[House Report 111-493]
[From the U.S. Government Publishing Office]


111th Congress                                                   Report
                        HOUSE OF REPRESENTATIVES
 2d Session                                                     111-493

======================================================================



 
            GRID RELIABILITY AND INFRASTRUCTURE DEFENSE ACT

                                _______
                                

  May 25, 2010.--Committed to the Committee of the Whole House on the 
              State of the Union and ordered to be printed

                                _______
                                

 Mr. Waxman, from the Committee on Energy and Commerce, submitted the 
                               following

                              R E P O R T

                        [To accompany H.R. 5026]

      [Including cost estimate of the Congressional Budget Office]

  The Committee on Energy and Commerce, to whom was referred 
the bill (H.R. 5026) to amend the Federal Power Act to protect 
the bulk-power system and electric infrastructure critical to 
the defense of the United States from cybersecurity and other 
threats and vulnerabilities, having considered the same, report 
favorably thereon with amendments and recommend that the bill 
as amended do pass.

                                CONTENTS

                                                                   Page
Amendment........................................................     2
Purpose and Summary..............................................     6
Background and Need for Legislation..............................     7
Legislative History..............................................    11
Committee Consideration..........................................    11
Committee Votes..................................................    11
Committee Oversight Findings and Recommendations.................    14
New Budget Authority, Entitlement Authority, and Tax Expenditures    14
Statement of General Performance Goals and Objectives............    14
Constitutional Authority Statement...............................    14
Earmarks and Tax and Tariff Benefits.............................    14
Advisory Committee Statement.....................................    14
Applicability of Law to Legislative Branch.......................    14
Federal Mandates Statement.......................................    14
Committee Cost Estimate..........................................    14
Congressional Budget Office Estimate.............................    15
Section-by-Section Analysis of the Legislation...................    20
Changes in Existing Law Made by the Bill, as Reported............    23

                               Amendment

  The amendments are as follows:
  Strike all after the enacting clause and insert the 
following:

SECTION 1. SHORT TITLE.

  This Act may be cited as the ``Grid Reliability and Infrastructure 
Defense Act'' or the ``GRID Act''.

SEC. 2. AMENDMENT TO THE FEDERAL POWER ACT.

  (a) Critical Electric Infrastructure Security.--Part II of the 
Federal Power Act (16 U.S.C. 824 et seq.) is amended by adding after 
section 215 the following new section:

``SEC. 215A. CRITICAL ELECTRIC INFRASTRUCTURE SECURITY.

