[House Report 116-677]
[From the U.S. Government Publishing Office]


116th Congress }                                        { Rept. 116-677
                        HOUSE OF REPRESENTATIVES
 2d Session    }                                        {     Part 1

========================================================================



 
          PUBLIC LAND RENEWABLE ENERGY DEVELOPMENT ACT OF 2019

                                _______
                                

               December 18, 2020.--Ordered to be printed

                                _______
                                

 Mr. Grijalva, from the Committee on Natural Resources, submitted the 
                               following

                              R E P O R T

                        [To accompany H.R. 3794]

      [Including cost estimate of the Congressional Budget Office]

    The Committee on Natural Resources, to whom was referred 
the bill (H.R. 3794) to promote the development of renewable 
energy on public lands, and for other purposes, having 
considered the same, reports favorably thereon with an 
amendment and recommends that the bill as amended do pass.
    The amendment is as follows:
  Strike all after the enacting clause and insert the 
following:

SECTION 1. SHORT TITLE.

  This Act may be cited as the ``Public Land Renewable Energy 
Development Act of 2019''.

SEC. 2. TABLE OF CONTENTS.

  The table of contents for this Act is as follows:

Sec. 1. Short title.
Sec. 2. Table of contents.
Sec. 3. Definitions.
Sec. 4. Land use planning; supplements to programmatic environmental 
impact statements.
Sec. 5. Environmental review on covered land.
Sec. 6. Program to improve renewable energy project permit 
coordination.
Sec. 7. Increasing economic certainty.
Sec. 8. Limited grandfathering.
Sec. 9. Renewable energy goal.
Sec. 10. Disposition of revenues.
Sec. 11. Promoting and enhancing development of geothermal energy.
Sec. 12. Facilitation of coproduction of geothermal energy on oil and 
gas leases.
Sec. 13. Noncompetitive leasing of adjoining areas for development of 
geothermal resources.
Sec. 14. Savings clause.

SEC. 3. DEFINITIONS.

  In this Act:
          (1) Covered land.--The term ``covered land'' means land that 
        is--
                  (A) public lands administered by the Secretary; and
                  (B) not excluded from the development of geothermal, 
                solar, or wind energy under--
                          (i) a land use plan established under the 
                        Federal Land Policy and Management Act of 1976 
                        (43 U.S.C. 1701 et seq.); or
                          (ii) other Federal law.
          (2) Exclusion area.--The term ``exclusion area'' means 
        covered land that is identified by the Bureau of Land 
        Management as not suitable for development of renewable energy 
        projects.
          (3) Federal land.--The term ``Federal land'' means--
                  (A) land of the National Forest System (as defined in 
                section 11(a) of the Forest and Rangeland Renewable 
                Resources Planning Act of 1974 (16 U.S.C. 1609(a))); or
                  (B) public lands.
          (4) Fund.--The term ``Fund'' means the Renewable Energy 
        Resource Conservation Fund established by section 10(c)(1).
          (5) Priority area.--The term ``priority area'' means covered 
        land identified by the land use planning process of the Bureau 
        of Land Management as being a preferred location for a 
        renewable energy project, including a designated leasing area 
        (as defined in section 2801.5(b) of title 43, Code of Federal 
        Regulations (or a successor regulation)) that is identified 
        under the rule of the Bureau of Land Management entitled 
        ``Competitive Processes, Terms, and Conditions for Leasing 
        Public Lands for Solar and Wind Energy Development and 
        Technical Changes and Corrections'' (81 Fed. Reg. 92122 
        (December 19, 2016)) (or a successor regulation).
          (6) Public lands.--The term ``public lands'' has the meaning 
        given that term in section 103 of the Federal Land Policy and 
        Management Act of 1976 (43 U.S.C. 1702).
          (7) Renewable energy project.--The term ``renewable energy 
        project'' means a project carried out on covered land that uses 
        wind, solar, or geothermal energy to generate energy.
          (8) Secretary.--The term ``Secretary'' means the Secretary of 
        the Interior.
          (9) Variance area.--The term ``variance area'' means covered 
        land that is--
                  (A) not an exclusion area;
                  (B) not a priority area; and
                  (C) identified by the Secretary as potentially 
                available for renewable energy development and could be 
                approved without a plan amendment, consistent with the 
                principles of multiple use (as that term is defined in 
                the Federal Land Policy and Management Act of 1976 (43 
                U.S.C. 1701 et seq.)).

SEC. 4. LAND USE PLANNING; SUPPLEMENTS TO PROGRAMMATIC ENVIRONMENTAL 
                    IMPACT STATEMENTS.

  (a) Priority Areas.--
          (1) In general.--The Secretary, in consultation with the 
        Secretary of Energy, shall establish priority areas on covered 
        land for geothermal, solar, and wind energy projects. Projects 
        located in those priority areas shall be given the highest 
        priority for review, and shall be offered the opportunity to 
        participate in any regional mitigation plan developed for the 
        relevant priority areas.
          (2) Deadline.--
                  (A) Geothermal energy.--For geothermal energy, the 
                Secretary shall establish priority areas as soon as 
                practicable, but not later than 5 years, after the date 
                of the enactment of this Act.
                  (B) Solar energy.--For solar energy, solar Designated 
                Leasing Areas, including the solar energy zones 
                established by the 2012 western solar plan of the 
                Bureau of Land Management and any subsequent land use 
                plan amendments, shall be considered to be priority 
                areas for solar energy projects. The Secretary shall 
                establish additional solar priority areas as soon as 
                practicable, but not later than 3 years, after the date 
                of the enactment of this Act.
                  (C) Wind energy.--For wind energy, the Secretary 
                shall establish additional wind priority areas as soon 
                as practicable, but not later than 3 years, after the 
                date of the enactment of this Act.
  (b) Variance Areas.--To the maximum extent practicable, variance 
areas shall be considered for renewable energy project development, 
consistent with the principles of multiple use (as defined in the 
Federal Land Policy and Management Act of 1976 (43 U.S.C. 1701 et 
seq.)).
  (c) Review and Modification.--Not less than once every 5 years, the 
Secretary shall--
          (1) review the adequacy of land allocations for geothermal, 
        solar, and wind energy priority and variance areas for the 
        purpose of encouraging new renewable energy development 
        opportunities; and
          (2) based on the review carried out under paragraph (1), add, 
        modify, or eliminate priority, variance, and exclusion areas.
  (d) Compliance With the National Environmental Policy Act.--For 
purposes of this section, compliance with the National Environmental 
Policy Act of 1969 (42 U.S.C. 4321 et seq.) shall be accomplished--
          (1) for geothermal energy, by supplementing the October 2008 
        final programmatic environmental impact statement for 
        geothermal leasing in the Western United States and 
        incorporating any additional regional analyses that have been 
        completed by Federal agencies since the programmatic 
        environmental impact statement was finalized;
          (2) for solar energy, by supplementing the July 2012 final 
        programmatic environmental impact statement for solar energy 
        development and incorporating any additional regional analyses 
        that have been completed by Federal agencies since the 
        programmatic environmental impact statement was finalized; and
          (3) for wind energy, by supplementing the July 2005 final 
        programmatic environmental impact statement for wind energy 
        development and incorporating any additional regional analyses 
        that have been completed by Federal agencies since the 
        programmatic environmental impact statement was finalized.
  (e) No Effect on Processing Applications.--Any requirements to 
prepare a supplement to a programmatic environmental impact statement 
under this section shall not result in any delay in processing a 
pending application for a renewable energy project.
  (f) Coordination.--In developing a supplement required by this 
section, the Secretary shall coordinate, on an ongoing basis, with 
appropriate State, Tribal, and local governments, transmission 
infrastructure owners and operators, developers, and other appropriate 
entities to ensure that priority areas identified by the Secretary 
are--
          (1) economically viable (including having access to existing 
        and/or planned transmission lines);
          (2) likely to avoid or minimize impacts to habitat for 
        animals and plants, recreation, cultural resources, and other 
        uses of covered land; and
          (3) consistent with section 202 of the Federal Land Policy 
        and Management Act of 1976 (43 U.S.C. 1712), including 
        subsection (c)(9) of that section (43 U.S.C. 1712(c)(9)).

SEC. 5. ENVIRONMENTAL REVIEW ON COVERED LAND.

