk-power system; and
                  (C) a determination of whether additional 
                generation resources are necessary to supply 
                sufficient electric energy to maintain an 
                adequate level of reliability during the 
                assessment period.
          (3) Notice of generation inadequacy.--In conducting a 
        long-term assessment under paragraph (2), if the ERO 
        finds that the bulk-power system is at risk of not 
        having adequate generation resources to supply 
        sufficient electric energy to maintain an adequate 
        level of reliability, the ERO shall publicly notify the 
        Commission that the bulk-power system is in a state of 
        generation inadequacy.
          (4) Data collection.--To conduct a long-term 
        assessment under paragraph (2), the ERO may collect 
        information and data from users, owners, and operators 
        of the bulk-power system.
  (h) Commission Review and Comment for Covered Agency 
Actions.--
          (1) Notice to federal agencies.--If the ERO notifies 
        the Commission under subsection (g)(3) that the bulk-
        power system is in a state of generation inadequacy, 
        the Commission shall promptly notify the Department of 
        Energy, the Environmental Protection Agency, and any 
        other Federal agency the Commission determines 
        appropriate of such state of generation inadequacy.
          (2) Submission.--Upon receiving notice under 
        paragraph (1), the head of each Federal agency that 
        received such notice shall provide to the Commission 
        for review and comment any covered agency action by the 
        Federal agency--
                  (A) on the first date on which such covered 
                agency action is provided to the Office of 
                Management and Budget or any other Federal 
                agency for review and comment; or
                  (B) if such covered agency action is not 
                provided to the Office of Management and Budget 
                or any other Federal agency for review and 
                comment, not later than 90 days before the date 
                on which the covered agency action is published 
                in the Federal Register or is otherwise made 
                available for public inspection or comment.
          (3) Commission comments.--The Commission, in 
        consultation with the ERO and transmission 
        organizations, shall, by order, provide to the agency 
        head that provided to the Commission a covered agency 
        action under paragraph (2)--
                  (A) comments on such covered agency action, 
                which such comments may include an assessment 
                of the effect of the covered agency action on 
                rates, terms, and conditions for services 
                pursuant to the authority of the Commission 
                under sections 201 and 206; and
                  (B) if applicable, recommendations for 
                modifications to the covered agency action to 
                prevent a significant negative impact on the 
                ability of the bulk-power system to supply 
                sufficient electric energy necessary to 
                maintain an adequate level of reliability.
          (4) Agency response.--The head of a Federal agency 
        may not finalize a covered agency action that is 
        provided to the Commission under paragraph (2) until--
                  (A) the agency head responds in writing to 
                the Commission with an explanation of how the 
                agency head modified, or why the agency head 
                determined not to modify, such covered agency 
                action in response to any comments and 
                recommendations provided by the Commission 
                under paragraph (3); and
                  (B) the Commission finds that the covered 
                agency action will not be likely to have a 
                significant negative impact on the ability of 
                the bulk-power system to supply sufficient 
                electric energy necessary to maintain an 
                adequate level of reliability.
          (5) Public availability of comments and responses.--
        An agency head shall include any comments, 
        recommendations, and responses for the covered agency 
        action when--
                  (A) submitting the covered agency action to 
                the Federal Register for publication; or
                  (B) otherwise making the covered agency 
                action available for public inspection or 
                comment.
          (6) Definitions.--In this subsection:
                  (A) Covered agency action.--The term 
                ``covered agency action'' means a regulation 
                that--
                          (i) relates to, or otherwise directly 
                        affects, any generation resource in the 
                        bulk-power system; and
                          (ii) is under development to be 
                        proposed or otherwise under 
                        consideration in a rulemaking prior to 
                        finalization on the date on which the 
                        Federal agency receives notice from the 
                        Commission under paragraph (1).
                  (B) Federal agency.--The term ``Federal 
                agency'' means an Executive department (as that 
                term is defined in section 101 of title 5, 
                United States Code) or any other Executive 
                agency that is in the President's cabinet.
  [(h)] (i) Coordination With Canada and Mexico.--The President 
is urged to negotiate international agreements with the 
governments of Canada and Mexico to provide for effective 
compliance with reliability standards and the effectiveness of 
the ERO in the United States and Canada or Mexico.
  [(i)] (j) Savings Provisions.--(1) The ERO shall have 
authority to develop and enforce compliance with reliability 
standards for only the bulk-power system.
  (2) This section does not authorize the ERO or the Commission 
to order the construction of additional generation or 
transmission capacity or to set and enforce compliance with 
standards for adequacy or safety of electric facilities or 
services.
  (3) Nothing in this section shall be construed to preempt any 
authority of any State to take action to ensure the safety, 
adequacy, and reliability of electric service within that 
State, as long as such action is not inconsistent with any 
reliability standard, except that the State of New York may 
establish rules that result in greater reliability within that 
State, as long as such action does not result in lesser 
reliability outside the State than that provided by the 
reliability standards.
  (4) Within 90 days of the application of the Electric 
Reliability Organization or other affected party, and after 
notice and opportunity for comment, the Commission shall issue 
a final order determining whether a State action is 
inconsistent with a reliability standard, taking into 
consideration any recommendation of the ERO.
  (5) The Commission, after consultation with the ERO and the 
State taking action, may stay the effectiveness of any State 
action, pending the Commission's issuance of a final order.
  [(j)] (k) Regional Advisory Bodies.--The Commission shall 
establish a regional advisory body on the petition of at least 
two-thirds of the States within a region that have more than 
one-half of their electric load served within the region. A 
regional advisory body shall be composed of one member from 
each participating State in the region, appointed by the 
Governor of each State, and may include representatives of 
agencies, States, and provinces outside the United States. A 
regional advisory body may provide advice to the Electric 
Reliability Organization, a regional entity, or the Commission 
regarding the governance of an existing or proposed regional 
entity within the same region, whether a standard proposed to 
apply within the region is just, reasonable, not unduly 
discriminatory or preferential, and in the public interest, 
whether fees proposed to be assessed within the region are 
just, reasonable, not unduly discriminatory or preferential, 
and in the public interest and any other responsibilities 
requested by the Commission. The Commission may give deference 
to the advice of any such regional advisory body if that body 
is organized on an Interconnection-wide basis.
  [(k)] (l) Alaska and Hawaii.--The provisions of this section 
do not apply to Alaska or Hawaii.

