   EXTENSION OF TIME TO COMMENCE CONSTRUCTION OF CERTAIN HYDROPOWER 
                                PROJECTS

  Mrs. HARSHBARGER. Madam Speaker, I move to suspend the rules and pass 
the bill (S. 1020) to require the Federal Energy Regulatory Commission 
to extend the time period during which licensees are required to 
commence construction of certain hydropower projects.
  The Clerk read the title of the bill.
  The text of the bill is as follows:

                                S. 1020

       Be it enacted by the Senate and House of Representatives of 
     the United States of America in Congress assembled,

     SECTION 1. EXTENSION OF TIME TO COMMENCE CONSTRUCTION OF 
                   CERTAIN HYDROPOWER PROJECTS.

       (a) Definition of Covered Project.--In this section, the 
     term ``covered project'' means a hydropower project with 
     respect to which the Federal Energy Regulatory Commission 
     issued a license before March 13, 2020.
       (b) Authorization of Extension.--Notwithstanding section 13 
     of the Federal Power Act (16 U.S.C. 806), on the request of a 
     licensee of a covered project, the Federal Energy Regulatory 
     Commission may, after reasonable notice and for good cause 
     shown, extend in accordance with subsection (c) the period 
     during which the licensee is required to commence 
     construction of the covered project for not more than an 
     additional 6 years beyond the 8 years authorized by that 
     section.
       (c) Period of Extension.--An extension of time to commence 
     construction of a covered project under subsection (b) 
     shall--
       (1) consist of not more than 3 consecutive 2-year periods;
       (2) begin on the date on which the final extension of the 
     period for commencement of construction granted to the 
     licensee under section 13 of the Federal Power Act (16 U.S.C. 
     806) expires; and
       (3) end on the date that is not more than 6 years after the 
     latest date to which the Federal Energy Regulatory Commission 
     is authorized to extend the period for commencement of 
     construction under that section.
       (d) Reinstatement of Expired License.--If the time period 
     required under section 13 of the Federal Power Act (16 U.S.C. 
     806) to commence construction of a covered project expires 
     after December 31, 2023, and before the date of enactment of 
     this Act--
       (1) the Federal Energy Regulatory Commission may reinstate 
     the license for the applicable project effective as of the 
     date of expiration of the license; and
       (2) the extension authorized under subsection (b) shall 
     take effect on the date of that expiration.

  The SPEAKER pro tempore. Pursuant to the rule, the gentlewoman from 
Tennessee (Mrs. Harshbarger) and the gentleman from New Jersey (Mr. 
Pallone) each will control 20 minutes.
  The Chair recognizes the gentlewoman from Tennessee.