  (a) In General.--If the Secretary determines that a proposed 
renewable energy project has been sufficiently analyzed by a 
programmatic environmental impact statement conducted under section 
4(d), the Secretary shall not require any additional review under the 
National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.). The 
Secretary shall publish any such project determinations on a publicly 
available website.
  (b) Additional Environmental Review.--If the Secretary determines 
that additional environmental review under the National Environmental 
Policy Act of 1969 (42 U.S.C. 4321 et seq.) is necessary for a proposed 
renewable energy project, the Secretary shall rely on the analysis in 
the programmatic environmental impact statement conducted under section 
4(d), to the maximum extent practicable when analyzing the potential 
impacts of the project.
  (c) Relationship to Other Law.--Nothing in this section modifies or 
supersedes any requirement under applicable law.

SEC. 6. PROGRAM TO IMPROVE RENEWABLE ENERGY PROJECT PERMIT 
                    COORDINATION.

  (a) Establishment.--The Secretary shall establish a national 
Renewable Energy Coordination Office and State, district, or field 
offices with responsibility to establish and implement a program to 
improve Federal permit coordination with respect to renewable energy 
projects on covered land and other activities deemed necessary by the 
Secretary. In carrying out the program, the Secretary may temporarily 
assign qualified staff to Renewable Energy Coordination Offices to 
expedite the permitting of renewable energy projects.
  (b) Memorandum of Understanding.--
          (1) In general.--Not later than 180 days after the date of 
        the enactment of this Act, the Secretary shall enter into a 
        memorandum of understanding for purposes of this section, 
        including to specifically expedite the environmental analysis 
        of applications for projects proposed in a variance area or a 
        priority area, with the Secretary of Defense and the Secretary 
        of Agriculture.
          (2) State and tribal participation.--The Secretary may 
        request the Governor of any interested State or any Tribal 
        leader of any interested Indian Tribe (as defined in section 4 
        of the Indian Self-Determination and Education Assistance Act 
        (25 U.S.C. 5304)) to be a signatory to the memorandum of 
        understanding under paragraph (1).
  (c) Designation of Qualified Staff.--
          (1) In general.--Not later than 30 days after the date on 
        which the memorandum of understanding under subsection (b) is 
        executed, all Federal signatories, as appropriate, shall 
        identify for each of the Bureau of Land Management Renewable 
        Energy Coordination Offices one or more employees who have 
        expertise in the regulatory issues relating to the office in 
        which the employee is employed, including, as applicable, 
        particular expertise in--
                  (A) consultation regarding, and preparation of, 
                biological opinions under section 7 of the Endangered 
                Species Act of 1973 (16 U.S.C. 1536);
                  (B) permits under section 404 of the Federal Water 
                Pollution Control Act (33 U.S.C. 1344);
                  (C) regulatory matters under the Clean Air Act (42 
                U.S.C. 7401 et seq.);
                  (D) the Federal Land Policy and Management Act of 
                1976 (43 U.S.C. 1701 et seq.);
                  (E) the Migratory Bird Treaty Act (16 U.S.C. 703 et 
                seq.);
                  (F) the preparation of analyses under the National 
                Environmental Policy Act of 1969 (42 U.S.C. 4321 et 
                seq.);
                  (G) implementation of the requirements of section 
                306108 of title 54, United States Code (formerly known 
                as section 106 of the National Historic Preservation 
                Act);
                  (H) planning under section 14 of the National Forest 
                Management Act of 1976 (16 U.S.C. 472a);
                  (I) the Bald and Golden Eagle Protection Act (16 
                U.S.C. 668-668d); and
                  (J) section 100101(a), chapter 1003, and sections 
                100751(a), 100752, 100753 and 102101 of title 54 , 
                United States Code (previously known as the ``National 
                Park Service Organic Act'').
          (2) Duties.--Each employee assigned under paragraph (1) 
        shall--
                  (A) be responsible for addressing all issues relating 
                to the jurisdiction of the home office or agency of the 
                employee; and
                  (B) participate as part of the team of personnel 
                working on proposed energy projects, planning, 
                monitoring, inspection, enforcement, and environmental 
                analyses.
  (d) Additional Personnel.--The Secretary may assign such additional 
personnel for the Bureau of Land Management Renewable Energy 
Coordination Offices as are necessary to ensure the effective 
implementation of any programs administered by the offices in 
accordance with the multiple use mandate of the Federal Land Policy and 
Management Act of 1976 (43 U.S.C. 1701 et seq.).
  (e) Clarification of Existing Authority.--Under section 307 of the 
Federal Land Policy and Management Act of 1976 (43 U.S.C. 1737), the 
Bureau of Land Management may--
          (1) accept donations for the purposes of public lands 
        management; and
          (2) accept donations from renewable energy companies working 
        on public lands to help cover the costs of environmental 
        reviews.
  (f) Report to Congress.--
          (1) In general.--Not later than February 1 of the first 
        fiscal year beginning after the date of the enactment of this 
        Act, and each February 1 thereafter, the Secretary shall submit 
        to the Committee on Energy and Natural Resources of the Senate 
        and the Committee on Natural Resources of the House of 
        Representatives a report describing the progress made under the 
        program established under subsection (a) during the preceding 
        year.
          (2) Inclusions.--Each report under this subsection shall 
        include--
                  (A) projections for renewable energy production and 
                capacity installations; and
                  (B) a description of any problems relating to 
                leasing, permitting, siting, or production.

SEC. 7. INCREASING ECONOMIC CERTAINTY.

  (a) Considerations.--The Secretary is authorized to and shall 
consider acreage rental rates, capacity fees, and other recurring 
annual fees in total when evaluating existing rates paid for the use of 
Federal land by renewable energy projects.
  (b) Increases in Base Rental Rates.--Once a base rental rate is 
established upon the issuance of a right-of-way authorization, 
increases in the base rent shall be limited to the Implicit Price 
Deflator-Gross Domestic Product (IPD-GDP) index for the entire term of 
the right-of-way authorization.
  (c) Reductions in Base Rental Rates.--The Secretary is authorized to 
reduce acreage rental rates and capacity fees, or both, for existing 
and new wind and solar authorizations if the Secretary determines--
          (1) that the existing rates--
                  (A) exceed fair market value;
                  (B) impose economic hardships;
                  (C) limit commercial interest in a competitive lease 
                sale or right-of-way grant; or
                  (D) are not competitively priced compared to other 
                available land; or
          (2) that a reduced rental rate or capacity fee is necessary 
        to promote the greatest use of wind and solar energy resources, 
        especially those resources inside priority areas. Rental rates 
        and capacity fees for projects that are within the boundaries 
        of a Designated Leasing Area but not formally recognized as 
        being in such an area shall be equivalent to rents and fees for 
        new leases inside of a Designated Leasing Area.

SEC. 8. LIMITED GRANDFATHERING.

  (a) Definition of Project.--In this section, the term ``project'' 
means a system described in section 2801.9(a)(4) of title 43, Code of 
Federal Regulations (as in effect on the date of enactment of this 
Act).
  (b) Requirement To Pay Rents and Fees.--Unless otherwise agreed to by 
the owner of a project, the owner of a project that applied for a 
right-of-way under section 501 of the Federal Land Policy and 
Management Act of 1976 (43 U.S.C. 1761) on or before December 19, 2016, 
shall be obligated to pay with respect to the right-of-way all rents 
and fees in effect before the effective date of the rule of the Bureau 
of Land Management entitled ``Competitive Processes, Terms, and 
Conditions for Leasing Public Lands for Solar and Wind Energy 
Development and Technical Changes and Corrections'' (81 Fed. Reg. 92122 
(December 19, 2016)).

SEC. 9. RENEWABLE ENERGY GOAL.

  The Secretary and the Secretary of Agriculture shall seek to issue 
permits that, in total, authorize production of not less than 25 
gigawatts of electricity from wind, solar, and geothermal energy 
projects by not later than 2025, through management of public lands and 
administration of Federal laws.

SEC. 10. DISPOSITION OF REVENUES.