           *       *       *       *       *       *       *

                             MINORITY VIEWS

    H.R. 3616, the Reliable Power Act H.R. 3616, the Reliable 
Power Act, would restructure section 215 of the Federal Power 
Act to grant the Federal Energy Regulatory Commission (FERC) 
veto authority over other agencies' regulations in certain 
circumstances. It would effectively elevate FERC's authority 
over all other agencies' statutory responsibilities. The bill 
would grant FERC an unprecedented veto over other agency 
actions while FERC's status as an independent regulator is in 
serious jeopardy.
    The bill grants FERC power over other agency regulations if 
the North American Electric Reliability Corporation (NERC) 
notifies FERC that the bulk-power system is in a ``state of 
generation inadequacy.''\1\ This would transform NERC from a 
neutral arbiter of the electric sector's reliability into a 
political actor, deciding when to grant FERC additional powers.
---------------------------------------------------------------------------
    \1\H.R. 3616.
---------------------------------------------------------------------------
    NERC's annual long-term reliability assessments would 
become politicized, and Congress would delegate a decision 
about what powers FERC should have to an industry body.
    Furthermore, while NERC and its staff do an admirable job 
with relatively few resources, their judgment is only as good 
as the data inputs they receive. This recently became an issue 
when NERC announced that it was reclassifying the footprint of 
the Midcontinent Independent System Operator (MISO) from a 
state of high risk to a state of elevated risk later this 
decade, because MISO had mismatched data submitted to NERC.\2\ 
This episode highlights the sheer complexity of NERC's 
reliability assessments, and, while useful, they are uncertain 
enough that they should not be used to trigger additional FERC 
authorities.
---------------------------------------------------------------------------
    \2\North American Electric Reliability Corporation, Statement on 
NERC's 2024 Long-Term Assessment (June 17, 2025) (https://www.nerc.com/
news/Pages/Statement-on-NERC%E2%80%99s-2024-Long-Term-Reliability-
Assessment.aspx).
---------------------------------------------------------------------------
    The majority's report singles out the Environmental 
Protection Agency's (EPA) 2024 rule on New Source Performance 
Standards for new, modified, and reconstructed power plants. 
However, the majority can hardly argue that EPA lacked 
information on potential reliability impacts when crafting the 
rule. In April 2023, a year before the rule was finalized, FERC 
staff from the Office of Electric Reliability met with EPA 
staff regarding the rule.\3\ In November 2023, FERC held a 
technical conference that featured EPA's then-Principal Deputy 
Assistant Administrator for the Office of Air and Radiation, 
Joseph Goffman, as a witness and included an additional two 
panels from electric industry stakeholders discussing the 
rule.\4\ Following the technical conference, EPA noticed a 
supplemental notice of proposed rulemaking, specifically 
soliciting comments on how the proposed rule related to 
electric reliability, and received over one hundred 
comments.\5\ Finally, then-FERC Commissioner James Danly 
himself submitted two comments on the rule to EPA.\6\
---------------------------------------------------------------------------
    \3\House Committee on Energy and Commerce, Response from Dr. David 
Ortiz, Director, Office of Electric Reliability, Federal Energy 
Regulatory Commission, to a Question for the Record from Chair Jeff 
Duncan, Subcommittee on Climate and Grid Security, Hearing on Keeping 
the Lights on: Enhancing Reliability and Efficiency to Power American 
Homes, 118th Cong. (Sept. 13, 2023).