  ``(a)  Definitions.--For purposes of this section:
          ``(1) Bulk-power system; electric reliability organization; 
        regional entity.--The terms `bulk-power system', `Electric 
        Reliability Organization', and `regional entity' have the 
        meanings given such terms in paragraphs (1), (2), and (7) of 
        section 215(a), respectively.
          ``(2) Defense critical electric infrastructure.--The term 
        `defense critical electric infrastructure' means any 
        infrastructure located in the United States (including the 
        territories) used for the generation, transmission, or 
        distribution of electric energy that--
                  ``(A) is not part of the bulk-power system; and
                  ``(B) serves a facility designated by the President 
                pursuant to subsection (d)(1), but is not owned or 
                operated by the owner or operator of such facility.
          ``(3) Defense critical electric infrastructure 
        vulnerability.--The term `defense critical electric 
        infrastructure vulnerability' means a weakness in defense 
        critical electric infrastructure that, in the event of a 
        malicious act using electronic communication or an 
        electromagnetic pulse, would pose a substantial risk of 
        disruption of those electronic devices or communications 
        networks, including hardware, software, and data, that are 
        essential to the reliability of defense critical electric 
        infrastructure.
          ``(4) Electromagnetic pulse.--The term `electromagnetic 
        pulse' means 1 or more pulses of electromagnetic energy emitted 
        by a device capable of disabling, disrupting, or destroying 
        electronic equipment by means of such a pulse.
          ``(5) Geomagnetic storm.--The term `geomagnetic storm' means 
        a temporary disturbance of the Earth's magnetic field resulting 
        from solar activity.
          ``(6) Grid security threat.--The term `grid security threat' 
        means a substantial likelihood of--
                  ``(A)(i) a malicious act using electronic 
                communication or an electromagnetic pulse, or a 
                geomagnetic storm event, that could disrupt the 
                operation of those electronic devices or communications 
                networks, including hardware, software, and data, that 
                are essential to the reliability of the bulk-power 
                system or of defense critical electric infrastructure; 
                and
                  ``(ii) disruption of the operation of such devices or 
                networks, with significant adverse effects on the 
                reliability of the bulk-power system or of defense 
                critical electric infrastructure, as a result of such 
                act or event; or
                  ``(B)(i) a direct physical attack on the bulk-power 
                system or on defense critical electric infrastructure; 
                and
                  ``(ii) significant adverse effects on the reliability 
                of the bulk-power system or of defense critical 
                electric infrastructure as a result of such physical 
                attack.
          ``(7) Grid security vulnerability.--The term `grid security 
        vulnerability' means a weakness that, in the event of a 
        malicious act using electronic communication or an 
        electromagnetic pulse, would pose a substantial risk of 
        disruption to the operation of those electronic devices or 
        communications networks, including hardware, software, and 
        data, that are essential to the reliability of the bulk-power 
        system.
          ``(8) Large transformer.--The term `large transformer' means 
        an electric transformer that is part of the bulk-power system.
          ``(9) Protected information.--The term `protected 
        information' means information, other than classified national 
        security information, designated as protected information by 
        the Commission under subsection (e)(2)--
                  ``(A) that was developed or submitted in connection 
                with the implementation of this section;
                  ``(B) that specifically discusses grid security 
                threats, grid security vulnerabilities, defense 
                critical electric infrastructure vulnerabilities, or 
                plans, procedures, or measures to address such threats 
                or vulnerabilities; and
                  ``(C) the unauthorized disclosure of which could be 
                used in a malicious manner to impair the reliability of 
                the bulk-power system or of defense critical electric 
                infrastructure.
          ``(10) Secretary.--The term `Secretary' means the Secretary 
        of Energy.
          ``(11) Security.--The definition of `security' in section 
        3(16) shall not apply to the provisions in this section.
  ``(b) Emergency Response Measures.--
          ``(1) Authority to address grid security threats.--Whenever 
        the President issues and provides to the Commission (either 
        directly or through the Secretary) a written directive or 
        determination identifying an imminent grid security threat, the 
        Commission may, with or without notice, hearing, or report, 
        issue such orders for emergency measures as are necessary in 
        its judgment to protect the reliability of the bulk-power 
        system or of defense critical electric infrastructure against 
        such threat. As soon as practicable but not later than 180 days 
        after the date of enactment of this section, the Commission 
        shall, after notice and opportunity for comment, establish 
        rules of procedure that ensure that such authority can be 
        exercised expeditiously.
          ``(2) Notification of congress.--Whenever the President 
        issues and provides to the Commission (either directly or 
        through the Secretary) a written directive or determination 
        under paragraph (1), the President (or the Secretary, as the 
        case may be) shall promptly notify congressional committees of 
        relevant jurisdiction, including the Committee on Energy and 
        Commerce of the House of Representatives and the Committee on 
        Energy and Natural Resources of the Senate, of the contents of, 
        and justification for, such directive or determination.
          ``(3) Consultation.--Before issuing an order for emergency 
        measures under paragraph (1), the Commission shall, to the 
        extent practicable in light of the nature of the grid security 
        threat and the urgency of the need for such emergency measures, 
        consult with appropriate governmental authorities in Canada and 
        Mexico, entities described in paragraph (4), the Secretary, and 
        other appropriate Federal agencies regarding implementation of 
        such emergency measures.
          ``(4) Application.--An order for emergency measures under 
        this subsection may apply to--
                  ``(A) the Electric Reliability Organization;
                  ``(B) a regional entity; or
                  ``(C) any owner, user, or operator of the bulk-power 
                system or of defense critical electric infrastructure 
                within the United States.
          ``(5) Discontinuance.--The Commission shall issue an order 
        discontinuing any emergency measures ordered under this 
        subsection, effective not later than 30 days after the earliest 
        of the following:
                  ``(A) The date upon which the President issues and 
                provides to the Commission (either directly or through 
                the Secretary) a written directive or determination 
                that the grid security threat identified under 
                paragraph (1) no longer exists.
                  ``(B) The date upon which the Commission issues a 
                written determination that the emergency measures are 
                no longer needed to address the grid security threat 
                identified under paragraph (1), including by means of 
                Commission approval of a reliability standard under 
                section 215 that the Commission determines adequately 
                addresses such threat.
                  ``(C) The date that is 1 year after the issuance of 
                an order under paragraph (1).
          ``(6) Cost recovery.--If the Commission determines that 
        owners, operators, or users of the bulk-power system or of 
        defense critical electric infrastructure have incurred 
        substantial costs to comply with an order under this subsection 
        and that such costs were prudently incurred and cannot 
        reasonably be recovered through regulated rates or market 
        prices for the electric energy or services sold by such owners, 
        operators, or users, the Commission shall, after notice and an 
        opportunity for comment, establish a mechanism that permits 
        such owners, operators, or users to recover such costs.
  ``(c) Measures to Address Grid Security Vulnerabilities.--
          ``(1) Commission authority.--If the Commission, in 
        consultation with appropriate Federal agencies, identifies a 
        grid security vulnerability that the Commission determines has 
        not adequately been addressed through a reliability standard 
        developed and approved under section 215, the Commission shall, 
        after notice and opportunity for comment and after consultation 
        with the Secretary, other appropriate Federal agencies, and 
        appropriate governmental authorities in Canada and Mexico, 
        promulgate a rule or issue an order requiring implementation, 
        by any owner, operator, or user of the bulk-power system in the 
        United States, of measures to protect the bulk-power system 
        against such vulnerability. Before promulgating a rule or 
        issuing an order under this paragraph, the Commission shall, to 
        the extent practicable in light of the urgency of the need for 
        action to address the grid security vulnerability, request and 
        consider recommendations from the Electric Reliability 
        Organization regarding such rule or order. The Commission may 
        establish an appropriate deadline for the submission of such 
        recommendations.
          ``(2) Certain existing cybersecurity vulnerabilities.--Not 
        later than 180 days after the date of enactment of this 
        section, the Commission shall, after notice and opportunity for 
        comment and after consultation with the Secretary, other 
        appropriate Federal agencies, and appropriate governmental 
        authorities in Canada and Mexico, promulgate a rule or issue an 
        order requiring the implementation, by any owner, user, or 
        operator of the bulk-power system in the United States, of such 
        measures as are necessary to protect the bulk-power system 
        against the vulnerabilities identified in the June 21, 2007, 
        communication to certain `Electricity Sector Owners and 
        Operators' from the North American Electric Reliability 
        Corporation, acting in its capacity as the Electricity Sector 
        Information and Analysis Center.
          ``(3) Rescission.--The Commission shall approve a reliability 
        standard developed under section 215 that addresses a grid 
        security vulnerability that is the subject of a rule or order 
        under paragraph (1) or (2), unless the Commission determines 
        that such reliability standard does not adequately protect 
        against such vulnerability or otherwise does not satisfy the 
        requirements of section 215. Upon such approval, the Commission 
        shall rescind the rule promulgated or order issued under 
        paragraph (1) or (2) addressing such vulnerability, effective 
        upon the effective date of the newly approved reliability 
        standard.
          ``(4) Geomagnetic storms.--Not later than 1 year after the 
        date of enactment of this section, the Commission shall, after 
        notice and an opportunity for comment and after consultation 
        with the Secretary and other appropriate Federal agencies, 
        issue an order directing the Electric Reliability Organization 
        to submit to the Commission for approval under section 215, not 
        later than 1 year after the issuance of such order, reliability 
        standards adequate to protect the bulk-power system from any 
        reasonably foreseeable geomagnetic storm event. The 
        Commission's order shall specify the nature and magnitude of 
        the reasonably foreseeable events against which such standards 
        must protect. Such standards shall appropriately balance the 
        risks to the bulk-power system associated with such events, 
        including any regional variation in such risks, and the costs 
        of mitigating such risks.
          ``(5) Large transformer availability.--Not later than 1 year 
        after the date of enactment of this section, the Commission 
        shall, after notice and an opportunity for comment and after 
        consultation with the Secretary and other appropriate Federal 
        agencies, issue an order directing the Electric Reliability 
        Organization to submit to the Commission for approval under 
        section 215, not later than 1 year after the issuance of such 
        order, reliability standards addressing availability of large 
        transformers. Such standards shall require entities that own or 
        operate large transformers to ensure, individually or jointly, 
        adequate availability of large transformers to promptly restore 
        the reliable operation of the bulk-power system in the event 
        that any such transformer is destroyed or disabled as a result 
        of a reasonably foreseeable physical or other attack or 
        geomagnetic storm event. The Commission's order shall specify 
        the nature and magnitude of the reasonably foreseeable attacks 
        or events that shall provide the basis for such standards. Such 
        standards shall--
                  ``(A) provide entities subject to the standards with 
                the option of meeting such standards individually or 
                jointly; and
                  ``(B) appropriately balance the risks associated with 
                a reasonably foreseeable attack or event, including any 
                regional variation in such risks, and the costs of 
                ensuring adequate availability of spare transformers.
  ``(d) Critical Defense Facilities.--
          ``(1) Designation.--Not later than 180 days after the date of 
        enactment of this section, the President shall designate, in a 
        written directive or determination provided to the Commission, 
        facilities located in the United States (including the 
        territories) that are--
                  ``(A) critical to the defense of the United States; 
                and
                  ``(B) vulnerable to a disruption of the supply of 
                electric energy provided to such facility by an 
                external provider.
          The number of facilities designated by such directive or 
        determination shall not exceed 100. The President may 
        periodically revise the list of designated facilities through a 
        subsequent written directive or determination provided to the 
        Commission, provided that the total number of designated 
        facilities at any time shall not exceed 100.
          ``(2) Commission authority.--If the Commission identifies a 
        defense critical electric infrastructure vulnerability that the 
        Commission, in consultation with owners and operators of any 
        facility or facilities designated by the President pursuant to 
        paragraph (1), determines has not adequately been addressed 
        through measures undertaken by owners or operators of defense 
        critical electric infrastructure, the Commission shall, after 
        notice and an opportunity for comment and after consultation 
        with the Secretary and other appropriate Federal agencies, 
        promulgate a rule or issue an order requiring implementation, 
        by any owner or operator of defense critical electric 
        infrastructure, of measures to protect the defense critical 
        electric infrastructure against such vulnerability. The 
        Commission shall exempt from any such rule or order any 
        specific defense critical electric infrastructure that the 
        Commission determines already has been adequately protected 
        against the identified vulnerability. The Commission shall make 
        any such determination in consultation with the owner or 
        operator of the facility designated by the President pursuant 
        to paragraph (1) that relies upon such defense critical 
        electric infrastructure.
          ``(3) Cost recovery.--An owner or operator of defense 
        critical electric infrastructure shall be required to take 
        measures under paragraph (2) only to the extent that the owners 
        or operators of a facility or facilities designated by the 
        President pursuant to paragraph (1) that rely upon such 
        infrastructure agree to bear the full incremental costs of 
        compliance with a rule promulgated or order issued under 
        paragraph (2).
  ``(e) Protection of Information.--
          ``(1) Prohibition of public disclosure of protected 
        information.--Protected information--
                  ``(A) shall be exempt from disclosure under section 
                552(b)(3) of title 5, United States Code; and
                  ``(B) shall not be made available pursuant to any 
                State, local, or tribal law requiring disclosure of 
                information or records.
          ``(2) Information sharing.--
                  ``(A) In general.--Consistent with the Controlled 
                Unclassified Information framework established by the 
                President, the Commission shall promulgate such 
                regulations and issue such orders as necessary to 
                designate protected information and to prohibit the 
                unauthorized disclosure of such protected information.
                  ``(B) Sharing of protected information.--The 
                regulations promulgated and orders issued pursuant to 
                subparagraph (A) shall provide standards for and 
                facilitate the appropriate sharing of protected 
                information with, between, and by Federal, State, 
                local, and tribal authorities, the Electric Reliability 
                Organization, regional entities, and owners, operators, 
                and users of the bulk-power system in the United States 
                and of defense critical electric infrastructure. In 
                promulgating such regulations and issuing such orders, 
                the Commission shall take account of the role of State 
                commissions in reviewing the prudence and cost of 
                investments within their respective jurisdictions. The 
                Commission shall consult with appropriate Canadian and 
                Mexican authorities to develop protocols for the 
                sharing of protected information with, between, and by 
                appropriate Canadian and Mexican authorities and 
                owners, operators, and users of the bulk-power system 
                outside the United States.
          ``(3) Submission of information to congress.--Nothing in this 
        section shall permit or authorize the withholding of 
        information from Congress, any committee or subcommittee 
        thereof, or the Comptroller General.
          ``(4) Disclosure of non-protected information.--In 
        implementing this section, the Commission shall protect from 
        disclosure only the minimum amount of information necessary to 
        protect the reliability of the bulk-power system and of defense 
        critical electric infrastructure. The Commission shall 
        segregate protected information within documents and electronic 
        communications, wherever feasible, to facilitate disclosure of 
        information that is not designated as protected information.
          ``(5) Duration of designation.--Information may not be 
        designated as protected information for longer than 5 years, 
        unless specifically redesignated by the Commission.
          ``(6) Removal of designation.--The Commission may remove the 
        designation of protected information, in whole or in part, from 
        a document or electronic communication if the unauthorized 
        disclosure of such information could no longer be used to 
        impair the reliability of the bulk-power system or of defense 
        critical electric infrastructure.
          ``(7) Judicial review of designations.--Notwithstanding 
        subsection (f) of this section or section 313, a person or 
        entity may seek judicial review of a determination by the 
        Commission concerning the designation of protected information 
        under this subsection exclusively in the district court of the 
        United States in the district in which the complainant resides, 
        or has his principal place of business, or in the District of 
        Columbia. In such a case the court shall determine the matter 
        de novo, and may examine the contents of documents or 
        electronic communications designated as protected information 
        in camera to determine whether such documents or any part 
        thereof were improperly designated as protected information. 
        The burden is on the Commission to sustain its designation.
  ``(f) Judicial Review.--The Commission shall act expeditiously to 
resolve all applications for rehearing of orders issued pursuant to 
this section that are filed under section 313(a). Any party seeking 
judicial review pursuant to section 313 of an order issued under this 
section may obtain such review only in the United States Court of 
Appeals for the District of Columbia Circuit.
  ``(g) Provision of Assistance to Industry in Meeting Grid Security 
Protection Needs.--
          ``(1) Expertise and resources.--The Secretary shall establish 
        a program, in consultation with other appropriate Federal 
        agencies, to develop technical expertise in the protection of 
        systems for the generation, transmission, and distribution of 
        electric energy against geomagnetic storms or malicious acts 
        using electronic communications or electromagnetic pulse that 
        would pose a substantial risk of disruption to the operation of 
        those electronic devices or communications networks, including 
        hardware, software, and data, that are essential to the 
        reliability of such systems. Such program shall include the 
        identification and development of appropriate technical and 
        electronic resources, including hardware, software, and system 
        equipment.
          ``(2) Sharing expertise.--As appropriate, the Secretary shall 
        offer to share technical expertise developed under the program 
        under paragraph (1), through consultation and assistance, with 
        owners, operators, or users of systems for the generation, 
        transmission, or distribution of electric energy located in the 
        United States and with State commissions. In offering such 
        support, the Secretary shall assign higher priority to systems 
        serving facilities designated by the President pursuant to 
        subsection (d)(1) and other critical-infrastructure facilities, 
        which the Secretary shall identify in consultation with the 
        Commission and other appropriate Federal agencies.
          ``(3) Security clearances and communication.--The Secretary 
        shall facilitate and, to the extent practicable, expedite the 
        acquisition of adequate security clearances by key personnel of 
        any entity subject to the requirements of this section to 
        enable optimum communication with Federal agencies regarding 
        grid security threats, grid security vulnerabilities, and 
        defense critical electric infrastructure vulnerabilities. The 
        Secretary, the Commission, and other appropriate Federal 
        agencies shall, to the extent practicable and consistent with 
        their obligations to protect classified and protected 
        information, share timely actionable information regarding grid 
        security threats, grid security vulnerabilities, and defense 
        critical electric infrastructure vulnerabilities with 
        appropriate key personnel of owners, operators, and users of 
        the bulk-power system and of defense critical electric 
        infrastructure.''.
  (b) Conforming Amendments.--
          (1) Jurisdiction.--Section 201(b)(2) of the Federal Power Act 
        (16 U.S.C. 824(b)(2)) is amended by inserting ``215A,'' after 
        ``215,'' each place it appears.
          (2) Public utility.--Section 201(e) of the Federal Power Act 
        (16 U.S.C. 824(e)) is amended by inserting ``215A,'' after 
        ``215,''.