  (a) Disposition of Revenues.--Beginning on January 1, 2020, of the 
amounts collected as bonus bids, rentals, fees, or other payments under 
a right-of-way, permit, lease, or other authorization (other than under 
section 504(g) of the Federal Land Policy and Management Act of 1976 
(43 U.S.C. 1764(g))) for the development of wind or solar energy on 
covered land or National Forest System land, the following shall be 
made available without further appropriation or fiscal year limitation 
as follows:
          (1) Twenty-five percent shall be paid by the Secretary of the 
        Treasury to the State within the boundaries of which the 
        revenue is derived.
          (2) Twenty-five percent shall be paid by the Secretary of the 
        Treasury to the one or more counties within the boundaries of 
        which the revenue is derived, to be allocated among the 
        counties based on the percentage of land from which the revenue 
        is derived.
          (3) Fifteen percent shall be deposited in the Treasury and be 
        made available to the Secretary to carry out the program 
        established under this Act, including the transfer of the funds 
        by the Bureau of Land Management to other Federal agencies and 
        State agencies to facilitate the processing of renewable energy 
        permits on Federal land, with priority given to using the 
        amounts, to the maximum extent practicable without detrimental 
        impacts to emerging markets, to expediting the issuance of 
        permits required for the development of renewable energy 
        projects in the States from which the revenues are derived.
          (4) Twenty-five percent shall be deposited in the Renewable 
        Energy Resource Conservation Fund established by subsection 
        (c).
          (5) The remainder shall be deposited into the general fund of 
        the Treasury for purposes of reducing the annual Federal budget 
        deficit.
  (b) Payments to States and Counties.--
          (1) In general.--Amounts paid to States and counties under 
        subsection (a) shall be used consistent with section 35 of the 
        Mineral Leasing Act (30 U.S.C. 191).
          (2) Payments in lieu of taxes.--A payment to a county under 
        paragraph (1) shall be in addition to a payment in lieu of 
        taxes received by the county under chapter 69 of title 31, 
        United States Code.
  (c) Renewable Energy Resource Conservation Fund.--
          (1) In general.--There is established in the Treasury a fund 
        to be known as the Renewable Energy Resource Conservation Fund, 
        which shall be administered by the Secretary, in consultation 
        with the Secretary of Agriculture.
          (2) Use of funds.--The Secretary may make amounts in the Fund 
        available to Federal, State, local, and Tribal agencies to be 
        distributed in regions in which renewable energy projects are 
        located on Federal land, for the purposes of--
                  (A) restoring and protecting--
                          (i) fish and wildlife habitat for affected 
                        species;
                          (ii) fish and wildlife corridors for affected 
                        species; and
                          (iii) wetlands, streams, rivers, and other 
                        natural water bodies in areas affected by wind, 
                        geothermal, or solar energy development; and
                  (B) preserving and improving recreational access to 
                Federal land and water in an affected region through an 
                easement, right-of-way, or other instrument from 
                willing landowners for the purpose of enhancing public 
                access to existing Federal land and water that is 
                inaccessible or restricted.
          (3) Restriction on use of funds.--No funds made available 
        under this subsection may be used for the purchase of real 
        property unless in fulfillment of paragraph (2)(B).
          (4) Partnerships.--The Secretary may enter into cooperative 
        agreements with State and Tribal agencies, nonprofit 
        organizations, and other appropriate entities to carry out the 
        activities described in subparagraphs (A) and (B) of paragraph 
        (2).
          (5) Investment of fund.--
                  (A) In general.--Any amounts deposited in the Fund 
                shall earn interest in an amount determined by the 
                Secretary of the Treasury on the basis of the current 
                average market yield on outstanding marketable 
                obligations of the United States of comparable 
                maturities.
                  (B) Use.--Any interest earned under subparagraph (A) 
                may be expended in accordance with this subsection.
          (6) Report to congress.--At the end of each fiscal year, the 
        Secretary shall report to the Committee on Natural Resources of 
        the House of Representatives and the Committee on Energy and 
        Natural Resources of the Senate--
                  (A) the amount collected as described in subsection 
                (a), by source, during that fiscal year;
                  (B) the amount and purpose of payments during that 
                fiscal year to each Federal, State, local, and Tribal 
                agency under paragraph (2); and
                  (C) the amount remaining in the Fund at the end of 
                the fiscal year.
          (7) Intent of congress.--It is the intent of Congress that 
        the revenues deposited and used in the Fund shall supplement 
        (and not supplant) annual appropriations for activities 
        described in subparagraphs (A) and (B) of paragraph (2).

SEC. 11. PROMOTING AND ENHANCING DEVELOPMENT OF GEOTHERMAL ENERGY.

  (a) In General.--Section 234(a) of the Energy Policy Act of 2005 (42 
U.S.C. 15873(a)) is amended by striking ``in the first 5 fiscal years 
beginning after the date of enactment of this Act'' and inserting 
``through fiscal year 2022''.
  (b) Authorization.--Section 234(b) of the Energy Policy Act of 2005 
(42 U.S.C. 15873(b)) is amended--
          (1) by striking ``Amounts'' and inserting the following:
          ``(1) In general.--Amounts''; and
          (2) by adding at the end the following:
          ``(2) Authorization.--Effective for fiscal year 2019 and each 
        fiscal year thereafter, amounts deposited under subsection (a) 
        shall be available to the Secretary of the Interior for 
        expenditure, without further appropriation or fiscal year 
        limitation, to implement the Geothermal Steam Act of 1970 (30 
        U.S.C. 1001 et seq.) and this Act.''.

SEC. 12. FACILITATION OF COPRODUCTION OF GEOTHERMAL ENERGY ON OIL AND 
                    GAS LEASES.

  Section 4(b) of the Geothermal Steam Act of 1970 (30 U.S.C. 1003(b)) 
is amended by adding at the end the following:
          ``(4) Land subject to oil and gas lease.--Land under an oil 
        and gas lease issued pursuant to the Mineral Leasing Act (30 
        U.S.C. 181 et seq.) or the Mineral Leasing Act for Acquired 
        Lands (30 U.S.C. 351 et seq.) that is subject to an approved 
        application for permit to drill and from which oil and gas 
        production is occurring may be available for noncompetitive 
        leasing under subsection (c) by the holder of the oil and gas 
        lease--
                  ``(A) on a determination that geothermal energy will 
                be produced from a well producing or capable of 
                producing oil and gas; and
                  ``(B) in order to provide for the coproduction of 
                geothermal energy with oil and gas.''.

SEC. 13. NONCOMPETITIVE LEASING OF ADJOINING AREAS FOR DEVELOPMENT OF 
                    GEOTHERMAL RESOURCES.

  Section 4(b) of the Geothermal Steam Act of 1970 (30 U.S.C. 1003(b)) 
is further amended by adding at the end the following:
          ``(5) Adjoining land.--
                  ``(A) Definitions.--In this paragraph:
                          ``(i) Fair market value per acre.--The term 
                        `fair market value per acre' means a dollar 
                        amount per acre that--
                                  ``(I) except as provided in this 
                                clause, shall be equal to the market 
                                value per acre (taking into account the 
                                determination under subparagraph 
                                (B)(iii) regarding a valid discovery on 
                                the adjoining land) as determined by 
                                the Secretary under regulations issued 
                                under this paragraph;
                                  ``(II) shall be determined by the 
                                Secretary with respect to a lease under 
                                this paragraph, by not later than the 
                                end of the 180-day period beginning on 
                                the date the Secretary receives an 
                                application for the lease; and
                                  ``(III) shall be not less than the 
                                greater of--
                                          ``(aa) 4 times the median 
                                        amount paid per acre for all 
                                        land leased under this Act 
                                        during the preceding year; or
                                          ``(bb) $50.
                          ``(ii) Industry standards.--The term 
                        `industry standards' means the standards by 
                        which a qualified geothermal professional 
                        assesses whether downhole or flowing 
                        temperature measurements with indications of 
                        permeability are sufficient to produce energy 
                        from geothermal resources, as determined 
                        through flow or injection testing or 
                        measurement of lost circulation while drilling.
                          ``(iii) Qualified federal land.--The term 
                        `qualified Federal land' means land that is 
                        otherwise available for leasing under this Act.
                          ``(iv) Qualified geothermal professional.--
                        The term `qualified geothermal professional' 
                        means an individual who is an engineer or 
                        geoscientist in good professional standing with 
                        at least 5 years of experience in geothermal 
                        exploration, development, or project 
                        assessment.
                          ``(v) Qualified lessee.--The term `qualified 
                        lessee' means a person who may hold a 
                        geothermal lease under this Act (including 
                        applicable regulations).
                          ``(vi) Valid discovery.--The term `valid 
                        discovery' means a discovery of a geothermal 
                        resource by a new or existing slim hole or 
                        production well, that exhibits downhole or 
                        flowing temperature measurements with 
                        indications of permeability that are sufficient 
                        to meet industry standards.
                  ``(B) Authority.--An area of qualified Federal land 
                that adjoins other land for which a qualified lessee 
                holds a legal right to develop geothermal resources may 
                be available for a noncompetitive lease under this 
                section to the qualified lessee at the fair market 
                value per acre, if--
                          ``(i) the area of qualified Federal land--
                                  ``(I) consists of not less than 1 
                                acre and not more than 640 acres; and
                                  ``(II) is not already leased under 
                                this Act or nominated to be leased 
                                under subsection (a);
                          ``(ii) the qualified lessee has not 
                        previously received a noncompetitive lease 
                        under this paragraph in connection with the 
                        valid discovery for which data has been 
                        submitted under clause (iii)(I); and
                          ``(iii) sufficient geological and other 
                        technical data prepared by a qualified 
                        geothermal professional has been submitted by 
                        the qualified lessee to the applicable Federal 
                        land management agency that would lead 
                        individuals who are experienced in the subject 
                        matter to believe that--
                                  ``(I) there is a valid discovery of 
                                geothermal resources on the land for 
                                which the qualified lessee holds the 
                                legal right to develop geothermal 
                                resources; and
                                  ``(II) that geothermal feature 
                                extends into the adjoining areas.
                  ``(C) Determination of fair market value.--
                          ``(i) In general.--The Secretary shall--
                                  ``(I) publish a notice of any request 
                                to lease land under this paragraph;
                                  ``(II) determine fair market value 
                                for purposes of this paragraph in 
                                accordance with procedures for making 
                                those determinations that are 
                                established by regulations issued by 
                                the Secretary;
                                  ``(III) provide to a qualified lessee 
                                and publish, with an opportunity for 
                                public comment for a period of 30 days, 
                                any proposed determination under this 
                                subparagraph of the fair market value 
                                of an area that the qualified lessee 
                                seeks to lease under this paragraph; 
                                and
                                  ``(IV) provide to the qualified 
                                lessee and any adversely affected party 
                                the opportunity to appeal the final 
                                determination of fair market value in 
                                an administrative proceeding before the 
                                applicable Federal land management 
                                agency, in accordance with applicable 
                                law (including regulations).
                          ``(ii) Limitation on nomination.--After 
                        publication of a notice of request to lease 
                        land under this paragraph, the Secretary may 
                        not accept under subsection (a) any nomination 
                        of the land for leasing unless the request has 
                        been denied or withdrawn.
                          ``(iii) Annual rental.--For purposes of 
                        section 5(a)(3), a lease awarded under this 
                        paragraph shall be considered a lease awarded 
                        in a competitive lease sale.
                  ``(D) Regulations.--Not later than 270 days after the 
                date of the enactment of this paragraph, the Secretary 
                shall issue regulations to carry out this paragraph.''.