                             General Leave

  Mrs. HARSHBARGER. Madam Speaker, I ask unanimous consent that all 
Members may have 5 legislative days to revise and extend their remarks 
on the legislation and to insert extraneous material on S. 1020.
  The SPEAKER pro tempore. Is there objection to the request of the 
gentlewoman from Tennessee?
  There was no objection.
  Mrs. HARSHBARGER. Madam Speaker, I yield myself such time as I may 
consume.
  Madam Speaker, I rise in support of S. 1020, led by Senator Daines 
and, in the House of Representatives, by Representative Newhouse.
  Hydropower is a critical part of our Nation's energy mix, supplying 
baseload power to approximately 30 million homes and businesses and 
accounting for 40 percent of our black start capacity.
  S. 1020 authorizes the Federal Energy Regulatory Commission, or FERC, 
to extend construction deadlines for critical hydropower projects 
licensed before March 2020, when the COVID-19 pandemic disrupted global 
supply chains and halted many projects.
  Current law requires hydropower projects to commence construction 
within 10 years of receiving a license. This legislation allows FERC to 
authorize an additional 6 years for certain projects to ensure fully 
licensed infrastructure is not permanently halted, depriving Americans 
of reliable energy.
  There are currently 37 projects, across 15 States, that are at risk 
of losing licenses without the passage of this bill providing 
additional construction time.
  These projects in limbo would provide energy that is imperative to 
power our communities, win the artificial intelligence race, and lower 
electricity prices for consumers.
  I urge my colleagues to support S. 1020, and I reserve the balance of 
my time.
  Mr. PALLONE. Madam Speaker, I yield myself such time as I may 
consume.
  Madam Speaker, I rise today in support of S. 1020, which will grant 
an extension to hydropower projects impacted by the COVID pandemic.
  The Federal Power Act requires hydropower projects to start 
construction within 2 years of receiving a license from the Federal 
Energy Regulatory Commission, or FERC. Subsequent amendments have 
allowed FERC to grant extensions of up to 8 years to a project's 
construction deadline.
  While I think it makes sense to have a hydropower license expire if a 
project can't start construction within a decade of the license being 
issued, I recognize that the COVID pandemic and resulting supply chain 
issues wreaked havoc on the hydropower industry. Therefore, this bill 
would allow FERC to grant up to 6 additional years for projects whose 
licenses were issued prior to COVID to start construction and would 
allow FERC to reinstate the licenses of projects whose authorizations 
have since expired.
  Madam Speaker, I will note that this authority is not a blank check 
to any developer with a license issued pre-COVID. The bill explicitly 
only allows FERC to grant an extension for good cause. I expect FERC to 
adhere to that restriction.
  In addition, I will also note that while the House has been able to 
complete work on this bill, my colleagues from the Energy and Commerce 
Committee, Representatives Schrier and Fulcher, have another bill on 
hydropower, H.R. 3657, that has been sitting in the Senate for 9 
months. I certainly hope our friends over in the Senate can pass that 
bill, which grants additional transparency into the hydropower 
licensing process as soon as possible.
  Madam Speaker, in any case, I urge my colleagues to support this 
bill, and I reserve the balance of my time.
  Mrs. HARSHBARGER. Madam Speaker, I reserve the balance of my time.
  Mr. PALLONE. Madam Speaker, I close by saying, again, that our 
committee is always concerned about hydropower. I urge my colleagues to 
support this bill, and I yield back the balance of my time.
  Mrs. HARSHBARGER. Madam Speaker, I yield such time as he may consume 
to the gentleman from Washington (Mr. Newhouse).
  Mr. NEWHOUSE. Madam Speaker, I appreciate the opportunity to talk on 
this very important bill.
  As everybody who knows me knows, I am a huge fan of hydropower. The 
Pacific Northwest boasts some of the most abundant form of low-cost, 
carbon-free renewable baseload power in the country, and I want to see 
other parts of the country be able to enjoy the same kind of benefits 
that we do in the Pacific Northwest from hydropower.
  That is why this legislation is so important. It will extend the 
deadline so that construction projects can commence because their 
licensing opportunities will be extended.
  Our country needs this hydropower. We need all forms of power, but 
this, in particular, is something that will help us provide a critical 
role in meeting the growing demand that we see throughout our country.
  As I said, this is baseload power. It is carbon-free. It is something 
that is important to everybody in the country to make sure that we are 
good stewards of our environment.
  I appreciate the opportunity to be able to speak in favor of an 
option that we have in front of us that potentially could provide 2.5 
gigawatts more power in the near future, which will go a long ways in 
meeting the important demands that we have in our electrical future.
  Madam Speaker, I urge all of my colleagues to support this 
legislation.
  Mrs. HARSHBARGER. Madam Speaker, I encourage my colleagues to vote 
``yes'' on S. 1020, and I yield back the balance of my time.
  The SPEAKER pro tempore. The question is on the motion offered by the 
gentlewoman from Tennessee (Mrs. Harshbarger) that the House suspend 
the rules and pass the bill, S. 1020.
  The question was taken.
  The SPEAKER pro tempore. In the opinion of the Chair, two-thirds 
being in the affirmative, the ayes have it.

[[Page H3025]]

  

  Mrs. HARSHBARGER. Madam Speaker, on that I demand the yeas and nays.
  The yeas and nays were ordered.
  The SPEAKER pro tempore. Pursuant to clause 8 of rule XX, further 
proceedings on this motion will be postponed.

                          ____________________