[House Hearing, 119 Congress]
[From the U.S. Government Publishing Office]


                    PROPOSALS FOR A WATER RESOURCES
                        DEVELOPMENT ACT OF 2026_
                       ADMINISTRATION PRIORITIES
=======================================================================

                                (119-38)

                                HEARING

                               BEFORE THE

                            SUBCOMMITTEE ON
                    WATER RESOURCES AND ENVIRONMENT

                                 OF THE

                              COMMITTEE ON
                   TRANSPORTATION AND INFRASTRUCTURE
                        HOUSE OF REPRESENTATIVES

                    ONE HUNDRED NINETEENTH CONGRESS

                             SECOND SESSION

                               __________

                           FEBRUARY 24, 2026

                               __________

                       Printed for the use of the
             Committee on Transportation and Infrastructure
             
[GRAPHIC NOT AVAILABLE IN TIFF FORMAT]             

     Available online at: https://www.govinfo.gov/committee/house-
     transportation?path=/browsecommittee/chamber/house/committee/
                             transportation
                             
                                __________ 
                                
                   U.S. GOVERNMENT PUBLISHING OFFICE
64-140 PDF                WASHINGTON : 2026
=======================================================================

             COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE

		  Sam Graves, Missouri, Chairman
		  Rick Larsen, Washington, Ranking Member
		  
Eleanor Holmes Norton,               Eric A. ``Rick'' Crawford, 
  District of Columbia               Arkansas,
Jerrold Nadler, New York               Vice Chairman
John Garamendi, California           Daniel Webster, Florida
Henry C. ``Hank'' Johnson, Jr., Georgiaomas Massie, Kentucky
Andre Carson, Indiana                Scott Perry, Pennsylvania
Dina Titus, Nevada                   Brian Babin, Texas
Jared Huffman, California            David Rouzer, North Carolina
Julia Brownley, California           Mike Bost, Illinois
Frederica S. Wilson, Florida         Bruce Westerman, Arkansas
Mark DeSaulnier, California          Brian J. Mast, Florida
Salud O. Carbajal, California        Pete Stauber, Minnesota
Greg Stanton, Arizona                Tim Burchett, Tennessee
Sharice Davids, Kansas               Dusty Johnson, South Dakota
Jesus G. ``Chuy'' Garcia, Illinois   Jefferson Van Drew, New Jersey
Chris Pappas, New Hampshire          Troy E. Nehls, Texas
Seth Moulton, Massachusetts          Tracey Mann, Kansas
Marilyn Strickland, Washington       Burgess Owens, Utah
Patrick Ryan, New York               Eric Burlison, Missouri
Val T. Hoyle, Oregon                 Mike Collins, Georgia
Emilia Strong Sykes, Ohio,           Mike Ezell, Mississippi
  Vice Ranking Member                Kevin Kiley, California
Hillary J. Scholten, Michigan        Vince Fong, California
Valerie P. Foushee, North Carolina   Tony Wied, Wisconsin
Christopher R. Deluzio, Pennsylvania Tom Barrett, Michigan
Robert Garcia, California            Nicholas J. Begich III, Alaska
Nellie Pou, New Jersey               Robert P. Bresnahan, Jr., 
Kristen McDonald Rivet, Michigan     Pennsylvania
Laura Friedman, California           Jeff Hurd, Colorado
Laura Gillen, New York               Jefferson Shreve, Indiana
Shomari Figures, Alabama             Addison P. McDowell, North 
Maxwell Frost, Florida               Carolina
                                     David J. Taylor, Ohio
                                     Brad Knott, North Carolina
                                     Kimberlyn King-Hinds,
                                       Northern Mariana Islands
                                     Mike Kennedy, Utah
                                     Robert F. Onder, Jr., Missouri
                                     Jimmy Patronis, Florida
                                     Vacancy

            Subcommittee on Water Resources and Environment

  		Mike Collins, Georgia, Chairman
  		Frederica S. Wilson, Florida, 
          				Ranking Member
John Garamendi, California           Eric A. ``Rick'' Crawford, 
Jared Huffman, California            Arkansas
Patrick Ryan, New York               Thomas Massie, Kentucky
Val T. Hoyle, Oregon                 Brian Babin, Texas
Emilia Strong Sykes, Ohio            Mike Bost, Illinois
Laura Friedman, California           Bruce Westerman, Arkansas
Shomari Figures, Alabama             Brian J. Mast, Florida
Julia Brownley, California           Tracey Mann, Kansas
Mark DeSaulnier, California          Eric Burlison, Missouri
Chris Pappas, New Hampshire          Kevin Kiley, California
Hillary J. Scholten, Michigan,       Vince Fong, California
  Vice Ranking Member                Tony Wied, Wisconsin
Nellie Pou, New Jersey               Jeff Hurd, Colorado
Laura Gillen, New York               David J. Taylor, Ohio, Vice 
Eleanor Holmes Norton,               Chairman
  District of Columbia               Brad Knott, North Carolina
Rick Larsen, Washington (Ex Officio) Robert F. Onder, Jr., Missouri
                                     Jimmy Patronis, Florida
                                     Vacancy
                                     Sam Graves, Missouri (Ex Officio)

                                CONTENTS

                                                                   Page

Summary of Subject Matter........................................   vii

                 STATEMENTS OF MEMBERS OF THE COMMITTEE

Hon. Mike Collins, a Representative in Congress from the State of 
  Georgia, and Chairman, Subcommittee on Water Resources and 
  Environment, opening statement.................................     1
    Prepared statement...........................................     2
Hon. Hillary J. Scholten, a Representative in Congress from the 
  State of Michigan, and Vice Ranking Member, Subcommittee on 
  Water Resources and Environment, opening statement.............     3
    Prepared statement...........................................     4
Hon. Rick Larsen, a Representative in Congress from the State of 
  Washington, and Ranking Member, Committee on Transportation and 
  Infrastructure, opening statement..............................     5
    Prepared statement...........................................     7
Hon. Brian J. Mast, a Representative in Congress from the State 
  of Florida, prepared statement.................................    54

                               WITNESSES

Hon. Adam R. Telle, Assistant Secretary of the Army for Civil 
  Works, Department of the Army, oral statement..................     8
    Prepared statement...........................................    10
Lieutenant General William H. ``Butch'' Graham, Jr., Chief of 
  Engineers and Commanding General, U.S. Army Corps of Engineers, 
  oral statement.................................................    11
    Prepared statement...........................................    12

                       SUBMISSIONS FOR THE RECORD

Submissions for the Record by Hon. Mike Collins:
    Letter of February 24, 2026, from Brandon Farris, Executive 
      Vice President, Steel Manufacturers Association, to Hon. 
      Mike Collins, Chairman, and Hon. Frederica S. Wilson, 
      Ranking Member, Subcommittee on Water Resources and 
      Environment................................................    53
    Prepared Statement of Hon. J. French Hill, a Representative 
      in Congress from the State of Arkansas.....................    54
Letter of February 27, 2026, from Colonel Brandon L. Bowman, 
  District Commander, U.S. Army Corps of Engineers, Jacksonville 
  District, to Hon. Brian J. Mast, Member of Congress, Submitted 
  for the Record by Hon. Brian J. Mast...........................    55

                                APPENDIX

Post-Hearing Questions for the Record to Hon. Adam R. Telle, 
  Assistant Secretary of the Army for Civil Works, Department of 
  the Army, from:
    Hon. Mike Collins............................................    57
    Hon. Eric A. ``Rick'' Crawford...............................    57
    Hon. Jared Huffman...........................................    58
    Hon. Hillary J. Scholten.....................................    59
Post-Hearing Questions for the Record to Lieutenant General 
  William H. ``Butch'' Graham, Jr., Chief of Engineers and 
  Commanding General, U.S. Army Corps of Engineers, from:
    Hon. Mike Collins............................................    59
    Hon. Eric A. ``Rick'' Crawford...............................    59
    Hon. Laura Friedman..........................................    60
Post-Hearing Questions for the Record to Hon. Adam R. Telle, 
  Assistant Secretary of the Army for Civil Works, Department of 
  the Army, and Lieutenant General William H. ``Butch'' Graham, 
  Jr., Chief of Engineers and Commanding General, U.S. Army Corps 
  of Engineers, from:
    Hon. Eric A. ``Rick'' Crawford...............................    62
    Hon. Greg Stanton............................................    63

[GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]


                           February 20, 2026

    SUMMARY OF SUBJECT MATTER

    TO:      LMembers, Subcommittee on Water Resources and 
Environment
    FROM:  LStaff, Subcommittee on Water Resources and 
Environment
    RE:      LSubcommittee Hearing on ``Proposals for a Water 
Resources Development Act of 2026--Administration Priorities''
_______________________________________________________________________


                               I. PURPOSE

    The Subcommittee on Water Resources and Environment of the 
Committee on Transportation and Infrastructure will meet on 
Tuesday, February 24, 2026, at 10:00 a.m. ET in 2167 of the 
Rayburn House Office Building to receive testimony at a hearing 
entitled, ``Proposals for a Water Resources Development Act of 
2026--Administration Priorities.'' The hearing will provide 
Members with an opportunity to ask the Assistant Secretary of 
the Army (Civil Works) and the Chief of Engineers about the 
status of the 2026 Report to Congress on Future Water Resources 
Development, upcoming and prior Chief's Reports, and receive 
testimony and proposals for WRDA 2026 from the Administration.
    At the hearing, Members will receive testimony from the 
Honorable Adam R. Telle, Assistant Secretary of the Army (Civil 
Works) and Lieutenant General William H. ``Butch'' Graham, 
Chief of Engineers and Commanding General, United States Army 
Corps of Engineers.

                             II. BACKGROUND

THE UNITED STATES ARMY CORPS OF ENGINEERS-CIVIL WORKS

    The United States Army Corps of Engineers (Corps) is the 
Federal Government's lead water resource development and 
management agency.\1\ Its mission is to deliver ``vital 
engineering solutions, in collaboration with [their] partners, 
to secure our Nation, energize our economy, and reduce disaster 
risk.'' \2\ The Corps' water resource program dates back to 
1824 when it was established for the purpose of improving river 
navigation.\3\ The role of the Corps has evolved and expanded 
since then to include other main water resource 
responsibilities.
---------------------------------------------------------------------------
    \1\ Corps, About Corps Water Resources Planning, (last accessed 
Feb. 4, 2026), available at 
https://planning.erdc.dren.mil/toolbox/
guidance.cfm?Id=0&Option=Planning%20Fundamentals
&Type=About#::text=The%20U.%20S.%20Army%20Corps%20of.
    \2\ Corps, Mission and Vision, (last accessed Feb. 4, 2026), 
available at https://www.usace.army.mil/About/Mission-and-Vision/.
    \3\ Id.
---------------------------------------------------------------------------
    Today, the Corps' primary civil works responsibilities are 
to support coastal and river navigation, address flood risk 
management and storm damage, and protect and restore aquatic 
ecosystems.\4\ Specifically, through its eight divisions and 44 
district offices, the Corps manages over 14,000 miles of 
levees, 740 dams, 12,000 miles of inland and intercoastal 
waterways, and 218 lock chambers.\5\
---------------------------------------------------------------------------
    \4\ See generally, Anna Normand & Nicole Carter, Cong. Rsch. Serv. 
(IF13112), Water Resources Development Acts: Primer and Action in the 
119th Congress (Sept. 25, 2025), available at https://www.congress.gov/
crs-product/IF13112 [hereinafter CRS Report IF13112].
    \5\ Corps, Value to the Nation, (last accessed Feb. 4, 2026), 
available at https://www.iwr.usace.army.mil/Missions/Value-to-the-
Nation/.
---------------------------------------------------------------------------
    The Corps also provides outdoor recreation opportunities, 
offers water supply storage to state and local partners, 
assists in emergency response, and is a leading producer of 
hydropower in the United States.\6\ Many Corps projects are 
multipurpose, incorporating navigation, flood risk management, 
and/or ecosystem restoration in conjunction with water supply 
and conservation, recreation, and/or hydropower into their 
design, construction, and operation.\7\ The Corps, at its 
sites, sees 269 million recreational visitors a year, provides 
25 percent of the country's hydropower output, and manages 135 
reservoirs with municipal and industrial water supply.\8\ The 
Corps also provides support in responding to natural disasters 
by supporting the Federal Emergency Management Agency (FEMA) 
when requested or through the Flood Control and Coastal 
Emergencies program (often referred to as ``P.L. 84-99'').\9\
---------------------------------------------------------------------------
    \6\ Id.
    \7\ CRS Report IF13112, supra note 4.
    \8\ Corps, Value to the Nation, (last accessed Feb. 4, 2026), 
available at https://www.iwr.usace.army.mil/Missions/Value-to-the-
Nation/.
    \9\ Id.
---------------------------------------------------------------------------
    The Corps' infrastructure portfolio is currently valued at 
$227 billion.\10\ This valuation is referred to as its 
``capital stock'' and includes all water resources 
infrastructure built by the Corps since 1928.\11\ The estimated 
capital stock value increased $7.1 billion on average each year 
until 1982 when it peaked at $393 billion.\12\ The Corps has 
reported that deterioration, general wear and tear of 
infrastructure needs, and asset retirements have contributed to 
a decline in the value of the capital stock.\13\ Furthermore, 
the Corps has a growing construction backlog in addition to 
various authorized but unfunded studies and operation and 
maintenance activities.\14\
---------------------------------------------------------------------------
    \10\ Corps, Capital Stock: Summary, (last accessed Feb. 4, 2026), 
available at https://www.iwr.usace.army.mil/Missions/Value-to-the-
Nation/Fast-Facts/Capital-Stock/Summary/.
    \11\ Id.
    \12\ Id.
    \13\ Id.
    \14\ CRS Report IF13112, supra note 4.
---------------------------------------------------------------------------
    To achieve its civil works mission, the Corps plans, 
designs, and constructs water resources development projects, 
typically in partnership with, and utilizing the financial 
support of non-Federal interests, commonly referred to as 
project sponsors. The Corps' planning process requires that 
Federal water resources investments reflect national 
priorities, encourage economic development, and protect the 
environment, and that the Corps seek to maximize net public 
benefits to society.

WATER RESOURCE DEVELOPMENT ACTS

    Congress generally authorizes Corps studies, projects, and 
programs and makes changes to agency policies through 
legislation referred to as Water Resources Development Acts 
(WRDAs). Congress has developed and enacted WRDAs 
intermittently since the 1980s and has biennially enacted a 
WRDA since 2014.\15\
---------------------------------------------------------------------------
    \15\ Id.
---------------------------------------------------------------------------
    Authorizing provisions in WRDAs can be project-specific, 
programmatic, or general directives for the Corps. Project-
specific authorizations most often fall into one of three broad 
categories: project studies, construction projects, or 
modifications to existing projects. Furthermore, water resource 
projects typically require two types of Congressional 
authorization: (1) authority to study the feasibility of the 
project and (2) authority to construct (and operate and 
maintain, as applicable) the project.\16\
---------------------------------------------------------------------------
    \16\ Id.
---------------------------------------------------------------------------
    Most recently, WRDA 2024 was signed into law as Division A 
of the Thomas R. Carper Water Resources Development Act of 2024 
(P.L. 118-272) in January 2025.\17\ WRDA 2024 authorized 17 new 
construction projects, four project modifications, one project 
for construction based on a feasibility study carried out by a 
non-Federal interest, and over 200 new or modified feasibility 
studies.\18\
---------------------------------------------------------------------------
    \17\ WRDA 2024, Pub. L. 118-272, 138 Stat. 2996.
    \18\ Id.
---------------------------------------------------------------------------
    WRDA 2024 made policy reforms to empower the non-Federal 
sponsors of projects, increase transparency, and improve 
project delivery. For example, WRDA 2024 facilitated the 
creation of Continuing Authorities Program (CAP), a new pilot 
program for alternative project delivery. Additionally, the 
legislation amended sections 203 and 204 of WRDA 1986 to 
clarify and enhance the responsibilities of non-Federal 
interests in conducting studies and construction activities for 
authorized projects.\19\ WRDA 2024 also improved transparency 
and consistency to assist non-Federal entities achieve 
compliance with the P.L. 84-99 program and the process to 
modify existing projects under Section 408.\20\
---------------------------------------------------------------------------
    \19\ Id. at Sec.  1107(a), 1109, 1110.
    \20\ Id. at Sec.  1105, 1146.
---------------------------------------------------------------------------
    Further, WRDA 2024 included the Grace F. Napolitano 
Priority for Water Supply, Water Conservation, and Drought 
Resiliency Act, which emphasizes the Corps' role in water 
supply and water resiliency efforts.\21\ WRDA 2024 instructed 
the Corps to prioritize and maximize water supply, water 
conservation, and drought resiliency efforts that are in 
alignment with the authorized purposes of water resources 
development projects.\22\
---------------------------------------------------------------------------
    \21\ WRDA 2024, supra note 14, at Subtitle B, Title I, Division A, 
138 Stat. 3046.
    \22\ Id. at Sec.  1161, 1162, 1108.
---------------------------------------------------------------------------
    For WRDA 2024, the Corps held a series of listening 
sessions and a 60-day public comment period on implementation, 
which were completed by the end of April 2025.\23\ Through the 
process, the Corps determined which provisions of WRDA 2024 
require specific implementation guidance, and which provisions 
may be implemented without specific guidance. As of February 
10, 2026, the Corps has released implementation guidance for 
three sections of WRDA 2024.\24\
---------------------------------------------------------------------------
    \23\ See Corps, Water Resources Development Act (WRDA) 2024, 
available at https://www.usace.army.mil/Missions/Civil-Works/Project-
Planning/Legislative-Links/wrda_2024/.
    \24\ Id.
---------------------------------------------------------------------------

IDENTIFYING WATER RESOURCE NEEDS

    Generally, the first step in developing a project through 
the Corps is to study the feasibility of the proposed project, 
which typically requires Congressional authorization. Once 
authorized, the Corps enters into a cost-sharing agreement with 
a non-Federal project sponsor to initiate the feasibility 
process. The cost of a feasibility study is usually split 
evenly between the Federal Government, which is subject to 
appropriations, and the non-Federal project sponsor.\25\
---------------------------------------------------------------------------
    \25\ CRS Report IF13112, supra note 4.
---------------------------------------------------------------------------
    Under current law, the feasibility reports should generally 
be produced within four years with a Federal cost of no more 
than $5 million.\26\ Waivers of the feasibility criteria for 
project studies are available under section 1001 of the Water 
Resources Reform and Development Act (WRRDA) of 2014.\27\
---------------------------------------------------------------------------
    \26\ WRDA 2024, Pub. L. 118-272, 138 Stat. 2996.
    \27\ 33 U.S.C. 2282c.
---------------------------------------------------------------------------
    During a feasibility study phase, the Corps' district 
office prepares a draft study report containing a detailed 
analysis on the economic costs and benefits of carrying out the 
project and identifies any associated environmental, social, or 
cultural impacts. The feasibility study typically describes, 
with reasonable certainty, the economic, social, and 
environmental benefits and detriments of project alternatives 
being considered, and identifies the engineering features, 
public acceptability, and the purpose, scope, and scale of 
each.\28\ It also contains the views of other Federal and non-
Federal agencies on project alternatives, a description of non-
structural alternatives to the recommended plans, and a 
description of the anticipated Federal and non-Federal 
participation in the project.\29\
---------------------------------------------------------------------------
    \28\ Id.
    \29\ Id.
---------------------------------------------------------------------------
    In July 2025, the Corps released a revised Engineering and 
Construction Bulletin that established a new design maturity 
threshold before feasibility studies are submitted to Congress 
for authorization.\30\ Under this new policy, the Corps will no 
longer request authority to build a new project before reaching 
an approximately 35 percent design threshold.\31\
---------------------------------------------------------------------------
    \30\ Corps, Engineering and Construction Bulletin, (last updated 
July 29, 2025), available at https://www.wbdg.org/FFC/ARMYCOE/COEECB/
ecb_2023_9_rev_1.pdf.
    \31\ James Leggate, Army Corps Will Advance Designs Further Before 
Seeking Congress' OK to Build, Chief of Engineers Says, ENR (Sept. 25, 
2025), available at https://www.enr.com/articles/61429-army-corps-will-
advance-designs-further-before-seeking-congress-ok-to-build-chief-of-
engineers-says.
---------------------------------------------------------------------------
    After a full feasibility study is completed, the results 
and recommendations of the study are submitted to Congress in 
the form of a Report of the United States Army Corps of 
Engineers Chief of Engineers (more commonly referred to as a 
Chief's Report).\32\ If the results and recommendations on the 
proposed project are favorable, then the next step is 
Congressional authorization for construction of the project, 
which is typically given in a WRDA.
---------------------------------------------------------------------------
    \32\ Corps, Planner's Library, (last accessed Feb. 4, 2026), 
available at https://planning.erdc.dren.mil/toolbox/
library.cfm?Option=Direct&Group=Main&Item=Chief%20Report
&Sub=None&Sort=Default.
---------------------------------------------------------------------------
    Section 902 of WRDA 1986, as amended, generally allows for 
increases in total project costs of up to 20 percent (after 
accounting for inflation of construction costs) without 
additional Congressional authorization.\33\ A Post-
Authorization Change Report (PACR) is developed when an 
authorized project encounters a cost increase greater than 20 
percent of the authorized amount, changes in scope of the 
project, location, or design modifications.\34\ Typically, 
Congress will then consider the PACR for inclusion in a WRDA.
---------------------------------------------------------------------------
    \33\ Anna Normand & Nicole Carter, Cong. Rsch. Serv. (R47946), 
Process for U.S. Army Corps of Engineers Projects (Aug. 29, 2025), 
available at https://www.congress.gov/crs-product/R47946.
    \34\ Wes Coleman & Jeremy LaDart, Post Authorization Change Reports 
(PACRS)--Myths, Mysteries, and Legends, United States Army Corps of 
Engineers, (May 20, 2021), available at https://planning.erdc.dren.mil/
toolbox/webinars/20May21-PACRs.pdf.
---------------------------------------------------------------------------

ADDITIONAL CORPS AUTHORITIES

    The CAP program enables the Corps to undertake small-scale 
projects with limited scope and cost without requiring project-
specific Congressional authorization.\35\ These projects 
typically require a cost-share with a non-Federal project 
sponsor.\36\
---------------------------------------------------------------------------
    \35\ See generally Anna Normand, Cong. Rsch. Serv. (IF12635), 
Continuing Authorities Programs of the U.S. Army Corps of Engineers, 
(updated Aug. 6, 2025), available at https://www.congress.gov/crs-
product/IF12635.
    \36\ Id.
---------------------------------------------------------------------------
    There are currently nine CAP categories:
     LStreambank erosion and shoreline protection; \37\
---------------------------------------------------------------------------
    \37\ See the Flood Control Act of 1946, 33 U.S.C. 701r Sec.  14.
---------------------------------------------------------------------------
     LBeach erosion control; \38\
---------------------------------------------------------------------------
    \38\ See the Act of August 13, 1946, 33 U.S.C. 426g Sec.  3.
---------------------------------------------------------------------------
     LNavigation improvement; \39\
---------------------------------------------------------------------------
    \39\ See the River and Harbor Act of 1960, 33 U.S.C. 577 Sec.  107.
---------------------------------------------------------------------------
     LMitigation of shore damage by Federal navigation 
projects; \40\
---------------------------------------------------------------------------
    \40\ See the River and Harbor Act of 1968, 33 U.S.C. 426(i) Sec.  
11.
---------------------------------------------------------------------------
     LRegional sediment management/beneficial use of 
dredged material; \41\
---------------------------------------------------------------------------
    \41\ See the WRDA 1992, 33 U.S.C. 2326 Sec.  204.
---------------------------------------------------------------------------
     LFlood control; \42\
---------------------------------------------------------------------------
    \42\ See the Flood Control Act of 1948, 33 U.S.C. 701s Sec.  205.
---------------------------------------------------------------------------
     LAquatic ecosystem restoration; \43\
---------------------------------------------------------------------------
    \43\ See the WRDA 1996, 33 U.S.C. 2330 Sec.  206.
---------------------------------------------------------------------------
     LRemoval of obstructions and clearing channels for 
flood control; \44\
---------------------------------------------------------------------------
    \44\ See the Act of August 28, 1937, 33 U.S.C. 701g Sec.  2.
---------------------------------------------------------------------------
     LProject modifications for improvement of the 
environment or drought resiliency; \45\ and
---------------------------------------------------------------------------
    \45\ See the WRDA 1986, 33 U.S.C. 2309a Sec.  1135.
---------------------------------------------------------------------------
     LStormwater management projects.\46\
---------------------------------------------------------------------------
    \46\ See section 1108 of the WRDA 2024, 33 U.S.C. 2289b.