    \4\Federal Energy Regulatory Commission, Second Supplemental Notice 
of Technical Conference, Reliability Technical Conference, Docket No. 
AD23-9 (Oct. 30, 2023).
    \5\Environmental Protection Agency, New Source Performance 
Standards for Greenhouse Gas Emissions From New, Modified, and 
Reconstructed Fossil Fuel-Fired Electric Generating Units, 88 Fed. Reg. 
80682. (Nov. 20, 2023) (proposed rule).
    \6\Commissioner James Danly, Comment to Docket No. EPA-HQ-OAR-2023-
0072 (Aug. 8, 2023); Commissioner James Danly, Comment to Docket No. 
EPA-HQ-OAR-2023-0072 (Dec. 20, 2023).
---------------------------------------------------------------------------
    The majority may dislike the conclusions EPA came to, but 
the agency's process was undeniably thorough. EPA considered a 
number of factors, including electric reliability, and came to 
a conclusion of what was required of it under the Clean Air 
Act. Here, the majority seeks to upset the law without actually 
doing the hard work of amending agency authorizing statutes, 
instead simply giving the final call to FERC--an independent 
commission that ``has no business promoting the policies of any 
one party or presidential administration.''\7\
---------------------------------------------------------------------------
    \7\Federal Energy Regulatory Commission, Building for the Future 
Through Electric Regional Transmission Planning and Cost Allocation, 
Order No. 1920, 187 FERC  61,068 (May 13, 2024) (Christie, 
Commissioner, dissenting at PP 4).
---------------------------------------------------------------------------
    Giving FERC the final call on regulations is even more 
concerning now than it was in prior administrations due to an 
exodus of staff over the previous nine months. The agency has 
lost 11 percent of its workforce since the Trump Administration 
took office, meaning that it will struggle to carry out its 
basic activities regulating the energy sector, let alone 
policing other agencies' regulations.\8\ This amplifies fears 
that even at pre-Trump Administration staffing levels, FERC 
lacked the capacity to implement the bill, as the Committee 
heard from Dr. David Ortiz, then-Director of FERC's Office of 
Electric Reliability in 2023 and FERC's Acting General Counsel 
David L. Morenoff earlier this year.\9\
---------------------------------------------------------------------------
    \8\`Brain Drain' at FERC Hits Legal and Policy Staff, E&E News 
(Sep. 5, 2025).
    \9\House Committee on Energy and Commerce, Testimony of Dr. David 
Ortiz, Director, Office of Electric Reliability, Federal Energy 
Regulatory Commission, Hearing on Keeping the Lights on: Enhancing 
Reliability and Efficiency to Power American Homes, 118th Cong. (Sept. 
13, 2023); House Committee on Energy and Commerce, Testimony of David 
L. Morenoff, Acting General Counsel, Federal Energy Regulatory 
Commission, Hearing on Assuring Abundant, Reliable American Energy to 
Power Innovation, 119th Cong. (Apr. 30, 2024).
---------------------------------------------------------------------------
    At the Energy Subcommittee Markup, Rep. Diana DeGette (D-
CO) offered an amendment that would have fixed this portion of 
the bill by preventing it from taking effect until FERC 
certified that it had sufficient staffing capacity to analyze 
all covered agency actions.\10\ That amendment failed on a 
party-line vote.
---------------------------------------------------------------------------
    \10\House Committee on Energy and Commerce, Subcommittee on Energy, 
Markup of 13 Bills, 119th Cong. (June 5, 2025).
---------------------------------------------------------------------------
    For the reasons stated above, I oppose this legislation.

                                        Frank Pallone, Jr.,
                                                    Ranking Member.

                                  [all]