SEC. 14. SAVINGS CLAUSE.

  Notwithstanding any other provision of this Act, the Secretary shall 
continue to manage public lands under the principles of multiple use 
and sustained yield in accordance with title I of the Federal Land 
Policy and Management Act of 1976 (43 U.S.C. 1701 et seq.), including 
due consideration of mineral and nonrenewable energy-related projects 
and other nonrenewable energy uses, for the purposes of land use 
planning, permit processing, and conducting environmental reviews.

                          Purpose of the Bill

    The purpose of H.R. 3794 is to promote the development of 
renewable energy on public lands.

                  Background and Need for Legislation

    The urgent need to address climate change demands a rapid 
transition away from fossil fuels and toward a clean-energy 
economy. Renewable energy resources on public lands and waters 
can and must play a leading role in driving this energy 
transition.
    Thanks to decades of innovation, steeply declining costs, 
and smart policies at both the federal and state levels, the 
amount of electricity generated by wind and solar in the United 
States has increased tremendously. The United States currently 
generates approximately 18 percent of its electricity from 
renewable energy resources--two times more than a decade 
ago.\1\ When President Obama took office, there were no solar 
plants on public lands. By the time he left, thirty-six 
projects had been approved. Including new wind and geothermal, 
the Obama administration approved enough new renewable energy 
to power more than five million homes. But despite the strong 
growth of renewable energy nationally and millions of acres 
still open for development, construction of wind, solar, and 
geothermal projects on public lands has stalled in recent 
years. At the time of H.R. 3794's consideration by the 
Committee, the Trump administration had approved only two new 
solar projects, one wind project, and zero new geothermal 
plants on public lands. H.R. 3794 makes bipartisan reforms to 
promote renewable energy projects on public lands that benefit 
local communities while preserving access to recreation 
opportunities and protecting wildlife habitat.
---------------------------------------------------------------------------
    \1\2019 Sustainable Energy in American Factbook. Business Council 
for Sustainable Energy and Bloomberg New Energy Finance. https://
www.bcse.org/factbook/#.
---------------------------------------------------------------------------
    H.R. 3794 addresses concerns about the renewable energy 
permitting process by codifying a ``smart from the start'' 
approach to renewable energy development. Until 2017, the 
process for approving wind and solar projects on public lands 
generally involved the Bureau of Land Management (BLM) 
reviewing right-of-way applications from developers on a first-
come, first-serve basis. This system didn't do enough to ensure 
a fair return to taxpayers and proved inefficient for 
construction of large-scale infrastructure projects like wind 
and solar projects, while allowing speculators to delay review 
of more promising projects. To address these problems, the 
Obama administration implemented an approach it dubbed ``smart 
from the start'' that encouraged development in pre-screened 
areas that have fewer conflicts with other activities on public 
lands. The value of that approach was demonstrated in 2014, 
when BLM held its first successful auction for a pre-screened 
region, the Dry Lake Solar Energy Zone in Clark County, Nevada. 
The auction brought in $5.8 million in winning bids to the U.S. 
Treasury, and three projects inside the zone were reviewed and 
approved in less than ten months, less than half the time of a 
typical project.\2\
---------------------------------------------------------------------------
    \2\``Interior Department Approves First Solar Energy Zone 
Projects.'' U.S. Department of the Interior, 1 June 2015. https://
www.doi.gov/pressreleases/interior-department-approves-first-solar-
energy-zone-projects.
---------------------------------------------------------------------------
    Under this legislation, the Department of the Interior 
(DOI) will continue this ``smart from the start'' approach by 
designating and periodically updating priority areas for wind, 
solar, and geothermal energy on public lands. These priority 
areas minimize both environmental impacts and conflicts with 
other uses of public lands such as recreation, conservation, 
and preservation of wildlife habitat, while maximizing the 
economic potential for developers by, for example, being close 
to existing or planned transmission infrastructure. Projects 
proposed inside these priority areas will pay lower fees and 
receive expedited permitting thanks to advanced preliminary 
environmental review under the National Environmental Policy 
Act (NEPA). Developers will not be prohibited from proposing 
renewable energy projects outside of priority areas, but the 
legislation is designed to encourage focused development in the 
priority areas. By implementing this ``smart from the start'' 
approach, the Committee is confident that development of much-
needed renewable energy projects can successfully move forward 
while the many other values provided by public lands to the 
American people are protected.
    The legislation makes several other changes to improve 
permitting of projects on public lands, including requiring DOI 
to permanently establish a Renewable Energy Coordination Office 
that was first established by the Obama administration but 
eliminated in early 2017. This office will reduce conflicts 
between agencies within the Interior Department by providing a 
bird's-eye view over all renewable energy development on public 
lands, ensuring that permitting and interagency coordination is 
happening in a timely manner, and making sure that the 
Department is working toward the goal of permitting a total of 
25 GW of wind, solar, and geothermal on public lands by 2025. 
The bill also clarifies that DOI has the authority to accept 
voluntary payments from clean energy companies to fund 
environmental reviews, a common practice for the oil and gas 
industry that is not widely used for renewables. These payments 
are not to dictate a preferred outcome, but instead help 
alleviate DOI resource constraints, provide regulatory 
certainty, and allow for timely, comprehensive environmental 
reviews. These payments are not a substitute for regular 
appropriations from Congress, which has the ultimate 
responsibility to ensuring that the Department has the proper 
resources for all permitting activities.
    A concern heard by the Committee when developing this 
legislation was the continued high cost of development. In 
January 2017, BLM implemented the Wind and Solar Leasing Rule, 
which transitioned wind and solar development in part to a 
competitive bidding system and set up a new process for 
determining rents and capacity fees. The Committee supports the 
continued use of competitive lease sales, rental payments, and 
capacity payments to determine fair market value for American 
taxpayers, but acknowledges that the industry finds that high 
costs are making public lands less competitive with private 
lands.\3\ These concerns about cost are reflected in the dearth 
of new project proposals submitted to BLM; companies do not 
appear to be actively pursuing new projects on public lands. At 
the time of the Committee's markup of H.R. 3794 in November 
2019, BLM had yet to approve any renewable energy projects that 
had been proposed after 2016.
---------------------------------------------------------------------------
    \3\Testimony by Abigail Ross Hopper of the Solar Energy Industries 
Association. Subcommittee on Energy and Mineral Resources, July 25, 
2019. https://naturalresources.house.gov/imo/media/doc/
1.%20Testimony%20-%20Abigail%20Ross%20Hopper%20-
%20EMR%20Leg%20Hrg%2007.25 .19.pdf.
---------------------------------------------------------------------------
    The slowdown of renewable energy development on public 
lands is an unacceptable trend if we are to seriously address 
the climate crisis and transition our nation to a clean-energy 
economy. H.R. 3794 gives the Secretary of the Interior more 
discretion and flexibility to set fair, predictable rent and 
fee schedules for developers while still ensuring that the 
Department receives fair value for American taxpayers. Language 
is included in the legislation to level the playing field 
across industries and provide royalty relief options for 
renewable energy that already exist for oil, gas, and coal 
production on public lands. The bill also provides limited 
grandfathering to renewable energy projects impacted by 
unexpected rate increases under the Wind and Solar Leasing 
Rule. It was brought to the Committee's attention, for example, 
that one wind project's rental payments increased by more than 
300 percent as a result of the rule and another expects to see 
over $100 million in additional costs. Such significant cost 
increases were not factored into the original business plans 
and therefore not incorporated into contracts signed with 
utility companies. Limited grandfathering allows these projects 
to remain economically viable, ensuring that federal taxpayers 
and local communities will receive their promised benefits.
    Another disparity between fossil fuel and wind and solar 
development on public lands is the distribution of revenues. 
For oil, gas, coal, and other leasable minerals, states receive 
roughly half of all bonus bids, rents, and royalties, creating 
local support for, and even dependency on, such development for 
budgetary reasons alone. Wind and solar revenues, in contrast, 
flow exclusively to the federal government. By diverting some 
of these revenues to states and counties, H.R. 3794 promises to 
create additional local support for renewable energy projects 
while also providing a source of funds that could allow some 
states and localities to reduce their dependence on fossil fuel 
derived income, potentially further accelerating the transition 
to a clean energy economy.
    Just like any other use of public lands, renewable energy 
projects must be held to high standards for mitigating 
environmental impacts and minimizing conflicts with other uses 
of public lands. The existing NEPA and land-use planning 
processes are designed to address this on a project-by-project 
basis, but H.R. 3794 aims for a broader positive impact by 
directing 25 percent of wind and solar energy revenues to a 
newly established Renewable Energy Resource Conservation Fund, 
which will make funds available to federal, state, and tribal 
agencies for projects that restore and protect wildlife habitat 
and improve recreation access on public lands.
    Focusing on the energy of the past and ignoring the impacts 
of climate change is not a formula for a healthy or sustainable 
future. Instead, it will simply marginalize us internationally 
and handicap us economically. H.R. 3794 is designed to strike 
the appropriate balance between responsible renewable energy 
development and conservation while also benefitting local 
communities and federal taxpayers.