    Congress has also provided authority for the Corps to 
assist with the planning, design, and construction of drinking 
water and wastewater projects in specified areas, known broadly 
as Environmental Infrastructure (EI) assistance.\47\ The EI 
programs support publicly owned and operated facilities, such 
as distribution and collection works, stormwater collection and 
recycled water distribution, and surface water protection and 
development projects.\48\
---------------------------------------------------------------------------
    \47\ WRDA of 1992, Pub. L. No. 102-580, 106 Stat. 4835, Sec.  219.; 
WRDA of 1999, Pub. L. No. 106-53, 113 Stat. 352, Sec.  552.; WRDA of 
2022, Pub. L. No. 117-263, 136 Stat. 3819, Sec.  8376.
    \48\ Corps, Environmental Infrastructure, (last accessed Feb. 4, 
2026), available at https://www.nap.usace.army.mil/Missions/Civil-
Works/Environmental-Infrastructure/.
---------------------------------------------------------------------------

                       III. OUTLOOK FOR WRDA 2026

PENDING CHIEF'S REPORTS AND DIRECTOR'S REPORTS

    Currently, the Committee is in possession of two Chief's 
Reports for possible inclusion in WRDA 2026: Surf City, NC 
Coastal Storm Risk Management (CSRM) study and the Columbia 
River Turning Basin. The Committee has also received one 
Director's Report on the Port Royal Harbor Disposition Study, 
SC.

7001 REPORT

    Section 7001 of the Water Resources Reform and Development 
Act of 2014 (WRRDA 2014) (P.L. 113-121) requires the Corps to 
transmit an annual report to the authorizing committees that 
identifies, for potential Congressional authorization, 
completed feasibility reports, proposed feasibility studies 
submitted by non-Federal interests through a public comment 
period, proposed modifications to authorized water resources 
development projects or feasibility studies, and proposed 
modifications to environmental infrastructure program 
authorities. This report is entitled ``Report to Congress on 
Future Water Resources Development'' and is due by February 1st 
of each year. As of February 20, 2026, the Committee has not 
officially received the 2026 7001 report. The non-Federal 
proposal submission period for the 2026 Report to Congress was 
open from April 17, 2025 through August 15, 2025.\49\
---------------------------------------------------------------------------
    \49\ Proposals by Non-Federal Interests for Inclusion in the Annual 
Report to Congress on Future Water Resources Development, 90 Fed. Reg. 
16114 (April 17, 2025).
---------------------------------------------------------------------------

                             IV. WITNESSES

     LThe Honorable Adam R. Telle, Assistant Secretary, 
United States Army (Civil Works)
     LLt. Gen. William H. ``Butch'' Graham, Jr., Chief 
of Engineers and Commanding General, United States Army Corps 
of Engineers

 
                    PROPOSALS FOR A WATER RESOURCES
                       DEVELOPMENT ACT OF 2026--
                       ADMINISTRATION PRIORITIES

                              ----------                              


                       TUESDAY, FEBRUARY 24, 2026

                  House of Representatives,
   Subcommittee on Water Resources and Environment,
            Committee on Transportation and Infrastructure,
                                                    Washington, DC.
    The subcommittee met, pursuant to call, at 10:02 a.m., in 
Room 2167, Rayburn House Office Building, Hon. Mike Collins 
(Chairman of the subcommittee) presiding.
    Mr. Collins. The Subcommittee on Water Resources and 
Environment will come to order.
    I ask unanimous consent that the chairman be authorized to 
declare a recess at any time during today's hearing.
    Without objection, so ordered.
    I also ask unanimous consent that Members not on the 
subcommittee be permitted to sit with the subcommittee at 
today's hearing and ask questions.
    Without objection, so ordered.
    As a reminder, if Members wish to insert a document into 
the record, please also email it to [email protected].
    I now recognize myself for the purposes of an opening 
statement for 5 minutes.

 OPENING STATEMENT OF HON. MIKE COLLINS OF GEORGIA, CHAIRMAN, 
        SUBCOMMITTEE ON WATER RESOURCES AND ENVIRONMENT

    Mr. Collins. I would like to thank Assistant Secretary 
Telle and Lieutenant General Graham for joining us today as we 
discuss the administration's priorities for the Water Resources 
Development Act of 2026.
    The biennial WRDA bill is the primary way that Congress 
guides the Corps' projects and priorities. It is important for 
the committee to hear directly from the Corps' leaders at the 
beginning of the WRDA process. By authorizing projects and 
studies and providing direction on programmatic changes, WRDA 
bills improve the ability of the Corps to achieve its Civil 
Works missions of navigation, flood control, and ecosystem 
restoration.
    WRDA 2026 will be the seventh WRDA bill since the committee 
returned to the biennial structure in 2014. A dependable 2-year 
WRDA cycle provides the Corps and its non-Federal sponsors an 
opportunity to keep critical water infrastructure projects 
moving forward and respond to local water resource needs more 
effectively.
    An efficient response to the evolving water resource needs 
across the country is vital for our security, safety, and 
economic stability. Our Nation's ports and inland waterways 
move essential goods, support local economies, and provide the 
marine infrastructure that contributes over $500 billion to the 
Nation's GDP. A consistent WRDA process helps to improve and 
maintain our ports and waterways to meet growing needs.
    As I proudly shared last fall, in my home State of Georgia, 
the Port of Savannah achieved its second busiest year ever in 
2025, serving nearly 1,700 containerships and handling around 
15,000 truckload moves daily. This growth and success are 
supported by a consistent and reliable WRDA process.
    I was happy to hear that dredging is finally underway at 
the Port of Brunswick's inner and outer harbor, but it has been 
several years since this vital port received routine 
maintenance dredging. Similar routine dredging projects across 
the country are burdened by an undue regulatory process and 
environmental windows that seems to prevent the consistent 
maintenance of Federal channels. I look forward to hearing from 
today's witnesses to get a better understanding of how we can 
prevent such delays.
    In addition to our Nation's ports, the inland waterways are 
critical arteries for transportation and commerce. Since 
becoming chairman of this subcommittee, I have been able to 
visit several of the Corps' projects across the country, 
including the Wilson and Chickamauga locks in Alabama and 
Tennessee. These critical assets that serve our Nation's 
economic national security are in need of rehabilitation. The 
necessary maintenance for these projects is taking too long and 
costing taxpayers too much.
    In Congress, we have a responsibility to be good stewards 
of taxpayer money. The Corps must do better to complete 
projects on time and on budget. I look forward to hearing about 
ways this can be done from our panel this morning.
    With that, I want to welcome Assistant Secretary Telle and 
Lieutenant General Graham here today to discuss their 
priorities for WRDA 2026.
    [Mr. Collins' prepared statement follows:]

                                 
 Prepared Statement of Hon. Mike Collins, a Representative in Congress 
    from the State of Georgia, and Chairman, Subcommittee on Water 
                       Resources and Environment
    I'd like to thank Assistant Secretary Telle and Lieutenant General 
Graham for joining us today as we discuss the Administration's 
priorities for the Water Resources Development Act of 2026.
    The biennial WRDA bill is the primary way that Congress guides the 
Corps' projects and priorities. It is important for the Committee to 
hear directly from Corps leadership at the beginning of the WRDA 
process. By authorizing projects and studies, and providing direction 
on programmatic changes, WRDA bills improve the ability of the Corps to 
achieve its key civil works missions of navigation, flood control, and 
ecosystem restoration.
    WRDA 2026 will be the seventh WRDA bill since the Committee 
returned to the biennial structure in 2014. A dependable two-year WRDA 
cycle has allowed for the Corps and its non-federal sponsors to keep 
critical water infrastructure projects moving forward and respond to 
local water resource needs more effectively.
    An efficient response to the evolving water resource needs across 
the country is vital for our security, safety, and economic stability. 
Our nation's ports and inland waterways move essential goods, support 
local economies, and provide the marine infrastructure that contributes 
over $500 billion to the nation's GDP. A consistent WRDA process helps 
to improve and maintain our ports and waterways to meet growing needs.
    As I proudly shared last fall, in my home state of Georgia, the 
Port of Savannah achieved its second busiest year ever in 2025, serving 
nearly 1,700 container ships and handling around 15,000 truck moves 
daily. This growth and success are supported by a consistent and 
reliable WRDA process.
    I was happy to hear that dredging is finally underway in the Port 
of Brunswick's inner and outer harbor, but it has been several years 
since this vital port received routine maintenance dredging. Similar 
routine dredging projects across the country are burdened by an undue 
regulatory process and environmental windows that seem to prevent the 
consistent maintenance of federal channels. I look forward to hearing 
from today's witnesses to get a better understanding of how we can 
prevent such delays.
    In addition to our nation's ports, the inland waterways are 
critical arteries for transportation and commerce. Since becoming 
Chairman of this subcommittee, I have been able to visit several Corps 
projects across the country, including the Wilson and Chickamauga Locks 
in Alabama and Tennessee. These critical assets that serve our nation's 
economic and national security are in need of rehabilitation. The 
necessary maintenance for these projects is taking too long and costing 
taxpayers too much.
    In Congress, we have a responsibility to be good stewards of 
taxpayer money, and the Corps must do better to complete projects on 
time and on budget. I look forward to hearing about ways this can be 
done from our panel this morning. With that, I want to welcome 
Assistant Secretary Telle and Lieutenant General Graham here today to 
discuss their priorities for WRDA 2026.

    Mr. Collins. I now recognize Ranking Member Scholten for 5 
minutes for an opening statement.

OPENING STATEMENT OF HON. HILLARY J. SCHOLTEN OF MICHIGAN, VICE 
RANKING MEMBER, SUBCOMMITTEE ON WATER RESOURCES AND ENVIRONMENT

    Ms. Scholten. Thank you, Chair Collins, and welcome to our 
witnesses. Thank you for your commitment to working with the 
committee as we develop what I hope will be a bipartisan, 
robust Water Resources Development Act of 2026.
    At a time when the affordability crisis is affecting every 
corner of our country, and our communities are navigating the 
threats of climate change, it is incumbent on Congress to 
prioritize keeping water resource projects affordable and 
resilient.
    Back home in west Michigan, water is a way of life, and our 
waterways are critical to our regional economies and culture. A 
strong WRDA is absolutely essential for Congress to meet our 
local communities' economic and environmental needs.
    Passing WRDA 2026 is a first step toward granting the Army 
Corps the authority that they need to carry out water resource 
projects and studies. However, we need the funding to back up 
our action.
    It was devastating to see the President's fiscal year 2026 
budget request proposed a nearly 25-percent slash to the Corps' 
budget. Fortunately, Congress rejected this funding cut, but we 
still need to meaningfully address the Corps' backlog of WRDA 
project and maintenance needs, which is currently estimated to 
be over $100 billion, with a ``B.''
    The Trump administration has also been less than diligent 
about the law regarding the Harbor Maintenance Trust Fund and 
those investments. Our ports are critical to our local 
economies as well as our national supply chains.
    Time is not on our side here. The longer we wait, the more 
expensive these projects will become, and our ports will start 
to fall behind. Failing to meaningfully invest in port and 
harbor maintenance and upgrades will threaten job growth, 
reliable supply chains, and global competitiveness.
    We also need full cooperation from our Corps partners to 
navigate the inherently collaborative effort of a new WRDA. 
That is why it is so frustrating that the administration has 
decided that the Corps needs Department of Defense approval 
before district offices can share project details and updates 
with congressional offices.
    We don't need this kind of bureaucratic obstacle. We cannot 
allow partisanship and bureaucracy to undercut this process, 
and I encourage the administration to reverse this policy so 
Congress can best serve the American people.
    I need to warn you, gentlemen, as we look ahead to WRDA 
2026, this subcommittee will be keeping the pressure on you 
two, our Corps leaders, to promptly and effectively implement 
previous WRDA policies, effectively and promptly.
    The pace of implementation is going to be key. When we were 
passing WRDA 2024, we heard nonstop about the glacial pace of 
implementation under the previous administration, but this 
administration, this administration is even slower. What 
happened to the pressure for the pace on implementation?
    We have yet to see guidance on dozens of critical 
provisions, such as to reduce cost share for communities in 
need, to utilize new Continuing Authority Programs, to address 
dredging needs in smaller communities, and to maximize 
opportunities for water supply and conservation where possible.
    It is unacceptable. The Corps must implement the law and 
hold up its end of the bargain to best safeguard our water 
resources.
    I sincerely hope that our conversation today will include 
ideas and solutions on what the Corps needs to execute past 
WRDAs, as well as how we can work together to continue to 
deliver for Americans across the Nation through this year's 
legislation.
    Thank you again for your time. I look forward to the 
conversation.
    I yield back.
    [Ms. Scholten's prepared statement follows:]

                                 
  Prepared Statement of Hon. Hillary J. Scholten, a Representative in 
     Congress from the State of Michigan, and Vice Ranking Member, 
            Subcommittee on Water Resources and Environment
    Thank you, Chair Collins, and welcome to our witnesses. Thank you 
for your commitment to working with the Committee as we develop what I 
hope will be a bipartisan, robust Water Resources Development Act of 
2026.
    At a time when the affordability crisis is affecting every corner 
of our country and communities are navigating the threats of climate 
change, it is incumbent on Congress to prioritize keeping water 
resource projects affordable and resilient.
    Back home in West Michigan, water is a way of life, and our 
waterways are critical to our regional economies and culture. A strong 
WRDA is absolutely critical for Congress to meet our local communities' 
economic and environmental needs.
    Passing WRDA 2026 is the first step towards granting the Army Corps 
the authority they need to carry out water resource projects and 
studies.
    However, we need the funding to back up our action.
    It was devastating to see that the President's Fiscal Year 2026 
budget request proposed a nearly 25 percent slash to the Corps' budget.
    Fortunately, Congress rejected this funding cut; but, we still need 
to meaningfully address the Corps' backlog of WRDA project and 
maintenance needs, currently estimated to be over $100 billion.
    The Trump Administration has also been less than diligent about the 
law regarding harbor maintenance trust fund (HMTF) investments. Our 
ports are critical to our local economies as well as our national 
supply chains.
    Time is not on our side: the longer we wait, the more expensive 
these projects will become and our ports may start to fall behind. 
Failing to meaningfully invest in port and harbor maintenance and 
upgrades will threaten job growth, reliable supply chains, and global 
competitiveness.
    We also need full cooperation from our Corps partners to navigate 
the inherently collaborative effort of a new WRDA. That's why it is so 
frustrating that the Administration has decided that the Corps needs 
the Department of Defense's approval before district offices can share 
project details and updates with Congressional offices.
    We cannot allow partisanship and bureaucracy to undercut this 
process, and I encourage the Administration to reverse this policy so 
Congress can best serve the American people.
    As we look ahead to WRDA 2026, this subcommittee will still be 
keeping the pressure on you two, our Corps Leaders, to promptly and 
effectively implement previous WRDA policies.
    We have yet to see guidance on dozens of critical provisions, such 
as to reduce cost share for communities in need; to utilize new 
Continuing Authority Programs; to address dredging needs in smaller 
communities; and to maximize opportunities for water supply and 
conservation where possible.
    This is unacceptable; the Corps must implement the law and hold up 
its end of the bargain to best safeguard our water resources.
    I hope our conversation today will include ideas and solutions on 
what the Corps needs to execute past WRDAs, as well as how we can work 
together to continue to deliver for Americans across the nation through 
this year's new legislation.
    Thank you, I yield back.

    Mr. Collins. I now recognize the ranking member of the full 
committee, Mr. Larsen, for 5 minutes for an opening statement.

 OPENING STATEMENT OF HON. RICK LARSEN OF WASHINGTON, RANKING 
     MEMBER, COMMITTEE ON TRANSPORTATION AND INFRASTRUCTURE

    Mr. Larsen of Washington. Thank you, Chair Collins and Vice 
Ranking Member Scholten, for holding the hearing. And welcome 
back, Assistant Secretary Telle and Lieutenant General Graham. 
Thank you for being here this morning.
    Since 2014, this committee has honored its commitment to 
meet local water resource needs across the country through 
bipartisan and biennial enactment of the Water Resources 
Development Act.
    Predictable WRDAs support Corps projects while creating 
good-paying jobs in the construction industry and supporting 
countless more jobs in the U.S. industries and businesses that 
benefit directly from these projects. Regular enactment of 
WRDAs also provides critical policy reforms that improve the 
function and flexibility of the Corps to respond to local 
challenges. Failure to implement WRDA on time results in delays 
and denies critical economic, environmental, and societal 
benefits to communities across the country.
    Each Presidential administration wants to put its own mark 
on the management of Federal agencies, and based on your ideas 
for reducing paperwork at the Corps, we are starting to 
understand your priorities.
    However, no administration gets to ignore the law and to 
manage Federal agencies as they please, untethered from the 
legal obligations that Congress mandates.
    For example, as of yesterday, this administration has 
formally implemented only three provisions from the Water 
Resources Development Act of 2024 enacted in January 2025. 
Three. This means that bipartisan benefits that an overwhelming 
majority of Republican and Democratic Members of the House and 
Senate enacted are not reaching their communities.
    Failure to implement WRDA 2024 denies the country the 
benefits of 21 Chief's Reports that had authorized benefits 
such as upgraded navigation, flood risk reduction, and storm 
protection projects, as well as ecological restoration and the 
societal benefits associated with these projects.
    Failure to implement WRDA 2024 means that small, rural, 
Tribal, and other communities will continue to struggle to meet 
local challenges as these projects remain unaffordable.
    Failure to implement WRDA 2024 increases the vulnerability 
of America's navigational capacity, both through its coastal 
and inland ports, as well as the vulnerability of communities 
to the challenges of climate change and drought. This 
administration needs to do better.
    At today's hearing, I expect to hear you recognize Congress 
as an essential partner in directing and scoping how the Corps 
implements its missions.
    I also expect to hear that you will work diligently to make 
sure that every enacted provision of existing WRDAs is fully 
implemented in a timely fashion and that you will provide the 
committee with periodic updates on your progress.
    This committee recently closed its Member portal that 
contains roughly 2,400 project, policy, and environmental 
infrastructure requests for the upcoming WRDA for 2026.
    Based on Member requests, my top-line priorities for WRDA 
2026 will be: ensuring that we authorize the next generation of 
local water resource projects and studies; ensuring that all 
communities, including rural, small, and Tribal communities, 
can affordably partner with the Corps to resolve local 
challenges; and ensuring that all Corps projects are designed 
to meet the challenges of climate change and make communities 
more resilient to stronger storms, rising sea levels, and 
severe droughts.
    I look forward to today's testimony and my continued 
partnership with the chair of the full committee, the chair of 
this subcommittee, and the ranking member and vice ranking 
member to develop a bill in our traditional bipartisan fashion.
    With that, I yield back.
    [Mr. Larsen of Washington's prepared statement follows:]

                                 
 Prepared Statement of Hon. Rick Larsen, a Representative in Congress 
    from the State of Washington, and Ranking Member, Committee on 
                   Transportation and Infrastructure
    Thank you, Chairman Collins and Vice Ranking Member Scholten, for 
holding this hearing.
    Welcome back, Assistant Secretary Telle and Lieutenant General 
Graham. Thank you for being here this morning.
    Since 2014, this Committee has honored its commitment to meet local 
water resources needs across the country through the bipartisan and 
biennial enactment of Water Resources Development Acts (WRDAs).
    Predictable WRDAs support Corps projects while creating good-paying 
jobs in the construction industry and supporting countless more jobs in 
the U.S. industries and businesses that benefit directly from these 
projects.
    Regular enactment of WRDAs also provides critical policy reforms 
that improve the function and flexibility of the Corps to respond to 
local challenges.
    Failure to implement WRDA on time results in delays and denies 
critical economic, environmental and societal benefits to communities 
across the country.
    Each presidential administration wants to put its own mark on 
management of federal agencies--and based on your ideas for reducing 
paperwork at the Corps, we are starting to understand your priorities.
    However, no administration gets to ignore the law and to manage 
federal agencies as they please, untethered from their legal 
obligations mandated by Congress.
    For example, as of yesterday, this administration has formally 
implemented only three provisions from the Water Resources Development 
Act of 2024, enacted in January of 2025.
    Three provisions.
    This means that the bipartisan benefits enacted by an overwhelming 
majority of Republican and Democratic members of the House and Senate 
are not reaching their communities.
    Failure to implement WRDA 2024 denies our country the benefits of 
the 21 Chief's Reports it authorized--benefits such as upgraded 
navigation, flood risk reduction and storm protection projects, as well 
as ecological restoration and the societal benefits associated with 
these projects.
    Failure to implement WRDA 2024 means that small, rural, Tribal, and 
other communities will continue to struggle to meet local challenges as 
these projects remain unaffordable.
    Failure to implement WRDA 2024 increases the vulnerability of 
America's navigational capacity--both through its coastal and inland 
ports--as well as the vulnerability of communities to the challenges of 
climate change and drought.
    This administration needs to do better.
    At today's hearing, I expect to hear that you recognize Congress as 
an essential partner in directing and scoping how the Corps implements 
its missions.
    I also expect to hear that you will work diligently to make sure 
that every enacted provision of existing WRDAs is fully implemented in 
a timely fashion and that you will provide this Committee with periodic 
updates on your progress.
    This Committee recently closed its member portal that contains 
roughly 2,400 project, policy and environmental infrastructure requests 
for the upcoming WRDA 2026.
    Based on our member requests, my top-line priorities for WRDA26 
will be:
      Ensuring that the next generation of local water 
resources projects and studies is authorized;
      Ensuring that all communities, including rural, small and 
Tribal communities, can affordably partner with the Corps to resolve 
local challenges; and
      Ensuring that all Corps projects are designed to meet the 
challenges of climate change and make communities more resilient to 
stronger storms, rising sea-levels and severe droughts.

