  SA 2867. Mr. FLAKE submitted an amendment intended to be proposed to 
amendment SA 2812 proposed by Ms. Collins (for herself and Mr. Reed) to 
the bill H.R. 2577, making appropriations for the Departments of 
Transportation, and Housing and Urban Development, and related agencies 
for the fiscal year ending September 30, 2016, and for other purposes; 
which was ordered to lie on the table; as follows:

       At the end of title IV, add the following:
       Sec. __. (a) In this section, the term ``covered agency'' 
     means--
       (1) the Department of Housing and Urban Development;
       (2) the Department of Transportation;
       (3) the Federal Maritime Commission;
       (4) the National Railroad Passenger Corporation;
       (5) the National Transportation Safety Board;
       (6) the Neighborhood Reinvestment Corporation; and
       (7) the United States Interagency Council on Homelessness.
       (b) Not later than September 30, 2016, the head of each 
     covered agency shall submit to Congress and post on the 
     website of the covered agency a report on projects funded by 
     the covered agency.
       (c) Each report submitted and posted under subsection (b) 
     shall include, for each project included in the report--
       (1) a brief description of the project, including--
       (A) the purpose of the project;
       (B) each location in which the project is carried out;
       (C) the year in which the project was initiated; and
       (D) each primary contractor and grant recipient for the 
     project;
       (2) the original expected date for completion of the 
     project;
       (3) the current expected date for completion of the 
     project;
       (4) the original cost estimate for the project;
       (5) the current cost estimate for the project; and
       (6) if known, an explanation for a delay in completion or 
     increase in the original cost estimate for the project.