[House Report 119-295]
[From the U.S. Government Publishing Office]


119th Congress }                                              { Report
                        HOUSE OF REPRESENTATIVES
 1st Session   }                                              { 119-295

=======================================================================



 
                  GUARANTEEING RELIABILITY THROUGH THE
               INTERCONNECTION OF DISPATCHABLE POWER ACT

                            ----------------
                                
 September 15, 2025.--Committed to the Committee of the Whole House on 
            the State of the Union and ordered to be printed

                            ----------------
                                
          Mr. Guthrie, from the Committee on Energy and Commerce,
                         submitted the following


                              R E P O R T

                             together with

                             MINORITY VIEWS

                        [To accompany H.R. 1047]

    The Committee on Energy and Commerce, to whom was referred 
the bill (H.R. 1047) to require the Federal Energy Regulatory 
Commission to reform the interconnection queue process for the 
prioritization and approval of certain projects, and for other 
purposes, having considered the same, reports favorably thereon 
without amendment and recommends that the bill do pass.

                                CONTENTS

                                                                   Page
Purpose and Summary..............................................     2
Background and Need for Legislation..............................     2
Committee Action.................................................     4
Committee Votes..................................................     4
Oversight Findings and Recommendations...........................     7
New Budget Authority, Entitlement Authority, and Tax Expenditures     7
Congressional Budget Office Estimate.............................     7
Federal Mandates Statement.......................................     7
Statement of General Performance Goals and Objectives............     7
Duplication of Federal Programs..................................     7
Related Committee and Subcommittee Hearings......................     7
Committee Cost Estimate..........................................     9
Earmark, Limited Tax Benefits, and Limited Tariff Benefits.......     9
Advisory Committee Statement.....................................     9
Applicability to Legislative Branch..............................     9
Section-by-Section Analysis of the Legislation...................     9
Changes in Existing Law Made by the Bill, as Reported............     9
Minority, Additional, or Dissenting Views........................    10

                          PURPOSE AND SUMMARY

    H.R. 1047 the ``Guaranteeing Reliable Interconnection of 
Dispatchable (GRID) Power Act'' was introduced by 
Representative Troy Balderson (R-OH) on February 6, 2025. This 
legislation would direct FERC to issue a rulemaking authorizing 
transmission providers to prioritize and expedite 
interconnection queue requests for dispatchable generation 
projects and projects that enhance grid resilience and 
reliability. The legislation would require FERC to conduct 
periodic review and updates of regulations promulgated under 
this rulemaking to ensure interconnection regulations remain 
effective and relevant to grid reliability and resilience 
challenges.