    I look forward to today's testimony and my continued partnership 
with Chairman Graves, Chairman Collins, Ranking Member Wilson and Vice 
Ranking Member Scholten to develop this bill in our traditional 
bipartisan fashion.

    Mr. Collins. I would now like to welcome our witnesses and 
thank them for being here today. Briefly, I know I don't need 
to, but I am going to take a moment just to explain our 
lighting system.
    There are three lights in front of you. Green means to 
continue, yellow means you are running out of time, and when it 
turns red, please conclude your remarks.
    I ask unanimous consent that the witnesses' full statements 
be included in the record.
    Without objection, so ordered.
    I ask unanimous consent that the record of today's hearing 
remain open until such time as our witnesses have provided 
answers to any questions that may be submitted to them in 
writing.
    Without objection, so ordered.
    I also ask unanimous consent that the record remain open 
for 15 days for any additional comments and information 
submitted by Members or witnesses to be included in the record 
of today's hearing.
    Without objection, so ordered.
    As your written testimony has been made part of the record, 
the subcommittee asks that you limit your oral remarks to 5 
minutes.
    With that, Mr. Telle, you are recognized for 5 minutes for 
your testimony.

  TESTIMONY OF HON. ADAM R. TELLE, ASSISTANT SECRETARY OF THE 
 ARMY FOR CIVIL WORKS, DEPARTMENT OF THE ARMY; AND LIEUTENANT 
 GENERAL WILLIAM H. ``BUTCH'' GRAHAM, Jr., CHIEF OF ENGINEERS 
      AND COMMANDING GENERAL, U.S. ARMY CORPS OF ENGINEERS

  TESTIMONY OF HON. ADAM R. TELLE, ASSISTANT SECRETARY OF THE 
          ARMY FOR CIVIL WORKS, DEPARTMENT OF THE ARMY

    Mr. Telle. Thank you, Chairman Collins.
    Chairman Collins, Ranking Member Larsen, Ranking Member 
Scholten, and distinguished members of the committee, thank you 
for the opportunity to be here today to discuss the development 
of the proposed Water Resources Development Act of 2026.
    Before I get started, I want to recognize the passing of 
Congressman Doug LaMalfa, who was an outstanding member of this 
committee, someone who was a passionate advocate for 
California's water issues and someone who taught me, as I am 
sure he did many members of this committee, all about 
California water. And so we miss him.
    I am eager to share with you my perspective after 6 months 
as the Assistant Secretary of the Army for Civil Works, 
including what the Corps of Engineers is doing well and where 
significant reform is warranted. I hope my perspective is 
valuable to you as you develop proposals for WRDA 2026.
    I also wish to share an update on the implementation of 
past WRDAs, which was just raised. It remains a topic of 
critical interest to members of this committee. Since my last 
appearance before this committee, the Army Civil Works program 
has finalized implementation guidance for the remaining 
provisions of WRDA 2020 and WRDA 2022, with the exception of 
provisions modified further by WRDA 2024.
    WRDA is the law. We are following it. The last three WRDAs 
included 552 provisions, and we are developing guidance for the 
remaining 19 of those provisions. I just signed implementation 
guidance for two of them yesterday. We are going to make sure 
they are consistently implemented through this guidance.
    I remain committed to completing the implementation 
guidance as soon as practicable and look forward to working 
with this committee to identify opportunities to improve the 
process for implementing future WRDAs.
    One thing I have observed to this point is that the Army 
Corps of Engineers is at its very best when it is responding to 
emergencies, where it is unburdened by redtape, and enters what 
we like to call Army mode. Specific examples of that come to 
mind, including the Corps' execution of assignments to clear 
and remove debris after Hurricane Helene throughout Appalachia, 
particularly in western North Carolina, and after the 2025 Los 
Angeles wildfires.
    Last August, the Corps successfully supplemented State and 
local efforts in anticipation of glacial outburst flooding in 
Juneau, Alaska. And finally, just last month, the Corps 
executed assignments in response to Winter Storm Fern across 
the Southeastern United States. And we are currently responding 
to the disaster in the Potomac River.
    But when it comes to our primary missions, our everyday 
missions, for decades the Army Civil Works program hasn't 
really had a plan. The status quo has been to execute 
everything all at once, moving each project down the yellow 
brick road of redtape 1 inch at a time, resulting in 
inexplicable delays, including to projects that are of 
strategic national importance. Meanwhile, reaching paperwork 
milestones is elevated as evidence of achievement.
    This is simply unacceptable for an agency that is so 
important to the safety and prosperity of the American people. 
Stacks of important Government paperwork have never saved an 
American life or community except perhaps in very cold weather 
when no other fuel is available.
    We have to change the way the Army Civil Works program 
conducts its business or the next decades will be more of the 
same. The stars are aligned under President Trump's leadership 
to change this now.
    We have in hand $45 billion that the Congress has 
previously appropriated to our programs, but the Corps has not 
yet executed. Shockingly, $15 billion of this funding is more 
than 6 years old.
    We also have many ongoing projects that the Congress has 
authorized and that the Corps is building, but that require 
significant additional funding to complete. The status quo 
approach is insufficient, meaning we will never deliver on what 
you expect of us without fundamentally changing our behavior.
    To meet this challenge, yesterday we unveiled a plan that 
we call Building Infrastructure, Not Paperwork. It is a plan 
that was partially inspired by members of this committee and 
particularly the chairman of this subcommittee.
    It is comprised of approximately 27 individual but 
complementary initiatives to start to reimagine and rejuvenate 
the Army Civil Works program. And with your support, this will 
be the most significant transformation of the program since at 
least 1986.
    Through this suite of strategic initiatives, it is my goal 
to harmonize the Army Civil Works program and to realign and 
rightsize the incentive structures of the Corps of Engineers, 
with an emphasis again on building infrastructure and not 
paperwork.
    This new plan is driven by a sense of urgency. Our strategy 
is centered on a fundamental cultural transformation to enhance 
our effectiveness and restore discipline. We are sharpening our 
focus on our primary missions under a strategic plan that will 
deliver on the mandate you have given us.
    To accelerate project delivery, we are implementing smarter 
contracting practices, upholding higher design standards, and 
reforming our partnership pipeline to build what America needs 
faster and more cost-effectively.
    A key component to this transformation is overhauling our 
internal processes. But as President Trump has directed and as 
bipartisan members of this committee have directed, cutting 
bureaucratic redtape by reforming our entire regulatory 
permitting system is important to provide fast, clear, and 
consistent decisions to the public.
    I see I am running out of time, so I will submit the 
remainder of my statement for the record, but I look forward to 
your questions. Thank you.
    [Mr. Telle's prepared statement follows:]

                                 
 Prepared Statement of Hon. Adam R. Telle, Assistant Secretary of the 
              Army for Civil Works, Department of the Army
    Chairman Collins, Ranking Member Wilson, and distinguished members 
of the committee, thank you for the opportunity to be here today to 
discuss the development of the proposed Water Resources Development Act 
of 2026. I am eager to share with you my perspective after six months 
as the Assistant Secretary of the Army for Civil Works, including what 
the Corps of Engineers is doing well and where significant reform is 
warranted. I hope my perspective is valuable to you as you develop 
proposals for WRDA 2026.
    I also wish to share an update on the implementation of past WRDAs, 
which remains a topic of critical interest to members of this 
committee. Since my last appearance before this committee, the Army 
Civil Works Program has finalized implementation guidance for the 
remaining provisions of WRDA 2020 and 2022 that warranted such 
guidance, with the exception of provisions from WRDA 2020 that were 
modified in WRDA 2024. WRDA is the law, and we are implementing the 
law. Of the 552 provisions included in those three laws, we are 
developing additional guidance for 19 provisions to ensure consistent 
implementation across the Corps. I remain committed to completing the 
implementation guidance as soon as practicable and look forward to 
working with this committee to identify opportunities to improve the 
processes for implementing future WRDAs.
    One thing I've observed in my short tenure is that the Army Corps 
of Engineers is at its very best when responding to emergencies, where 
it is unburdened by red tape, and enters Army mode. Specific examples 
that come to mind include the Corps' execution of Federal Emergency 
Management Act (FEMA) assignments to clear and remove debris after 
Hurricane Helene in Western North Carolina and throughout Appalachia 
and after the 2025 Los Angeles wildfires. Last August, the Corps 
successfully supplemented state and local efforts under PL 84-99 in 
anticipation of glacial outburst flooding in Juneau, Alaska. Finally, 
just last month, the Corps executed FEMA assignments in response to 
winter storm Fern.
    But when it comes to our primary missions, for decades, the Army 
Civil Works Program hasn't really had a plan. The status quo has been 
to execute everything all at once, moving each project down the yellow 
brick road of red tape one inch at a time, resulting in inexplicable 
delays, including projects that are of strategic national importance. 
Meanwhile, reaching paperwork milestones is elevated as evidence of 
achievement. This is simply unacceptable for an agency that is so 
important to the safety and prosperity of the American people. Stacks 
of important government paperwork have never saved an American life or 
community, except perhaps in very cold weather when no other fuel is 
available. We have to change the way the Army Civil Works Program 
conducts business, or the next decades will be more of the same.
    We have in hand $45 billion that the Congress has previously 
appropriated, but the Corps has not yet delivered. Shockingly, $15 
billion of this funding is more than six years old. We also have many 
ongoing projects, which the Congress has authorized and the Corps is 
building, which will require significant additional funding to 
complete. The status quo approach is insufficient, meaning we will 
never deliver on what you expect of us without fundamentally changing 
our behavior.
    To meet this challenge, we have unveiled a plan comprised of 
approximately 27 individual but complementary initiatives to reimagine 
and rejuvenate the Army Civil Works program. This will be the most 
significant transformation of the program since at least 1986, which 
was a watershed year for the authorities of the Program.
    Through this suite of strategic initiatives, it is my goal to 
harmonize the Army Civil Works Program and to realign and right-size 
the incentive structures of the Corps of Engineers, with an emphasis on 
building infrastructure, not paperwork.
    This new plan is driven by a sense of urgency. Our strategy is 
centered on a fundamental cultural transformation to enhance our 
effectiveness and restore discipline. We are sharpening our focus on 
core missions that serve the national interest under a strategic plan 
that will deliver on the mandate you've given us. To accelerate project 
delivery, we are implementing smarter contracting practices, upholding 
higher design standards, and reforming our partnership pipeline to 
build what America needs, faster and more cost-effectively.
    A key component of this transformation is overhauling our internal 
processes. As President Trump has directed, and bipartisan members of 
this committee have called for, we are cutting bureaucratic red tape by 
reforming the entire regulatory and permitting system to provide fast, 
clear, and consistent decisions. This will eliminate costly delays and 
accelerate our economy at a time that we find ourselves in a global 
competition that will determine whether the United States of America 
remains the greatest nation in the history of the world. Internally, we 
are making the organization leaner and more effective by optimizing our 
assets, modernizing operations, and ensuring all messaging aligns with 
our primary missions.
    Finally, we are instilling a new culture of fiscal discipline and 
operational excellence by fundamentally overhauling our financial and 
operational practices to attack waste and inefficiency. We are 
committed to executing our mission with a higher standard of integrity, 
ensuring every dollar is spent with purpose to achieve clear, 
measurable results for the American people.
    President Trump, Secretary Hegseth, and Secretary Driscoll want to 
deliver infrastructure now, and our partners in Congress are tired of 
decades-long delays and cost overruns. The time is right for this 
change, and we have a unique opportunity to transform the way the Corps 
of Engineers conducts its business to meet this moment in history.
    Thank you, and I look forward to your questions.

    Mr. Collins. Thank you.
    Next, General Graham, you are recognized for 5 minutes for 
your testimony.

 TESTIMONY OF LIEUTENANT GENERAL WILLIAM H. ``BUTCH'' GRAHAM, 
Jr., CHIEF OF ENGINEERS AND COMMANDING GENERAL, U.S. ARMY CORPS 
                          OF ENGINEERS

    General Graham. Chairman Collins, Vice Ranking Member 
Scholten, Ranking Member Larsen, I am honored to testify before 
you today in regard to the 2026 Water Resources Development 
Act.
    Through the Civil Works program, the Army Corps works with 
our partners to study, build, and operate water resource 
projects focusing on our three main mission areas of commercial 
navigation, flood and coastal storm damage reduction, and 
aquatic ecosystem restoration.
    Breaking those down, the navigation program, which consists 
of our coastal Great Lakes channels as well as the inland 
rivers and intercoastal waterways, underpins much of the 
national economy, ensuring that commodities can move reliably 
and efficiently.
    Our flood and coastal storm damage reduction program 
maintains 746 dams, over 13,000 miles of Federal levees, and 
450 miles of shore protection that provide, on average, $200 
billion per year in flood damages avoided.
    To continuously maintain and improve these mission areas, I 
want to thank this subcommittee for supporting the Corps Civil 
Works program. Your commitment, as we heard from the chair, 
since 2014 to pass biennial Water Resources Development Acts, 
has provided us with the authorities necessary to address the 
changing needs of the Nation's water resources infrastructure.
    We deeply value the authorities you have entrusted to us. 
Our pledge is to put them to work to deliver for the American 
people. To that end, the Army Corps' objective each and every 
day is to safely and efficiently deliver quality studies and 
projects on schedule within budget.
    Our current on-schedule rate, as I measured it this 
morning, for the Civil Works portfolio is 86 percent. That is 
an improvement from the 80 percent that I reported to this 
subcommittee back in September.
    So by focusing on the basics of getting the engineering 
right, of getting the project management right, and of getting 
the project delivery team right, we are making our cost 
estimates more reliable and our project delivery more 
efficient.
    That said, there is more work to do, more improvements to 
make. To that end, we are very excited about the Building 
Infrastructure, Not Paperwork initiative that Mr. Telle 
outlined. These improvements, delivered by district engineers 
who are empowered to manage risk, not avoid it, will allow the 
Army Corps to make the changes necessary to best deliver our 
important infrastructure mission for the Nation.
    Finally, I, too, would also like to take a moment to 
express our deepest condolences to the family, friends, and 
colleagues of Congressman LaMalfa of California. We will do our 
best to honor his passion, his absolute passion for the Federal 
water resources mission by continuing our efforts to optimally 
balance our flood risk management responsibilities with growing 
water supply needs.
    Thank you for the opportunity to testify before you today, 
and I look forward to addressing your questions.
    [General Graham's prepared statement follows:]

                                 
 Prepared Statement of Lieutenant General William H. ``Butch'' Graham, 
  Jr., Chief of Engineers and Commanding General, U.S. Army Corps of 
                               Engineers
    Chairman Collins, Ranking Member Wilson, and Members of the 
Subcommittee:
    Before I proceed with my testimony, I would like to take a moment 
to express my deepest condolences to the family, friends, and 
colleagues of Congressman Doug LaMalfa of California, who passed 
earlier this year. He was not only an esteemed member of this 
committee, but also a dedicated public servant whose contributions to 
water resources policy will have a lasting impact on our Nation.
    I am honored to testify before your committee today, along with Mr. 
Adam Telle, the Assistant Secretary of the Army for Civil Works, 
regarding the development of the Water Resources Development Act (WRDA) 
of 2026. I look forward to continuing our work with this committee, the 
Congress, and the Administration to help address the Nation's water 
resources challenges.
    Through the Civil Works Program, the Corps works with other Federal 
agencies, and with state, Tribal, and local agencies and others, to 
develop, manage, restore, and protect water resources, primarily 
through the construction, operation and maintenance, and study of 
water-related infrastructure projects. The Corps focuses on work that 
provides high economic, environmental, and public safety returns to the 
Nation. The Corps also regulates development in waters of the United 
States and works with other Federal agencies to help communities 
respond to, and recover from, floods and other natural disasters.
    The authorizations and funding that Congress provides to the Corps 
allow us to advance our three main missions of commercial navigation, 
flood and storm damage reduction, and aquatic ecosystem restoration, as 
well as support related project purposes, such as water supply, 
hydropower, and recreation. The Civil Works program is performance-
based and focuses on high-performing projects and programs within these 
three main mission areas. The Corps uses its engineering expertise and 
relationships with project sponsors and other stakeholders to develop 
innovative approaches to address some of the most pressing water 
resources challenges facing the Nation. Since 2014, the Congress has 
passed a WRDA bill every two years to address evolving water resources 
issues.
    WRDA 2024 advances the Corps' principal Civil Works missions. The 
legislation reinforces the Corps' partnership with non-federal sponsors 
by refining existing programs, while introducing new tools to enhance 
coordination with non-federal partners, improve project delivery, and 
address evolving national priorities.
    To promote long-term infrastructure resilience and to support 
coastal and riverine communities, WRDA 2024 provides expanded authority 
for forecast-informed reservoir operations and supports beneficial use 
of dredged material for shoreline restoration and flood risk reduction. 
It also authorizes recurring coastal mapping activities to ensure 
timely data for navigation safety and storm preparedness. Across all 
mission areas, WRDA 2024 includes provisions to streamline project 
implementation, facilitate crediting for non-federal contributions such 
as technical models, and improve transparency in project 
prioritization, strengthening the Corps ability to deliver safe, high-
quality water resources infrastructure that supports both local 
communities and national economic interests.
    My primary commitment is the successful execution of the Army Civil 
Works Program, ensuring projects are completed safely, on schedule, and 
within budget. I remain focused on implementing strategies to make our 
project delivery more efficient and our cost estimates more reliable. 
By improving our initial planning and design phases and applying 
rigorous risk management, we are enhancing the accuracy of our 
timelines and budgets. Furthermore, we are boosting our engagement with 
industry partners through early collaboration and market research to 
align our goals and secure more competitive proposals.
    A successful Civil Works program depends on efficient project 
delivery and close partnerships with stakeholders at all levels. We are 
actively refining the early stages of our projects and managing risks 
to ensure every infrastructure investment delivers net national 
benefits cost-effectively. Ultimately, these priorities mean a better 
deal for the taxpayer and a better future for all Americans.
    Thank you, Chairman Collins, Ranking Member Wilson, and Members of 
the Subcommittee. This concludes my statement. I look forward to 
answering any questions you or other Members of the Subcommittee may 
have.