                            Committee Action

    H.R. 3794 was introduced on July 17, 2019, by 
Representative Paul Gosar (R-AZ). The bill was referred to the 
Committee on Natural Resources, and in addition to the 
Committee on Agriculture. Within the Natural Resources 
Committee, the bill was referred to the Subcommittee on Energy 
and Mineral Resources. On July 25, 2019, the Subcommittee held 
a hearing on the bill. On November 20, 2019, the Natural 
Resources Committee met to consider the bill. The Subcommittee 
was discharged by unanimous consent. Representative Mike Levin 
(D-CA) offered an amendment designated Levin #033. The 
amendment was agreed to by voice vote. No additional amendments 
were offered, and the bill, as amended, was adopted and ordered 
favorably reported to the House of Representatives by voice 
vote.
    On July 1, 2020, the House of Representatives passed H.R. 
2, the Moving Forward Act, which included a version of the text 
of H.R. 3794.\4\
---------------------------------------------------------------------------
    \4\H.R. 2, 116th Cong. (as passed by and engrossed in the House, 
July 1, 2020).
---------------------------------------------------------------------------

                                Hearings

    For the purposes of section 103(i) of H. Res. 6 of the 
116th Congress--the following hearing was used to develop or 
consider H.R. 3794: legislative hearing by the Subcommittee on 
Energy and Mineral Resources held on July 25, 2019.

                      Section-by-Section Analysis


Section 1. Short title

    This section provides the short title of the bill, the 
``Public Land Renewable Energy Development Act of 2019''.

Section 2. Table of contents

    This section provides the table of contents of the 
legislation.

Section 3. Definitions

    This section defines key terms in the bill. Definitions in 
this section make clear that renewable energy development 
continues to be prohibited inside national parks, wilderness 
areas, and other federally protected public lands where energy 
development is prohibited under existing federal law.

Section 4. Land use planning; supplements to programmatic environmental 
        impact statements

    This section directs the Secretary of the Interior, in 
consultation with the Secretary of Energy, to designate, 
periodically review, and encourage development inside pre-
screened priority areas for wind, solar, and geothermal energy. 
Projects inside designated leasing areas will receive faster 
permit approvals, pay lower fees, and received highest priority 
for review by the Bureau of Land Management. Land 
classifications will be reviewed at least once every five 
years, with modifications made if necessary. Solar priority 
areas established in 2012 shall be reviewed within three years 
of enactment. This section also directs DOI to coordinate with 
states, tribes, local governments, transmission owners and 
operators, developers, and other appropriate entities when 
establishing priority areas. This section also clarifies that, 
in accordance with current law, renewable energy permitting 
activities can proceed under the current wind and solar 
programmatic environmental impact statements (PEIS) with any 
required additional environmental review while a supplement to 
a PEIS is being prepared.

Section 5. Environmental review on covered land

    This section states that a renewable energy project will 
not need to undergo further environmental review if the 
Secretary determines that it has been sufficiently analyzed by 
a programmatic environmental impact statement. The Secretary 
shall publish any such determinations on a publicly available 
website as soon as possible. When additional review is 
required, the Secretary shall rely on analysis from existing 
programmatic environmental impact statements as much as 
possible.

Section 6. Program to improve renewable energy project permit 
        coordination

    This section outlines steps that the Secretary of the 
Interior shall take to improve renewable energy permitting 
programs. The Secretary shall establish a national Renewable 
Energy Coordination Office and affiliated state and field 
offices across the country where such expertise would be most 
valuable. The Secretary is directed to sign a Memorandum of 
Understanding (MOU) with the Secretary of Defense and the 
Secretary of Agriculture for the purposes of improving 
renewable energy permit reviews; governors and tribal leaders 
may also be invited to join this MOU. All federal agencies that 
sign the MOU must identify staff with expertise on regulatory 
issues relevant to renewable energy project reviews. The 
section also clarifies that BLM is authorized to accept 
donations from renewable energy developers for environmental 
reviews, authority that is routinely used by the oil and gas 
industry but not by the renewable energy industry. The 
Secretary of the Interior shall submit an annual report to 
Congress that includes information on projects operating on 
public lands and summaries of any problems that arise 
throughout the leasing, permitting, and production processes.

Section 7. Increasing economic certainty

    This section gives the Secretary authority to reduce wind 
and solar rental rates and capacity fees if there is a 
demonstrated economic need. This authority is modeled after 
existing authorities already provided in statute for the coal, 
oil, and gas industries. The Secretary shall limit increases in 
base rental rates to the Implicit Price Deflator-Gross Domestic 
Product for the entire life of a right-of-way authorization. 
This section also allows the Secretary to reduce fees paid by 
solar projects affected by the 2012 Western Solar Plan. It is 
the Committee's understanding that a number of existing solar 
projects found themselves inside Designated Leasing Areas under 
the Western Solar Plan but are paying fees as if they were 
located outside of such priority areas.

Section 8. Limited grandfathering

    This section provides limited grandfathering to certain 
wind and solar energy projects that had already applied for a 
right-of-way before implementation of the Wind and Solar 
Leasing Rule. This section is intended to address unexpected 
changes to the fee structure for projects that had already 
begun the permit application process before implementation of 
the Wind and Solar Leasing Rule. This section is not intended 
to limit BLM's ability to periodically review and increase 
rental rates and fees over time. Project owners can choose to 
opt-in or opt-out of this limited grandfathering.

Section 9. Renewable energy goal

    This section establishes a goal of permitting 25 gigawatts 
of renewable energy on public lands by 2025. This goal is 
cumulative and shall include all previously permitted projects 
on lands managed by the Department of the Interior and the 
Department of Agriculture at the date of enactment. The 
Secretary may not count any permitted offshore wind projects 
toward this goal.