                  BACKGROUND AND NEED FOR LEGISLATION

    Generator interconnection agreements are the formal process 
for generating units to connect to high voltage transmission 
lines of the bulk power system. Interconnection agreements 
require studies and analyses to assess the impact that new 
generation units may have on the bulk-power system. In 2003, 
FERC finalized Order 2003, its first formal standardization of 
interconnection agreements and procedures for all public 
utilities that operate facilities that transmit electricity in 
interstate commerce.\1\ The commission stated in Order 2003 
that the intent of standardizing the interconnection process 
was to prevent undue discrimination, increase energy supply, 
and lower wholesale prices for customers by increasing the 
variety of generating resources.\2\
---------------------------------------------------------------------------
    \1\U.S. Fed. Energy Regul. Comm'n (FERC), Standardization of 
Generator Interconnection Agreements and Procedures, Docket No. RM02-1-
001; Order No. 2003-A, (Issued Mar. 5, 2004), https://www.ferc.gov/
sites/default/files/2020-06/order-2003.pdf.
    \2\Id.
---------------------------------------------------------------------------
    Since Order 2003, the electricity sector has changed 
dramatically, presenting new challenges to the existing and a 
growing prevalence of interconnection backlogs and approval 
delays. Further complicating these challenges is the historic 
increases of projected electricity demands, largely driven by 
new data centers, domestic manufacturing, and general economy-
wide electrification that is occurring while record levels of 
baseload power are seeking to retire. The North American 
Electric Reliability Corporation (NERC) projects peak demand to 
grow by 151 GW by 2034.\3\ At the same time, NERC reports that 
as much as 115 GW of thermal generation has announced to retire 
within the same time period.\4\
---------------------------------------------------------------------------
    \3\North American Reliability Corporation (NERC), 2024 Long-Term 
Reliability Assessment (December 2024), https://www.nerc.com/pa/RAPA/
ra/Reliability%20Assessments%20DL/
NERC_Long%20Term%20Reliability%20Assessment_2024.pdf.
    \4\Id.
---------------------------------------------------------------------------
    It is estimated that 95 percent of current interconnection 
requests come from wind, solar, or battery storage 
resources.\5\ This is driven by a confluence of factors, 
including federal and state subsidies for intermittent energy 
resources, state policies that require utilities to deploy 
intermittent energy resources, and state and federal 
regulations that discourage the continued operation of, or new 
investments into, baseload generating resources, such as 
natural gas, oil, and coal. The growing presence of variable 
energy resources on the bulk power system creates significant 
challenges for grid operators to properly plan and protect 
reliability and stability of the grid while also creating 
approval backlogs for new resources seeking interconnection. 
Much of these resources remain speculative and are not 
considered shovel ready. As an example, PJM finds that the 
historical completion rate for renewable energy projects is 5 
percent.\6\
---------------------------------------------------------------------------
    \5\Joseph Rand et al., Queued Up: 2024 Edition, Characteristics of 
Power Plants Seeking Transmission Interconnection as of the End of 
2023, Lawrence Berkely National Laboratory, funded by the U.S. Dep't. 
of Energy under Contract No. DE-AC02-05CH11231 (April 2024), https://
emp.lbl.gov/sites/default/files/2024-04/
Queued%20Up%202024%20Edition_R2.pdf.
    \6\PJM, Energy Transitions in PJM: Resource Retirements, 
Replacements & Risks (Feb. 24, 2023), https://www.pjm.com/-/media/
DotCom/library/reports-notices/special-reports/2023/energy-transition-
in-pjm-resource-retirements-replacements-and-risks.ashx.
---------------------------------------------------------------------------
    In 2023, FERC finalized Order 2023, its next most 
comprehensive alterations to the interconnection process.\7\ 
Among other things, Order 2023 changed the interconnection 
queue from a ``first come first serve'' model to a ``first 
ready first serve'' model, required the use of cluster studies 
to study multiple projects simultaneously, and required 
generating customers to provide readiness deposits to secure a 
spot in the interconnection queue. These reforms are seeking to 
ensure project viability and remove speculators from taking up 
valuable space on the interconnection queue. At the time of 
this report, FERC continues evaluating grid operator filings to 
comply with requirements from Order 2023, which has not been 
fully implemented.
---------------------------------------------------------------------------
    \7\FERC, Improvements to Generator Interconnection Procedures and 
Agreements, Docket No. RM22-14-000; Order No. 2023 (Issued Jul. 28, 
2023), https://www.ferc.gov/media/order-no-2023.
---------------------------------------------------------------------------
    During the Energy Subcommittee's hearing on March 25th, 
2025, with regional grid operators, witness testimony 
identified the challenges of maintaining reliability amidst 
growing reliance on variable energy resources and the need for 
baseload, dispatchable, and on-demand generating units to 
maintain sufficient frequency and voltage support.\8\ In 
recognition of the growing imbalance of generating resources on 
the bulk power system, growing backlog of interconnection queue 
requests, rapid pace of baseload retirements, and historic 
increases in projected demand, PJM, MISO, CAISO, and SPP have 
implemented, or put forward proposals, to expedite the approval 
of generation projects that can meaningfully contribute to 
resource adequacy.
---------------------------------------------------------------------------
    \8\Keeping the Lights On: Examining the State of Regional Grid 
Reliability: Hearing before the H. Comm. on Energy and Commerce 
Subcommittee on Energy, 119th Cong. (Mar. 25, 2025), https://
energycommerce.house.gov/events/energy-subcommittee-keeping-the-lights-
on-examining-the-state-of-regional-grid-reliability.
---------------------------------------------------------------------------
    To ensure the reliability and stability of the bulk power 
system, the Committee finds there is a need to bring 
dispatchable and on-demand generating resources onto the system 
that can balance the growing presence of variable resources, 
such as wind and solar. During our Energy Subcommittee's 
hearing on March 25th, 2025, with regional grid operators, 
Southwest Power Pool (SPP) noted a recent weather event where 
the region lost 12,000 MW of available wind resources in a 2-
hour timeframe and replaced the lost power supplies with 
readily available natural gas generating units.\9\
---------------------------------------------------------------------------
    \9\Id.
---------------------------------------------------------------------------
    To that end, the GRID Power Act would provide grid 
operators additional tools to methodically advance resources 
through the interconnection queue to protect the reliability 
and stability of the electric grid.