  Amend the title so as to read:

    A bill to amend the Federal Power Act to protect the bulk-
power system and electric infrastructure critical to the 
defense of the United States against cybersecurity and other 
threats and vulnerabilities.

                          Purpose and Summary

    H.R. 5026, the Grid Reliability and Infrastructure Defense 
Act, or ``GRID Act'', was introduced by Reps. Edward J. Markey 
(D-MA) and Fred Upton (R-MI) on April 14, 2010. The purpose of 
H.R. 5026 is to provide the Federal Energy Regulatory 
Commission with new authorities under the Federal Power Act to 
protect the electric grid against cybersecurity and other 
threats and vulnerabilities.

                  Background and Need for Legislation

    The U.S. electric grid consists of interconnected 
transmission lines, local distribution systems to deliver 
electricity to end-users, generation facilities, and related 
communications systems. The bulk-power system in the United 
States and Canada has more than 200,000 miles of transmission 
lines, has more than 800,000 megawatts of generating capacity, 
is valued at over $1 trillion, and serves more than 300 million 
people.\1\ The components of the grid are highly 
interdependent, such that a line outage or system condition 
problems in one area can lead to reliability concerns in other 
areas. In addition, the operations controls over the 
transmission grid and generators are increasingly managed by 
computer systems (notably Supervisory Control and Data 
Acquisition, or SCADA, systems) linked to the Internet or other 
communications systems and to each other. The grid's increasing 
reliance on automation and two-way communications increases its 
vulnerability to remote cyber attacks.
---------------------------------------------------------------------------
    \1\U.S. Government Accountability Office, Critical Infrastructure 
Protection: Multiple Efforts to Secure Control Systems Are Under Way, 
but Challenges Remain, at 22 (Oct. 2007) (GAO-07-1036).
---------------------------------------------------------------------------
    Public reports relating to cyber vulnerabilities of and 
threats to the electric grid have increased in recent years and 
have been the subject of several hearings in the 110th and 
111th Congresses. Especially noteworthy are reports on what is 
known as the ``Aurora'' vulnerability. In 2006, the Department 
of Homeland Security's Control Systems Security Program 
conducted an analysis--performed by the Department of Energy's 
Idaho National Laboratory--that came to be known as Aurora. 
This analysis demonstrated that an attacker could hack into the 
control system of an electric generator or other rotating 
equipment connected to the grid and throw the equipment out of 
phase, causing severe physical damage to the equipment.
    In addition, it has been reported that actors based in 
China, Russia, and other nations have conducted cyber 
``probes'' of U.S. grid systems, and that cyber attacks have 
been conducted against critical infrastructure in other 
countries. Cyber attacks may create instant effects at very low 
cost, and are very difficult to positively attribute back to 
the attacker. These features could make such attacks attractive 
not only for criminal purposes, but also as a possible element 
of future national hostilities.\2\ Utilization of cyber attacks 
on civilian critical infrastructure has reportedly become an 
important element of Chinese military strategy.\3\
---------------------------------------------------------------------------
    \2\U.S. Government Accountability Office, Cybersecurity: Continued 
Efforts Are Needed to Protect Information Systems from Evolving 
Threats, at 4, Table 1 (Nov. 17, 2009) (GAO-10-230T).
    \3\Bryan Krekel et al., Capability of the People's Republic of 
China to Conduct Cyber Warfare and Computer Network Exploitation, 
prepared by Northrop Grumman Corporation for The US-China Economic and 
Security Review Commission, at 22-26 (Oct. 9, 2009).
---------------------------------------------------------------------------
    There also has been growing attention to physical 
vulnerabilities of the grid. For example, large transformers 
essential to the reliable operation of the grid are 
manufactured outside of the United States and replacement may 
require two years or longer. A limited number of spare, large 
transformers are available within the United States, and 
industry has developed a voluntary program (the spare 
transformer equipment program, or ``STEP'') providing for 
sharing of such assets in the event of a terrorist attack.
    A special subset of physical vulnerabilities and threats is 
associated with electromagnetic pulse (EMP), of which there are 
three general categories: (1) geomagnetic storms resulting from 
solar activity; (2) intentional electromagnetic interference 
from portable equipment that uses high-power radio frequency or 
microwave or other electromagnetic pulses to destroy or 
temporarily disable electronic equipment; and (3) EMP caused by 
a high-altitude detonation of a nuclear weapon.
    Solar coronal mass ejections emit electromagnetic particles 
that can disrupt the Earth's magnetic field. Such geomagnetic 
storms in turn can induce voltages in transmission lines, 
particularly in the northern-latitudes, which can damage 
electric transformers and other infrastructure. There are 
several historical examples of electric transformers being 
damaged or destroyed by geomagnetic storms, including the 
storms of 1859, 1921, and 1989. A recent National Academy of 
Sciences report estimated the effects of a geomagnetic storm of 
the magnitude of the 1921 storm on the current electrical grid, 
concluding that such a storm could cause permanent damage to 
more than 350 transformers, leaving as many as 130 million 
people without power. Impacts from a large geomagnetic storm 
could last for several years and cost in the range of several 
trillion dollars per year.\4\
---------------------------------------------------------------------------
    \4\National Research Council, Severe Space Weather Events--
Understanding Societal and Economic Impacts, Workshop Report, Committee 
on the Societal and Economic Impacts of Severe Space Weather Events: A 
Workshop, at 77-79 (2008).
---------------------------------------------------------------------------
    Portable electromagnetic weapons can be used to disrupt or 
disable the control systems that operate the electric grid. 
Such weapons can vary in size from a hand-held device to a 
large vehicle-borne device, can be used at a distance from a 
target, and can penetrate walls or other obstacles--making 
detection and attribution of an attack to a specific source 
difficult. More than a dozen countries have conducted research 
on such weapons, and the Department of Defense (DOD) has 
demonstrated that such weapons can be developed with modest 
financial resources and technical capability. Such weapons have 
been used to defeat security systems, commit robberies, disable 
police communications, induce fires, and disrupt banking 
computers.\5\
---------------------------------------------------------------------------
    \5\Technical Support Working Group and Directed Energy Technology 
Office, The Threat of Radio Frequency Weapons to Critical 
Infrastructure Facilities, at p. 1, 6-7 (Aug. 2005).
---------------------------------------------------------------------------
    In 2001, Congress established a commission to assess the 
threat of electromagnetic pulse from a high-altitude nuclear 
detonation, vulnerabilities of military and civilian 
infrastructure to such an attack, and the feasibility and cost 
of protecting such infrastructure. The commission issued a 
first report in 2004 and a second report in 2008. The 2004 
report concluded that the risks from high-altitude EMP to the 
U.S. electric grid are substantial and recommended that 
measures be taken to protect high-value transmission assets 
that would require a long lead time to replace, key electric 
generation capability, and critical communication channels.\6\
---------------------------------------------------------------------------
    \6\Commission to Assess the Threat to the United States from 
Electromagnetic Pulse (EMP) Attack, Report of the Commission to Assess 
the Threat to the United States from Electromagnetic Pulse (EMP) 
Attack: Volume 1: Executive Report, at pp. 17-23 (2004).
---------------------------------------------------------------------------
    The vulnerabilities of the electric grid present 
substantial risks to U.S. defense assets. A 2008 report by the 
Defense Science Board's Task Force on DOD Energy Strategy 
concluded that:

        critical missions . . . are almost entirely dependent 
        on the national transmission grid. About 85% of the 
        energy infrastructure upon which DoD depends is 
        commercially owned, and 99% of the electric energy DoD 
        installations consume originates outside the fence. . . 
        . In most cases, neither the grid nor on-base backup 
        power provides sufficient reliability to ensure 
        continuity of critical national priority functions and 
        oversight of strategic missions in the face of a long 
        term (several months) outage.\7\
---------------------------------------------------------------------------
    \7\Department of Defense, Report of the Defense Science Board Task 
Force on DoD Energy Strategy, More Fight--Less Fuel, at 18 (Feb. 2008).