    Mr. Collins. Thank you. I ask unanimous consent to enter 
into the record a statement from the Steel Manufacturers 
Association dated February 24, 2026.
    Without objection, so ordered.
    [The information is on page 53.]
    Mr. Collins. I want to thank you both for your testimony. 
We will now turn to questions from the panel, and I will 
recognize myself for 5 minutes for questions.
    Assistant Secretary Telle, when you were here last 
September, you stated that you supported the idea of delegating 
some authorities to improve efficiency in the Corps' process, 
especially when it comes to the recreation mission of the 
Corps.
    Does the Corps have the authority in the law to do this 
now, and, if anything, what do you need from Congress to carry 
this out?
    Mr. Telle. Chairman Collins, thank you for the question. 
Absolutely, the Corps has the authority to do this now. It is 
something that we should be taking advantage of.
    As an update on recreation, we are in a good spot in terms 
of hiring our organic employees for the coming spring and 
summer seasons, 188 individuals on board, which is 59 percent 
of our goal. We have gotten after it early.
    But delegation of these missions can be a critical way to 
expand our throughput and ensure we don't have future mishaps.
    Mr. Collins. Don't you think it would also help with some 
of the things that you are looking at internally to help 
improve efficiency and productivity and focus on what the Corps 
really needs to be focused on?
    Mr. Telle. Chairman Collins, you are absolutely right. This 
committee has given us authorities. I think about section 203, 
section 204, section 1043. This committee has spoken loud and 
clear that the Corps ought to take advantage of capable non-
Federal partners.
    If you think about the backlog that was mentioned earlier, 
the projects we have been authorized to perform that we are not 
performing, we need to expand our throughput. We have a limited 
amount of throughput. We need to reserve Corps of Engineers' 
engineering excellence for the largest challenges that confront 
our country. We need to take advantage of the capabilities of 
our non-Federal sponsors to expand the number of people in our 
country that are getting after all of these challenges that you 
all address.
    You have given us the authorities to do that. 
Unfortunately, to date, in my view, we have not taken full 
advantage of them. There has been a cultural challenge related 
to districts wanting to hold onto work for themselves. And, in 
my view, we have got to get everybody in the business of 
building America's infrastructure and reducing paperwork.
    Mr. Collins. Right. I think in so doing that, it also is 
going to speed up the time that the project is going to take, 
and it also helps save money.
    Mr. Telle. Mr. Chairman, you are absolutely right. I have 
seen instances at projects across our country where the price 
we are paying for dredging, for instance, may be 40, 50 or 60 
percent higher than the price that one of our ports might be 
paying for that dredging.
    And so, as often as we can delegate our responsibilities 
with oversight, of course, to meet the standards that this 
committee has put forth, we can expand our capability and often 
get a better price and better schedule by utilizing our non-
Federal sponsors.
    Mr. Collins. Right.
    And having said that, General Graham, section 8133 of WRDA 
2022 established the inland waterways regional dredge pilot 
program to award contracts up to 5 years for these dredging 
projects.
    Can you speak about the cost-effectiveness, the 
reliability, and the performance of this program?
    General Graham. Chairman Collins, thank you for that 
question. Absolutely. By looking regionally, we can get, well, 
put simply, a much better deal. And we also provide much more 
flexibility on when and where we dredge.
    Under Secretary Telle's guidance, we are looking to expand 
that beyond just a regional look to take advantage of all of 
the dredging that the Corps does.
    We are the largest buyer of dredging services in the 
Nation, and we ought to use that market power to get the best 
deal possible for the American taxpayers.
    Mr. Collins. Yes. I always have said the customer is king. 
So, I mean, I think if you look at it from that angle, then you 
have the upper hand and can negotiate not just maybe one 
dredging project, but multiple dredging projects. And let your 
dredging organization or the company that gets it, let them set 
their schedule, as long as it falls within our guidelines.
    All right. Do you consider multiyear contracting as an 
effective way to reduce these dredging costs?
    General Graham. Chairman Collins, absolutely. And as we 
discussed earlier, by looking nationwide, putting in broad 
multiyear contracts, we believe we will be able to get the best 
deal for the American taxpayers.
    Mr. Collins. Yes. I know when we were talking not too long 
ago about just the fact of how much it costs to actually--when 
you have to move a dredge off of a project and they could have 
been moving towards another project, but then you've got to pay 
them to move to that project. So you are actually saving a lot 
of money.
    And, Assistant Secretary, I don't know if you want to join.
    Mr. Telle. Chairman Collins, you are right. In addition to 
expanding our scope nationally, where we are a better 
negotiator across the negotiating table from private industry 
who are our partners, there is a challenge we have related to 
some of the environmental restrictions that often haven't been 
even reexamined in decades.
    I like to equate it to your spouse asking you to run 10 
errands on a Saturday, but requiring you to go to the post 
office, Walmart, the Home Depot, and to soccer practice in a 
specific order all across town. You can't do it in the most 
efficient way to execute your mission.
    And that is how we are doing dredging today. We are sending 
our dredgers here and there based on these environmental 
schedules. If we can reduce that burden on them, we can get a 
much more efficient product for the taxpayer.
    Mr. Collins. That's right. And a lot of times we make them 
come back home and then go to the next one and then come back 
home. And it just is not very efficient.
    I know I am out of time. With that, I now yield 5 minutes 
to Ms. Scholten.
    Ms. Scholten. I think you could get a working mom to work 
that schedule for you, Mr. Telle. We will give you a schedule 
for those errands on a Saturday. I joke. I joke.
    Assistant Secretary, the last time you testified before the 
subcommittee, I discussed how Grand Haven Inner Harbor almost 
missed a dredging cycle, which would have threatened the 
harbor's 450 jobs and carried $88 million in annual economic 
impact.
    After months of advocacy, local, State, Federal levels 
finally struck a compromise to dredge about 90 percent of the 
harbor to ensure that ships could move through the channel 
without light loading.
    However, the remainder of the harbor, that 10 percent, even 
though it is smaller, is critical, essential, right? If you 
can't get through that 10 percent, we can't get through at all.
    The State needs to conduct sediment testing to determine if 
the area has been contaminated by PFAS. On February 5th, 2026, 
I sent a letter to the State as well as the Corps to understand 
the extent of which the two are working together already to 
engage in advanced planning to address the dredging of this 
potentially contaminated water. I received a thorough, timely 
response from the State of Michigan, but have not received 
clarity from the Corps yet.
    One of my top priorities for WRDA 2026 is boosting 
collaboration and advanced planning between State and Federal 
leaders so that we can get to this quicker pace of these 
projects rolling out, right? Efficiency and effectiveness is 
what it's all about.
    So can you first commit to sending a written response to my 
February 5th inquiry? And additionally, can you speak to how 
critical it is for the Corps to work with its State partners to 
ensure timeliness here?
    Mr. Telle. Ranking Member Scholten, thank you for the 
question. You are hitting on something that is absolutely true 
in Michigan. It is true across the country.
    Dredging is the lifeblood of our economy. It is the hidden 
part of our economy that most Americans don't fully appreciate. 
It is the arteries of--dredging in our ports, our waterways are 
the arteries of competition and the arteries of our success. 
Everywhere that we can do this, we need to be doing it.
    I will commit to get you a written response to your letter.
    In every program that we take on, we have non-Federal 
partners, State, local, sometimes regional, that we must work 
closely with in every stage.
    And I will pitch it to General Graham to see if he has an 
update on this particular project that you have outlined.
    Ms. Scholten. Thank you, Mr. Telle.
    General Graham. Vice Ranking Member Scholten, thank you 
again for that question. We certainly understand the importance 
of Grand Haven Harbor to the economy.
    I think our collaboration with the State of Michigan on 
testing for PFAS contamination is going pretty well. They kind 
of worked through some of the challenges. If it is primarily 
sand, there is less likelihood that there is going to be PFAS 
contamination on it. It really only sticks to the fine silt. So 
they are working to characterize the sediment in the outer and 
inner harbor.
    And so right now, our understanding is that the deep-draft 
ships can get to all the commercial docks. And right now, we do 
understand that a task order to do the next round of 
contracting was issued in March of this year, and that will do 
a lot of the outer harbor dredging.
    We are looking for a follow-on contract that we will put in 
place this spring and summer if the testing that is ongoing 
shows that that middle section by Harbor Island isn't 
contaminated with PFAS to the Michigan standards. Then we will 
try to make sure that we are in a position to go ahead and 
dredge that later this year.
    Ms. Scholten. Thank you. I appreciate that thorough 
response. I still do request a written response, but we 
appreciate the update very much, and look forward to continuing 
conversations about how the Federal and State can continue to 
collaborate for advanced planning.
    I have about a minute, and I want to touch on data centers 
here really quickly, a huge hot topic all around the country, 
but especially back home in Michigan. And constituents 
throughout my district are rightfully concerned about how these 
projects are going to impact the State's water.
    I believe that we can strike the right balance between 
investing in our digital economy and creating good jobs without 
harming our natural resources or putting big data profits over 
our communities.
    But smart policy decisions start with good information. The 
Army Corps plays a really important role in water management, 
and I want to make sure that we can leverage the agency's 
expertise to understand how these data centers are impacting 
our precious water resources.
    So back to you, Assistant Secretary Telle. Can you touch on 
how the agency is thinking, if at all, about how data centers 
are affecting the use and amount of water maintained by the 
Corps?
    Mr. Telle. Madam Ranking Member, data centers, as you say, 
are a developing part of our economy and critical to our 
competition, our ability to compete.
    In terms of the specific ways we look at it, when it comes 
to water supply, which is not one of our primary missions, but 
it is certainly something we consider as we are updating water 
control manuals, we would not specifically look at one 
facility's water use, we would look at the whole system's water 
use as we analyze these items.
    When it comes to our permitting, we have updated our 
nationwide permits, which are complete, the renewal of our 
nationwide permits, to include data centers. Although data 
centers don't have any particular unique impact on waters of 
the United States in terms of our regulatory mission that other 
facilities do, but it is important to understand that data 
centers are modern facilities that do require permits under the 
Clean Water Act of 1972.
    Ms. Scholten. Thank you. Some followups there, but I will 
yield back my time, and we will keep going, but I appreciate 
the answer.
    Mr. Collins. I now recognize Mr. Babin for 5 minutes.
    Dr. Babin. Thank you, Mr. Chairman.
    Good morning. And I want to thank both of you gentlemen for 
being here today. I represent the 36th District of Texas, home 
to the Port of Houston, lots of ports other than that and 
waterways, refineries, petrochemical facilities. And we are no 
stranger to natural disasters. So I want to thank you all for 
your commitment to protecting and improving our Nation's 
infrastructure and our water resources.
    I also want to take a moment to recognize Assistant 
Secretary Telle. Mr. Secretary, I want to thank you for your 
leadership and for working with your team and Army Corps 
headquarters to help expedite non-Federal-led studies, your 
engagement, in fact, both of you, both of your engagement with 
stakeholders in southeast Texas, including Cedar Port, is very 
much appreciated. It makes a real difference on the ground.
    Cedar Port plays a vital role in supporting jobs and 
commerce and economic growth in our district, and we value the 
strong partnership between the Corps and local stakeholders, 
who are working hard moving these projects forward.
    I also want to thank you for your engagement in Buffalo 
Bayou and Tributaries Resiliency Study as well. They were 
devastated by Hurricane Harvey, and we are counting on 
meaningful flood protection. So looking forward to continue 
working with you.
    My first question is, Mr. Telle, you have announced a 
Building Infrastructure, Not Paperwork initiative. First off, I 
want to thank you for that. That ought to be across all the 
Federal Government, the same thing.
    So what specific regulatory steps are you eliminating or 
streamlining to shorten project timelines?
    Mr. Telle. Congressman Babin, thank you for the question, 
and thank you to your district for welcoming me when I was 
there recently.
    One of the ways that I think about it, and it particularly 
applies to coastal Texas, is we have not had a culture of 
prioritization. And I just want to point this out. We haven't 
really had a plan. If you ask a district commander at any of 
our 39 Civil Works districts, hey, what are the top priorities 
in your district? It is not a question that they have often 
been asked.
    And I think that the taxpayers are invested in these 
leaders, in their ability to lead and command and have military 
judgment. I think we ought to be listening to our district 
commanders. And I think about your district and the areas 
around it that are so critical to our projection of energy 
dominance.
    The American economy depends in many ways on coastal Texas, 
coastal Louisiana, and elsewhere, but it is also very 
vulnerable, as you said, to a hurricane like Hurricane Harvey 
or a hurricane with a storm surge.
    It is critically important that we analyze our assets as a 
Nation in terms of their importance. I can't think of a place 
off the top of my head that is more critical to our national 
security than your district and the areas around it.
    And so this is the type of thinking we need to empower our 
commanders--to answer your question, we need to empower our 
commanders to determine what is their priority and then hold 
them accountable from year to year about how they are cutting 
redtape and delivering on those projects, whether it is 
funding, but more importantly, process and effort, rather than 
expecting them to inch every project down the field 1 inch at a 
time and then have to restudy them after 10 years of studying.
    We need to identify which projects within the districts, 
within the divisions, and at headquarters are, on the basis of 
the military judgment of our commanders, most important to the 
Nation. And that is a very fundamental and simple way that I 
believe we can cut through much of the redtape that we face.
    Dr. Babin. That's wonderful.
    So what changes are you making to ensure feasibility 
studies and construction phases would be able to move faster 
without compromising safety or environmental standards?
    Mr. Telle. Congressman, it's a great question. And I will 
ask General Graham to add to what I am about to say, but one of 
the primary efforts--I talked about prioritization across the 
Nation, but there is also an effort to prioritize within 
projects.
    Quite often, we study a very large swath, a very large 
area. And we study it, we try to boil the ocean with studies 
for decades rather than in an early phase, identify a feature 
or an initiative that can start delivering for the American 
public now.
    So we have implemented a new process called RAPID, which is 
designed to make these early decisions, get features that can 
be authorized and funded by Congress to the Hill as quickly as 
we can, so that rather than study the universe for decades, we 
are able to start building things now.
    Dr. Babin. Absolutely.
    General Graham.
    General Graham. I just want to add emphasis to Mr. Telle's 
point of the sooner we get the decisionmakers, the district 
engineer involved at the earliest stages, the better our 
outcomes are going to be.
    Like Mr. Telle spoke to, we can study a whole bunch of 
various options, but there are decisions we can readily make at 
the beginning of a study to winnow that down to just what the 
leading options are, the leading alternatives are, and then we 
should focus on that. And that will give us a faster product 
more efficiently delivered.
    Dr. Babin. Absolutely. Thank you. I am looking forward to 
continuing our collaboration for water projects in the future.
    I yield back, Mr. Chairman. Thank you.
    Mr. Collins. The Chair now recognizes Mr. Larsen for 5 
minutes.
    Mr. Larsen of Washington. Thank you.
    Mr. Telle, in July of 2025, the Corps estimated that there 
would be 12 Chief's Reports completed for WRDA 2026. And to 
date, Congress has received two of those reports. One of them 
happens to be the Turning Basin of the Columbia River between 
Washington and Oregon.
    What additional Chief's Reports should we expect in time 
for incorporation into WRDA 2026?
    Mr. Telle. Ranking Member Larsen, thank you for the 
question. I will defer that question to the Chief. They are his 
reports.
    General Graham. Ranking Member Larsen, I am tracking 
somewhere between 7 and 13 additional Chief's Reports or 
Director's Reports that we will try to get in.
    I talked to the staff this morning. We know that the end of 
May is usually the hard deadline, but we are not going to go 
pencils down. We are going to keep working on these additional 
Director's Reports and Chief's Reports throughout the summer. 
But to your staff, we absolutely want to get these in as soon 
as possible.
    Mr. Larsen of Washington. So when you get them on your 
desk, how long is the turnaround?
    General Graham. I will sign those usually immediately. To 
the earlier question, we want all of the Corps' leadership to 
be taking a look at these projects earlier.
    So at the time the Chief's Report gets to my desk, I have 
seen it. General Kelly has seen it. Mr. Telle is certainly well 
aware of it. And that will speed this whole process up.
    Mr. Larsen of Washington. Thanks.
    Assistant Secretary Telle, several ports have expressed 
concern to me that the administration is going to propose using 
Harbor Maintenance Trust Fund receipts to construct or maintain 
projects on the inland waterway system.
    That is a tremendously bad idea. It would break the 
commitment we have made to shippers that these funds would be 
dedicated to maintenance of the coastal harbors, since that is 
where this money largely comes from.
    Does the administration support using Harbor Maintenance 
Trust Fund receipts for inland waterways projects?
    Mr. Telle. Ranking Member Larsen, I am not going to speak 
for the administration's policy on this topic I don't know the 
answer to, but what I will say is that what you have described 
is not part of the Building Infrastructure, Not Paperwork 
initiative that we put out yesterday. And so I can't speak----
    Mr. Larsen of Washington [interrupting]. It wouldn't be, 
because it is a different set of things, but I just want to be 
sure that you understand that if that is going to be a budget 
proposal or a proposal from the administration that using 
Harbor Maintenance Trust Fund receipts for inland waterways 
when the dollars for the fund is produced by the coastal 
harbors, there is going to be a problem.
    Mr. Telle. Thank you, sir.
    Mr. Larsen of Washington. Secretary, thanks for briefing me 
on your upcoming proposal on the BINP. One of my priorities is 
that Corps projects be affordable to communities of all sizes. 
And in your proposal, you discuss expanding Corps authorities 
to allow non-Federal sponsors to take on design and 
construction of projects and seek repayment for the Federal 
share after the fact.
    How would that expanded use of alternative delivery methods 
benefit smaller, rural, Tribal communities that can't afford to 
advance these funds and then to wait for reimbursement? Have 
you thought through that?
    Mr. Telle. Ranking Member Larsen, you raise a great point 
here. And the way that we see it is that if we use the 
authorities that you provided to us to expand the overall 
capacity of our Nation to deliver on infrastructure, it will 
reserve the use of U.S. Army Corps of Engineers' excellence for 
projects that are national in scale or projects for communities 
that don't have those capabilities, the ones you describe.
    But we do have non-Federal sponsors that do have those 
capabilities. And so, to the degree that we can let them help 
shoulder the workload burden, it is going to make it better for 
everyone, because it will reserve General Graham's team's 
expertise for communities like the ones you describe.
    Mr. Larsen of Washington. And in the Pacific Northwest, I 
have worked on projects using Corps 206 authorities on a very 
successful restoration, a fairly small project compared to much 
larger projects.
    And so, there are different sizes of projects the Corps has 
authority to act on as well as different abilities that these 
jurisdictions have to participate without Corps.
    So finally, WRDA 2024 formally expanded the target timeline 
for study development to 4 years and $5 million. Non-Federal 
sponsors are concerned the Corps continues to scale down 
projects to conform to the 3-year, the three and three.
    When your staff briefed the committee on your potential 
reforms, it continued to cling to the three and three goal 
despite the fact that we changed that. So can you explain the 
difference here, the disconnect?
    Mr. Telle. Sure, Ranking Member Larsen. The law obviously 
provides us with 4 years and a $5 million limit to complete a 
feasibility study. That replaces a law that gave us 3 years and 
a $3 million limit.
    My view is that the tool that you gave us in terms of 
putting this box around how soon and how cost-effectively we 
need to complete these ability studies is a great tool for 
discipline, to impose discipline on the system to help produce 
an answer for you to your point about Chief's Reports rather 
than studying these things forever.
    And so, I am not going to--although the law gives me the 
ability to waive the 4x5x3 requirement, I don't take it as this 
committee's position that I am going to be the waiver factory.
    I think you imposed this discipline on the system for a 
reason. It is because you want studies completed in a 
reasonable amount of time for a reasonable amount of money. And 
I am going to be very reluctant to give any relief to that 
discipline, because I think it is an incredible tool that you 
have given us, and I think General Graham agrees.
    Mr. Larsen of Washington. Thank you. I yield back.
    Mr. Collins. The Chair now recognizes Mr. Kiley for 5 
minutes.
    Mr. Kiley of California. Thank you, Mr. Chair.
    Thank you for your testimony and all of your efforts to 
accelerate the process of building that is so important. It is 
vitally important in my State of California where we have had 
many issues related to our water supply and have been hamstrung 
by the State's failure to build adequate water storage really 
for decades now.
    So it has really fallen upon local communities to do the 
best that they can to provide for their own residents. And to 
that end, I want to thank you for the work you have done with 
me and my office on a $5.3 million project for preliminary and 
final design work, along with environmental compliance, for a 
15-mile raw water pipeline serving west Placer County.
    This project is going to connect an existing Placer County 
Water Agency intake on the upper American River to Roseville's 
Barton Road Water Treatment Plant. And once completed, 
Roseville will retain access to their surface water resources 
during times of drought or emergency.
    This will have many benefits. It is going to reduce 
reliance on a single aging intake at Folsom Reservoir; improve 
water reliability during emergencies and droughts; serve 
residents, two regional hospitals, and a robust manufacturing 
and business economy; enhance groundwater banking and efficient 
water use; and increase surface water availability in the lower 
American River for municipal, industrial, and environmental 
needs.
    And we have worked very hard the last few years. This was 
originally improved in WRDA. And thank you very much for 
getting this to the point where it can move forward.
    Also, as one of the projects that we have gotten Federal 
funding for, we have enhanced culverts that are very vital to 
water infrastructure in our area with the Placer County Water 
Agency.
    And we are finally starting to have some hope of larger 
scale changes in California as well. As part of H.R. 1 this 
last year, there was $1 billion that was secured for new water 
infrastructure. This was primarily secured through the 
California delegation.
    So we look forward to seeing that funding--this is really a 
Department of the Interior decision--wind up supporting 
enhanced capacity, like raising Shasta Dam in California.
    And then finally, we have gotten Federal approval and 
significant Federal funding for Sites Reservoir in California, 
which is an offstream facility that is going to provide upwards 
of 1.5 million acre-feet of storage.
    This is the first new significant water storage California 
has seen in several decades and holds the hope of getting us 
out of this cycle of floods and droughts, where we have 
sometimes both at the same time, by the way, in terms of states 
of emergency, so that we can actually save the water that comes 
in the wet years and use it in the dry years so that we are not 
taking water away from our farmers, forcing them to fallow 
their fields, forcing our citizens not to water their lawns or 
take shorter showers.
    So your work is critical to many pieces of that. I want to 
thank you for everything that you are doing and for the very 
constructive relationship you have had with my office.
    I yield back.
    Mr. Collins. The Chair now recognizes Mr. Garamendi for 5 
minutes.
    Mr. Garamendi. Thank you, Mr. Chairman.
    Secretary Telle and General Graham, thank you very much for 
your testimony today and for the answers that you have provided 
thus far.
    I want to go through three issues. I am going to start with 
the California Delta and a decision that is now before the Army 
Corps of Engineers. And I suppose, Mr. Telle, you will also be 
involved.
    It is the record of decision. I would hope that the Army 
Corps of Engineers would deny the Federal permits to allow the 
State of California to dig its proposed Delta Conveyance 
Project tunnel. It has very serious impacts on the delta.
    So that is question number one. Where is that? We sent a 
letter on February 3rd to you, General Graham. I would not 
expect a reply in 2\1/2\ weeks, but here you are, so that is 
question number one.
    Question number two goes to the Mare Island Strait channel 
dredging. This was in the 2024. It directed the Army Corps of 
Engineers to expedite the completion of the Mare Island Strait 
feasibility study. This has to do with the SHIPS Act and the 
ability of that particular facility in Mare Island to handle 
larger ships.
    And the third question deals with the overall dredging in 
the San Francisco Bay area, including to Sacramento and 
Stockton. What is the status of that?
    And so those are the three questions. Let's start with the 
delta. General Graham.
    General Graham. Representative Garamendi, thank you for 
that question. Primarily, our role in the Delta Conveyance 
Project is just our regulatory work under the Clean Water Act, 
404, any impacts to waters of the United States that the new 
infrastructure that is required for that intake would be.
    And we will get back to your office on exactly when we 
expect to release a supplemental EIS, but we are tracking this 
closely.
    Mr. Garamendi. The existing EIS indicates that there are 
very significant environmental issues associated with the 
delta. I won't go through all of them here. They are 
significant. It is a perfect way to destroy the largest inland 
freshwater estuary on the west coast. So this project that is 
proposed by our Governor and others should be a nonstarter. The 
role of the Corps of Engineers is significant.
    So please get back to us, and be happy to further enlighten 
you on the potential problems associated with it. Most of those 