                            COMMITTEE ACTION

    On April 30, 2025, the Subcommittee on Energy held a 
legislative hearing on 14 bills, including H.R. 1047. The 
Subcommittee received testimony from:
           Mike Goff, Acting Undersecretary of Energy, 
        U.S. Department of Energy;
           David L. Morenoff, Acting General Counsel, 
        Federal Energy Regulatory Commission;
           Terry Turpin, Director, Office of Energy 
        Projects, Federal Energy Regulatory Commission;
           Jim Matheson, Chief Executive Officer, 
        National Rural Electric Cooperative Association;
           Amy Andryszak, President and Chief Executive 
        Officer, Interstate Natural Gas Association of America;
           Todd A. Snitchler, President and Chief 
        Executive Officer, Electric Power Supply Association 
        and;
           Kim Smaczniak, Partner, Roselle LLP.
    On June 5, 2025, the Subcommittee on Energy met in open 
markup session and forwarded H.R. 1047, without amendment, to 
the full Committee by a record vote of 16 yeas and 14 nays. On 
June 25, 2025, the full Committee on Energy and Commerce met in 
open markup session and ordered H.R. 1047, without amendment, 
favorably reported to the House by a record vote of 28 yeas and 
23 nays.

                            COMMITTEE VOTES

    Clause 3(b) of rule XIII requires the Committee to list the 
record votes on the motion to report legislation and amendments 
thereto. The following reflects the record votes taken during 
the Committee consideration:

[GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]

                 OVERSIGHT FINDINGS AND RECOMMENDATIONS

    Pursuant to clause 2(b)(1) of rule X and clause 3(c)(1) of 
rule XIII, the Committee held hearings and made findings that 
are reflected in this report.

   NEW BUDGET AUTHORITY, ENTITLEMENT AUTHORITY, AND TAX EXPENDITURES

    Pursuant to clause 3(c)(2) of rule XIII, the Committee 
finds that H.R. 1047 would result in no new or increased budget 
authority, entitlement authority, or tax expenditures or 
revenues.

                  CONGRESSIONAL BUDGET OFFICE ESTIMATE

    Pursuant to clause 3(c)(3) of rule XIII, at the time this 
report was filed, the cost estimate prepared by the Director of 
the Congressional Budget Office pursuant to section 402 of the 
Congressional Budget Act of 1974 was not available.

                       FEDERAL MANDATES STATEMENT

    The Committee adopts as its own the estimate of Federal 
mandates prepared by the Director of the Congressional Budget 
Office pursuant to section 423 of the Unfunded Mandates Reform 
Act.

         STATEMENT OF GENERAL PERFORMANCE GOALS AND OBJECTIVES

    Pursuant to clause 3(c)(4) of rule XIII, the general 
performance goal or objective of this legislation is to direct 
FERC to initiate a rulemaking to authorize transmission 
providers to adjust interconnection queue schedules for 
resources that meaningfully contribute to the stability and 
resource adequacy of the bulk power system.

