  Mr. COURTNEY. Madam Speaker, on August 22, the Trump administration, 
with absolutely no warning, issued a halt work order to an offshore 
wind project off the coast of southern New England that has been in the 
works for 9 years.
  The developers of this project have invested close to $4 billion, 
employed thousands of workers, and installed 45 out of 65 wind turbines 
that the Federal Government permitted in 2023.
  As of August 22, 80 percent of the project is complete, and 100 
percent of the turbine foundations have been placed on the ocean floor.
  When the turbines are turned on, 704 megawatts of power will be 
transmitted by cable to Rhode Island and Connecticut. That is enough 
electricity to power 350,000 homes--400 megawatts to Rhode Island and 
304 megawatts to Connecticut.
  The wind power contracts approved by both States at a guaranteed rate 
will over time save money for ratepayers, particularly during cold, 
winter months, and will add to the grid at a time we all know demand 
for electricity is going to increase.
  Incredibly, the Department of Energy's halt order was one-page long 
and cited nonspecific, vague ``national security concerns'' as the 
reason to suddenly eliminate good jobs and a plentiful supply of 
affordable electricity.
  Despite repeated requests from the operators, the two States, and the 
congressional delegations, the Bureau of Ocean Energy Management, BOEM, 
has provided absolutely no description or detail of what exactly are 
the national security concerns that at this late hour could possibly 
justify such a drastic action.
  The closest thing to an explanation came in a CNN interview with the 
Secretary of the Interior a few days ago, who cited ``radar 
interference'' and possible swarm attacks from undersea drones at the 
wind farm as potential threats.
  Madam Speaker, here is the thing: During the yearslong permitting 
process, BOEM meticulously investigated all national security concerns, 
and its 2023 Record of Decision approving the project specifically had 
a section on national security. It specifically addressed the issue of 
radars which was resolved to the satisfaction of the Department of 
Defense and NORAD.

[[Page H3868]]

  Madam Speaker, I have a letter from the Department of Defense dated 
December 2024, which states that the Department ``has found that 
construction of the Revolution Wind project . . . would not have 
adverse impacts to DOD missions in the area.'' I include this letter in 
the Record.

                                           Office of the Assistant


                                         Secretary Of Defense,

                                Washington, DC, December 13, 2024.
     Reference: Federal Aviation Administration Aeronautical Study 
         Number: 2021-WTE-2881-OE and 23 associated structures.

     Ms. Whitney Marsh,
     ;rsted, Providence, RI.
       Dear Ms. Marsh: Thank you for your participation in the 
     Mitigation Response Team to assess and overcome military 
     impacts from your proposed Revolution Wind project off the 
     coast of Squibnocket Beach in Chilmark, Massachusetts. In a 
     letter dated October 27, 2021, the Department of Defense 
     (DoD) described the potential impacts to military operations 
     for the project.
       As a result of discussions between ;rsted and the U.S. Air 
     Force and a resulting mitigation agreement signed by the 
     Assistant Secretary of Defense for Energy, Installations, and 
     Environment on November 4, 2024, the Military Aviation and 
     Installation Assurance Siting Clearinghouse (Clearinghouse) 
     has found that construction of the Revolution Wind Wind 
     project, with no more than 65 wind turbines up to 873 feet 
     above sea level and no more than two offshore substations up 
     to 228 feet above sea level, would not have adverse impacts 
     to DoD missions in the area. The Clearinghouse has entered a 
     determination of ``No Objection with Provision'' for this 
     project via the Federal Aviation Administration's (FAA) 
     Obstruction Evaluation/Airport Airspace Analysis system.
       Our response to the FAA included a notification that 
     additional structure proposals or an increase to the current 
     maximum structure height may present an adverse impact. We 
     encourage you to engage DoD prior to any proposed expansion 
     or height increase.
       If you have any concerns, please contact Ms. Robbin Beard, 
     Clearinghouse Deputy Director.
           Sincerely,
                                                 Steven J. Sample,
           Executive Director, Military Aviation and Installation 
                                   Assurance Siting Clearinghouse.

  Mr. COURTNEY. Regarding the swarming undersea drones, Revolution Wind 
has a contract with ThayerMahan, a maritime company that installs and 
operates undersea surveillance technology using sonar rays and pickets 
to keep watch and detect malign activity. They protect wind farms 
today. They protect oil rigs today. They protect U.S. maritime ports 
today with the finest technology.
  Madam Speaker, Secretary Burgum and his staff at BOEM should review 
its own prior investigation on national security and actually meet with 
the developers and undersea experts in Connecticut and Rhode Island to 
learn about the thorough, comprehensive investments and systems that 
were developed with the U.S. Coast Guard, the U.S. Navy, the Department 
of Defense, and the Federal Aviation Administration to ensure the safe, 
reliable operation of the wind farms.
  Madam Speaker, this halt work order needs to be overturned quickly. 
As we heard on Friday, the U.S. labor market is weakening, and we know 
the cost of electricity is going up.
  Leaving Revolution Wind in limbo with thousands of jobs on the line 
is completely unacceptable.
  It is no secret that the President doesn't like wind power, but this 
project has been permanent, paid for, and is 80 percent finished. 
Leaving the halt work order in place is hurting working families and 
electric ratepayers.
  Lawsuits have been filed, and the U.S. Government and taxpayers are 
going to pay dearly for this uncalled for about-face on a project that 
the government approved 2 years ago.
  The better path is to quickly lift the order, meet face-to-face with 
the developer and the Governors of Rhode Island and Connecticut to end 
this chaos and get the operating engineers, the longshoremen, the 
laborers, and the electrical workers back on track to finish the job 
that today is 80 percent finished.
  That is not a partisan statement. That is simple common sense.