are in the record.
    Okay. The next one having to do with Mare Island.
    General Graham. Sir, Mare Island, understand that 
administration's priority is to restore America's maritime 
dominance, and that is what you are working on here on the old 
ship, or Navy facility, that used to be out there.
    The district has been working on that 216 study. Right now, 
it is not looking all that favorable. That is not great news, 
but the good news is most of that channel is self-scouring down 
to 30 feet. So that is the good news. We are happy to come 
brief you on everything that we looked at.
    Mr. Garamendi. General, we certainly appreciate the 
briefing, but the fact of the matter is that the administration 
came out with their maritime strategy last week, and it would 
call for the revitalization of the commercial maritime 
industry. And, of course, we already have a shortage on the 
west coast of docks that are available for the Navy.
    Dredging becomes critically important, and I would take 
issue with your assessment of the dredging and the normal 
scouring from the river itself. Not happening. A major project. 
If we are going to rebuild our maritime industry, we are going 
to have to deal with this particular one. And, of course, there 
is always Richmond that we could add to it and the other 
harbors.
    And finally, the final issue really deals with how we are 
going to deal with the problems that are associated, again, 
general issue of dredging in San Francisco Bay.
    General Graham. Representative Garamendi, delighted to say 
that we are starting to treat dredge material not as a waste 
product but as a vital resource. We have got great authorities 
from this committee to work to better use----
    Mr. Garamendi [interrupting]. My final point, General, 
excuse me for interrupting, but you should keep in mind using 
the Adaptive Management Program of the Endangered Species Act, 
thereby providing flexibility, not based on the calendar, but 
rather on where the species are and what potential harm there 
may be. So adaptive management, Endangered Species Act.
    Thank you, Mr. Chairman, yield back.
    Mr. Collins. The Chair now recognizes Mr. Taylor for 5 
minutes.
    Mr. Taylor. Thank you, Chairman and Ranking Member, for 
holding this hearing today. And thank you very much to our 
witnesses for being here. The sacrifices you guys made to be 
here today don't go unnoticed, and we appreciate it very much.
    I represent many counties along the Ohio River. Congress 
must pass legislation that encourages growth and development, 
that speeds up project timelines, and protects our communities 
from flooding without being filled with frivolous regulations.
    Public-private partnerships have historically benefited the 
Federal Government and taxpayers. The Meldahl locks and dam in 
my district is a prime example of how public-private 
partnerships with the Army Corps can protect communities while 
providing economic opportunities.
    Completed in 2016, the three-turbine hydroelectric plant 
and spillway were added to the Meldahl locks and dam, 
generating 105 megawatts for the community.
    Secretary Telle, I understand that the Corps coordinates 
with the Federal Energy Regulatory Commission for these 
potential partnerships. Is there any opportunity in this 
upcoming WRDA reauthorization to encourage or promote these 
partnerships to help create new domestic energy production 
along this existing infrastructure?
    Mr. Telle. Congressman Taylor, you are absolutely right. 
And 6 percent of our Nation's energy is from hydropower, 25 
percent--the U.S. Army Corps of Engineers is the largest owner 
of hydropower facilities. But we have so many of our dams where 
hydropower is not part of the equation.
    And this is not one of our primary missions, but through 
our section 408 regulatory program, we can create a streamlined 
process that allows the entire Nation to take advantage of the 
situation that you describe in your home State.
    And we are undertaking, this committee--and WRDA 2024 
weighed in on--streamlining section 408. General Graham and his 
team have got a good grasp on 404 Clean Water Act permits.
    But when you go around to our districts, they all handle 
section 408 a little bit differently, because it has to do with 
touching our infrastructure, like dams, and it is a more 
sensitive life and safety issue.
    If we can come up with a streamlined national approach to 
section 408, we can unlock hydropower potential energy that 
exists in our system today. In the same way we did it in Ohio, 
we can do it nationwide. Through Building Infrastructure, Not 
Paperwork, this is one of the exact things that we are doing. 
So thank you for bringing it up.
    Mr. Taylor. Thank you. The Corps' construction and 
management of levees across the Ohio River have historically 
protected communities along the Ohio River from flooding, 
saving countless lives.
    As these communities grow in population and economic 
development, local communities may seek to modify the Corps' 
existing infrastructure through the section 408 program.
    Unfortunately, some communities ran into, in my opinion, 
unnecessary bureaucratic delays while the Corps was completing 
its completeness determination for a project in my district.
    My constituents reported that repeatedly, the Corps took 
the full 30 days to respond to each correspondence, delaying 
the project and holding up critical development.
    This process began in early June of 2025 and was not 
resolved until late January 2026, 7 months after the 
application was submitted for review.
    I understand that some approvals take time, but project 
delivery is crucial for folks on the ground, and 7 months for 
approval can put projects like this one in my district in 
jeopardy and drive up costs.
    Secretary Telle, when looking at an upcoming WRDA 
reauthorization, how can Congress ensure that the section 408 
approval process is completed promptly and communities are not 
worried about losing Federal funding?
    Mr. Telle. Congressman Taylor, you are absolutely right. 
This is a place, as I said before, this committee has spoken on 
before. Before I leave this job, I hope to have a new 
rulemaking that streamlines section 408 for the entire country 
so that each member of the public who seeks a section 408 
permit from the Corps of Engineers can have a process that is 
timely that they can rely on getting answers.
    Obviously, we are not going to compromise our 
infrastructure, but we have to be able to streamline this 
process. It's buried way down in our bureaucracy, and it is 
something we need to elevate.
    General Graham, anything to add?
    General Graham. I couldn't agree more. We won't sacrifice 
the integrity of, say, that dam on the Ohio River, but the 
paperwork processes, absolutely.
    And I think, as Mr. Telle outlined, it is to give district 
engineers more authorities in that so they can move faster. One 
piece I could add on the Ohio River, all the icing conditions, 
the team in the Ohio River, particularly down in your area, 
performed magnificently well, keeping those vital arteries open 
during some truly challenging conditions, and I am tremendously 
proud of them.
    Mr. Taylor. Likewise. I was over there with an opportunity 
to look at some of that work being done, and I really 
appreciate what was done to help those folks.
    I am going to submit this last question, and you guys, 
maybe the lieutenant general, can get back to me with the 
answer. Ohio is home to many abandoned mines, with over 1,300 
miles of streams impacted by potential acid mine drainage, many 
of these streams falling into the Ohio River.
    That is why I was pleased to see in the last WRDA 
reauthorization authorization for the Secretary to establish a 
pilot program designed to establish treatment works for 
abandoned mine drainage in Ohio, Pennsylvania, and West 
Virginia.
    Lieutenant General, has the Army Corps of Engineers begun 
the process of establishing this pilot program?
    General Graham. Congressman, we will get back to you with 
an answer to that. But having grown up in Pittsburgh, I 
certainly understand the importance of this issue.
    Mr. Taylor. I appreciate that. I yield back, Chairman.
    Mr. Collins. The Chair now recognizes Mr. Ryan for 5 
minutes.
    Mr. Ryan. Thank you, Mr. Chair. Thank you both for being 
here again. Good to have you back.
    When you were here in September--and appreciated that 
visit--I focused on what I made very clear as a top priority 
for my 800,000 constituents. I want to bring that project up 
again and maintain that focus. This is the Kiryas Joel Aqueduct 
Connection Project. At that time, appreciated that you both 
acknowledged that you were tracking this and working on it.
    I also want to thank you, General Graham. I asked you 
during that hearing for a commitment to meeting with your 
senior leadership, and you followed through on time and under 
budget on that meeting with General Gibbs. Appreciated that, 
appreciated all the local leadership, and Colonel Young in the 
district being very engaged in this. So I just want to thank 
you both, first and foremost, for your continued timely and 
deep engagement and commitment on this.
    What has changed even in the few months since I brought 
this up in September is that the urgency and the dire need for 
water in this community unfortunately just continues to grow, 
and I want to just give you some fresh data points there.
    And just to refresh your memories, this is a village, it is 
the biggest municipality in my district. It is one of the 
youngest and fastest growing communities in the country. The 
average family size is nearly double the national size of 
families, at 5.37 people per family to be exact. Since 1990, 
the population has grown 500 percent in this village. So they 
are doing everything right to, essentially, race to keep up 
with their rapid growth, which we appreciate and want in other 
parts of the district and the country, and they just need some 
help to really do that.
    What has particularly changed is just, as they have 
continued to work this, they are just in a severe water supply 
deficit at this point. As they work through what is the final 
phase of a successful 20-year project, the concerns that 
without just--we have gotten State funding, we have gotten 
additional prior Federal funding, but we need to speed up the 
urgency, and so we are asking your help on this.
    In the last year or two, the village has been forced to 
rely on temporary unsustainable measures for supplying water. 
They have been trucking in drinking water. They have been 
purchasing water at incredible markups just to make sure that 
their folks--there are a lot of kids, in particular, in this 
community--just have adequate water. And this isn't even 
covering a fraction of their needs.
    So we were able to get the authorization up for this 
project in the 2024 WRDA. I am going to attempt to do that 
again. But I specifically wanted to ask, now that the 
appropriations work is done, how you are thinking about and 
whether we can get any support in the upcoming work plan that I 
know you are working on to try to speed this up. Because it is 
just really hard for me to look my constituents in the eyes and 
say we are not doing everything we can to just make sure they 
have got water. So would appreciate both of your input on that. 
And again, thanks for your engagement on this.
    Mr. Telle. Congressman Ryan, just to respond, thanks to 
your advocacy for this community. I think I was on the phone 
with General Gibbs a few hours after he met with your 
constituents. I think General Graham was also getting that 
update at the same time. This is something you brought very 
clearly to our attention. We are currently in the process of 
working with Office of Management and Budget to develop our 
2026 work plan in response to the Energy and Water 
Appropriations Act, and appreciate your advocacy on this 
program.
    Mr. Ryan. When are you guys, roughly, expecting that? I 
know we----
    Mr. Telle [interrupting]. The data states and the law says 
we have 60 days to deliver that work plan to Congress from the 
date of enactment.
    Mr. Ryan. We did our part, and certainly, you need adequate 
time to do yours. I appreciate that.
    Again, I just want to thank you both for the work that you 
are doing, and your teams, and ask really just on behalf of my 
constituents, as you are making those hard calls--I know EI 
projects in particular are often seen as lower priority, and I 
understand that--there is a huge need across the country--but 
this one has just reached a really critical point. So thank you 
all.
    I will yield back the balance of my time. Thank you, Mr. 
Chair.
    Mr. Collins. The Chair now recognizes Mr. Westerman for 5 
minutes.
    Mr. Westerman. Thank you, Mr. Chair. And thank you to the 
witnesses for being here today.
    I grew up listening to President Reagan tell stories to 
illustrate some hard facts in life. And one of them he used to 
tell was about the Communist Soviet Union. And the guy bought a 
new car and he asked them when he would have it, and they said 
6 years from now. And he said, is that morning or afternoon. 
And the guy said, what do you mean, 6 years from now, why do 
you care if it's the morning or the afternoon. He said, well, 
because the plumber is coming in the morning.
    And when I think of some of these projects with the Corps, 
I can see stories that make 6 years look like a very short 
amount of time.
    There is some great illustrations--I have dealt with the 
Corps since I have been in Congress--and then some not so great 
ones. The first not so great one was my hometown needed one-
quarter inch of water out of a lake that is about 260 feet deep 
in places. They needed one-quarter inch of water per year out 
of that lake, and it took 16 years to get the Corps to 
authorize the project, while the cost of building the water 
supply system skyrocketed. We finally got that done. No common 
sense whatsoever in doing that.
    Then I reflect back to a flood on the Arkansas River 5 or 6 
years ago, a terrible flood, took sections of levee out. And I 
had all these farmers wanting to--they were trying to figure 
out where they were going to be able to plant their crop in the 
fall, and they couldn't get an answer from the Federal 
Government on whether they could get crop insurance if the 
levee wasn't in place.
    And Colonel Eric Noe, he is my Corps of Engineers hero, he 
is retired now, but he came out and looked at the project and 
started talking about how many years it would take to go 
through the environmental assessment and historic preservation, 
and he got it, though. He realized that was a lot of nonsense 
that was holding up progress, and he fixed that levee in about 
2 to 3 months.
    So I know that when the right efforts are put forth, the 
Corps can move mountains, they can move a lot of dirt in a 
short amount of time, and that gave me great faith in the 
Corps.
    Which brings me to my next issue, and that is the 12-foot 
channel of the Arkansas River on the MKARNS system. So it was 
first authorized in 2004, and here we are, 2026, and there 
hasn't been one effort made to deepen the channel in the 
Arkansas River, even though--a few years back, I was the 
ranking member on the Water Resources and Environment 
Subcommittee, and we put new language out there to deepen the 
channel, there was $200 million that the Corps had for 
maintenance on the MKARNS, and still nothing has happened.
    So my question is, when is something going to happen on the 
MKARNS, and what else does Congress have to do, other than 
authorize and you have funding to do it? How do we get this 
project to actually happen? Because when I am back home, people 
who use the MKARNS, that is pretty much the number one and only 
question I get asked.
    Mr. Telle. Congressman Westerman, the frustrations you 
expressed are exactly why we are getting after the Building 
Infrastructure, Not Paperwork initiative. We are hoping that we 
hear fewer and fewer stories like this.
    As it relates to the MKARNS, I am pleased to say that I was 
there recently. It is an incredible facility, an incredible 
capability we have as a Nation. I was at the Port of Catoosa, 
which is upriver from you, and even past Tulsa, what an amazing 
facility to deliver products that are created right in 
America's heartland to the world.
    With regard to the 12-foot channel depth, I will defer to 
General Graham on that. I do know that when we are looking at 
these types of systems, making sure we don't strand deeper 
channels against shallower channels is a big consideration.
    But, General Graham, I don't know if you want to provide an 
update.
    General Graham. Thank you.
    First, I am just going to pivot to the levees. Absolutely, 
when a flood hits, we need to stay in Army mode and to get 
those levees repaired, not within 6 years, not within 5 years, 
before the next storm hits. That is our absolute goal. And we 
are here to protect the people's livelihoods behind there. We 
are not here to defend any of our bureaucracy. So, 
Representative, you have our absolute commitment to that.
    On the MKARNS system, understand the folks you talk to, 
their number one concern is getting more savings by a deeper 
river. My number one concern for that system is the reliability 
of it. It is about 15 years behind where, say, the Ohio River 
system is in terms of needing major recapitalization. So when I 
look at all the engineering reports that come in, making sure 
that what we have stays reliable is my number one concern.
    Mr. Westerman. I understand that. And that $200 million I 
was talking about, it got moved down to the Three Rivers 
Project, which is infrastructure, which is very important. But 
unfortunately, it wasn't used, so it went back into the 
maintenance fund.
    So I want to work with you. I get it that infrastructure 
needs repairs up and down the river, but it just seems to take 
forever to get things done. And it's not like you have got to 
dig a new channel the full length of the river. There are a few 
places where it's not 12 feet deep that need to be dredged out 
and fixed so that the river can be used.
    So, Mr. Chairman, I appreciate the indulgence, and I yield 
back.
    Mr. Collins. The Chair now recognizes Ms. Friedman for 5 
minutes.
    Ms. Friedman. Thank you, Mr. Chair.
    A point of personal privilege. After his military service, 
my grandfather spent his entire career with the Army Corps, so 
I have a tremendous amount of respect for the organization and 
for what you all do. So, thank you so much for being here.
    Lieutenant General Graham, I had the opportunity to ask you 
a few questions the last time you were here about the PACR for 
the L.A. River Restoration Project, a very important long-time 
project in my area in Los Angeles.
    During that hearing, you had told me that the Corps was 
committed to completing the PACR in time for the 2026 WRDA. 
Unfortunately, on February 9, after asking for a status update 
on the PACR, my staff received communication from the Corps 
that stated, quote, ``Federal funding is not available to 
continue the project's PACR completion in support of the WRDA 
2026 timeline,'' end quote.
    Now, my staff and I have sent several followup questions, 
which as of now have not been answered. So I would like to use 
part of my time to get some clarity on the status of this very 
important project which L.A. has invested millions of dollars 
over the years.
    First, Lieutenant General Graham, can you provide me with a 
timeline for the completion of the PACR?
    General Graham. Representative Friedman, I will not be able 
to honor the commitment we made at the last hearing to finish 
that PACR before the next WRDA bill is due. A multitude of 
reasons are behind that. Some are the challenges, the 
absolutely ballooning astronomical cost of real estate, 
question the viability of it and the ability of our Federal 
sponsor to provide the funding to get that real estate. There 
are also some environmental concerns.
    I have walked that whole region. I understand how important 
it is to the community. And nobody likes large concrete 
trapezoidal ditches running through their community. Although 
in the recent rainstorms out there, L.A. River did its flood 
risk management job magnificently well.
    So, we are committed to working to see, can we balance the 
flood risk management needs and the aquatic ecosystem 
restoration needs. But in the case of L.A. River, we are 
challenged to put the conditions together that we believe we 
are going to have a viable way forward.
    Ms. Friedman. Thank you. It is disappointing to hear, and I 
would love to have more communication with the Corps as we move 
forward. I mean, certainly, L.A. has put a lot of their own 
resources into this project over the years. It has been 
promised to the community. It serves a very important function. 
It could also serve a more important function if we can do the 
investments to help capture more water. And my fellow 
Representative from California mentioned water storage, and we 
have got a lot of water that runs down the river out to the 
ocean every time it rains, and there are reclamation and 
capture projects as part of this project that are planned.
    But for the communities that have lived alongside of this 
for years and have been promised an amenity that they can use, 
the communities that have been divided from parts of the city 
because of this infrastructure project who want crossings, want 
to be able to have this not be blighted, but be an amenity for 
their children, moving forward, this would be a huge 
disappointment.
    And as the project continues, and as it drags on, the costs 
are only going to increase. So if we just kick the can down the 
road because of current costs, we are looking at ballooning 
costs over the years. And, again, there is a lot of sunk 
investment into this, so I would hope that we can keep finding 
ways to move this forward.
    In my last minute here, I do want to also mention the 
deeply concerning directive issued on October 15, 2025, by the 
Department of War, which requires the Corps district to obtain 
approval from the Office of the Assistant Secretary of War for 
Legislative Affairs before engagement with Federal or State-
elected officials and their staff. I mean, this is something--
as we are talking about removing redtape, and that seems to be 
a priority of the Trump administration and of yours, this is 
adding layers of redtape that WRDA is never going to be able to 
unstick.
    So, Lieutenant General Graham, how has this directive 
impeded the Corps' ability to work with Congress, and how do 
you plan to ensure timely communication with offices regarding 
time-sensitive information, like the L.A. River Restoration 
Project, if you can't talk to us without going through another 
agency?
    General Graham. Thank you for that question. The Army Corps 
of Engineers, we strive every day to function as one team. One 
team from the district level that are interfacing with your 
constituents, up through our division level, through my 
headquarters, and up to Mr. Telle's office. Our goal is to 
function as one team.
    And as my interpretation of the guidance from the Secretary 
of War and the Secretary of the Army, it revolves around the 
basic principle that the left hand of the organization should 
know what the right hand of the organization is doing. And it 
is also around the basic principle that at the lower levels of 
the organization, they should be entirely nested with the 
guidance and direction that senior leadership is providing. And 
so I think that is all well just and proper.
    If the actual execution of that is clunky right now, that 
is my responsibility to fix it, and that is our commitment to 
you here today.
    Ms. Friedman. Well, seems to me that adding this layer of 
bureaucracy is going to make things slower and maybe us not 
getting a response as part of that.
    With that, I yield back. Thank you.
    Mr. Collins. The Chair now recognizes Mr. Onder for 5 
minutes.
    Dr. Onder. Thank you, Mr. Chairman.
    Secretary Telle, General Graham, thank you for being here 
today.
    WRDA works best when Congress sets clear priorities, and 
the Corps delivers real infrastructure, not just process 
milestones. Secretary Telle noted that the Corps performs best 
when it is unburdened by redtape and is free to focus on 
execution. I couldn't agree more.
    In Missouri, we don't measure success by how many reports 
are issued, but whether our levees hold, whether our locks 
operate, and if our communities are protected. Missouri's Third 
District depends on a reliable inland river system. The 
Missouri and Mississippi Rivers, which converge in my district, 
support agriculture, manufacturing, energy, and multiple 
businesses throughout the district. We also have aging 
infrastructure that the Federal Government built decades ago 
and then sold off and abandoned.
    So as we work to develop WRDA 2026, I want to focus on 
three things. First, delivering on the already authorized 
projects and clearing the construction backlog. Second, 
prioritizing flood risk reduction and ecosystem restoration 
projects that address the real and present risks to Missouri 
families and landowners. And third, improving transparency and 
accountability so Congress and local sponsors know exactly what 
projects remain unfunded and, more importantly, why.
    Secretary Telle also pointed out that we have over $45 
billion sitting undelivered nationwide, much of it decades old. 
That is unacceptable, especially when we have communities 
waiting for much needed infrastructure upgrades.
    So I look forward to discussing how WRDA 2026 can sharpen 
focus, restore fiscal discipline, and ensure the Corps builds 
what America and Missouri actually need.
    Secretary Telle, you stated that the Corps currently has 
$45 billion previously appropriated but not yet delivered, with 
$15 billion of that being more than 6 years old. Are there 
specific reforms that you would like to see implemented in WRDA 
2026 to help prioritize completion of these already authorized 
construction projects, particularly flood risk and navigation 
projects in States like Missouri, before authorizing new ones?
    Mr. Telle. Congressman, thank you for the question. And 
congratulations on representing the part of America where the 
longest river intersects with the second longest river, the 
longest being Missouri, just slightly.
    Look, I have been over it. I think some of this stuff is 
very fundamental and may not require an act of Congress to 
deliver on, just simply a change in culture. We have to empower 
our commanders. We are not doing that today. We are asking them 
to do everything all at once with the same level of effort.
    The reason a lot of this funding is stranded is because we 
get caught in endless loops of negotiation and back-and-forth, 
and this bureaucrat talking to that bureaucrat, this agency 
talking to that agency. And so I would say that that 
fundamental management change will do a lot to help free those 
resources.
    I think a directive from Congress to us to reexamine 
whether that $45 billion that is currently stranded, if it 
could be applied somewhere else more efficiently or 
appropriately would be useful. But I think, more importantly, 
we have to just get out of--we have to make sure that--in 
particular, we get caught up in arguments with other Federal 
agencies, our partners.
    My view, and what's part of Building Infrastructure, Not 
Paperwork, is that if we elevate these challenges here to 
echelon in Washington, we can look across at another agency and 
say, hey, let's solve this problem.
    I think about a project in Florida, in south Florida, Port 
Everglades. That project costs, to deepen and widen that port, 
costs $600 million, but the current pricetag for that project 
is $3.2 billion. That means we, the United States of America, 
are paying 5x for a port on the basis of haggling between the 
interagency, and we can do a lot to fix that----
    Dr. Onder [interposing]. Right. Yes. A lot better than 
that.
    Mr. Telle [continuing]. If we elevate it. So thank you for 
bringing that up.
    Dr. Onder. Thank you. Also for you, Secretary Telle, the 
Federal Government constructed and later abandoned the Lock and 
Dam No. 1 on the lower Osage River in Missouri. It now poses 
safety and liability risks. Given that this is a clear legacy 
Federal project, will the administration support WRDA 2026 
authorization and funding prioritization for removal and 
ecosystem restoration on Lock and Dam No. 1?
    Mr. Telle. Sir, I am going to let General Graham take that 
one. He has the latest on that project.
    Dr. Onder. Thank you.
    General Graham. Sir, quite versed in the challenge with 
Lock and Dam No. 1 on the lower Osage River. Our commitment to 
you is to have a Chief's Report that I will sign by the end of 
May.
    Dr. Onder. Thank you very much. I yield back.
    Mr. Collins. The Chair now recognizes Mr. Figures for 5 
minutes.
    Mr. Figures. Thank you, Mr. Chair. And thank you, Secretary 
Telle and Lieutenant General Graham, for being here today.
    Secretary, it is good to see you again. We were down--I had 
the privilege to spend a little time with you down in Mobile a 
few months back when we were celebrating the deepening of that 
port, which is an example of what happens when communities can 
work together with the Corps to prioritize local and regional 
priorities from an infrastructure standpoint. And now we can 
proudly say--no disrespect to any of my other colleagues on the 
committee--that the Port of Mobile, Alabama, is the deepest 
port in the gulf. The deepest. So deeper than Houston, deeper 
than New Orleans, deeper than Miami, deeper than Tampa. We are, 