Section 10. Disposition of revenues

    This section establishes the distribution of revenues from 
wind and solar energy projects: 25 percent to states, 25 
percent to counties, 25 percent to a new Renewable Energy 
Resource Conservation Fund, 15 percent to BLM to assist with 
renewable energy permitting, and 10 percent to the Treasury for 
deficit reduction. Money in the new fund will be distributed by 
the Secretary of the Interior to federal, state, local, and 
tribal agencies for projects protecting and restoring fish and 
wildlife habitat, or to ensure and improve access for hunting, 
fishing, and other outdoor recreational activities.

Section 11. Promoting and enhancing development of geothermal energy

    This section reauthorizes the Geothermal Steam Act, the 
statute that governs geothermal energy production on public 
lands.

Section 12. Facilitation of coproduction of geothermal energy on oil 
        and gas leases

    This section allows holders of oil and gas leases to obtain 
noncompetitive geothermal leases under the Geothermal Steam Act 
to allow for the co-production of geothermal energy from an oil 
and gas well.

Section 13. Noncompetitive leasing of adjoining areas for development 
        of geothermal resources

    This section allows the Secretary of the Interior to award 
non-competitive leases for geothermal energy production on 
adjoining areas of an existing lease under specific conditions. 
Non-competitive leases awarded in this manner will be required 
to pay a fee determined by the Secretary of the Interior based 
on fair market value with a determination subject to public 
comment and appeal.

Section 14. Savings clause

    This section states that nothing in the bill shall change 
the Secretary's responsibility to manage public lands under the 
principles of multiple use and sustained yield in accordance 
with the Federal Land Policy and Management Act (FLPMA).

            Committee Oversight Findings and Recommendations

    Regarding clause 2(b)(1) of rule X and clause 3(c)(1) of 
rule XIII of the Rules of the House of Representatives, the 
Committee on Natural Resources' oversight findings and 
recommendations are reflected in the body of this report.

      Compliance With House Rule XIII and Congressional Budget Act

    1. Cost of Legislation and the Congressional Budget Act. 
With respect to the requirements of clause 3(c)(2) and (3) of 
rule XIII of the Rules of the House of Representatives and 
sections 308(a) and 402 of the Congressional Budget Act of 
1974, the Committee has received the following estimate for the 
bill from the Director of the Congressional Budget Office:

                                     U.S. Congress,
                               Congressional Budget Office,
                                     Washington, DC, March 4, 2020.
Hon. Raul M. Grijalva,
Chairman, Committee on Natural Resources,
House of Representatives, Washington, DC.
    Dear Mr. Chairman: The Congressional Budget Office has 
prepared the enclosed cost estimate for H.R. 3794, the Public 
Land Renewable Energy Development Act of 2019.
    If you wish further details on this estimate, we will be 
pleased to provide them. The CBO staff contact is Janani 
Shankaran.
            Sincerely,
                                         Phillip L. Swagel,
                                                          Director.
    Enclosure.

    [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]
    

    The bill would
           Authorize the Bureau of Land Management 
        (BLM) to spend income from renewable-energy projects 
        located on federal land without further appropriation
           Reduce the rates charged for certain wind 
        and solar energy projects located on federal land
           Direct BLM to establish priority areas on 
        federal land for renewable-energy projects
    Estimated budgetary effects would primarily stem from
           Spending of income from renewable-energy 
        projects
           Forgone government income resulting from 
        reduced rates
    Bill summary: H.R. 3794 would authorize the Bureau of Land 
Management (BLM) to spend income received from renewable-energy 
projects located on federal land without further appropriation. 
The bill also would reduce the rates charged for certain wind 
and solar energy projects located on federal land, and would 
direct the BLM to establish priority areas on federal land for 
renewable energy projects.
    Estimated Federal cost: The estimated budgetary effect of 
H.R. 3794 is shown in Table 1. The costs of the legislation 
fall within budget functions 300 (natural resources and 
environment) and 800 (general government).

                               TABLE 1.--ESTIMATED BUDGETARY EFFECTS OF H.R. 3794
----------------------------------------------------------------------------------------------------------------
                                                                    By fiscal year, millions of dollars--
                                                            ----------------------------------------------------
                                                              2020   2021   2022   2023   2024   2025  2020-2025
----------------------------------------------------------------------------------------------------------------
                                          Increases in Direct Spending
 
Estimated Budget Authority.................................     27     30     31     27     28     29       172
Estimated Outlays..........................................     12     25     29     30     32     29       157
 
                                 Increases in Spending Subject to Appropriation
 
Estimated Authorization....................................      *      1      1      1      1      1         5
Estimated Outlays..........................................      *      1      1      1      1      1         5
----------------------------------------------------------------------------------------------------------------
*= between zero and $500,000.

    Basis of estimate: For this estimate, CBO assumes that the 
legislation will be enacted in 2020 and that the necessary 
amounts will be provided in each year. Estimated outlays are 
based on historical spending patterns for similar activities.
    Background: Under current law, businesses that seek to 
develop wind and solar energy projects on federal land apply to 
BLM for a right-of-way grant. After obtaining a grant, 
businesses pay the federal government annual rent based on land 
values and a megawatt capacity fee. (If multiple businesses are 
interested in the same parcel, BLM may issue a right-of-way 
grant to the highest bidder.) Those payments, which totaled $28 
million in 2019, are classified in the budget as offsetting 
receipts, which are recorded as reductions in direct spending. 
CBO projects that under current law, the government will 
collect $341 million in receipts from wind and solar energy 
projects over the 2020-2030 period. Spending of those receipts 
is subject to appropriation.
    BLM also administers geothermal leasing on federal land. 
For all executed leases, lessees pay the federal government a 
bonus bid (the amount that a business is willing to pay for the 
right to extract geothermal resources), annual rent to retain 
the lease, and royalties based on the value of any geothermal 
resources produced. Those payments, which totaled $16 million 
in 2019, are recorded in the budget as offsetting receipts. CBO 
projects that the government will collect gross receipts of 
$176 million from geothermal leasing over the 2020-2030 period. 
Under current law, states and counties receive 75 percent of 
those amounts; thus, net federal receipts will total $44 
million over that same period.
    Direct spending: CBO estimates that enacting H.R. 3794 
would increase direct spending by $307 million over the 2020-
2030 period (see Table 2).

                                                 TABLE 2.--INCREASES IN DIRECT SPENDING UNDER H.R. 3794
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                     By fiscal year, millions of dollars--
                                                      --------------------------------------------------------------------------------------------------
                                                        2020   2021   2022   2023   2024   2025   2026   2027   2028   2029   2030  2020-2025  2020-2030
--------------------------------------------------------------------------------------------------------------------------------------------------------
Rate Reductions for Certain Wind and Solar Projects:
    Estimated Budget Authority.......................      2      6      6      6      6      6      6      6      6      6      6        32         62
    Estimated Outlays................................      2      6      6      6      6      6      6      6      6      6      6        32         62
Spending of Wind and Solar Proceeds:
    Estimated Budget Authority.......................     17     20     21     21     22     23     23     24     24     25     25       124        245
    Estimated Outlays................................     10     16     19     20     22     22     23     23     24     25     25       109        229
Spending of Geothermal Proceeds:
    Estimated Budget Authority.......................      8      4      4      0      0      0      0      0      0      0      0        16         16
    Estimated Outlays................................      *      3      4      4      4      1      0      0      0      0      0        16         16
    Total Changes:
        Estimated Budget Authority...................     27     30     31     27     28     29     29     30     30     31     31       172        323
        Estimated Outlays............................     12     25     29     30     32     29     29     29     30     31     31       157        307
--------------------------------------------------------------------------------------------------------------------------------------------------------
* = between zero and $500,000.