                    DUPLICATION OF FEDERAL PROGRAMS

    Pursuant to clause 3(c)(5) of rule XIII, no provision of 
H.R. 1047 is known to be duplicative of another Federal 
program, including any program that was included in a report to 
Congress pursuant to section 21 of Public Law 111-139 or the 
most recent Catalog of Federal Domestic Assistance.

              RELATED COMMITTEE AND SUBCOMMITTEE HEARINGS

    Pursuant to clause 3(c)(6) of rule XIII, the following 
related hearings were used to develop or consider H.R. 1047:
    On February 5, 2025, the Subcommittee on Energy held a 
hearing on H.R. 1047, titled ``Powering America's Future: 
Unleashing American Energy.'' The Subcommittee received 
testimony from:
           Amanda Eversole, Executive Vice President 
        and Chief Advocacy Officer, American Petroleum 
        Institute;
           Brigham McCown, Senior Fellow and Director, 
        Initiative on American Energy Security, The Hudson 
        Institute;
           Gary Arnold, Business Manager, Denver 
        Pipefitters Local 208 and;
           Tyler O'Connor, Partner, Crowell & Moring 
        LLP.
    On March 5, 2025, the Subcommittee on Energy held a hearing 
on H.R. 1047, titled ``Scaling for Growth: Meeting the Demand 
for Reliable, Affordable Electricity.'' The Subcommittee 
received testimony from:
           Todd Brickhouse, CEO and General Manager, 
        Basin Electric Power Cooperative;
           Asim Haque, Senior Vice President for 
        Governmental and Member Services, PJM;
           Noel W. Black, Senior VP of Regulatory 
        Affairs, Southern Company and;
           Tyler H. Norris, James B. Duke Fellow, Duke 
        University.
    On March 25, 2025, the Subcommittee on Energy held a 
hearing on H.R. 1047, titled ``Keeping the Lights On: Examining 
the State of Regional Grid Reliability.'' The Subcommittee 
received testimony from:
           Gordon van Welie, President and Chief 
        Executive Officer, ISO New England;
           Richard J. Dewey, President and Chief 
        Executive Officer, New York Independent System 
        Operator;
            Manu Asthana, President and Chief Executive 
        Officer, PJM Interconnection LLC;
            Jennifer Curran, Senior Vice President for 
        Planning and Operations, Midcontinent ISO;
            Lanny Nickell, Chief Operating Officer, 
        Southwest Power Pool;
            Elliot Mainzer, President and Chief 
        Executive Officer, California Independent System 
        Operator and;
            Pablo Vegas President and Chief Executive 
        Officer, Electric Reliability Council of Texas, Inc.
    On April 9, 2025, the Committee on Energy and Commerce held 
a hearing on H.R. 1047, titled ``Converting Energy into 
Intelligence: The Future of AI Technology, Human Discovery, and 
American Global Competitiveness.'' The Committee received 
testimony from:
            Eric Schmidt, Chair, Special Competitive 
        Studies Project;
            Manish Bhatia, Executive Vice President of 
        Global Operations, Micron Technology;
            Alexander Wang, Founder and Chief Executive 
        Officer, Scale AI, and;
            David Turk, Distinguished Visiting Fellow, 
        Center on Global Energy Policy, Columbia University.
    On April 30, 2025, the Subcommittee on Energy held a 
legislative hearing on H.R. 1047, titled ``Assuring Abundant, 
Reliable American Energy to Power Innovation''. The 
Subcommittee received testimony from:
            Mike Goff, Acting Undersecretary of Energy, 
        U.S. Department of Energy;
            David L. Morenoff, Acting General Counsel, 
        Federal Energy Regulatory Commission;
            Terry Turpin, Director, Office of Energy 
        Projects, Federal Energy Regulatory Commission;
            Jim Matheson, Chief Executive Officer, 
        National Rural Electric Cooperative Association;
            Amy Andryszak, President and Chief 
        Executive Officer, Interstate Natural Gas Association 
        of America;
            Todd A. Snitchler, President and Chief 
        Executive Officer, Electric Power Supply Association 
        and;
            Kim Smaczniak, Partner, Roselle LLP.