hopefully soon, to be home to the largest amount of imports and 
exports coming in and out of the gulf.
    As we begin work towards WRDA 2026, it is important that we 
recognize the breadth of water infrastructure challenges facing 
communities across the country. While navigation and major 
coastal projects often receive the brunt of the attention, many 
cities, large and small, and rural especially, are grappling 
with aging water systems, inadequate stormwater infrastructure, 
sediment management challenges, and mounting wastewater needs.
    In my district, these are not abstract concerns. 
Communities are dealing with recurring flooding, failing or 
outdated water systems. In fact, one city in my district, 
Prichard, Alabama, has a water system that has been described 
by experts who have worked in Flint, worked in Jackson, as 
America's worst water system.
    This certainly creates challenges that affect public 
health, economic development, environmental quality, and 
overall quality of life. And WRDA has long served as a 
bipartisan vehicle to address pressing water resource needs, as 
you guys well know.
    As we consider WRDA 2026, we must ensure that the Corps is 
equipped, not only to maintain major navigation channels and 
large-scale projects, but also to partner with local 
communities on comprehensive water management solutions, 
particularly in areas facing infrastructure deficits.
    I look forward to discussing with you guys and working with 
you guys how the administration will prioritize water supply, 
wastewater, stormwater, and sediment management projects in 
WRDA 2026, and how we can ensure communities, especially small 
and midsize cities, and rural communities, can effectively move 
projects forward through the Corps' process.
    Our goal should be clear: We should be striving for a WRDA 
bill that strengthens infrastructure resilience, improves water 
quality, supports economic growth, and delivers meaningful 
long-term benefits to communities across this country, both 
large and small. Many of the Corps' projects authorized under 
the Water Resources Development Act are vital for community 
safety, economic growth, and environmental and coastal 
resilience.
    Secretary Telle, I will start with you. How could 
underfunding, how could us not providing enough funding in WRDA 
for operations, maintenance, and construction affect the Corps' 
ability to deliver these authorized projects effectively?
    Mr. Telle. Congressman, thank you for the question. And I 
would note that you invited me to join you, in Mobile at the 
event that we attended together, in this room from that very 
chair, and we wound up sitting next to each other. So that was 
great.
    In terms of resourcing operations and maintenance, this is 
critical. You will see us emphasize operations and maintenance. 
General Graham just did. And, absolutely, there are key issues 
where additional funding, including the President's budget, is 
required, but I believe that we can accomplish so much with the 
authorities and the funding that we have.
    We are not delivering sufficiently, in my view, on schedule 
and cost with what we have, and that is why you saw us 
yesterday introduce the Building Infrastructure, Not Paperwork 
initiative. This is designed to squeeze more out for every 
American community out of the resources that you provided.
    These decades-long schedules, these billions of dollars in 
costs, we can do better as America. Our water infrastructure is 
really the secret ingredient to our communities' health and 
safety, it is the secret ingredient to our economy. And we have 
to as a Nation--I mean, this is the greatest civil engineering 
entity humanity has ever known sitting next to me.
    Mr. Figures. Thank you for that. I don't want to cut you 
off, but I do want to go to Lieutenant General Graham.
    Mr. Telle. Yes, sir.
    Mr. Figures. I first want to highlight the work and 
reputation that your district commander in Mobile, Alabama, is 
establishing for himself. Kelcey Shaw is doing a hell of a job 
by all accounts that we receive from local authorities, mayors, 
members of the city council, people that he engages with across 
my district, which is broad and vast. They are thrilled to have 
him there, they are enjoying working with him, and they feel 
heard more than anything else. And so I want to give him that 
acknowledgment.
    Lastly, look, I live in--I represent part of Hurricane 
Alley. And from an engineering perspective, obviously given 
funding cuts and staffing changes that we have seen over the 
past year-plus, want to make sure that the Corps is ready and 
able. If a category--if a major hurricane today is to hit the 
gulf coast, or anywhere in America, are you confident in the 
Corps' ability with its current resources to be able to respond 
effectively and efficiently to provide a timely response to 
major infrastructure damage that may happen from those storms 
or do you need more?
    General Graham. Representative Figures, we absolutely are. 
With leaders like Colonel Shaw making sure that we are staying 
in Army mode, whether that being under Corps authorities or 
whether we are working under Stafford Act under FEMA's 
authorities, our goal is always to help people as fast as we 
possibly can. And in your vulnerable part of this country, that 
is absolutely true.
    Mr. Figures. Thank you. And I yield back.
    Mr. Collins. Thank you.
    And as somebody that wanted to attend that event, I 
couldn't, and I hate it, because it was a great project and a 
good example of what the Corps can do under--came in under 
budget and under time. So it is a good project.
    The Chair now recognizes Mr. Burlison for 5 minutes.
    Mr. Burlison. Thank you, Mr. Chairman.
    After decades of frustration, and myself being frustrated, 
representing my district for 3 years coming here to our annual 
hearing that we would have, what a change. What a change.
    Secretary Telle, I cannot thank you enough for the sea 
change in attitude and respect for the citizens and the 
taxpayers and their neighbors. What a difference.
    Thank you for your leadership, General Graham. Thank you.
    You and Brigadier General Walter have just demonstrated 
tremendous leadership that we haven't seen in decades. And I am 
so impressed with Lieutenant Colonel Jesse Carter. And just 
last week, he led a team from the Little Rock office to my 
district to have a series of community meetings to explain the 
changes in the policies that they are going to have, and they 
were welcomed with positive feedback from the constituents in 
my district, and I cannot thank you enough. First, I just 
wanted to say thank you.
    You have clearly demonstrated, Secretary Telle, almost a 
private sector attitude the way in which you address trying to 
streamline processes, make the Corps faster, quicker, 
responsible. And, again, this goes to both of you. It is 
impressive to see happen.
    Can you highlight some of the new initiatives that you guys 
have worked on? And if you want to make any comments about your 
experience at Table Rock Lake, that would be great.
    Mr. Telle. Well, Congressman, I will just say, we made a 
commitment to you in this room in September, and we followed 
through with that commitment. And I am pleased to see that the 
situation has improved in Table Rock Lake.
    With regard to our initiatives, we are so proud of our 
Building Infrastructure, Not Paperwork initiative. There are so 
many ways that we can improve here. I want to hit on something, 
since you give me the opportunity, that General Graham hit on 
earlier but we haven't fully articulated, which has to do with 
the way we contract for dredging.
    If you think about dredging, this is--really, it's the 
equivalent of a snowplow plowing your street. It allows you to 
get back to work, and it is the equivalent for our Nation of a 
snowplow clearing your street and enabling productivity.
    Unfortunately, the way we contract for this is regional in 
scope. We talked about this. We have less intelligence about 
the dredging activity across the Nation when we are sitting 
across a negotiating table from a dredging provider than they 
do. And we are often competing against ourselves, driving up 
costs across the country, having to run errands across the 
country in a way that is incredibly inefficient.
    We are already underway, under Building Infrastructure, Not 
Paperwork, to elevating that contracting activity to a place 
where we have a national view, and it is going to make us far 
more efficient. It is going to allow us to squeeze every drop 
out of taxpayer dollars that we can. And so I am extremely 
excited about that.
    There are a number of other ways that we can get into. I 
have got 1 minute and 23 seconds left. I can provide another 
vignette for you, if you would like, or I can answer another 
question, sir.
    Mr. Burlison. I wanted to make sure that I didn't miss 
thanking you also for the water allocation that we got from 
Stockton Lake after decades of southwest Missouri sweating and 
worried about having drinking water availability in the future. 
That was something that was finally accomplished, and I can't 
thank you and my district cannot thank you enough.
    I wanted to ask about some of the funding that the Corps 
has, about $45 billion in congressionally appropriated funds 
that included about $15 billion that had remained unspent for 
about 15 years. Knowing that in my district there is 
infrastructure that needs improvement, can you address that 
issue and what we may need to do if we need to make any changes 
in order to make sure that those funds are utilized?
    Mr. Telle. Congressman, thank you for the question. And 
this is something we are working on every single day. We have 
analyzed every dollar of those $45 billion that are out there. 
Some of them are still part of a project that is active, and 
for one reason or another, we just haven't gotten to the point 
where we can start spending it.
    Some of it is stranded. Some of it will never be spent 
unless we repurpose it. And so we have been working with the 
Office of Management and Budget, we will work with the 
Appropriations Committee, we will work with this committee to 
try to make sure that, one, we are carrying through and 
executing the dollars that Congress has provided but to the 
degree that those dollars are not--I mean, the enterprise, the 
Corps has never had anyone--most agencies have funding that 
expires. Much of our funding never expires. And the Corps has 
rarely had anybody come around and say, hey, if you don't spend 
this money, it is going to go away.
    We are going to execute the law, and we are going to spend 
the money that Congress has given us in a way that Congress 
expects. However, someone needs to put some discipline into the 
system to get some decisions made on how to execute this money, 
and I have been doing that. I have been letting the enterprise 
know that if you don't spend the money you have, eventually, 
Congress is going to take it back.
    And so we have been getting that message out. It has put a 
shock into the system. I think our fiscal folks across the 
board are now awake and interested in spending this money.
    Mr. Burlison. Thank you. And last, I just want to invite 
you again to come back to Table Rock. Every Veterans Day we 
have an amazing event where our fishing guides, dozens and 
dozens of fishing guides offer free guided service to our 
veterans. It is one of the most beautiful and Americana kind of 
event that you could ever see, and you both are invited to 
come. I would greatly appreciate it.
    Mr. Telle. Thank you, Congressman. If not for the lapse in 
appropriations, we might have joined you for that back in 
November.
    Mr. Burlison. Thank you. I yield back.
    Mr. Collins. Thank you, Mr. Table Rock.
    The Chair now recognizes Ms. Norton for 5 minutes.
    Ms. Norton. Thank you, Mr. Chair.
    The Army Corps supplies the District of Columbia's drinking 
water, and the Potomac River is the only source of that 
drinking water. With only 1 day of backup water supply, man-
made or natural events that make the river unusable for 
drinking water would put residents, the District government, 
and the regional economy at risk.
    In 2022, at my request, the Congress authorized the Corps 
to conduct a feasibility study of a project, quote, ``project 
for the water supply, including the identification of a 
secondary water source and additional water storage capability 
for the Washington metropolitan area,'' end quote.
    Congress has appropriated $2,000,300,000 for the study. Two 
weeks ago, the Corps informed me that it will likely limit the 
scope of the study to an expansion of the existing primary 
storage basin. That violates both the study's authorization and 
appropriation. Expansion of the reservoir is not a secondary 
water source.
    Lieutenant General Graham, why has the Corps decided to 
limit the study of the expansion of the reservoir?
    General Graham. Delegate Holmes Norton, thank you for that 
question.
    First off, I just want to assure the committee members and 
everybody listening that the water supply for the city, parts 
of Fairfax, and Arlington County, are safe. The Army has been 
entrusted to run that water supply since right after the Civil 
War.
    So I know there are concerns with the sewage spill from the 
Potomac interceptor up there up by I-495, but that is a 
completely different system. We provide the treated water, and 
DC Water is responsible for distributing that water through the 
city, and they are also responsible for collecting and treating 
the sewage.
    Fortunately for the Washington aqueduct, and, ma'am, you 
are absolutely correct, our sole source of water, raw water, is 
the Potomac. We have two intakes in the Potomac River: one at 
Great Falls and one at Little Falls. The sewage interceptor 
leak was in between the two. And so the source of raw water 
coming into our treatment plant is pristine Potomac water right 
now, and we have shut off the Little Falls intake that is below 
the sewage spill.
    The Corps is, under FEMA authorities and under EPA 
guidance, responding to assist as part of the Federal response. 
Our job right now, we have crews out there making sure that no 
additional stormwater interferes with what DC Water is doing to 
fix the interceptor. And we are also keeping additional 
stormwater from flowing to where the contaminated biosoil had 
accumulated after the break.
    Ma'am, to your question directly on the feasibility study 
that is going on, to Mr. Telle's point, we need to get to 
quick, immediate decisions on what can we do now to make things 
better. So the expansion of the Dalecarlia Reservoir would add 
an additional 12 hours of supply. That is a 33-percent 
increase. That's achievable near term.
    Ma'am, we are absolutely not taking off the table a look 
at, say, the Travilah--if I said that right--Quarry to look at 
a more longer term off-Potomac tertiary source of water. So 
that certainly is not off the table.
    Ms. Norton. Well, will you commit to expanding the scope of 
a study to identifying a secondary water source and additional 
water storage capability as required by Federal law?
    General Graham. Ma'am, absolutely. We are not limiting the 
scope of this study, but we are looking for early actionable 
elements that we can put to make the resiliency of the city's 
drinking water safer as soon as possible.
    Ms. Norton. What is the Federal Government's plan to 
provide emergency drinking water to DC in the event that the 
Potomac River becomes unusable for drinking water, as could 
have happened had a different portion of the Potomac 
interceptor collapsed last month?
    General Graham. Delegate Holmes Norton, that is absolutely 
an important question that we need to address. Our sole source 
is the Potomac, and as I said, we have built resiliency into 
that with an upstream intake and a downstream intake. But there 
is no primary source that is off of the Potomac.
    We are looking to see if there are other interconnects we 
can possibly do with the other water providers around the city, 
but that is a question that we will continue to explore.
    Ms. Norton. Thank you. Last month, a section of the Potomac 
interceptor collapsed causing hundreds of millions of gallons 
of wastewater to flow into the Potomac River. Not only is this 
an environmental disaster, but it also underscored the urgency 
of a secondary water source.
    Lieutenant General Graham, will the Corps provide DC Water 
financial assistance for the long-term rehabilitation of the 
Potomac interceptor?
    Mr. Telle. Ma'am, thank you for the question. And I will 
just say, this challenge in the Potomac River is one of the 
greatest ecological disasters of its type to ever occur in our 
Nation. We share your goal to ensure that the Washington, DC, 
water supply has the necessary redundancies given that the seat 
of Government is here in Washington. It is a critically 
important goal.
    This is National Engineers Week, and I just want you to 
know, I have done a special message to congratulate all of our 
engineers on the occasion of National Engineers Week, and I did 
it from the Washington aqueduct because it is such an important 
facility.
    And I do think that this disaster underscores the 
importance of this facility for our Nation. We are in the same 
position that you are, we agree, and I think it is a question 
of getting it right for the citizens, but also for the 
functioning of our Government.
    Ms. Norton. Thank you. And I yield back.
    Mr. Collins. The Chair now recognizes Mr. Crawford for 5 
minutes.
    Mr. Crawford. Thank you, Mr. Chairman. I thank the 
witnesses for being here.
    In January of this year, you announced the removal of the 
Little Rock District commander, citing, quote, ``a loss of 
confidence in his ability to command.'' This commander had 
assumed command less than 6 months prior to that decision.
    As you both know, leading an Army Corps district involves 
significant responsibility, and I would say a pretty steep 
learning curve, particularly for an individual who may not have 
served in that capacity before. Given the relatively short 
tenure, it would be helpful to fully understand the context 
surrounding that decision.
    Can you share some details regarding the factors that led 
to the removal of the Little Rock District commander?
    Mr. Telle. I am going to let General Graham address that 
question, Congressman Crawford. But I will just say, we talked 
with Congressman Burlison a few minutes ago. When we were in 
this hearing room in September, I announced to Congressman 
Burlison, in response to his question, that we had paused 
enforcement of encroachment at Table Rock Lake in order--we had 
to analyze the information that his office had sent us. Really 
we were doing casework on behalf of one of the members of this 
committee. I let Congressman Burlison know that we had paused 
enforcement while we came up with a commonsense solution.
    Two months later, I called down to the Little Rock District 
and said, hey, we are still hearing you haven't paused this 
activity. And I again directed them to pause this activity in 
accordance with the commitment I made to Congressman Burlison 
and other Members of Congress.
    It wasn't until December when I was on the ground there in 
the Little Rock District that I was talking to one of 
Congressman Burlison's constituents in her driveway, and this 
individual told me that she was facing DOJ--heading to court 
under criminal accusations with DOJ as a result of the 
inability of the Little Rock District to follow the directions 
that General Graham gave them.
    And it broke my heart. It was right before Christmas. And 
this constituent of Congressman Burlison's, who I happened to 
meet that day, let me know that General Graham's direction had 
not been followed and that she was headed to court with the 
Federal Government chasing her on criminal accusations related 
to encroachment enforcement that we viewed as overly heavy 
handed and not in the interest of the American public.
    And I will let General Graham take it from there.
    General Graham. So, Representative Crawford, thank you for 
that question.
    Just elaborate a bit on what Mr. Telle outlined. So it was 
my decision to remove the Little Rock District engineer from 
command, not as a result of any ethical or moral failings, but 
rather because I lost confidence in their ability to exercise 
sound judgment.
    Mr. Crawford. I am going to ask you to pause right there. 
So this was strictly the colonel's lack of judgment.
    Was there any assessment of the staff there that played a 
role in the decision to continue after they had been given the 
direction to cease but they continued? Was there any action 
taken against those staff, those civilian staff?
    General Graham. So, Representative Crawford, the commander 
is ultimately responsible for everything that organization 
does. That is the bedrock principles of the United States Army, 
and that is what makes us the best in the world.
    Mr. Crawford. Right. Fair enough. But----
    General Graham [interrupting]. So the answer to your 
question, sir, is there were some additional individuals, many 
who have since retired, or--well, or have left Government 
service. We are right now moving in a seasoned second-year 
colonel who has commanded before, and he will take a look at 
all the individuals and all of the policies of the district to 
see if any additional actions need to take place or what needs 
to change on the ground.
    Mr. Crawford. Okay. Let me ask you this. So this is kind of 
where we run into a little bit of a gray area here, because the 
individuals in the office are civilians, long term, been there 
for many, many years. And then you have a colonel that comes 
in, he is brand new, he is 6 months on the job, and you issue a 
standdown.
    Is that accurate, you issued a standdown on that particular 
operation on Table Rock Lake?
    General Graham. A pause on enforcement.
    Mr. Crawford. A pause?
    Mr. Telle. A pause on enforcement so that we could assess 
and come up with a commonsense solution.
    Mr. Crawford. And we have had similar instances, not on 
Table Rock Lake, but, say, for example, Bull Shoals, or Norfork 
Lake, or whatever, similar types of dynamics that have taken 
place.
    So not faulting you at all on the cease enforcement notice. 
That is fair enough. The question I have is, when there is a 
violation of this nature, and it was so egregious that you 
removed the colonel from command, what further steps are taken 
to address this downstream of the colonel? Because he may be 
one of two or three that are actually Active Duty military 
present in that office. The rest are civilians.
    I am curious what you do and how that chain of command 
works and how you address that problem going forward if you 
have another colonel that may be being led by the office staff 
to do one thing after he has been given another set of 
instructions, like a cease of enforcement. What are you going 
to do in the future? Are we going to continue to fire colonels 
or are we going to look at the office staff below the colonel?
    General Graham. Representative Crawford, it is a great 
question. And the way the, again, the Army works, we want to 
make sure that the chain of command is responsible for the 
change in that culture that should never have existed at Table 
Rock Lake. That is the chain of command's responsibility. It is 
the chain of command's responsibility to make sure that those 
folks underneath them aren't being overly harsh on the 
enforcement of these rules, as we saw at Table Rock Lake. That 
is their responsibility, and we are going to hold them 
accountable for it.
    Mr. Crawford. I appreciate that. The chairman has been very 
gracious in the latitude. I will say that Table Rock is not the 
only place that that has taken place. And I would also say that 
there is a cultural issue that needs to be addressed below the 
level of colonel.
    General Graham. Sir, acknowledged.
    Mr. Crawford. Thank you. I appreciate it.
    Mr. Collins. The Chair now recognizes Mr. DeSaulnier for 5 
minutes.
    Mr. DeSaulnier. Thank you, Mr. Chairman.
    I want to, first of all, thank you for being here in the 
Corps, and also my deep appreciation and respect for the Corps' 
work representing a district in the area for a long time at 
multiple levels of Government in the San Francisco Bay where 
the delta meets it. The Corps has traditionally been very 
engineering-like and professional to work with, irrespective of 
administrations; frequently, however, not so much today. And 
that is a concern for me that I want to bring up for Mr. Telle.
    The number of authorized projects--and this is nationally, 
not just regionally--that aren't actually getting funding is a 
real problem because of the unique partnership that we have 
here with the State and local officials, particularly in 
sensitive areas like the one I get to represent.
    So we have asked you, the Congress, in 2018, 2020, and 
2024, to give us an update. So we just want to know why it is 
that these are authorized but funding has not been allocated. 
Given the pressure and the addition--I think I mention every 
year--is the addition to the change in weather, irrespective of 
how you believe that is happening, it is really important for 
our local and State officials to be able to do the engineering, 
fund these projects, and rely on you to get them out after they 
have been authorized.
    Mr. Telle. Congressman, you are correct. The current 
authorized but unfunded total of our portfolio is $78 billion. 
That number is likely an underestimate of the work that has 
been authorized by this committee in cooperation with the 
Congress at large.
    One thing is for sure, the demand on the services that the 
Corps of Engineers provides is higher than the supply that we 
can provide. But as we just had a discussion a few minutes ago 
about $45 billion of funds that have been appropriated but 
unexpended, our problem is not that we need more money in every 
case. In most cases, we need to be better at executing that 
funding. We need to be better at delivering that funding. We 
need to be better at overcoming obstacles.
    That is why the Building Infrastructure, Not Paperwork 
initiative that we announced yesterday is going to empower our 
commanders. It is going to empower our commanders to identify 
which priorities are important for their district, and then we 
are going to hold them accountable year to year for executing 
against them. And that includes moving projects from 
authorization to feasibility, to engineering, to design, and 
then to construction, and eventually to operations and 
maintenance.
    And so I share your frustration. That is my perspective on 
it.
    Mr. DeSaulnier. Just, again, having been at this for a 
while, my hair has changed color, it is just frustrating. And 
engineering is engineering, and to the degree that we--we trust 
you to do the engineering side of it, but the project delivery, 
there sometimes is a lack of urgency, from my perspective. And 
if it needs permitting, if it is rational and makes it more 
efficient but doesn't--we can analyze what we may be losing 
from permit efficiency and not just opening up further 
problems. It should be completely bipartisan, and my experience 
on this committee is, it is.
    So from an analytical standpoint, let us know what the 
problems are and just get down and figure out what it is to 
make sure we get this done.
    Mr. Telle. Sir, if I could just let you know my 
perspective. This is included in the Building Infrastructure, 
Not Paperwork initiative that we rolled out yesterday. One of 
the odd things about the Civil Works mission is that the 
project funding that Congress provides to the Corps of 
Engineers is, then, also the funding that pays for the salaries 
of our district employees----
    Mr. DeSaulnier [interposing]. Right.
    Mr. Telle [continuing]. Who are wonderful, in most cases. 
That means that if you--if this committee--or the Congress 
appropriates $100 million for a project, $33 million of that 
project, on average, is paying the salaries of our employees. 
In my view, this can create a perverse incentive to our 
employees, our districts, to continue projects long beyond when 
they could have delivered them because there is an incentive to 
always add a new bell or a new whistle, study something a 
little bit longer, that actually sustains the district, or to 
grab a project off the shelf that maybe isn't a strategically 
important project in order to sustain it.
    And I think if we separate execution of project funding 
from the district salaries, I think it will remove that 
perverse incentive, and General Graham will be able to manage 
his organization in a way where delivery is the objective, not 
sustainment of districts.
    Mr. DeSaulnier. I wish we could be more analytical about 
this. I represent an area in region 9, and when you cut EPA, 
that affects everybody. And if you get rid of really good 
employees--because as you said, not everybody is good in any 
organization--but we have lost really good employees in other 
agencies that affects your work, and you know that.
    General Graham, just briefly, how do you prioritize these 
projects given everything we just said?
    General Graham. Representative DeSaulnier, thank you very 
much for that question.
    If I could just quickly go back to your previous question, 
one of the initiatives under Building Infrastructure, Not 
Paperwork is, let's get the project right at the beginning, 
which is your frustration. All these projects--we sometimes 
lose sight of this--there is a need out in somebody's community 
to fix a navigation project or there is a flooding challenge, 
right.