An October 2009 report by the Government Accountability Office 
concluded that of the Department of Defense's 34 most critical 
global assets, 31 of which rely on commercially operated 
electricity grids for their primary source of electricity.\8\
---------------------------------------------------------------------------
    \8\U.S. Government Accountability Office, Defense Critical 
Infrastructure: Actions Needed to Improve the Identification and 
Management of Electrical Power Risks and Vulnerabilities to DOD 
Critical Assets (Oct. 2009) (GAO-10-147).
---------------------------------------------------------------------------
    All of the threats to and vulnerabilities of the U.S. 
electric grid described above have been addressed in multiple 
hearings in the 110th and 111th Congresses, both in the 
Subcommittee on Energy and Environment of the Committee on 
Energy and Commerce, as well as in other committees. In 
addition, these threats and vulnerabilities were the subject of 
classified briefings on grid security, provided jointly by 
multiple federal agencies to the members of the Committee on 
Energy and Commerce, during both the 110th Congress and the 
111th Congress.
    Section 215 of the Federal Power Act, enacted as part of 
the Energy Policy Act of 2005, provides for the establishment 
of mandatory reliability standards for the bulk-power system, 
including standards addressing cybersecurity threats. Under 
section 215, the Federal Energy Regulatory Commission (FERC) 
has designated the North American Electric Reliability 
Corporation (NERC) as the electric reliability organization. 
NERC is responsible for proposing, for FERC review and 
approval, reliability standards to protect and enhance the 
reliability of the bulk-power system, including cybersecurity 
standards. NERC is a not-for-profit corporation, the principal 
members of which are owners, operators, and users of the bulk-
power system. More than 1,800 different entities own or operate 
components of the bulk-power system that is subject to the NERC 
standard-setting process. NERC develops standards on an open 
basis through its standards committee, which is composed of 
member representatives. Approval of a reliability standard 
requires a quorum of 75% of the stakeholder ballot pool and 
support from a supermajority of at least two-thirds of the 
votes. The process of developing reliability standards is 
lengthy; for example, the critical infrastructure protection 
(CIP) standards approved by FERC in January 2008 took three 
years for NERC to develop. NERC procedures approved in February 
2010 allow for an accelerated process for developing standards 
in case of a ``national security emergency situation,'' but 
these procedures have not yet been used.\9\
---------------------------------------------------------------------------
    \9\North American Electric Reliability Corporation, Reliability 
Standards Development Procedure, Version 7 (Feb. 5, 2010).
---------------------------------------------------------------------------
    The Canadian and Mexican electric grids are directly linked 
to the U.S. bulk-power system, and Canadian (and to a lesser 
extent Mexican) utilities participate in NERC and have agreed 
to be subject to NERC-adopted standards. They are not, however, 
subject to FERC jurisdiction.
    Reliability standards developed by NERC and approved by 
FERC under section 215 apply to the users, owners, and 
operators of the bulk-power system and are mandatory and 
subject to enforcement by FERC with respect to U.S. entities. 
FERC cannot prescribe standards under section 215, but it has 
authority to direct NERC to develop standards or to modify 
existing standards. Importantly, the scope of these standards 
is limited by section 215's definition of the ``bulk-power 
system,'' which specifically excludes ``facilities used in the 
local distribution of electric energy.'' Accordingly, these 
standards do not apply to lower-voltage distribution facilities 
that normally serve critical defense facilities and other end-
users of electricity. In addition, the provisions of section 
215 do not apply to Alaska or Hawaii, where a number of 
important defense facilities are located.
    To date, FERC has approved nine CIP reliability standards 
developed by NERC. With regard to cybersecurity, the CIP 
standards address critical cyber asset identification, security 
management controls, personnel and training, electronic 
security perimeters, physical security of critical cyber 
assets, systems security management, incident reporting and 
response planning, and recovery plans for critical cyber 
assets. In approving these standards, FERC directed that NERC 
develop revised standards--including a first phase of high-
priority modifications and a second phase. On September 30, 
2009, FERC approved phase I of the modifications to the 
standards. The second phase is currently under development. 
With regard to malicious physical attacks on the bulk-power 
system, the sole NERC standard is one that requires reporting 
within industry and to government of disturbances or unusual 
occurrences, suspected or determined to be caused by sabotage.
    NERC's record with regard to grid security vulnerabilities 
and threats has raised concerns. For example, three years after 
the identification of the Aurora vulnerability discussed above, 
NERC still has not proposed any reliability standard directly 
addressing that vulnerability. In addition, NERC's current CIP 
standards apply only to ``critical assets and associated 
critical cyber assets,'' as self-identified by owners and 
operators of such assets. In a December 2008 NERC survey of 
self-certification of critical assets and critical cyber 
assets, only 31% of respondents to the survey, and only 29% of 
owners and operators of electric generation, identified even a 
single critical asset. Only 63% of transmission owners 
identified even a single critical asset. Consequently, a 
substantial proportion of bulk-power system assets are not 
actually covered by any CIP standard. NERC expressed its 
concern with these results in a letter to industry stakeholders 
dated April 7, 2009, but an April 2010 survey does not indicate 
any improvement in coverage. Finally, in testimony before the 
Committee, FERC raised concerns about whether NERC's open 
stakeholder process is capable of addressing rapidly emerging 
grid security vulnerabilities with sufficient speed and 
protection of sensitive information.

                          Legislative History

    H.R. 2165, the Bulk Power System Protection Act of 2009, 
was introduced by Rep. John Barrow (with Reps. Henry A. Waxman 
and Edward J. Markey as co-sponsors) on April 29, 2009. On 
October 27, 2009, the Subcommittee on Energy and Environment 
held a legislative hearing on this bill and related 
legislation. In preparation for that hearing, the Subcommittee 
convened a classified briefing on grid security vulnerabilities 
and threats for members of the full Committee on Energy and 
Commerce and staff with appropriate clearances.
    After the hearing, the majority and minority staffs of the 
Subcommittee and full Committee joined in a bipartisan effort 
to develop grid security legislation. The results of this 
effort were embodied in a Committee print, considered in markup 
by the Subcommittee on Energy and Environment on March 24, 
2010. The Subcommittee approved by voice vote the Committee 
print for consideration by the full Committee with the 
recommendation that the legislation pass. The text of H.R. 
5026, which was introduced by Reps. Edward J. Markey and Fred 
Upton on April 14, 2010, is identical in substance to the text 
of the Committee print forwarded by the Subcommittee. On April 
15, 2010, the Committee on Energy and Commerce held a markup to 
consider H.R. 5026 and, after approving a manager's amendment 
in the nature of a substitute by voice vote, unanimously agreed 
to a motion for final passage of the bill.

                        Committee Consideration

    The Subcommittee on Energy and Environment met in open 
markup session on March 24, 2010, to consider a Committee Print 
dated March 22, 2010, on H.R. ___, to amend the Federal Power 
Act to protect the bulk-power system and electric 
infrastructure critical to the defense of the United States 
from cybersecurity and other threats and vulnerabilities. 
Subsequently, the Subcommittee approved the text of the 
Committee Print to be forwarded to the full Committee without 
amendments by a voice vote. H.R. 5026 was introduced on April 
14, 2010, with the identical language of the Committee Print as 
approved by the Subcommittee, and was referred to the Committee 
on Energy and Commerce.
    The full Committee met in open markup session on April 15, 
2010, to consider H.R. 5026. A manager's amendment by Mr. 
Waxman was adopted by a voice vote. Subsequently, the Committee 
ordered H.R. 5026 favorably reported to the House, amended, by 
a roll call vote of 47 yeas and 0 nays.

                            Committee Votes

    Clause 3(b) of rule XIII of the Rules of the House of 
Representatives requires the Committee to list the record votes 
on the motion to report legislation and amendments thereto. The 
Committee agreed to a motion by Mr. Waxman to order H.R. 5026 
favorably reported to the House, amended, by a record vote of 
47 yeas and 0 nays. The following is the recorded vote taken 
during Committee consideration, including the names of those 
Members voting for and against:


            Committee Oversight Findings and Recommendations

    In compliance with clause 3(c)(1) of rule XIII of the Rules 
of the House of Representatives, the findings and 
recommendations of the Committee are reflected in the 
descriptive portions of this report.

   New Budget Authority, Entitlement Authority, and Tax Expenditures

    Regarding compliance with clause 3(c)(2) of rule XIII of 
the Rules of the House of Representatives, the Committee adopts 
as its own the estimate of budget authority and revenues 
regarding H.R. 5026 prepared by the Director of the 
Congressional Budget Office pursuant to section 402 of the 
Congressional Budget Act of 1974. The Committee finds that H.R. 
5026 would result in no new or increased entitlement authority 
or tax expenditures.

         Statement of General Performance Goals and Objectives

    In accordance with clause 3(c)(4) of rule XIII of the Rules 
of the House of Representatives, the Committee's performance 
goals and objectives are reflected in the descriptive portions 
of this report.

                   Constitutional Authority Statement

    Pursuant to clause 3(d)(1) of rule XIII of the Rules of the 
House of Representatives, the Committee finds that the 
constitutional authority for H.R. 5026 is provided in Article 
I, section 8, clauses 3 and 18.

                  Earmarks and Tax and Tariff Benefits

    H.R. 5026 does not contain any congressional earmarks, 
limited tax benefits, or limited tariff benefits as defined in 
clause 9 of rule XXI of the Rules of the House of 
Representatives.

                      Advisory Committee Statement

    No advisory committees were created by H.R. 5026 within the 
meaning of section 5 U.S.C. App., 5(b) of the Federal Advisory 
Committee Act.

             Applicability of Law to the Legislative Branch

    The Committee finds that H.R. 5026 does not relate to the 
terms and conditions of employment or access to public services 
or accommodations within the meaning of section 102(b)(3) of 
the Congressional Accountability Act of 1985.

                       Federal Mandates Statement

    The Committee adopts as its own the estimates of federal 
mandates prepared by the Director of the Congressional Budget 
Office pursuant to section 423 of the Unfunded Mandate Reform 
Act.

                        Committee Cost Estimate

    Pursuant to clause 3(d) of rule XIII of the Rules of the 
House of Representatives, the Committee adopts as its own the 
cost estimate on H.R. 5026 prepared by the Director of the 
Congressional Budget Office pursuant to section 402 of the 
Congressional Budget Act.

                  Congressional Budget Office Estimate

    Pursuant to clause 3(c)(3) of rule XIII of the Rules of the 
House of Representatives, the following is the cost estimate on 
H.R. 5026 provided by the Congressional Budget Office pursuant 
to section 402 of the Congressional Budget Act of 1974:

                                                      May 19, 2010.
Hon. Henry A. Waxman,
Chairman, Committee on Energy and Commerce,
House of Representatives, Washington, DC.
    Dear Mr. Chairman: The Congressional Budget Office has 
prepared the enclosed cost estimate for H.R. 5026, the Grid 
Reliability and Infrastructure Defense Act.
    If you wish further details on this estimate, we will be 
pleased to provide them. The CBO staff contact is Kathleen 
Gramp,
            Sincerely,
                                              Douglas W. Elmendorf.
    Enclosure.

H.R. 5026--Grid Reliability and Infrastructure Defense Act

    Summary: H.R. 5026 would amend existing law regarding the 
regulation of electric power transmission facilities. Under 
current law, most of the standards governing the reliability of 
the bulk-power system are issued by the Electric Reliability 
Organization (ERO), subject to approval and enforcement by the 
Federal Energy Regulatory Commission (FERC). This bill would 
set deadlines for FERC to issue standards regarding the 
security of computer networks used in electric power 
transmission (known as cybersecurity) and other risks to the 
electric power transmission grid, subject to certain 
conditions. In addition, both FERC and ERO would be directed to 
ensure that utilities maintain adequate supplies of large 
electrical transformers and implement measures to protect their 
systems against geomagnetic storms (incidents involving solar 
radiation). Other provisions would authorize a new technical 
assistance program related to grid security and establish terms 
and procedures for responding to emergencies, protecting 
information, and identifying strategically important electric 
facilities.
    CBO estimates that implementing this bill would increase 
net direct spending by about $5 million over the 2011-2015 
period and $40 million over the 2011-2020 period.\1\ 
Implementing the bill would increase discretionary spending by 
$219 million over the 2011-2015 period. CBO estimates that 
enacting this bill would not affect revenues.
---------------------------------------------------------------------------
    \1\Enacting H.R. 5026 would not increase direct spending over the 
2010-2014 period and would increase direct spending by $33 million over 
the 2010-2019 period.
---------------------------------------------------------------------------
    Pay-as-you-go procedures apply because enacting the 
legislation would affect direct spending.
    H.R. 5026 would impose intergovernmental and private-sector 
mandates, as defined in the Unfunded Mandates Reform Act 
(UMRA), on owners and operators of electric infrastructure and 
a private-sector mandate on ERO. Because of uncertainty about 
the number of entities affected, the scope of future 
regulations, and the implementation timeline, CBO cannot 
determine whether the aggregate cost of the mandates in the 
bill would exceed the annual thresholds established in UMRA for 
intergovernmental or private-sector mandates ($70 million and 
$141 million in 2010, respectively, adjusted annually for 
inflation).
    CBO has not reviewed a provision that would provide FERC 
with emergency authority to protect the electric transmission 
grid from security threats for intergovernmental or private-
sector mandates. Section 4 of UMRA excludes from the 
application of that act any legislative provisions that are 
necessary for national security. CBO has determined that the 
provision falls within that exclusion.
    Estimated cost to the Federal Government: The estimated 
budgetary impact of H.R. 5026 is shown in the following table. 
The costs of this legislation fall within budget function 270 
(energy).