                        COMMITTEE COST ESTIMATE

    Pursuant to clause 3(d)(1) of rule XIII, the Committee 
adopts as its own the cost estimate prepared by the Director of 
the Congressional Budget Office pursuant to section 402 of the 
Congressional Budget Act of 1974. At the time this report was 
filed, the estimate was not available.

       EARMARK, LIMITED TAX BENEFITS, AND LIMITED TARIFF BENEFITS

    Pursuant to clause 9(e), 9(f), and 9(g) of rule XXI, the 
Committee finds that H.R. 1047 contains no earmarks, limited 
tax benefits, or limited tariff benefits.

                      ADVISORY COMMITTEE STATEMENT

    No advisory committees within the meaning of section 5(b) 
of the Federal Advisory Committee Act were created by this 
legislation.

                  APPLICABILITY TO LEGISLATIVE BRANCH

    The Committee finds that the legislation does not relate to 
the terms and conditions of employment or access to public 
services or accommodations within the meaning of section 
102(b)(3) of the Congressional Accountability Act.

             SECTION-BY-SECTION ANALYSIS OF THE LEGISLATION

Section 1. Short title

    Section 1 provides that the Act may be cited as the 
``Guaranteeing Reliability through the Interconnection of 
Dispatchable Power Act'' or the ``GRID Power Act.''

Section 2. Definitions

    Section 2 defines terms included in the Act.

Section 3. Rulemaking to improve interconnection queue flexibility

    Section 3 directs FERC to initiate a rulemaking to address 
the inefficiencies and ineffectiveness of existing procedures 
for generation interconnection requests by authorizing 
transmission providers to submit proposals that adjust 
interconnection queue schedules that prioritize projects which 
improve grid reliability and resource adequacy. Proposals 
submitted pursuant to this rulemaking must demonstrate a need 
for prioritization, reporting requirements, and opportunity for 
public comment before being submitted to the commission.

         CHANGES IN EXISTING LAW MADE BY THE BILL, AS REPORTED

    This legislation does not amend any existing Federal 
statute.