    If we don't get the engineering upfront, this committee 
can't authorize to build this scope of project correctly. And 
if we don't get the engineering right upfront, we can't 
possibly give you a good cost estimate. And so that is what has 
bedeviled us on a lot of that $78 billion is it's sitting at 
really immature engineering. So we haven't really told you what 
we are going to go build, and we certainly haven't made solid 
commitments on what the cost is going to be.
    Prioritization on my end--to answer your second question, 
sir, directly--is finish what we start. Efficient funding for 
the work that we have been told to start is the best way to 
project delivery and delivery for your constituents.
    Mr. DeSaulnier. Thank you. Thank you, Mr. Chairman.
    Mr. Collins. The Chair now recognizes Ms. Pou for 5 
minutes.
    Ms. Pou. Thank you, Mr. Chairman.
    First, let me just say I want to thank both the Assistant 
Secretary and Lieutenant Graham for being here.
    The work of the U.S. Army Corps of Engineers is deeply 
personal for the families and small businesses in the New 
Jersey Ninth Congressional District. My district includes 
communities along the Passaic River Basin, one of the most 
flood-prone watersheds in the United States. Towns like 
Paterson, Clifton, Edgewater, Lodi, and Elmwood Park have 
suffered from repeated and devastating flooding, needing our 
help. Heavy rains, higher tides, and coastal storms have caused 
repeated flooding erosions and new threats to infrastructure.
    When these crises arise, we need to quickly communicate 
with the Army Corps. Sadly, recent politicizing efforts by the 
Pentagon have made quick and necessary communication all but 
impossible. Now, the Army Corps must get approval before even 
speaking with congressional offices. And here I thought this 
administration wanted to cut redtape instead of cause more.
    Fortunately, WRDA gives us a unique opportunity to 
streamline the backlog of Army Corps projects and mitigate 
indemnification challenges that have left communities like mine 
waiting for far too long. That is why I introduced the CLEAN-UP 
Act, legislation that allows the Army Corps to remediate 
contaminated sediments under the CERCLA by using an EPA-
approved cleanup plan developed with local partners for 
authorized water projects.
    Assistant Secretary Telle and Lieutenant General Graham, 
this question is for both of you. Do you believe an EPA-
approved indemnification waiver for the Army Corps would reduce 
decades-old projects' timelines like the ones we have in the 
lower Saddle River, and if yes, can you please talk about how 
it would help?
    Mr. Telle. Congresswoman Pou, thank you for the question.
    And I am not--I haven't been able to review your 
legislation yet. I am happy to take a look. I will say that a 
project in your district, New York-New Jersey HATS, which is a 
broad and important project, large in scope, we believe may be 
one of the first projects in the Nation to benefit from the 
rapid process that we are instilling as a result of Building 
Infrastructure, Not Paperwork.
    I will let General Graham hit the specifics of that, but we 
actually--we think we have a real opportunity in your district 
to start bringing a very complex project, breaking it up into 
the piece parts that are most important to your constituents, 
get to work, and then move on to the next steps.
    Ms. Pou. That is wonderful. Thank you, Secretary.
    General Graham. So, Representative Pou, certainly the East 
Riser Ditch Project, as a spinoff from the Hudson River and 
Tributaries Project, is a great one for us to get started to 
better provide flood protection to your constituents.
    To the indemnification issue, we greatly appreciate you 
taking a look at that. So under some authorities, if there is a 
contaminated area, if we go in there, and, say, it is highly 
contaminated, we then potentially could become a principal 
responsible party. And that sometimes gets us just stuck, that 
we can't move what's needed. The contamination is not going to 
clean itself. And so I think exploring that topic would be a 
great way to clean up the environment more readily, and I think 
it is much needed.
    Ms. Pou. Thank you. Thank you so very much for that answer. 
Let me just say--and I believe you just mentioned some--the New 
York-New Jersey Harbor and Tributaries Study is also essential, 
as you just mentioned, for preparing the region for future 
storms and increasingly frequent flooding.
    Congress, as you know, has directed the Corps in the last 
three WRDAs to leverage the HATS analysis to address all types 
of flooding for the entire study area. It also requires the 
Corps to advance interim projects that are smaller in size, 
lower in cost, and prioritize nature-based solutions to reduce 
risk in the near term.
    Now, section 1343 of the 2024 WRDA directs the Corps to 
investigate and recommend projects that reduce flood risk in 
the HATS area. This includes examining individual flood risk 
and the combined effects of heavy rainstorms, storm surge, 
river flooding, sea level rise, and groundwater. This directive 
also emphasizes not just preventing damage, but producing new 
public benefits to habitat and natural systems, as well as 
community benefits like safety, resilience, and quality of 
life.
    Assistant Secretary Telle and Lieutenant General Graham, 
what actions does the Corps plan to take to implement the WRDA 
2024 section 1343? Specifically, what is the Corps specifically 
doing to evaluate and recommend projects to address both 
individual and combined flood risk while maximizing benefits 
for the New York-New Jersey Harbor and Tributaries Study?
    General Graham. Representative Pou, I will take that start. 
We will have the East Riser Ditch Chief's Report over to this 
committee by--I am tracking right now--in June. I know the 
committee----
    Ms. Pou [interrupting]. This June?
    General Graham. This June.
    Ms. Pou. Okay.
    General Graham. For us to do just that. Large problem 
flooding throughout the Hudson Bay, Raritan Bay, and to break 
that down into chunks that we can get after. Certainly, East 
Riser Ditch is one we are going to recommend for approval in 
WRDA 2026.
    Ms. Pou. Thank you. Thank you so very much. It is vital 
that we work together on this.
    Thank you, Mr. Chairman. I yield back.
    Mr. Collins. The Chair now recognizes Mr. Ezell for 5 
minutes.
    Mr. Ezell. Thank you, Mr. Chairman.
    It is good seeing both you guys here today, and I really 
appreciate all your hard work and the hard work of this 
committee. Thank you for letting me waive on.
    Secretary Telle, non-Federal stakeholders in my district 
are often given cost estimates from the Cost Engineering Center 
of Expertise, but there is no transparency into how those costs 
were calculated.
    Is there any way that we can address this in WRDA, or is 
this going to be an administrative priority?
    Mr. Telle. Well, Congressman, I share much of your 
frustration. You have been a great advocate for the Port of 
Gulfport. A lot of the work that you have done to identify this 
problem for us has caused us to relook and work with the non-
Federal sponsor to get an answer that makes more sense. I think 
General Graham may have some news to share with you there. I am 
not going to get in front of him on that.
    But this is a challenge. We have benefit-to-cost ratio, and 
both math problems, the numerator and the denominator, often 
confuse our non-Federal sponsor. So I think transparency, which 
is exactly what we did in your district with your non-Federal 
sponsor, was to sit down at the table, share our math, compare 
notes, and get to a result that everybody could stand behind.
    Mr. Ezell. Thank you.
    General?
    General Graham. Representative, so, absolutely, we are 
looking for more transparency, more partnership with our non-
Federal partners, as its name implies. Somewhere in that mix, 
though, is this is a contract that is going to go out, and we 
have just got to be careful on some of our acquisition pricing 
to make sure that that information remains with the 
confidentiality that it deserves. But I think we can absolutely 
strike the right balance and become much more transparent.
    Mr. Ezell. Thank you.
    To follow up on that, Mr. Telle, is it an administrative 
priority to implement a stakeholder review of the cost 
estimation process? For example, Gulfport was given a cost 
estimate of $40 million for its overhead dredging facilities, 
yet there is no appeal process to help us understand where that 
number came from, likely because the port and probably even the 
Mobile District don't believe it is accurate.
    Mr. Telle. Congressman Ezell, I share your frustration. 
Again, I think that this is something we can do better at. I 
think we can be more transparent. I think we can save our non-
Federal sponsors a lot of time and effort if we would share 
with them our math and work together. And that doesn't always 
mean they are going to get a BCR above 1, but we can do much 
better.
    Mr. Ezell. Thank you. I want to turn to dredging just for a 
second and the dredging material. The gulf coast, as you know, 
could use dredging material almost anywhere.
    I will ask both of you, is there any update on where the 
Corps is with implementing reusable dredging material?
    Mr. Telle. General Graham, I will let you take that one.
    General Graham. Representative Ezell, absolutely. Treating 
dredge material not as a waste product but as a valuable 
commodity is our absolute commitment. We had been doing about 
30 percent what is called beneficial reuse, taking that mud or 
sand where it is in the way of our ships and moving it 
somewhere, usually in the environment where it will do 
something good. Our goal is to get to 70 percent. So we are 
kind of moving past 30 percent right now, and our goal is to 
get to 70 percent. And this committee has given us some 
additional authorities to do that, which we appreciate.
    Mr. Telle. I will just add, Congressman Ezell, that under 
Building Infrastructure, Not Paperwork, one of the initiatives 
we have is to--a couple of the initiatives we have, one, 
encourage non-Federal sponsors, ports like the Port of Gulfport 
or others, to have a plan of what they do with their dredge 
material ahead of time so we are not confronting these issues 
in the middle of a project. We can incentivize and encourage 
that type of behavior.
    And the other is to open up mitigation banking in a way 
that allows for more flexibility and better environmental 
outcomes when we do the work we have to do to dredge important 
ports like Gulfport.
    Mr. Ezell. Thank you. Mr. Telle, we talked about your 
initiative to build infrastructure, not paperwork, and I want 
to say that this is the best news I have heard coming from the 
Corps in a long time.
    I think everyone here would agree that the Army Corps needs 
to build or assist with building and move away from the 
burdensome bureaucratic process that has hindered States and 
local communities for decades. Anything I can do to help with 
this, please let us know. And thank you both for your time 
today and all your hard work.
    And I yield back, Mr. Chairman.
    Mr. Collins. The Chair now recognizes Mr. Stanton for 5 
minutes.
    Mr. Stanton. Thank you very much, Mr. Chairman.
    Assistant Secretary Telle and General Graham, thank you for 
being here today. I don't have to tell either of you how urgent 
water security challenges that Arizona faces, how bad they are, 
with national security impacts that go far beyond State lines, 
particularly with our leadership in the critical semiconductor 
industry. They demand quick Federal action. Yet Secretary 
Hegseth's October 2025 directive that all congressional 
communications from the Corps be funneled first through the 
Pentagon has interrupted regular communication and close 
collaboration between my office and the Corps.
    Congress cannot be left in the dark on project 
implementation and delays in our districts. I trust our 
conversation today will be quickly followed by a commitment to 
schedule a meeting with myself and my staff.
    Mr. Telle. Sir, we are at your service anytime you want to 
talk to us.
    Mr. Stanton. Thank you very much. I look forward to working 
closely together as WRDA 2026 progresses.
    Arizona and the rest of the West have long suffered a 
historic drought, but we are operating in increasing 
uncertainty over the diminishing Colorado River. Negotiations 
over the river's future have not led to a lasting agreement 
between the Colorado River Basin States, despite a strong offer 
from Arizona, Nevada, and California. And worse, the Bureau of 
Reclamation's backup plan for the river threatens deep cuts to 
Arizona's water supplies.
    Look, Arizona knows how we do more with less regarding 
water. Arizona's leadership in water conservation storage, 
particularly in high-tech irrigation and water recycling, means 
we already use less water now than we did 60 years ago, even 
with a growing population. But these looming cuts make 
continued support for environmental infrastructure assistance 
in the 2026 WRDA even more critical.
    In Arizona, EI dollars support meaningful drought 
resiliency efforts in communities and Tribal nations. That's 
water lines, wastewater improvements, and aquifer recharge 
projects that will make a real difference as we make the most 
of limited Colorado River supplies.
    But getting to groundbreaking has been beyond frustrating. 
Just one of two dozen funded projects under Arizona EI has 
started construction. That is unworkable. Unfortunately, we 
have seen lengthy environmental reviews put a hold on projects 
Arizona needs today. I appreciate that the Corps has 
streamlined its NEPA processes last June and utilizes more 
categorical exclusions for EI projects. But our water situation 
demands we work faster, making more improvements to expedite 
these reviews.
    Assistant Secretary Telle, how is the Corps working to 
ensure that EI projects funded by Congress get out the door to 
communities in a timely and efficient manner? What additional 
resources or authorities, like expanded categorical exclusions 
or flexible funding reallocations, would help move these 
important projects forward?
    Mr. Telle. Congressman, thank you for the question. And I 
will just say, General Graham and I were recently in Phoenix 
together. This is a community that has been figuring it out 
when it comes to water since before Arizona was a State, before 
the United States of America was a country. So it is a 
community that understands this challenge.
    With regard to NEPA, I will say, thank you for recognizing 
the reforms that we implemented last year to NEPA to follow the 
law. But as you said, it included categorical exclusions, which 
are almost like TSA PreCheck for environmental review. It makes 
things faster, clear rules of the road.
    Here, this is what we are doing throughout Building 
Infrastructure, Not Paperwork is reducing the regulatory 
challenges by implementing smart policies that will allow 
projects like this to move ahead.
    And obviously, when it comes to environmental 
infrastructure, it is a different type of project and something 
that we--frankly, it is not within the Corps' missions, the 
Corps' expertise of the U.S. Army Corps of Engineers. We are in 
the business of major flood control projects, major navigation 
projects, major aquatic ecosystem restoration projects.
    General Graham and his team don't have particular expertise 
when it comes to municipal water systems. So one of the ways 
that we can actually deliver these projects more efficiently is 
by going out to the private sector folks who a municipality 
would otherwise contract with for this. And when Congress does 
provide money for this purpose, we believe that our private 
sector partners can quite often execute it much more 
efficiently than we can.
    Mr. Stanton. Thank you very much. I was able to secure 
authorization for increased spending limit for Tres Rios in the 
Phoenix area in WRDA 2024, but it has been years with no 
substantive movement towards resuming construction. It is a 
critical project for my community.
    Assistant Secretary Telle, will the Corps commit to 
prioritizing funding and staff resources to finally move Tres 
Rios forward?
    Mr. Telle. Congressman, I will defer to General Graham for 
an update on Tres Rios.
    Mr. Stanton. Thank you.
    General Graham. So we understand how important that project 
is for you and your constituents and the fact that that has 
been ongoing for a while. I don't have the specifics with me, 
but we are happy to get back to you on when we are moving 
forward.
    But what I do recall is that this last increment was going 
to be positively received. And we will get the exact specifics 
back to you. But it is on my radar as a very important project.
    Mr. Stanton. Thank you very much. I yield back.
    Mr. Collins. The Chair now recognizes Mr. Fong for 5 
minutes.
    Mr. Fong. Thank you, Mr. Chair.
    Assistant Secretary Telle, Lieutenant General Graham, thank 
you for being here. Thank you for your leadership.
    Secretary Telle, especially for you, thank you for coming 
to my district to see our water projects firsthand. Your 
personal attention, words can't describe how important that is 
to my community.
    I was encouraged to see your announcement of the Corps' new 
initiative, Building Infrastructure, Not Paperwork. I see this 
as an exciting, promising step towards delivering more cost-
effective water resources projects on time and on budget.
    As I have outlined to you, just in my district alone, there 
are a number of feasibility studies in the queue that are 
currently underway or hopefully will be currently underway.
    How do you foresee this initiative delivering more projects 
to the construction phase in the near term?
    Mr. Telle. Congressman Fong, thank you for the question.
    I mean, I will just say, as we were putting the finishing 
touches on Building Infrastructure, Not Paperwork, there was a 
moment we had when we were out in your district and one of the 
local officials was talking about his hope that the investments 
that we make today might benefit his grandchildren. And he had 
a realistic perspective on our program, which is it takes 
generations quite often to deliver things like Pine Flat Dam, 
which is important to your district.
    I mean, it was a sad moment for me, because I don't--we 
have almost conditioned our stakeholders out in the field to 
think that our work is going to take generations, and it 
shouldn't be that way. A Member of Congress who gets elected to 
represent their district ought to have the ability to deliver 
results for their district while they are a Member of Congress, 
not decades later.
    And so I just want to tell you how much our interaction out 
there in the Fresno area really informed our perspective on how 
important what we are doing is. And we believe this will 
benefit every project, including important projects like the 
raising of Pine Flat Dam.
    Mr. Fong. Perfect. Well, that is music to my ears. And I 
certainly appreciate you acknowledging the importance of the 
raise of Pine Flat Dam.
    In the last WRDA bill, Congress called for expediting 
certain studies, including this project, but have yet to 
discuss a cost-sharing agreement with our water districts.
    If you could, could you provide an update on the Pine Flat 
Dam Reservoir raise project? Can we commence the feasibility 
study by 2028?
    Mr. Telle. Congressman, I don't have the latest on Pine 
Flat. I am not sure if General Graham does. But you can rest 
assured we will get you an answer immediately.
    Mr. Fong. Perfect. Also, during our discussion in my 
district, we touched on the potential of the Corps continuing 
to use forecast-informed reservoir operations, otherwise known 
as FIRO, and incorporating airborne snow observation flights to 
better predict and manage snowpack, which is extremely 
important in California, especially with the snowstorms that 
just came through.
    How does the Corps plan to incorporate advanced 
technologies into their water control strategies, especially in 
the Western United States?
    Mr. Telle. Well, Congressman Fong, what we learned when we 
were in your district recently was--we like to talk about FIRO. 
It is a great tool to squeeze as much water as we can, as much 
flood relief as we can out of our existing facilities by 
looking at weather patterns and making smart judgments about 
when to take risk.
    What we really learned, though, from your district was that 
what is called SIRO, snow-informed reservoir operations, is 
even more important. And this is where we or our partners fly 
lidar flights above the mountains when there is no snow and 
then we fly lidar above the mountains when there is snow, and 
we make a determination about the snowpack.
    And this actually is an area where we can do more and 
better to, again, continue to squeeze as much as we possibly 
can out of our existing infrastructure at a relatively low 
cost.
    Mr. Fong. Well, thank you for that. As you know, water is 
life for us. I represent the food production capital of 
California. So we look forward to the partnership, 
incorporating this new technology, so that we can move more 
water in real time as we get it.
    Lastly, as you saw in your visit, there is significant 
potential to provide additional water resources in California 
through the Redbank and Fancher Creek Project, which is also 
undergoing a feasibility study.
    During your visit, I believe General Kelly offered his 
team's assistance in rescoping the existing study to 
incorporate a more streamlined and scalable decisionmaking 
scope to be aligned with the transformation initiative that you 
outlined, which would significantly reduce the budget of the 
existing study.
    Can the Army Corps' leadership work with the Sacramento 
District in reducing the scope even more while remaining 
compliant with the Corps' new initiative here?
    General Graham. Representative Fong, if I could, going back 
to your earlier question, when you spoke to Pine Flat study, 
funding will be one of the needs to move that dam raise study 
forward.
    Turning to Redbank and Fancher Creek, as General Kelly 
probably talked to you about, carving off the dry creek portion 
of that, taking a look, see what we can do with that dry 
reservoir to see if we can hold onto more floodwater longer and 
release that for managed aquifer recharge, certainly that is a 
bit of low-hanging fruit that we ought to work together on.
    Mr. Fong. Well, these projects are certainly very 
important. I have run out of time. But, Secretary Telle, 
General Graham, thank you for your leadership, thank you for 
your partnership, and I look forward to working with you.
    Thank you. I yield back.
    Mr. Collins. The Chair now recognizes Mr. Carbajal for 5 
minutes.
    Mr. Carbajal. Thank you very much.
    Thank you, Assistant Secretary Telle and Lieutenant General 
Graham, for testifying today. When you went to my colleague 
Representative Fong's district, you should have come over the 
mountains to paradise, which is my district right on the coast. 
But I am sure his district was almost as beautiful as mine.
    I represent the central coast of California, which 
encompasses a diverse portfolio of Corps projects that promote 
public safety, strengthen economic vitality, and support Coast 
Guard operations and national security.
    I have always appreciated the work that the Corps does 
through Democratic or Republican administrations. You guys 
always do extraordinary work and oftentimes in a nonpartisan 
way, which is really what the American people expect.
    Secretary Telle, for some reason, Santa Barbara Harbor 
dredging was left out of the President's budget for fiscal year 
2026, despite its critical role in supporting the Coast Guard, 
national security, our regional economy, and coastal 
operational needs.
    I sent you a letter on January 26th, following enactment of 
the energy and water appropriations bill, advocating on behalf 
of Santa Barbara Harbor and the $4 million they need in the 
fiscal year 2026 Corps work plan. I bring this to your 
attention to ask that you give it your full and fair 
consideration. I hope I can get your commitment that you will 
take a look at this, and my office can follow up with your team 
on this. Perhaps you could come out to paradise, just like you 
did to Mr. Fong's district, to see some of these projects.
    Secretary Telle, the Salinas Dam in San Luis Obispo County 
is currently owned by the Corps. San Luis Obispo County has 
indicated their interest in taking ownership of this project. 
We have had numerous conversations with the Corps, both the 
L.A. District and headquarters, regarding this ongoing--back to 
my first term in Congress in the 115th Congress, almost 10 
years ago.
    In the last bipartisan WRDA bill of 2024 enacted into law, 
I was able to successfully include a provision that allows the 
Corps to convey the Salinas Dam to the San Luis Obispo County 
government. This was section 1306 of the bill.
    Can you provide me with an update on ongoing discussions 
with San Luis Obispo County regarding this conveyance?
    Mr. Telle. Congressman Carbajal, I looked at General 
Graham. He does not have an update on that. We commit to get 
you one here before the end of the day.
    Mr. Carbajal. Great.
    Mr. Telle. And I will say that Congressman Fong's district 
is beautiful, and I hope to visit yours. I also got to say, 
we--the manager of Pine Flat Dam is the son of a citrus farmer, 
and we managed to find out where there are some oranges and 
some clementines and some lemons while we were out there. And I 
got to recommend them to everybody. It is the best thing we 
ever tasted.
    Mr. Carbajal. Well, that is because you haven't tasted the 
wine in my country, the central coast.
    Should we make the law more clear as it relates to the 
conveyance language that I got in the bill to help?
    Mr. Telle. Congressman Carbajal, I am not aware of any need 
we have related to legislation, but we will get you an update 
by the end of the day.
    Mr. Carbajal. Thank you. Let me just say that it feels like 
we have just been going in circles on this issue. So to the 
extent that you could give it your attention and help us 
resolve a clear path forward, I would greatly appreciate it.
    Secretary Telle, as you are probably aware, construction of 
the Lower Mission Creek Project in Santa Barbara has been 
authorized since the year 2000 and was later amended in 2007 to 
reflect the cost share between the Federal and non-Federal 
partners.
    Despite this project being shovel-ready, our local 
government having invested over $18 million in non-Federal 
resources, Federal dollars have not been made available.
    I understand the Corps has recently updated the principles, 
requirements, and guideline procedures to more accurately 
capture total public value and taxpayer return on Federal 
investments.
    Will these new standards help with a positive BCR score for 
the lower Mission Creek?
    Mr. Telle. Congressman, we just had an outstanding 
conversation with Congressman Ezell about this same issue. We 
believe that--I believe that we can do more in terms of 
providing transparency to non-Federal sponsors in relation to 
the costs and benefits and how we calculate them.
    We don't need to be doing this math in a black box. We need 
to be sharing it and making sure everybody is in agreement, 
even if the non-Federal sponsor disagrees.
    But I would anticipate that the updated guidance that you 
mentioned will benefit projects like this one, because we are 
always able to take into consideration more than just the raw 
economic numbers and consider other factors.
    Mr. Carbajal. Thank you very much. You have a standing 
invitation to visit my district anytime. I know traditionally, 
administrations make visits to only Members of their parties, 
but I sure hope you will consider coming to my district.
    Mr. Telle. Sir, I am happy to do it. We have been out to 
California numerous times since I have been in this role, and I 
look forward to getting back out there.
    Mr. Carbajal. Great. Thank you so much.
    Mr. Collins. Thank you. The gentleman yields back.
    Are there any further questions from any members of the 
subcommittee who have not been recognized?
    All right. Seeing none, the chairman is going to indulge 
because he can, because he is the chairman. I just thought I 
would take a couple of minutes.
    As I sat through this whole hearing and listened, I think 
you all understand a little bit of the issues, and that's the 
fact that people are always asking about the same projects over 
and over and over that haven't been authorized or the studies 
aren't complete.
    And as a small business person, been in small business all 
my life, it is nice to see that sometimes you take a look at 
just what the problem is. And it may not be bad people, it may 
be the process. And you take an inwardly look, and it is 
exciting to see that both of you are doing that, and to just 
look at the process maybe. Maybe we are looking at the process 
wrong so that we can speed up things for Mr. Carbajal, who 
probably would love to come to Georgia to get some good 
barbecue. But it is good to see that.
    And even though this will be my last WRDA bill as a Member 
of the House--or I won't be at the next one, anyway--it is 
exciting. I would love to see just how many of these projects 
that people just come in and sit down and say, thank you, it is 
completed, or it is in the appropriation phase.
    So, with that, I appreciate you all coming today. Thank you 
for your testimony.
    And this subcommittee stands adjourned.
    [Whereupon, at 12:24 p.m., the subcommittee was adjourned.]

