BILLION DOLLAR BOONDOGGLE ACT OF 2023
Mr. SCHUMER. Mr. President, I ask unanimous consent that the Senate
proceed to the immediate consideration of Calendar No. 334, S. 1258.
The PRESIDING OFFICER. The clerk will report the bill by title.
The senior assistant legislative clerk read as follows:
A bill (S. 1258) to require the Director of the Office of
Management and Budget to submit to Congress an annual report
on projects that are over budget and behind schedule, and for
other purposes.
There being no objection, the Senate proceeded to consider the bill,
which had been reported from the Committee on Homeland Security and
Governmental Affairs.
Mr. SCHUMER. I further ask that the bill be considered read a third
time and passed and the motion to reconsider be considered made and
laid upon the table with no intervening action or debate.
The PRESIDING OFFICER. Without objection, it is so ordered.
The bill (S. 1258) was ordered to be engrossed for a third reading,
was read the third time, and passed as follows:
S. 1258
Be it enacted by the Senate and House of Representatives of
the United States of America in Congress assembled,
SECTION 1. SHORT TITLE.
This Act may be cited as the ``Billion Dollar Boondoggle
Act of 2023''.
SEC. 2. ANNUAL REPORT.
(a) Definitions.--In this section--
(1) the term ``covered agency'' means--
(A) an Executive agency, as defined in section 105 of title
5, United States Code; and
(B) an independent regulatory agency, as defined in section
3502 of title 44, United States Code;
(2) the term ``covered project'' means a project funded by
a covered agency--
(A) that is more than 5 years behind schedule, as measured
against the original expected date for completion; or
(B) for which the amount spent on the project is not less
than $1,000,000,000 more than the original cost estimate for
the project; and
(3) the term ``project'' means a major acquisition, a major
defense acquisition program (as defined in section 4201 of
title 10, United States Code), a procurement, a construction
project, a remediation or clean-up effort, or any other time-
limited endeavor, that is not funded through direct spending
(as defined in section 250(c) of the Balanced Budget and
Emergency Deficit Control Act of 1985 (2 U.S.C. 900(c))).
(b) Requirement.--Not later than 1 year after the date of
enactment of this Act, the Director of the Office of
Management and Budget shall issue guidance requiring covered
agencies to include, on an annual basis in a report described
in paragraph (2) of section 3516(a) of title 31, United
States Code, or a consolidated report described in paragraph
(1) of such section, information relating to each covered
project of the covered agency, which shall include--
(1) a brief description of the covered project, including--
(A) the purpose of the covered project;
(B) each location in which the covered project is carried
out;
(C) the contract or award number of the covered project,
where applicable;
(D) the year in which the covered project was initiated;
(E) the Federal share of the total cost of the covered
project; and
[[Page S2617]]
(F) each primary contractor, subcontractor, grant
recipient, and subgrantee recipient of the covered project;
(2) an explanation of any change to the original scope of
the covered project, including by the addition or narrowing
of the initial requirements of the covered project;
(3) the original expected date for completion of the
covered project;
(4) the current expected date for completion of the covered
project;
(5) the original cost estimate for the covered project, as
adjusted to reflect increases in the Consumer Price Index for
All Urban Consumers, as published by the Bureau of Labor
Statistics;
(6) the current cost estimate for the covered project, as
adjusted to reflect increases in the Consumer Price Index for
All Urban Consumers, as published by the Bureau of Labor
Statistics;
(7) an explanation for a delay in completion or an increase
in the original cost estimate for the covered project,
including, where applicable, any impact of insufficient or
delayed appropriations; and
(8) the amount of and rationale for any award, incentive
fee, or other type of bonus, if any, awarded for the covered
project.