                             MINORITY VIEWS

    H.R. 1047, the GRID Power Act H.R. 1047, the GRID Power 
Act, would require the Federal Energy Regulatory Commission 
(FERC) to initiate a rulemaking allowing grid operators to 
submit filings to FERC to prioritize certain types of 
electricity generation resources, namely, fossil fuels. This 
legislation is another component of Republicans' plan to wage 
all-out war on zero-carbon sources of electricity. Instead of 
focusing on technology-neutral improvements to the generation 
interconnection process, the bill arbitrarily picks winners and 
losers.
    The main ostensible concept of the legislation--allowing 
grid operators to prioritize certain resources--is duplicative 
because it is already allowed under section 205 of the Federal 
Power Act. Remarkably, the majority's report fails to mention 
three major initiatives from grid operators that have 
successfully sought permission from FERC for a one-time 
intervention in their generation interconnection queues to 
prioritize dispatchable resources in the last year.\1\ If the 
bill was only aimed at allowing technology-agnostic 
interventions into the generation interconnection queue to 
stave off reliability concerns, it would merely be duplicative 
of existing authorities.
---------------------------------------------------------------------------
    \1\PJM Interconnection, L.L.C., 190 FERC  61,084 (Feb. 11, 2025); 
Southwest Power Pool, Inc., 192 FERC  61,062 (July 21, 2025); 
Midcontinent Independent System Operator, Inc., 192 FERC  61,064 (July 
21, 2025).
---------------------------------------------------------------------------
    However, there are significant differences between the 
process imagined by the legislation and FERC's existing 
process--all of which mean that the bill would make the status 
quo significantly worse. The Committee received testimony 
earlier this year that FERC's current approvals of 
interconnection queue interventions, such as those proposed by 
PJM, the Midcontinent Independent System Operator (MISO), and 
the Southwest Power Pool (SPP), must satisfy just and 
reasonable criteria under the Federal Power Act, and must not 
be unduly discriminatory or preferential.\2\ H.R. 1047, 
however, includes no such requirement of grid operator filings, 
meaning the bill could open up power markets to blatant 
resource discrimination. This is evident in the initial results 
from MISO's Expedited Resource Addition Study process, which 
included one battery storage project, one wind project, and 
three solar projects out of ten total projects.\3\ Grid 
operators would likely be barred from considering these types 
of projects under the bill's flawed definition of 
``dispatchable power,'' meaning the bill would restrict grid 
operators' ability to accelerate the resources their grids most 
acutely need.
---------------------------------------------------------------------------
    \2\House Committee on Energy and Commerce, Testimony of Kim 
Smaczniak, Partner, Roselle LLP, Hearing on Assuring Abundant, Reliable 
American Energy to Power Innovation, 119th Cong. (Apr. 30, 2024).
    \3\Midcontinent Independent System Operator, MISO Announces First 
10 ERAS Projects (Sep. 4, 2025) (https://www.misoenergy.org/meet-miso/
media-center/2025--news-releases/miso-
announces-first-10-eras-project/) (press release).
---------------------------------------------------------------------------
    The importance of guardrails to ensure that proposed queue 
interventions are just and reasonable and not unduly 
discriminatory or preferential is not merely hypothetical. 
Earlier this year, FERC rejected MISO's initial attempt to 
intervene in its interconnection queue because it lacked limits 
on the number of projects that could be considered.\4\ Had MISO 
instead made its proposal under the regime envisioned by this 
bill, it likely would have been approved, transforming a one-
time, emergency queue intervention into an open-ended 
preference for particular resources. When Energy Subcommittee 
Ranking Member Kathy Castor (D-FL) proposed an amendment that 
would have required FERC to deny any grid operator queue 
proposal under the bill that was not just or reasonable or was 
unduly discriminatory or preferential, Republicans rejected the 
amendment.\5\
---------------------------------------------------------------------------
    \4\FERC Rejects MISO Plan to Speed Generation Interconnection, 
Utility Dive (May 20, 2025).
    \5\House Committee on Energy and Commerce, Subcommittee on Energy, 
Markup of 13 Bills, 119th Cong. (June 5, 2025).
---------------------------------------------------------------------------
    The bill also lacks basic, commonsense protections to 
ensure it can be used to target the lack of generation projects 
the majority's report is concerned about. The bill contains no 
requirements that projects accelerated by a grid operator's 
intervention come online in a specific timeframe, nor does it 
do anything to help alleviate severe supply chain constraints 
that seem to be limiting how quickly natural gas-fired power 
plants can come online.\6\ As Kim Smaczniak, Partner at 
Roselle, LLP, noted in her testimony to the Committee earlier 
this year, these inadequacies in the bill could mean that it 
might harm electric reliability and would put affordability at 
risk.\7\
---------------------------------------------------------------------------
    \6\US Gas-Fired Turbine Wait Times as Much as Seven Years; Costs Up 
Sharply, S&P Global (May 20, 2025).
    \7\See note 2.
---------------------------------------------------------------------------
    The Committee received testimony that ``it would be a 
terrible mistake to only fix the interconnection process for 
certain types of generators, rather than advance broad-based 
solutions that benefit all commercially viable projects seeking 
to interconnect.''\8\ If the majority was truly interested in 
hastening the process of getting power generation online they 
should have advanced H.R. 2986, the Expediting Generator 
Interconnection Procedures Act of 2025, introduced by Ranking 
Member Castor. That bill would have built on the progress made 
by FERC's Order 2023, speeding up generation interconnection 
for all types of projects.
---------------------------------------------------------------------------
    \8\Id.
---------------------------------------------------------------------------
    For the reasons stated above, I oppose this legislation.

                                        Frank Pallone, Jr.,
                                                    Ranking Member.

                                  [all]