----------------------------------------------------------------------------------------------------------------
                                                               By fiscal year, in millions of dollars--
                                                     -----------------------------------------------------------
                                                                                                          2011-
                                                        2011      2012      2013      2014      2015      2015
----------------------------------------------------------------------------------------------------------------
                                          CHANGES IN DIRECT SPENDING\1\

Estimated Budget Authority..........................         0         0         0         0         5         5
Estimated Outlays...................................         0         0         0         0         5         5

                                  CHANGES IN SPENDING SUBJECT TO APPROPRIATION

Federal Power Agencies:
    Estimated Authorization Level...................         0         0         0         4        10        14
    Estimated Outlays...............................         0         0         0         4        10        14
Department of Energy:
    Estimated Authorization Level...................        50        51        51        52        52       256
    Estimated Outlays...............................        19        39        45        50        52       205
    Total Changes:
        Estimated Authorization Level...............        50        51        51        56        62       270
        Estimated Outlays...........................        19        39        45        54        62       219
----------------------------------------------------------------------------------------------------------------
\1\CBO estimates that enacting the bill would increase direct spending by $40 million over the 2011-2020 period.

    Basis of estimate: For this estimate, CBO assumes that the 
legislation will be enacted near the end of fiscal year 2010, 
that the necessary funds will be appropriated each year, and 
that spending patterns will be consistent with historical 
trends for similar activities.

Background

    Taken together, four federal agencies own and operate about 
15 percent of the nation's electric power grid, providing much 
of the transmission service in certain regions of the country. 
Capital expenditures for the federally owned transmission grid 
totaled about $645 million in 2009. Most of those costs were 
incurred by the Tennessee Valley Authority (TVA) and Bonneville 
Power Administration (BPA). Spending by TVA and BPA affects 
direct spending because those agencies are authorized to 
collect and spend proceeds from the sale of electricity and to 
borrow funds to finance capital projects. In contrast, the 
Western Area Power Administration (WAPA) and Southwestern Power 
Administration (SWPA) rely on annual appropriations for capital 
investments in transmission reliability measures. Regardless of 
the method of financing, the federal power agencies are 
required by law to set electricity prices high enough to recoup 
capital investments over the useful life of the assets.
    CBO estimates that H.R. 5026 would increase both direct 
spending and spending subject to appropriation for additional 
capital investments by federal power agencies. CBO estimates 
that other provisions of the bill would further increase 
spending subject to appropriation.

Additional capital spending by federal power agencies (Direct spending 
        and spending subject to appropriation)

    The budgetary impacts of this legislation on the federal 
power agencies would depend on the scope and substance of 
future regulations that are developed to implement it. FERC and 
ERO would be directed to require utilities to address various 
threats, taking into consideration the likelihood of those 
events and the cost-effectiveness of any mitigation measures. 
Given the lead times involved in changing standards for 
electric utilities, CBO expects that most of the budgetary 
impacts resulting from those rules would occur after 2014 and 
would involve only modest changes in performance standards 
through 2020.
    Assuming appropriation of the necessary amounts, CBO 
estimates that implementing H.R. 5026 would increase 
discretionary spending by WAPA and SWPA by $14 million over the 
2011-2015 period, and additional amounts thereafter. In 
addition, we estimate that additional capital spending by TVA 
and BPA would increase direct spending by about $40 million, 
net of recoveries from ratepayers, over the 2011-2020 period.
    Acquiring Additional Transformer Capacity. CBO expects that 
the regulations developed under this bill for large 
transformers would initially mirror the requirements of the 
industry's existing voluntary program for sharing spare 
transformers in the event of a terrorist attack. CBO estimates 
that complying with those benchmarks would have a negligible 
effect on spending by TVA, BPA, and SWPA because those agencies 
have sufficient spare transformers to meet the voluntary 
guidelines. In contrast, we estimate that WAPA would spend 
about $12 million over the 2011-2015 period to acquire 
additional transformers, assuming appropriation of the 
necessary amounts. Additional costs would occur after 2015 for 
WAPA. Costs for all of the agencies could be higher if the new 
rules require utilities to increase the number of spare 
transformers, which cost between $1 million and $15 million 
each.
    Mitigating Other Risks to Transmission Systems. Currently, 
there are no standards that address risks posed by natural or 
malicious disruptions to the grid, such as geomagnetic storms 
and electromagnetic pulses from weapons. As a result, CBO 
expects that directives addressing those threats would increase 
capital spending by the federal power agencies. Government 
reports have identified various actions that could be taken to 
mitigate those risks, with costs for the entire industry 
estimated to range from a few hundred million dollars (for 
example, for equipment that protects generators or 
transformers) to over a billion dollars (for example, for 
comprehensive strategies for the utility industry). For this 
estimate, CBO assumes that near-term measures would primarily 
involve small upgrades to equipment and facilities and would 
increase capital spending on bulk power facilities by less than 
1 percent annually. On that basis, CBO estimates that those 
investments would increase net direct spending by TVA and BPA 
by about $40 million over the 2011-2020 period, and 
discretionary spending for WAPA and SWPA by about $2 million 
over the 2011-2015 period.
    Finally, CBO estimates that other provisions in the bill 
concerning the security of computer networks used by the 
federal power agencies would have a negligible budgetary impact 
because the new standards would be similar to those followed by 
federal agencies as a result of other statutory directives.

Other impacts on spending subject to appropriation

    H.R. 5026 would direct the Secretary of Energy to establish 
a new technical assistance program related to grid security. 
According to the Department of Energy (DOE), the proposed 
program would build on existing efforts related to 
cybersecurity (currently funded at around $40 million annually) 
and would focus in particular on developing technologies to 
mitigate risks associated with geomagnetic storms or certain 
malicious acts. The bill would direct DOE to establish an 
outreach program to share expertise developed through those 
activities. Finally, H.R. 5026 would establish new requirements 
related to security clearances and sharing sensitive 
information on grid security among federal agencies.
    Based on information from DOE, CBO estimates that those 
activities would cost about $200 million over the 2011-2015 
period, with additional spending occurring in later years. That 
estimate is based on the cost of similar programs and reflects 
historical spending patterns for activities related to 
research, development, and technical assistance.
    In addition, CBO expects that implementing H.R. 5026 would 
expand FERC's workload and increase the agency's administrative 
costs, which are controlled through annual appropriation acts. 
Because FERC recovers 100 percent of its costs through user 
fees, any such increases in its costs would be offset by an 
equal change in fees that the commission charges, resulting in 
no net budgetary impact.
    Pay-As-You-Go considerations: The Statutory Pay-As-You-Go 
Act of 2010 establishes budget reporting and enforcement 
procedures for legislation affecting direct spending or 
revenues. The net changes in outlays that are subject to those 
pay-as-you-go procedures are shown in the following table.

         CBO ESTIMATE OF PAY-AS-YOU-GO EFFECTS FOR H.R. 5026 AS ORDERED REPORTED BY THE HOUSE COMMITTEE ON ENERGY AND COMMERCE ON APRIL 15, 2010
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                              By fiscal year, in millions of dollars--
                                           -------------------------------------------------------------------------------------------------------------
                                             2010    2011    2012    2013    2014    2015    2016    2017    2018    2019    2020   2010-2015  2010-2020
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                       NET INCREASE OR DECREASE (-) IN THE DEFICIT

Statutory Pay-As-You-Go Impact............       0       0       0       0       0       5       7       7       7       7       7         5         40
--------------------------------------------------------------------------------------------------------------------------------------------------------

    Intergovernmental and private-sector impact: H.R. 5026 
would impose intergovernmental and private-sector mandates, as 
defined in UMRA, on owners and operators of electric 
infrastructure and a private-sector mandate on the Electric 
Reliability Organization. Because of uncertainty about the 
number of entities affected, the scope of future regulations, 
and the implementation timeline, CBO cannot determine whether 
the aggregate cost of the mandates in the bill would exceed the 
annual thresholds established in UMRA for intergovernmental and 
private-sector mandates ($70 million and $141 million in 2010, 
respectively, adjusted annually for inflation).
    CBO has not reviewed a provision that would provide FERC 
with emergency authority to protect the electric transmission 
grid from security threats for intergovernmental or private-
sector mandates. Section 4 of UMRA excludes from the 
application of that act any legislative provisions that are 
necessary for national security. CBO has interpreted that 
exclusion to encompass provisions dealing with activities that 
are immediately necessary to protect vital national security 
interests. CBO has determined that the provision dealing with 
emergency authority falls within the exclusion for national 
security.

Mandates that apply to both public and private entities

    By requiring ERO and FERC to issue new standards to address 
vulnerabilities in the nation's energy grid, the bill would 
impose mandates on public and private owners and operators of 
electric infrastructure. The standards would address 
vulnerabilities related to cybersecurity, disruptions related 
to geomagnetic or electromagnetic events and unexpected losses 
of large transformers. Based on information from FERC and 
industry sources, the cost of complying with each of the 
mandates could equal tens of millions of dollars annually, 
depending on the scope and implementation timeline of future 
regulations. Because of those uncertainties, however, CBO 
cannot estimate the total costs of the mandates.
    Cybersecurity. The bill would require owners and operators 
of electric infrastructure to implement measures to mitigate 
the risk to the power grid from cybersecurity vulnerabilities. 
FERC would establish the standards for cybersecurity and 
implementation timelines after an assessment of current 
standards.
    Geomagnetic Storms and Electromagnetic Pulse Events. The 
bill would require owners and operators of electric 
infrastructure to protect against risks posed by natural or 
malicious disruptions to the grid resulting from geomagnetic 
storms or electromagnetic pulse events. Based on information 
from government reports, potential mitigation measures could 
involve significant capital investments in equipment and 
facilities.
    Large Transformers. The bill would require owners and 
operators of large transformers to maintain an adequate supply 
of spare transformers in order to restore the reliability of 
the power grid if any transformer is disabled. The number of 
spare transformers required by the bill would depend on future 
regulations.