    Rate reductions for certain wind and solar projects: In 
December 2016, BLM issued a rule that increased rents and 
megawatt capacity fees for wind and solar energy projects on 
federal land. Operators that submitted right-of-way 
applications or already had projects before BLM issued the rule 
began to pay new rates in 2018. Section 8 would allow those 
operators to pay the rates in effect before the rule. Using 
information from BLM, CBO estimates that enacting the section 
would reduce offsetting receipts by $6 million annually and by 
$62 million over the 2020-2030 period.
    Spending of wind and solar proceeds: Effective January 1, 
2020, section 10 would make 90 percent of bonus bids, rents, 
and capacity fees from wind and solar energy projects available 
to spend without further appropriation. CBO estimates that 
under the bill, the government would collect, on average, $25 
million annually in receipts over the 2020-2030 period. Fifty 
percent of receipts would be paid to states and counties where 
those projects are located; 25 percent would be deposited into 
a conservation fund for restoration activities; and 15 percent 
would be available for processing permits. CBO assumes that 
payments to states and counties would be made in the same year 
that the receipts are collected.
    H.R. 3794 would authorize the Department of the Treasury to 
pay interest on any balances in the conservation fund that are 
not needed for current expenditures; those amounts also would 
be available to spend without further appropriation. CBO 
estimates that enacting section 10 would increase direct 
spending by $229 million over the 2020-2030 period; about $2 
million of that amount would stem from interest credited to the 
conservation fund.
    Spending of geothermal proceeds: Section 11 would authorize 
BLM to spend, without further appropriation, 25 percent of 
gross receipts collected from geothermal leasing over the 2019-
2022 period. Those amounts would be available for administering 
the program. CBO estimates that enacting the section would 
increase direct spending by $16 million over the 2020-2030 
period.
    Other provisions: Section 12 would allow an operator with a 
federal oil and gas lease to noncompetitively acquire the 
rights to coproduce geothermal resources under that lease. 
Section 13 of the bill would permit an operator with a federal 
geothermal lease to noncompetitively lease land adjoining that 
lease. CBO expects that allowing businesses to acquire such 
rights noncompetitively would reduce bonus bids as some 
businesses would now acquire leases without bidding for them. 
However, the bill also could increase royalties from geothermal 
leasing if businesses obtain noncompetitive leases on the land 
they would not otherwise bid on. Using information from BLM, 
CBO expects that enacting this provision would affect few 
leases and that the net effect on direct spending would be 
negligible.
    Spending subject to appropriation: Section 4 would direct 
BLM to establish priority areas on federal land for solar, 
wind, and geothermal energy projects. Based on the costs of 
similar tasks, CBO estimates that implementing the provision 
would cost less than $500,000 in 2020 and about $1 million 
annually over the 2021-2025 period. That amount reflects six 
additional employees at an average annual cost of $150,000 
each.
    Pay-As-You-Go considerations: The Statutory Pay-As-You-Go 
Act of 2010 establishes budget-reporting and enforcement 
procedures for legislation affecting direct spending or 
revenues. The net changes in outlays that are subject to those 
pay-as-you-go procedures are shown in Table 3.

   TABLE 3.--CBO'S ESTIMATE OF THE STATUTORY PAY-AS-YOU-GO EFFECTS OF H.R. 3794, THE PUBLIC LAND RENEWABLE ENERGY DEVELOPMENT ACT OF 2019, AS ORDERED
                                        REPORTED BY THE HOUSE COMMITTEE ON NATURAL RESOURCES ON NOVEMBER 20, 2019
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                     By fiscal year, millions of dollars--
                                                      --------------------------------------------------------------------------------------------------
                                                        2020   2021   2022   2023   2024   2025   2026   2027   2028   2029   2030  2020-2025  2020-2030
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                               Net Increase in the Deficit
 
Pay-As-You-Go Effect.................................     12     25     29     30     32     29     29     29     30     31     31       157        307
--------------------------------------------------------------------------------------------------------------------------------------------------------

    Increase in long-term deficits: CBO estimates that enacting 
H.R. 3794 would not increase on-budget deficits by more than $5 
billion in any of the four consecutive 10-year periods 
beginning in 2031.
    Mandates: None.
    Estimate prepared by: Federal Costs: Janani Shankaran; 
Mandates: Lilia Ledezma.
    Estimate reviewed by: Kim P. Cawley, Chief, Natural and 
Physical Resources Cost Estimates Unit; H. Samuel Papenfuss, 
Deputy Director of Budget Analysis.
    2. General Performance Goals and Objectives. As required by 
clause 3(c)(4) of rule XIII, the general performance goals and 
objectives of this bill are to promote the development of 
renewable energy on public lands.

                           Earmark Statement

    This bill does not contain any Congressional earmarks, 
limited tax benefits, or limited tariff benefits as defined 
under clause 9(e), 9(f), and 9(g) of rule XXI of the Rules of 
the House of Representatives.

                 Unfunded Mandates Reform Act Statement

    This bill contains no unfunded mandates.

                           Existing Programs

    This bill does not establish or reauthorize a program of 
the federal government known to be duplicative of another 
program. Such program was not included in any report from the 
Government Accountability Office to Congress pursuant to 
section 21 of Public Law 111-139. The Renewable Energy Resource 
Conservation Fund established by this bill at section 10(c) is 
related and complementary to, but not duplicative of, the 
following programs identified in the most recent Catalog of 
Federal Domestic Assistance published pursuant to 31 U.S.C. 
Sec.  6104: Watershed Restoration and Enhancement Agreement 
Authority (CFDA No. 10.693), Plant Conservation and Restoration 
Management (CFDA No. 15.245), Fish and Wildlife Coordination 
Act (CFDA No. 15.517), Recreation Resources Management (CFDA 
No. 15.524), Sport Fish Restoration (CFDA No. 15.605), Wildlife 
Restoration and Basic Hunter Education (CFDA No. 15.611), 
Coastal Wetlands Planning, Protection and Restoration (CFDA No. 
15.614), and North American Wetlands Conservation Fund (CFDA 
No. 15.623).

                  Applicability to Legislative Branch

    The Committee finds that the legislation does not relate to 
the terms and conditions of employment or access to public 
services or accommodations within the meaning of section 
102(b)(3) of the Congressional Accountability Act.

               Preemption of State, Local, or Tribal Law

    Any preemptive effect of this bill over state, local, or 
tribal law is intended to be consistent with the bill's 
purposes and text and the Supremacy Clause of Article VI of the 
U.S. Constitution.

         Changes in Existing Law Made by the Bill, as Reported

  In compliance with clause 3(e) of rule XIII of the Rules of 
the House of Representatives, changes in existing law made by 
the bill, as reported, are shown as follows (existing law 
proposed to be omitted is enclosed in black brackets, new 
matter is printed in italics, and existing law in which no 
change is proposed is shown in roman):

                       ENERGY POLICY ACT OF 2005




           *       *       *       *       *       *       *
TITLE II--RENEWABLE ENERGY

           *       *       *       *       *       *       *


Subtitle B--Geothermal Energy

           *       *       *       *       *       *       *


SEC. 234. DEPOSIT AND USE OF GEOTHERMAL LEASE REVENUES FOR 5 FISCAL 
                    YEARS.

  (a) Deposit of Geothermal Resources Leases.--Notwithstanding 
any other provision of law, amounts received by the United 
States [in the first 5 fiscal years beginning after the date of 
enactment of this Act] through fiscal year 2022 as rentals, 
royalties, and other payments required under leases under the 
Geothermal Steam Act of 1970, excluding funds required to be 
paid to State and county governments, shall be deposited into a 
separate account in the Treasury.
  (b) Use of Deposits.--[Amounts]
          (1) In general._Amounts  deposited under subsection 
        (a) shall be available to the Secretary of the Interior 
        for expenditure, without further appropriation and 
        without fiscal year limitation, to implement the 
        Geothermal Steam Act of 1970 and this Act.
          (2) Authorization.--Effective for fiscal year 2019 
        and each fiscal year thereafter, amounts deposited 
        under subsection (a) shall be available to the 
        Secretary of the Interior for expenditure, without 
        further appropriation or fiscal year limitation, to 
        implement the Geothermal Steam Act of 1970 (30 U.S.C. 
        1001 et seq.) and this Act.
  (c) Transfer of Funds.--For the purposes of coordination and 
processing of geothermal leases and geothermal use 
authorizations on Federal land the Secretary of the Interior 
may authorize the expenditure or transfer of such funds as are 
necessary to the Forest Service.

           *       *       *       *       *       *       *

                              ----------                              


                      GEOTHERMAL STEAM ACT OF 1970



           *       *       *       *       *       *       *
SEC. 4. LEASING PROCEDURES.