Mandate that applies to public entities only

    The bill would preempt state, local, and tribal laws 
relating to the disclosure of information or records. Those 
preemptions would be intergovernmental mandates as defined in 
UMRA, but CBO estimates that they would impose no duty on 
states that would result in additional spending.

Mandate that applies to private entities only

    Under current law, FERC has the authority to require the 
ERO to develop reliability standards. The bill would impose a 
private-sector mandate by requiring ERO to develop standards 
earlier than it would have under current law. Based on 
information from ERO, CBO estimates that the cost to develop 
the standards would be small in relation to the annual 
threshold for private-sector mandates.
    Estimate prepared by: Federal Costs: Kathleen Gramp 
(federal power agencies), Megan Carroll (FERC, DOE); Impact on 
state, local, and tribal governments: Ryan Miller; Impact on 
the private sector: Amy Petz.
    Estimate approved by: Theresa Gullo, Deputy Assistant 
Director for Budget Analysis.

             Section-by-Section Analysis of the Legislation


Section 1. Short title

    This section provides that the short title of the bill is 
the ``Grid Reliability and Infrastructure Defense Act'' or the 
``GRID Act''.

Section 2. Amendment to the Federal Power Act

    Subsection (a) of this section would amend the Federal 
Power Act to add a new section 215A, providing FERC new 
authorities to protect the electric grid against cyber and 
other threats and vulnerabilities, as well as from geomagnetic 
storms created by coronal mass ejections and other solar 
activity.
    Subsection (a) of the new section 215A provides a number of 
definitions. The definition of ``bulk-power system'' is the 
same as in the existing section 215 of the Federal Power Act. 
As a result, except with regard to electric infrastructure 
serving critical defense facilities, the new authorities 
established by the bill would extend to matters affecting the 
reliability of the ``bulk-power system''--providing the same 
coverage as the existing section 215 of the Federal Power Act, 
enacted as part of the Energy Policy Act of 2005, which 
provides authority to establish mandatory reliability standards 
for the bulk-power system. As the agency charged with 
administering section 215A, FERC has the authority to interpret 
this and the other definitions included in subsection (a).
    Subsection (b) of the new section 215A gives FERC authority 
to issue emergency orders to protect against a ``grid security 
threat,'' with or without notice, if the President notifies the 
Commission (either directly or through the Secretary of Energy) 
that an imminent ``grid security threat'' exists. The term 
``imminent'' in this context means that the grid security 
threat is urgent, impending, or near at hand, but does not 
necessarily require that it be immediate in time. A grid 
security threat is defined under subsection (a) as a 
substantial likelihood of one of the following acts or events, 
provided there is a substantial likelihood the act or event 
would have a significant adverse effect on the reliability of 
the bulk-power system or of defense critical electric 
infrastructure:
           a malicious act using electronic 
        communication (i.e., a cyber attack) or an 
        electromagnetic pulse (i.e., one or more pulses of 
        electromagnetic energy, such as radio frequency or 
        microwave, emitted by a device capable of disabling, 
        disrupting, or destroying electronic equipment by means 
        of such a pulse);
           a geomagnetic storm (i.e., a solar storm); 
        or
           a direct physical attack on the bulk power 
        infrastructure or on defense critical electric 
        infrastructure.
    A malicious act ``using electronic communication'' is 
intended to refer to an act using the electronic communication 
as an actual vector for the attack (i.e., a cyber attack), as 
opposed to an act in which electronic communications are used 
only incidentally, such as the use of electronic communication 
to plan or execute a physical attack.
    Subsection (b) requires the President or Secretary of 
Energy to promptly notify the relevant congressional committees 
whenever the President provides a written directive or 
determination of a grid security threat to FERC under the 
subsection. Subsection (b) provides for the discontinuance of 
an order issued under this subsection whenever any of the 
following first occurs: the President determines the grid 
security threat no longer exists, FERC determines the emergency 
measures are no longer needed to protect against the threat, or 
one year elapses from the date the order was issued.
    Subsection (b) also provides FERC with authority to 
establish a mechanism for owners, operators, or users of the 
bulk-power system to recover prudently incurred costs of 
complying with an order under subsection (b) if FERC determines 
that such entities cannot otherwise recover such costs through 
market prices or rates. Nothing in this provision is intended 
to prevent or affect use of other existing mechanisms for the 
recovery of costs incurred in compliance with this subsection 
or the remainder of the new section 215A under existing 
procedures or mechanisms, whether under the Federal Power Act 
or state law.
    Subsection (c)(1) of the new section 215A provides FERC 
authority to promulgate a rule or issue an order, after notice 
and comment, requiring implementation of measures to protect 
against any ``grid security vulnerability'' that FERC 
determines has not been adequately addressed by a NERC 
reliability standard developed and approved under section 215. 
Subsection (a) defines a grid security vulnerability as a 
weakness that, in the event of a malicious act using electronic 
communication (i.e., a cyber attack) or an electromagnetic 
pulse, would pose a substantial risk of disruption to the 
operation of those electronic devices or communication networks 
that are essential to the reliability of the bulk-power system. 
Before promulgating a rule or issuing an order to address a 
grid security vulnerability under subsection (c)(1), FERC, to 
the extent practicable in light of the urgency of the need for 
action, is required to request and consider recommendations 
from NERC regarding such a rule or order. FERC may establish an 
appropriate deadline for NERC's submission of such 
recommendations.
    Subsection (c)(2) specifically requires FERC, within 180 
days of enactment, to promulgate a rule or issue an order 
requiring measures to address the ``Aurora vulnerability'' to 
cyber attack that was identified three years ago.
    Subsection (c)(3) directs FERC to approve a proposed NERC 
reliability standard (under section 215) that addresses a grid 
security vulnerability identified under subsection (c)(1) or 
(c)(2) unless FERC determines that the NERC standard does not 
adequately protect against the vulnerability. If FERC approves 
a proposed NERC standard, the corresponding FERC rule or order 
must be rescinded.
    Subsection (c)(4) requires FERC to direct NERC to submit 
for approval a reliability standard under section 215 to 
protect the bulk-power system against geomagnetic storms. FERC 
is directed to identify the nature and magnitude of the 
reasonably foreseeable geomagnetic storm events against which 
the standards should protect, similar to the identification of 
a ``design basis threat.'' The standards must balance risks 
against the cost of protecting against those risks.
    Subsection (c)(5) requires FERC to direct NERC to submit 
for approval a reliability standard under section 215 to 
require adequate availability of large transformers to ensure 
the reliability of the bulk-power system in the event of a 
reasonably foreseeable physical or other attack or a 
geomagnetic storm. FERC is directed to identify the nature and 
magnitude of the attack or event against which the standard 
must protect, similar to the identification of a ``design basis 
threat.'' The standard must allow entities required to comply 
with the standard the option of complying either individually 
or jointly (e.g., through a spare transformer sharing program), 
and must balance risks against the cost of protecting against 
those risks.
    Subsection (d) of the new section 215A directs the 
President to designate not more than 100 facilities located in 
the United States that are critical to the defense of the 
United States and vulnerable to interruption of an external 
supply of electricity to the facility. The bill classifies 
electric infrastructure that is not part of the bulk-power 
system, that serves such a facility, and that is not owned or 
operated by the owner or operator of the designated facility, 
as ``defense critical electric infrastructure.'' If FERC, in 
consultation with the owner or operator of a designated 
critical facility, identifies a vulnerability in such 
infrastructure to a cyber attack or attack using an 
electromagnetic pulse that has not adequately been addressed, 
FERC has authority to promulgate a rule or issue an order, 
after notice and opportunity for comment, to require measures 
to protect such infrastructure. Infrastructure can be exempted 
from such rules or orders, on a case-by-case basis, if FERC, in 
consultation with the owner or operator of the designated 
critical facility, determines that such infrastructure is 
adequately protected. An owner or operator of defense critical 
electric infrastructure shall be required to take such required 
measures only to the extent that the owners or operators of a 
facility designated by the President that rely on such 
infrastructure agree to bear the full incremental costs of 
compliance with such a rule or order.
    Subsection (e) of the new section 215A addresses the 
treatment of ``protected information,'' defined as information 
designated as such by FERC that is not classified national 
security information; that was developed or submitted in 
connection with the implementation of this section; that 
specifically discusses grid security threats, grid security 
vulnerabilities, or defense critical electric infrastructure 
vulnerabilities, or plans, procedures or measures to address 
such threats or vulnerabilities; and the unauthorized 
disclosure of which could be used in a malicious manner to 
impair the reliability of the bulk power system. The bill 
exempts such information from disclosure under the Freedom of 
Information Act or under state, local, or tribal disclosure 
laws. The bill also requires FERC to promulgate regulations and 
issue orders necessary to designate protected information, 
prohibit unauthorized disclosure of such information, and 
facilitate appropriate sharing of such information with, 
between, and by governmental authorities, NERC, the regional 
reliability councils, and owners, operators, and users of the 
bulk-power system.
    Subsection (f) of the new section 215A provides that any 
party seeking judicial review of an order issued under this 
section pursuant to section 313 of the Federal Power Act may 
obtain such review exclusively in the U.S. Court of Appeals for 
the District of Columbia Circuit.
    Subsection (g) of the new section 215A directs the 
Secretary of Energy to develop technical expertise in the 
protection of the grid against attacks using electronic 
communication or electromagnetic pulse, and against geomagnetic 
storms, and to provide technical assistance in this area to 
owners, operators, and users of systems for the generation, 
transmission and distribution of electric energy--with priority 
given to systems serving critical defense and other critical-
infrastructure facilities. The Secretary is directed to 
facilitate and, to the extent practicable, expedite acquisition 
of security clearances by key industry personnel to facilitate 
communication regarding grid security threats and 
vulnerabilities. In addition, the Secretary, FERC, and other 
federal authorities are directed, to the extent practicable, to 
share timely and actionable information regarding grid security 
threats and vulnerabilities and defense critical electric 
infrastructure vulnerabilities with appropriate key personnel 
of owners, operators, and users of the bulk-power system and 
defense critical electric infrastructure.
    Section 2(b) of the GRID Act makes conforming amendments to 
section 201 of the Federal Power Act.