  (a) Nominations.--The Secretary shall accept nominations of 
land to be leased at any time from qualified companies and 
individuals under this Act.
  (b) Competitive Lease Sale Required.--
          (1) In general.--Except as otherwise specifically 
        provided by this Act, all land to be leased that is not 
        subject to leasing under subsection (c) shall be leased 
        as provided in this subsection to the highest 
        responsible qualified bidder, as determined by the 
        Secretary.
          (2) Competitive lease sales.--The Secretary shall 
        hold a competitive lease sale at least once every 2 
        years for land in a State that has nominations pending 
        under subsection (a) if the land is otherwise available 
        for leasing.
          (3) Lands subject to mining claims.--Lands that are 
        subject to a mining claim for which a plan of 
        operations has been approved by the relevant Federal 
        land management agency may be available for 
        noncompetitive leasing under this section to the mining 
        claim holder.
          (4) Land subject to oil and gas lease.--Land under an 
        oil and gas lease issued pursuant to the Mineral 
        Leasing Act (30 U.S.C. 181 et seq.) or the Mineral 
        Leasing Act for Acquired Lands (30 U.S.C. 351 et seq.) 
        that is subject to an approved application for permit 
        to drill and from which oil and gas production is 
        occurring may be available for noncompetitive leasing 
        under subsection (c) by the holder of the oil and gas 
        lease--
                  (A) on a determination that geothermal energy 
                will be produced from a well producing or 
                capable of producing oil and gas; and
                  (B) in order to provide for the coproduction 
                of geothermal energy with oil and gas.
          (5) Adjoining land.--
                  (A) Definitions.--In this paragraph:
                          (i) Fair market value per acre.--The 
                        term ``fair market value per acre'' 
                        means a dollar amount per acre that--
                                  (I) except as provided in 
                                this clause, shall be equal to 
                                the market value per acre 
                                (taking into account the 
                                determination under 
                                subparagraph (B)(iii) regarding 
                                a valid discovery on the 
                                adjoining land) as determined 
                                by the Secretary under 
                                regulations issued under this 
                                paragraph;
                                  (II) shall be determined by 
                                the Secretary with respect to a 
                                lease under this paragraph, by 
                                not later than the end of the 
                                180-day period beginning on the 
                                date the Secretary receives an 
                                application for the lease; and
                                  (III) shall be not less than 
                                the greater of--
                                          (aa) 4 times the 
                                        median amount paid per 
                                        acre for all land 
                                        leased under this Act 
                                        during the preceding 
                                        year; or
                                          (bb) $50.
                          (ii) Industry standards.--The term 
                        ``industry standards'' means the 
                        standards by which a qualified 
                        geothermal professional assesses 
                        whether downhole or flowing temperature 
                        measurements with indications of 
                        permeability are sufficient to produce 
                        energy from geothermal resources, as 
                        determined through flow or injection 
                        testing or measurement of lost 
                        circulation while drilling.
                          (iii) Qualified federal land.--The 
                        term ``qualified Federal land'' means 
                        land that is otherwise available for 
                        leasing under this Act.
                          (iv) Qualified geothermal 
                        professional.--The term ``qualified 
                        geothermal professional'' means an 
                        individual who is an engineer or 
                        geoscientist in good professional 
                        standing with at least 5 years of 
                        experience in geothermal exploration, 
                        development, or project assessment.
                          (v) Qualified lessee.--The term 
                        ``qualified lessee'' means a person who 
                        may hold a geothermal lease under this 
                        Act (including applicable regulations).
                          (vi) Valid discovery.--The term 
                        ``valid discovery'' means a discovery 
                        of a geothermal resource by a new or 
                        existing slim hole or production well, 
                        that exhibits downhole or flowing 
                        temperature measurements with 
                        indications of permeability that are 
                        sufficient to meet industry standards.
                  (B) Authority.--An area of qualified Federal 
                land that adjoins other land for which a 
                qualified lessee holds a legal right to develop 
                geothermal resources may be available for a 
                noncompetitive lease under this section to the 
                qualified lessee at the fair market value per 
                acre, if--
                          (i) the area of qualified Federal 
                        land--
                                  (I) consists of not less than 
                                1 acre and not more than 640 
                                acres; and
                                  (II) is not already leased 
                                under this Act or nominated to 
                                be leased under subsection (a);
                          (ii) the qualified lessee has not 
                        previously received a noncompetitive 
                        lease under this paragraph in 
                        connection with the valid discovery for 
                        which data has been submitted under 
                        clause (iii)(I); and
                          (iii) sufficient geological and other 
                        technical data prepared by a qualified 
                        geothermal professional has been 
                        submitted by the qualified lessee to 
                        the applicable Federal land management 
                        agency that would lead individuals who 
                        are experienced in the subject matter 
                        to believe that--
                                  (I) there is a valid 
                                discovery of geothermal 
                                resources on the land for which 
                                the qualified lessee holds the 
                                legal right to develop 
                                geothermal resources; and
                                  (II) that geothermal feature 
                                extends into the adjoining 
                                areas.
                  (C) Determination of fair market value.--
                          (i) In general.--The Secretary 
                        shall--
                                  (I) publish a notice of any 
                                request to lease land under 
                                this paragraph;
                                  (II) determine fair market 
                                value for purposes of this 
                                paragraph in accordance with 
                                procedures for making those 
                                determinations that are 
                                established by regulations 
                                issued by the Secretary;
                                  (III) provide to a qualified 
                                lessee and publish, with an 
                                opportunity for public comment 
                                for a period of 30 days, any 
                                proposed determination under 
                                this subparagraph of the fair 
                                market value of an area that 
                                the qualified lessee seeks to 
                                lease under this paragraph; and
                                  (IV) provide to the qualified 
                                lessee and any adversely 
                                affected party the opportunity 
                                to appeal the final 
                                determination of fair market 
                                value in an administrative 
                                proceeding before the 
                                applicable Federal land 
                                management agency, in 
                                accordance with applicable law 
                                (including regulations).
                          (ii) Limitation on nomination.--After 
                        publication of a notice of request to 
                        lease land under this paragraph, the 
                        Secretary may not accept under 
                        subsection (a) any nomination of the 
                        land for leasing unless the request has 
                        been denied or withdrawn.
                          (iii) Annual rental.--For purposes of 
                        section 5(a)(3), a lease awarded under 
                        this paragraph shall be considered a 
                        lease awarded in a competitive lease 
                        sale.
                  (D) Regulations.--Not later than 270 days 
                after the date of the enactment of this 
                paragraph, the Secretary shall issue 
                regulations to carry out this paragraph.
  (c) Noncompetitive Leasing.--The Secretary shall make 
available for a period of 2 years for noncompetitive leasing 
any tract for which a competitive lease sale is held, but for 
which the Secretary does not receive any bids in a competitive 
lease sale.
  (d) Pending Lease Applications.--
          (1) In general.--It shall be a priority for the 
        Secretary, and for the Secretary of Agriculture with 
        respect to National Forest Systems land, to ensure 
        timely completion of administrative actions, including 
        amendments to applicable forest plans and resource 
        management plans, necessary to process applications for 
        geothermal leasing pending on the date of enactment of 
        this subsection. All future forest plans and resource 
        management plans for areas with high geothermal 
        resource potential shall consider geothermal leasing 
        and development.
          (2) Administration.--An application described in 
        paragraph (1) and any lease issued pursuant to the 
        application--
                  (A) except as provided in subparagraph (B), 
                shall be subject to this section as in effect 
                on the day before the date of enactment of this 
                paragraph; or
                  (B) at the election of the applicant, shall 
                be subject to this section as in effect on the 
                effective date of this paragraph.
  (e) Leases Sold as a Block.--If information is available to 
the Secretary indicating a geothermal resource that could be 
produced as 1 unit can reasonably be expected to underlie more 
than 1 parcel to be offered in a competitive lease sale, the 
parcels for such a resource may be offered for bidding as a 
block in the competitive lease sale.
  (f) Leasing for Direct Use of Geothermal Resources.--
Notwithstanding subsection (b), the Secretary may identify 
areas in which the land to be leased under this Act exclusively 
for direct use of geothermal resources, without sale for 
purposes other than commercial generation of electricity, may 
be leased to any qualified applicant that first applies for 
such a lease under regulations issued by the Secretary, if the 
Secretary--
          (1) publishes a notice of the land proposed for 
        leasing not later than 90 days before the date of the 
        issuance of the lease;
          (2) does not receive during the 90-day period 
        beginning on the date of the publication any nomination 
        to include the land concerned in the next competitive 
        lease sale; and
          (3) determines there is no competitive interest in 
        the geothermal resources in the land to be leased.
  (g) Area Subject to Lease for Direct Use.--
          (1) In general.--Subject to paragraph (2), a 
        geothermal lease for the direct use of geothermal 
        resources shall cover not more than the quantity of 
        acreage determined by the Secretary to be reasonably 
        necessary for the proposed use.
          (2) Limitations.--The quantity of acreage covered by 
        the lease shall not exceed the limitations established 
        under section 7.

           *       *       *       *       *       *       *


        Supplemental, Minority, Additional, or Dissenting Views

    None.