         Changes in Existing Law Made by the Bill, as Reported

  In compliance with clause 3(e) of rule XIII of the Rules of 
the House of Representatives, changes in existing law made by 
the bill, as reported, are shown as follows (existing law 
proposed to be omitted is enclosed in black brackets, new 
matter is printed in italic, existing law in which no change is 
proposed is shown in roman):

FEDERAL POWER ACT

           *       *       *       *       *       *       *


PART II--REGULATION OF ELECTRIC UTILITY COMPANIES ENGAGED IN INTERSTATE 
                                COMMERCE

        DECLARATION OF POLICY; APPLICATION OF PART; DEFINITIONS

  Section 201. (a) * * *
  (b)(1) * * *
  (2) Notwithstanding section 201(f), the provisions of 
sections 203(a)(2), 206(e), 210, 211, 211A, 212, 215, 215A, 
216, 217, 218, 219, 220, 221, and 222 shall apply to the 
entities described in such provisions, and such entities shall 
be subject to the jurisdiction of the Commission for purposes 
of carrying out such provisions and for purposes of applying 
the enforcement authorities of this Act with respect to such 
provisions. Compliance with any order of the Commission under 
the provisions of section 203(a)(2), 206(e), 210, 211, 211A, 
212, 215, 215A, 216, 217, 218, 219, 220, 221, or 222, shall not 
make an electric utility or other entity subject to the 
jurisdiction of the Commission for any purposes other than the 
purposes specified in the preceding sentence.

           *       *       *       *       *       *       *

  (e) The term ``public utility'' when used in this Part or in 
the Part next following means any person who owns or operates 
facilities subject to the jurisdiction of the Commission under 
this Part (other than facilities subject to such jurisdiction 
solely by reason of section 206(e), 206(f), 210, 211, 211A, 
212, 215, 215A, 216, 217, 218, 219, 220, 221, or 222).

           *       *       *       *       *       *       *


SEC. 215A. CRITICAL ELECTRIC INFRASTRUCTURE SECURITY.

  (a)  Definitions.--For purposes of this section:
          (1) Bulk-power system; electric reliability 
        organization; regional entity.--The terms ``bulk-power 
        system'', ``Electric Reliability Organization'', and 
        ``regional entity'' have the meanings given such terms 
        in paragraphs (1), (2), and (7) of section 215(a), 
        respectively.
          (2) Defense critical electric infrastructure.--The 
        term ``defense critical electric infrastructure'' means 
        any infrastructure located in the United States 
        (including the territories) used for the generation, 
        transmission, or distribution of electric energy that--
                  (A) is not part of the bulk-power system; and
                  (B) serves a facility designated by the 
                President pursuant to subsection (d)(1), but is 
                not owned or operated by the owner or operator 
                of such facility.
          (3) Defense critical electric infrastructure 
        vulnerability.--The term ``defense critical electric 
        infrastructure vulnerability'' means a weakness in 
        defense critical electric infrastructure that, in the 
        event of a malicious act using electronic communication 
        or an electromagnetic pulse, would pose a substantial 
        risk of disruption of those electronic devices or 
        communications networks, including hardware, software, 
        and data, that are essential to the reliability of 
        defense critical electric infrastructure.
          (4) Electromagnetic pulse.--The term 
        ``electromagnetic pulse'' means 1 or more pulses of 
        electromagnetic energy emitted by a device capable of 
        disabling, disrupting, or destroying electronic 
        equipment by means of such a pulse.
          (5) Geomagnetic storm.--The term ``geomagnetic 
        storm'' means a temporary disturbance of the Earth's 
        magnetic field resulting from solar activity.
          (6) Grid security threat.--The term ``grid security 
        threat'' means a substantial likelihood of--
                  (A)(i) a malicious act using electronic 
                communication or an electromagnetic pulse, or a 
                geomagnetic storm event, that could disrupt the 
                operation of those electronic devices or 
                communications networks, including hardware, 
                software, and data, that are essential to the 
                reliability of the bulk-power system or of 
                defense critical electric infrastructure; and
                  (ii) disruption of the operation of such 
                devices or networks, with significant adverse 
                effects on the reliability of the bulk-power 
                system or of defense critical electric 
                infrastructure, as a result of such act or 
                event; or
                  (B)(i) a direct physical attack on the bulk-
                power system or on defense critical electric 
                infrastructure; and
                  (ii) significant adverse effects on the 
                reliability of the bulk-power system or of 
                defense critical electric infrastructure as a 
                result of such physical attack.
          (7) Grid security vulnerability.--The term ``grid 
        security vulnerability'' means a weakness that, in the 
        event of a malicious act using electronic communication 
        or an electromagnetic pulse, would pose a substantial 
        risk of disruption to the operation of those electronic 
        devices or communications networks, including hardware, 
        software, and data, that are essential to the 
        reliability of the bulk-power system.
          (8) Large transformer.--The term ``large 
        transformer'' means an electric transformer that is 
        part of the bulk-power system.
          (9) Protected information.--The term ``protected 
        information'' means information, other than classified 
        national security information, designated as protected 
        information by the Commission under subsection (e)(2)--
                  (A) that was developed or submitted in 
                connection with the implementation of this 
                section;
                  (B) that specifically discusses grid security 
                threats, grid security vulnerabilities, defense 
                critical electric infrastructure 
                vulnerabilities, or plans, procedures, or 
                measures to address such threats or 
                vulnerabilities; and
                  (C) the unauthorized disclosure of which 
                could be used in a malicious manner to impair 
                the reliability of the bulk-power system or of 
                defense critical electric infrastructure.
          (10) Secretary.--The term ``Secretary'' means the 
        Secretary of Energy.
          (11) Security.--The definition of ``security'' in 
        section 3(16) shall not apply to the provisions in this 
        section.
  (b) Emergency Response Measures.--
          (1) Authority to address grid security threats.--
        Whenever the President issues and provides to the 
        Commission (either directly or through the Secretary) a 
        written directive or determination identifying an 
        imminent grid security threat, the Commission may, with 
        or without notice, hearing, or report, issue such 
        orders for emergency measures as are necessary in its 
        judgment to protect the reliability of the bulk-power 
        system or of defense critical electric infrastructure 
        against such threat. As soon as practicable but not 
        later than 180 days after the date of enactment of this 
        section, the Commission shall, after notice and 
        opportunity for comment, establish rules of procedure 
        that ensure that such authority can be exercised 
        expeditiously.
          (2) Notification of congress.--Whenever the President 
        issues and provides to the Commission (either directly 
        or through the Secretary) a written directive or 
        determination under paragraph (1), the President (or 
        the Secretary, as the case may be) shall promptly 
        notify congressional committees of relevant 
        jurisdiction, including the Committee on Energy and 
        Commerce of the House of Representatives and the 
        Committee on Energy and Natural Resources of the 
        Senate, of the contents of, and justification for, such 
        directive or determination.
          (3) Consultation.--Before issuing an order for 
        emergency measures under paragraph (1), the Commission 
        shall, to the extent practicable in light of the nature 
        of the grid security threat and the urgency of the need 
        for such emergency measures, consult with appropriate 
        governmental authorities in Canada and Mexico, entities 
        described in paragraph (4), the Secretary, and other 
        appropriate Federal agencies regarding implementation 
        of such emergency measures.
          (4) Application.--An order for emergency measures 
        under this subsection may apply to--
                  (A) the Electric Reliability Organization;
                  (B) a regional entity; or
                  (C) any owner, user, or operator of the bulk-
                power system or of defense critical electric 
                infrastructure within the United States.
          (5) Discontinuance.--The Commission shall issue an 
        order discontinuing any emergency measures ordered 
        under this subsection, effective not later than 30 days 
        after the earliest of the following:
                  (A) The date upon which the President issues 
                and provides to the Commission (either directly 
                or through the Secretary) a written directive 
                or determination that the grid security threat 
                identified under paragraph (1) no longer 
                exists.
                  (B) The date upon which the Commission issues 
                a written determination that the emergency 
                measures are no longer needed to address the 
                grid security threat identified under paragraph 
                (1), including by means of Commission approval 
                of a reliability standard under section 215 
                that the Commission determines adequately 
                addresses such threat.
                  (C) The date that is 1 year after the 
                issuance of an order under paragraph (1).
          (6) Cost recovery.--If the Commission determines that 
        owners, operators, or users of the bulk-power system or 
        of defense critical electric infrastructure have 
        incurred substantial costs to comply with an order 
        under this subsection and that such costs were 
        prudently incurred and cannot reasonably be recovered 
        through regulated rates or market prices for the 
        electric energy or services sold by such owners, 
        operators, or users, the Commission shall, after notice 
        and an opportunity for comment, establish a mechanism 
        that permits such owners, operators, or users to 
        recover such costs.
  (c) Measures to Address Grid Security Vulnerabilities.--
          (1) Commission authority.--If the Commission, in 
        consultation with appropriate Federal agencies, 
        identifies a grid security vulnerability that the 
        Commission determines has not adequately been addressed 
        through a reliability standard developed and approved 
        under section 215, the Commission shall, after notice 
        and opportunity for comment and after consultation with 
        the Secretary, other appropriate Federal agencies, and 
        appropriate governmental authorities in Canada and 
        Mexico, promulgate a rule or issue an order requiring 
        implementation, by any owner, operator, or user of the 
        bulk-power system in the United States, of measures to 
        protect the bulk-power system against such 
        vulnerability. Before promulgating a rule or issuing an 
        order under this paragraph, the Commission shall, to 
        the extent practicable in light of the urgency of the 
        need for action to address the grid security 
        vulnerability, request and consider recommendations 
        from the Electric Reliability Organization regarding 
        such rule or order. The Commission may establish an 
        appropriate deadline for the submission of such 
        recommendations.
          (2) Certain existing cybersecurity vulnerabilities.--
        Not later than 180 days after the date of enactment of 
        this section, the Commission shall, after notice and 
        opportunity for comment and after consultation with the 
        Secretary, other appropriate Federal agencies, and 
        appropriate governmental authorities in Canada and 
        Mexico, promulgate a rule or issue an order requiring 
        the implementation, by any owner, user, or operator of 
        the bulk-power system in the United States, of such 
        measures as are necessary to protect the bulk-power 
        system against the vulnerabilities identified in the 
        June 21, 2007, communication to certain 'Electricity 
        Sector Owners and Operators' from the North American 
        Electric Reliability Corporation, acting in its 
        capacity as the Electricity Sector Information and 
        Analysis Center.
          (3) Rescission.--The Commission shall approve a 
        reliability standard developed under section 215 that 
        addresses a grid security vulnerability that is the 
        subject of a rule or order under paragraph (1) or (2), 
        unless the Commission determines that such reliability 
        standard does not adequately protect against such 
        vulnerability or otherwise does not satisfy the 
        requirements of section 215. Upon such approval, the 
        Commission shall rescind the rule promulgated or order 
        issued under paragraph (1) or (2) addressing such 
        vulnerability, effective upon the effective date of the 
        newly approved reliability standard.
          (4) Geomagnetic storms.--Not later than 1 year after 
        the date of enactment of this section, the Commission 
        shall, after notice and an opportunity for comment and 
        after consultation with the Secretary and other 
        appropriate Federal agencies, issue an order directing 
        the Electric Reliability Organization to submit to the 
        Commission for approval under section 215, not later 
        than 1 year after the issuance of such order, 
        reliability standards adequate to protect the bulk-
        power system from any reasonably foreseeable 
        geomagnetic storm event. The Commission's order shall 
        specify the nature and magnitude of the reasonably 
        foreseeable events against which such standards must 
        protect. Such standards shall appropriately balance the 
        risks to the bulk-power system associated with such 
        events, including any regional variation in such risks, 
        and the costs of mitigating such risks.
          (5) Large transformer availability.--Not later than 1 
        year after the date of enactment of this section, the 
        Commission shall, after notice and an opportunity for 
        comment and after consultation with the Secretary and 
        other appropriate Federal agencies, issue an order 
        directing the Electric Reliability Organization to 
        submit to the Commission for approval under section 
        215, not later than 1 year after the issuance of such 
        order, reliability standards addressing availability of 
        large transformers. Such standards shall require 
        entities that own or operate large transformers to 
        ensure, individually or jointly, adequate availability 
        of large transformers to promptly restore the reliable 
        operation of the bulk-power system in the event that 
        any such transformer is destroyed or disabled as a 
        result of a reasonably foreseeable physical or other 
        attack or geomagnetic storm event. The Commission's 
        order shall specify the nature and magnitude of the 
        reasonably foreseeable attacks or events that shall 
        provide the basis for such standards. Such standards 
        shall--
                  (A) provide entities subject to the standards 
                with the option of meeting such standards 
                individually or jointly; and
                  (B) appropriately balance the risks 
                associated with a reasonably foreseeable attack 
                or event, including any regional variation in 
                such risks, and the costs of ensuring adequate 
                availability of spare transformers.
  (d) Critical Defense Facilities.--
          (1) Designation.--Not later than 180 days after the 
        date of enactment of this section, the President shall 
        designate, in a written directive or determination 
        provided to the Commission, facilities located in the 
        United States (including the territories) that are--
                  (A) critical to the defense of the United 
                States; and
                  (B) vulnerable to a disruption of the supply 
                of electric energy provided to such facility by 
                an external provider.
        The number of facilities designated by such directive 
        or determination shall not exceed 100. The President 
        may periodically revise the list of designated 
        facilities through a subsequent written directive or 
        determination provided to the Commission, provided that 
        the total number of designated facilities at any time 
        shall not exceed 100.
          (2) Commission authority.--If the Commission 
        identifies a defense critical electric infrastructure 
        vulnerability that the Commission, in consultation with 
        owners and operators of any facility or facilities 
        designated by the President pursuant to paragraph (1), 
        determines has not adequately been addressed through 
        measures undertaken by owners or operators of defense 
        critical electric infrastructure, the Commission shall, 
        after notice and an opportunity for comment and after 
        consultation with the Secretary and other appropriate 
        Federal agencies, promulgate a rule or issue an order 
        requiring implementation, by any owner or operator of 
        defense critical electric infrastructure, of measures 
        to protect the defense critical electric infrastructure 
        against such vulnerability. The Commission shall exempt 
        from any such rule or order any specific defense 
        critical electric infrastructure that the Commission 
        determines already has been adequately protected 
        against the identified vulnerability. The Commission 
        shall make any such determination in consultation with 
        the owner or operator of the facility designated by the 
        President pursuant to paragraph (1) that relies upon 
        such defense critical electric infrastructure.
          (3) Cost recovery.--An owner or operator of defense 
        critical electric infrastructure shall be required to 
        take measures under paragraph (2) only to the extent 
        that the owners or operators of a facility or 
        facilities designated by the President pursuant to 
        paragraph (1) that rely upon such infrastructure agree 
        to bear the full incremental costs of compliance with a 
        rule promulgated or order issued under paragraph (2).
  (e) Protection of Information.--
          (1) Prohibition of public disclosure of protected 
        information.--Protected information--
                  (A) shall be exempt from disclosure under 
                section 552(b)(3) of title 5, United States 
                Code; and
                  (B) shall not be made available pursuant to 
                any State, local, or tribal law requiring 
                disclosure of information or records.
          (2) Information sharing.--
                  (A) In general.--Consistent with the 
                Controlled Unclassified Information framework 
                established by the President, the Commission 
                shall promulgate such regulations and issue 
                such orders as necessary to designate protected 
                information and to prohibit the unauthorized 
                disclosure of such protected information.
                  (B) Sharing of protected information.--The 
                regulations promulgated and orders issued 
                pursuant to subparagraph (A) shall provide 
                standards for and facilitate the appropriate 
                sharing of protected information with, between, 
                and by Federal, State, local, and tribal 
                authorities, the Electric Reliability 
                Organization, regional entities, and owners, 
                operators, and users of the bulk-power system 
                in the United States and of defense critical 
                electric infrastructure. In promulgating such 
                regulations and issuing such orders, the 
                Commission shall take account of the role of 
                State commissions in reviewing the prudence and 
                cost of investments within their respective 
                jurisdictions. The Commission shall consult 
                with appropriate Canadian and Mexican 
                authorities to develop protocols for the 
                sharing of protected information with, between, 
                and by appropriate Canadian and Mexican 
                authorities and owners, operators, and users of 
                the bulk-power system outside the United 
                States.
          (3) Submission of information to congress.--Nothing 
        in this section shall permit or authorize the 
        withholding of information from Congress, any committee 
        or subcommittee thereof, or the Comptroller General.
          (4) Disclosure of non-protected information.--In 
        implementing this section, the Commission shall protect 
        from disclosure only the minimum amount of information 
        necessary to protect the reliability of the bulk-power 
        system and of defense critical electric infrastructure. 
        The Commission shall segregate protected information 
        within documents and electronic communications, 
        wherever feasible, to facilitate disclosure of 
        information that is not designated as protected 
        information.
          (5) Duration of designation.--Information may not be 
        designated as protected information for longer than 5 
        years, unless specifically redesignated by the 
        Commission.
          (6) Removal of designation.--The Commission may 
        remove the designation of protected information, in 
        whole or in part, from a document or electronic 
        communication if the unauthorized disclosure of such 
        information could no longer be used to impair the 
        reliability of the bulk-power system or of defense 
        critical electric infrastructure.
          (7) Judicial review of designations.--Notwithstanding 
        subsection (f) of this section or section 313, a person 
        or entity may seek judicial review of a determination 
        by the Commission concerning the designation of 
        protected information under this subsection exclusively 
        in the district court of the United States in the 
        district in which the complainant resides, or has his 
        principal place of business, or in the District of 
        Columbia. In such a case the court shall determine the 
        matter de novo, and may examine the contents of 
        documents or electronic communications designated as 
        protected information in camera to determine whether 
        such documents or any part thereof were improperly 
        designated as protected information. The burden is on 
        the Commission to sustain its designation.
  (f) Judicial Review.--The Commission shall act expeditiously 
to resolve all applications for rehearing of orders issued 
pursuant to this section that are filed under section 313(a). 
Any party seeking judicial review pursuant to section 313 of an 
order issued under this section may obtain such review only in 
the United States Court of Appeals for the District of Columbia 
Circuit.
  (g) Provision of Assistance to Industry in Meeting Grid 
Security Protection Needs.--
          (1) Expertise and resources.--The Secretary shall 
        establish a program, in consultation with other 
        appropriate Federal agencies, to develop technical 
        expertise in the protection of systems for the 
        generation, transmission, and distribution of electric 
        energy against geomagnetic storms or malicious acts 
        using electronic communications or electromagnetic 
        pulse that would pose a substantial risk of disruption 
        to the operation of those electronic devices or 
        communications networks, including hardware, software, 
        and data, that are essential to the reliability of such 
        systems. Such program shall include the identification 
        and development of appropriate technical and electronic 
        resources, including hardware, software, and system 
        equipment.
          (2) Sharing expertise.--As appropriate, the Secretary 
        shall offer to share technical expertise developed 
        under the program under paragraph (1), through 
        consultation and assistance, with owners, operators, or 
        users of systems for the generation, transmission, or 
        distribution of electric energy located in the United 
        States and with State commissions. In offering such 
        support, the Secretary shall assign higher priority to 
        systems serving facilities designated by the President 
        pursuant to subsection (d)(1) and other critical-
        infrastructure facilities, which the Secretary shall 
        identify in consultation with the Commission and other 
        appropriate Federal agencies.
          (3) Security clearances and communication.--The 
        Secretary shall facilitate and, to the extent 
        practicable, expedite the acquisition of adequate 
        security clearances by key personnel of any entity 
        subject to the requirements of this section to enable 
        optimum communication with Federal agencies regarding 
        grid security threats, grid security vulnerabilities, 
        and defense critical electric infrastructure 
        vulnerabilities. The Secretary, the Commission, and 
        other appropriate Federal agencies shall, to the extent 
        practicable and consistent with their obligations to 
        protect classified and protected information, share 
        timely actionable information regarding grid security 
        threats, grid security vulnerabilities, and defense 
        critical electric infrastructure vulnerabilities with 
        appropriate key personnel of owners, operators, and 
        users of the bulk-power system and of defense critical 
        electric infrastructure.

           *       *       *       *       *       *       *