                     Submissions for the Record

                              ----------                              


   Letter of February 24, 2026, from Brandon Farris, Executive Vice 
   President, Steel Manufacturers Association, to Hon. Mike Collins, 
Chairman, and Hon. Frederica S. Wilson, Ranking Member, Subcommittee on 
Water Resources and Environment, Submitted for the Record by Hon. Mike 
                                Collins
                                                 February 24, 2026.
The Honorable Mike Collins,
Chairman,
Subcommittee on Water Resources and Environment, U.S. House of 
        Representatives, Washington, DC 20515.
The Honorable Frederica S. Wilson,
Ranking Member,
Subcommittee on Water Resources and Environment, U.S. House of 
        Representatives, Washington, DC 20515.
    Dear Chairman Collins and Ranking Member Wilson:
    The Steel Manufacturers Association appreciates the opportunity to 
provide a statement for the record for the Subcommittee's hearing, 
entitled ``Proposals for a Water Resources Development Act of 2026--
Administration Priorities.''
    SMA stands for American steel. Our members operate in communities 
across the country and range from the nation's largest publicly traded 
steel producers to single-facility, family-owned businesses. Steel 
manufacturers generate $149.4 billion in annual economic impact, 
employing 87,266 men and women in community-sustaining jobs at an 
average annual wage of $142,730. They create the essential material 
that underpins American industry and national security.
    Steel manufacturers are investing in American's communities, 
deploying $25 billion in capital here in the U.S. to modernize, expand, 
and construct facilities. This is made possible by smart trade policies 
promulgated in 2018 and continued on a bipartisan basis that recognize 
the importance of domestic steel manufacturing to America's economy and 
national security.
    Continued federal support for infrastructure rehabilitation and 
construction is essential to capitalize on the investments made by 
American steel producers, inducing demand and supporting job creation. 
From surface transportation reauthorization to WRDA, Congress has a 
tremendous opportunity in the near term to ensure America continues to 
build, and to build with American steel. Furthermore, modernizing 
infrastructure will help ensure more efficient transportation supply 
chains for steel manufacturers and the entire economy.
    SMA applauds the Subcommittee for beginning consideration of WRDA 
2026. As development of the legislation begins, we respectfully urge 
members to focus on the Army Corps of Engineers core mission areas of 
navigation and flood risk management. Importantly, this recognizes the 
need for rehabilitation of aging inland waterways infrastructure, the 
failure of any project of which would be highly disruptive. We also 
encourage maintaining Build America, Buy America policies critical to a 
strong domestic steel industry and the family-supporting jobs that come 
with it. Our industry built America, and BABA provisions ensure those 
same jobs can continue to answer the call for all of our nation's 
needs.
    Steel manufacturers are committed to working with the Subcommittee 
and your colleagues to continue biennial development and passage of 
WRDA legislation. Thank you for your consideration.
            Sincerely,
                                            Brandon Farris,
         Executive Vice President, Steel Manufacturers Association.

                                 
Prepared Statement of Hon. J. French Hill, a Representative in Congress 
   from the State of Arkansas, Submitted for the Record by Hon. Mike 
                                Collins
    Chairman Graves, Ranking Member Larsen, thank you for the 
opportunity to submit a Statement for the Record for the hearing 
entitled Proposals for a Water Resources Development Act (WRDA) of 
2026. I appreciate the opportunity to offer my comments for 
consideration to your committee and witnesses.
    As you all likely know, I recently submitted a WRDA proposal 
requesting that the Little Rock Army Corps of Engineers conduct a 
Reallocation Study of Greers Ferry Lake concurrent with the ongoing 
White River Basin Study (WRBS). Conway is one of the fastest growing 
areas in Arkansas. Since 2000, in fact, Conway's population has grown 
61%, and it is projected to continue to grow throughout the next 
decade.
    Unfortunately, population growth is estimated to outpace water 
supply in the next decade. As such, without additional water storage 
allocations, parts of central Arkansas may have to deny industrial 
growth and economic development to ensure adequate drinking supplies 
for constituents. In anticipation of this need, Community Water System 
(CWS) and Conway Corp are collaborating on a regional water intake 
structure on Greers Ferry Lake, a transmission line to the northeast 
area of Conway, and construction of a new water treatment plant, 
however, they have yet to have confirmation on a water relocation study 
so that they can properly prepare for this need as they construct. In 
the meantime, Conway Corp and CWS are still paying the Little Rock Army 
Corps for water storage allocations that they cannot use.
    WRDA specifically authorizes studies and projects that include 
navigation, flood control, and ecosystem restoration. Congress also 
provides the United States Corps of Engineers with the authority to 
address water supply needs, as noted above. While I understand there 
has been some concern about conducting the two studies concurrently, 
the Little Rock Army Corps conducted a water supply storage 
reallocation study in 2017, which released the water in 2020.
    Given the need, I voice my support for including language in WRDA, 
requesting completion of a reallocation study on Greers Ferry Lake, 
notwithstanding or separate from Section 729 of the White River Basin 
Study. Should inclusion of this critical language be accepted, I also 
invite strong consideration that the Committee provide funding in the 
fiscal year (FY) 2026 work plan following FY 2026 enactment.
    Thank you for your consideration. These items are important to my 
home state of Arkansas. I stand at the ready to work with the Committee 
and lend my support for these matters.

                                 
Prepared Statement of Hon. Brian J. Mast, a Representative in Congress 
                       from the State of Florida
    Mr. Chairman, thank you for holding today's hearing on proposals 
for the Water Resources Development Act of 2026, and thank you to 
Assistant Secretary Telle and Lieutenant General Graham for being with 
us.
    WRDA is not just another infrastructure bill. It is Congress' 
directive to the U.S. Army Corps of Engineers on how to carry out its 
civil works mission. WRDA is the blueprint for how we manage water, 
protect ecosystems, support commerce, and restore communities. For my 
district in Florida, the decisions we make here in this committee have 
a direct impact on quality-of-life. The people in this room have the 
privilege of determining whether our rivers are healthy, whether our 
estuaries can survive, and whether our local economies have the tools 
to thrive.
    For Florida's 21st district, the health of the St. Lucie River and 
Estuary, the Indian River Lagoon, and the broader Everglades system are 
intertwined with tourism, fishing, small businesses, and property 
values. During harmful discharges from Lake Okeechobee, the 
consequences are immediate--everything from lost revenue, damaged 
ecosystems, and public health risks are on the table.
    In WRDA 2026, I am focusing on durable and clear priorities.
    First, we must accelerate Everglades restoration and take full 
advantage of new infrastructure, like the Everglades Agricultural Area 
Reservoir, so that water is stored and sent south--through Everglades 
National Park--instead of unnaturally discharged to our coastal 
estuaries.
    Second, we need greater accountability in water management 
decisions. When operational deviations occur, Congress and affected 
Americans deserve clear reporting on where water was sent, what 
environmental impacts resulted, and if better alternatives should have 
been utilized.
    Third, we must move toward ecologically-based standards for 
facilitating the flow of freshwater into our estuaries. A successful 
outcome would come from real, quantitative environmental recording--the 
health of seagrass, oysters, nutrient loading, and harmful algal bloom 
risk are all calculable. Modeling thresholds are no longer enough.
    Fourth, we should prioritize projects like muck removal in the 
Indian River Lagoon that produce specific water quality improvements, 
and see that any taxpayer dollar that goes toward restoration delivers 
results.
    And finally, WRDA should modernize how the Corps operates. New 
strategies like expanding the use of private-sector design services, 
embracing digital tools to streamline reviews, improving dredge fleet 
transparency, and eliminating any unnecessary costs on non-federal 
partners. If we want projects done right and done fast, we have to 
remove outdated constraints.
    WRDA 2026 is a unique opportunity to strengthen infrastructure, 
protect commerce, and restore America's most valuable ecosystems. With 
a clear plan, measurable standards, and increased accountability, 
communities like mine will experience real relief and improvement.

                                 
 Letter of February 27, 2026, from Colonel Brandon L. Bowman, District 
Commander, U.S. Army Corps of Engineers, Jacksonville District, to Hon. 
  Brian J. Mast, Member of Congress, Submitted for the Record by Hon. 
                             Brian J. Mast
                                                 February 27, 2026.
The Honorable Brian Mast,
United States House of Representatives,
2182 Rayburn House Office Building, Washington, DC 20515.
    Dear Representative Mast:
    This is in response to your letter dated February 20, 2026, 
regarding the Fort Pierce, Florida Shore Protection Project (SPP). It 
provides the requested information on renourishment frequency, 
shoreline stabilization measures, and project timelines.
    Regarding the frequency of renourishments for the current coastal 
storm risk management project, the U.S. Army Corps of Engineers 
conducts beach renourishment for the Fort Pierce, Florida SPP on an 
approximate two-year cycle. The project was authorized by Section 301 
of the Rivers and Harbors Act of 1965 (Public Law 89-298), as amended. 
To confirm, the last two renourishments were conducted April-May 2021 
and March-April 2023. The next renourishment for the Federal project is 
scheduled for March-May 2026. The approximate two-year frequency did 
not change after April 2023, but the Corps did not receive bids within 
the awardable range when the renourishment solicitation was issued in 
2025.
    Under Section 203 of WRDA 1986, as amended, the non-Federal sponsor 
(the St. Lucie County Erosion District) conducted a feasibility study 
to address hurricane and coastal storm damages in the area of Fort 
Pierce. The Recommended Plan includes beach and dune renourishment 
along 7,000 feet of shoreline with construction of shoreline 
stabilization structures at the north end of the existing Federal 
project, consisting of five T-head groins, a T-head weir, and a 
detached breakwater.
    In Section 403(a) of WRDA 2020, Congress provided conditional 
authorization for construction of the Fort Pierce, St. Lucie County, 
Florida Project based on the Section 203 study. The Energy and Water 
Bill of 2026 provided the project $500,000 in investigations through 
Congressionally Directed Spending to initiate the Pre-Construction 
Engineering and Design Phase, with a design agreement anticipated to be 
executed in FY 2026. Regarding your second inquiry, T-head groins can 
improve sand retention and extend the time between renourishments when 
erosion rates are high. However, T-groins redistribute rather than 
eliminate erosion and require careful siting and design to avoid 
downdrift impacts. They are generally most effective in closed or 
terminal beach systems and are more challenging to implement along 
open-coast shorelines. The Corps and non-Federal sponsor will address 
the challenges associated with T-groins during design.
    Regarding your third inquiry, contract award to initiate 
construction is anticipated in August 2029, with construction in 2030-
2031. This construction timeline is subject to receipt of future 
appropriations for construction.
    If you have additional questions or concerns, please contact me or 
your staff may contact Julie M. Treichel.
            Sincerely,
                                         Brandon L. Bowman,
        Colonel, District Commander, U.S. Army Corps of Engineers, 
                                             Jacksonville District.

                                Appendix

                              ----------                              


 Post-Hearing Question for the Record to Hon. Adam R. Telle, Assistant 
  Secretary of the Army for Civil Works, Department of the Army, from 
                           Hon. Mike Collins

    Question 1. Assistant Secretary Telle, could you please provide an 
update on the implementation of Section 1154a of the Water Resources 
Development Act of 2018, which requires the Assistant Secretary of the 
Army to create a searchable, downloadable database of all unfunded 
projects?
    Answer. The Corps is working to identify the information requested 
in Section 1154(a), which amended Section 1001 of the Water Resources 
Development Act of 1986 (33 U.S.C. 579a). After providing this 
information to the Senate Committee on Environment and Public Works, 
the House Committee on Transportation and Infrastructure, and the 
Committees on Appropriations, the Corps will post the lists described 
in subsection (b)(2)(A) of Section 1001 in a downloadable, searchable, 
and sortable format on a publicly accessible website.

Post-Hearing Questions for the Record to Hon. Adam R. Telle, Assistant 
  Secretary of the Army for Civil Works, Department of the Army, from 
                     Hon. Eric A. ``Rick'' Crawford

    Question 1. Secretary Telle, over the last few months, my staff and 
I have experienced increasing difficulty obtaining timely responses 
from Army Corps District offices that operate within my district. My 
district includes numerous Army Corps projects spanning three Districts 
and two Divisions, and when my staff requests basic status updates, 
answers can often take well over a week. I have been led to believe 
that this delay is due to larger Department of Defense regulations 
limiting personnel from outside the Office of the Legislative Affairs 
speaking directly with members of Congress or Congressional staff.
    As you know, timely communication is important to ensure we can 
effectively support these projects. During the WRDA priority submission 
process, it was challenging to connect with District leadership to 
better understand project needs and ongoing efforts. Improved 
communication would benefit both Congress and the Corps as we work 
toward shared goals. I want to ensure that we do not encounter similar 
challenges during the FY 2027 Appropriations process. We all share the 
goal of delivering results to the American people efficiently and 
effectively. I want to note that you have publicly stated on multiple 
occasions the importance of reducing bureaucratic delays and cutting 
red-tape. I appreciate that focus and believe strong communication 
between District offices and Congress is part of achieving that 
objective.
    Can you provide assurance that communication between the Army Corps 
Districts and Members of Congress and their staff will remain timely 
and fully accessible during the WRDA 2026 and FY 2027 Appropriations 
processes?
    Answer. I can assure you that I am committed to providing timely 
responses to Members of Congress.

    Question 2. Five years ago, the Army Corps published in an April 
2021 guidance document (Engineer Circular No. 1165-2-218) that it 
intended to establish and carry out federal levee safety program and 
performance metrics relating to federal levee safety program auditing; 
and independent peer reviews of federal levee program activities and 
achievements.
    Can you inform me where we stand on key performance indicators, 
auditing, and independent reviews for the Army Corps' levee safety 
program?
    Answer. In a memorandum dated September 15, 2023, the Corps 
established performance indicators to guide and monitor the 
effectiveness of its actions under the levee safety program. These 
metrics are directly aligned with the activities and concepts described 
in Engineer Circular 1165-2-218.
    The programmatic audits will be scheduled on a rotating basis, with 
an audit conducted for two divisions each year. Four of the Corps' 
eight divisions have participated in these programmatic audits thus 
far, either as part of the Army Organizational Inspection Program 
(which is a comprehensive process for coordinating various reviews to 
identify, prevent, and eliminate problem areas) or through a separate 
process. The remaining division audits have not yet occurred.
    It is still the intent of the Corps to initiate an independent 
review of the Corps Levee Safety Program; however, one has not been 
conducted yet.

Post-Hearing Questions for the Record to Hon. Adam R. Telle, Assistant 
  Secretary of the Army for Civil Works, Department of the Army, from 
                           Hon. Jared Huffman

    Question 1. What is the current status and anticipated completion 
date of the Coyote Valley Dam Raise feasibility study? Please identify 
any remaining barriers to completion.
    Answer. The study received $500,000 in FY 2024; the Corps had 
obligated just under half of that amount by the end of November 2025 to 
prepare for the Alternatives Milestone Meeting, and the project is 
currently under review.

    Question 2. What alternatives are being evaluated, including dam 
crest raise options, modified outfalls, or turbidity control 
infrastructure?
    Answer. Alternatives considered include the following: dam raise; 
raise and modify spillway; modify outlet works (pulling from different 
elevations, part of a dam raise); addition of a secondary outlet; 
reallocate water to different uses; modify water control manual; and 
dam notching.

    Question 3. What is the Corps' current assessment of turbidity 
impacts downstream of Coyote Dam on Chinook salmon and steelhead, and 
how frequently is turbidity monitored?
    Answer. In 2023, the Russian River Turbidity Assessment and 
Proposed Plan was published as part of the Coyote Valley Dam-Lake 
Mendocino Water Manual Control Update's final Environmental Assessment. 
This plan documents the long-term trend of increased turbidity in the 
Russian River in the last 20 years, with no clear seasonal patterns, 
and several possible contributing sources, including: 1) erosion during 
rainstorms; 2) turbid water from the Eel River being diverted into the 
East Fork of the Russian River; 3) turbid water persisting in Lake 
Mendocino due to slow settling of suspended sediment; 4) elevated flow 
releases from Lake Mendocino causing increased erosion downstream; 5) 
sand and gravel mining; 6) other human activities causing increased 
erosion, such as road construction and logging; 7) algal blooms; and 8) 
entrainment of fine sediments by release gates.
    An assessment of turbidity impacts to the species downstream 
requires observations over a period of years. This work is ongoing as 
part of the 2025 Russian River Watershed Water Supply and Channel 
Maintenance project Biological Opinion (Russian River Biological 
Opinion). Turbidity is monitored continuously at multiple locations as 
prescribed in the opinion.

    Question 4. What operational changes are under consideration to 
meet turbidity thresholds and reduce impacts on listed species?
    Answer. There are no turbidity thresholds for the project. The only 
recent operational changes implement the principles of forecast 
informed reservoir operations (FIRO), related to flood control 
releases, within the updated water control manual.

    Question 5. How does requiring additional department approval 
before district or field offices communicate with congressional offices 
improve project delivery, technical accuracy, or mission execution?
    Answer. It is important that all communications to the Congress 
related to the Army Civil Works Program are accurate, reflect Corps 
policy, and are consistent with Administration guidance.

    Question 6. Has the Corps conducted any analysis of how this policy 
may affect the timeliness of responses to Congress regarding 
feasibility studies, project implementation, or technical assistance?
    Answer. A process has been established that includes having 
dedicated staff reviewing and approving congressional inquiries and 
other requests.

 Post-Hearing Question for the Record to Hon. Adam R. Telle, Assistant 
  Secretary of the Army for Civil Works, Department of the Army, from 
                        Hon. Hillary J. Scholten

    Question 1. On September 25, 2024, the Assistant Secretary of the 
Army for Manpower and Reserve Affairs forwarded to the Under Secretary 
of Defense for Personnel and Readiness the Army Corps' SECOND request 
to establish a special salary rate for Soo Lock operators to reverse 
the 19% pay cut they are taking due to a quirk in Army Corps 
regulations.
    Assistant Secretary Telle, what response has the Army Corps 
received regarding the status of this request? Since these Soo Lock 
employees have been enduring pay cuts since 2022, would the Corps 
support a solution for these employees through WRDA 2026?
    Answer. The Corps requested a Special Salary Rate (SSR) for Soo 
Lock and Dam employees on August 4, 2022. The SSR request is under 
review.

 Post-Hearing Question for the Record to Lieutenant General William H. 
``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. 
            Army Corps of Engineers, from Hon. Mike Collins

    Question 1. The inland navigation industry pays for 25 percent of 
the costs for lock and dam projects through a diesel fuel tax. General 
Graham, what is the Corps doing to respond to industry's request to 
have a single dedicated person to oversee inland waterways construction 
as a program?
    Answer. The Corps has made the following changes to the delivery 
model:
      In October 2025, the Corps established an Engineering and 
Construction (E&C) Directorate that reports to the Chief of Engineers. 
This new directorate will provide centralized oversight for the 
construction programs. The Corps is also implementing a lifecycle 
delivery approach and applying Mega Project delivery principles to new 
lock design and construction to ensure the appropriate level of 
governance and oversight.
      We have clarified and consolidated design and 
construction responsibilities to improve efficiency and 
standardization. The Inland Navigation Design Center (INDC) is the 
designer of record for all new lock and dam work. The INDC is empowered 
to establish standardized designs and common work processes and is 
responsible for cost estimates and construction schedules. We are 
increasing staff in the INDC in accordance with the INDC Framework 
Report. We have established production centers in Rock Island and 
Pittsburgh districts that are responsible for INDC resourcing support 
for all major rehabilitations and new construction.
      To further improve project delivery and avoid rework, the 
Corps is implementing the following design process changes:
      +  The design completion level prior to congressional 
authorization will be 35%. After the project is authorized, the Corps 
will complete 100% design before starting construction.
      +  To allow for a more thorough process, design work will begin 3 
to 4 years before construction is scheduled to start.
      +  An enhanced review process is being implemented for all 
designs.

    We believe these changes are creating a more standardized and 
efficient approach to the inland waterways construction program and 
will improve execution.

 Post-Hearing Question for the Record to Lieutenant General William H. 
``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. 
      Army Corps of Engineers, from Hon. Eric A. ``Rick'' Crawford

    Question 1. Section 221 of the Flood Control Act of 1970 is one of 
many Congressional requirements in water resources law emphasizing the 
Corps' collaboration with local levee owners. However, significant 
changes on levee evaluation, including use of probabilistic methods on 
things like the accreditation of levees, are increasing Federal agency 
leverage at the expense of local decision making and input. I am 
concerned that under the guise of modernity, the Corps has replaced 
joint Corps-local sponsor levee inspections.
    How has the Corps' shift to a probabilistic levee evaluation 
approach, which relies on internal models and data, rather than the 
prior deterministic method, impacted the level of meaningful 
collaboration and shared decision making with local levee owners, and 
what measures are in place to ensure local input influences risk 
assessment and final outcomes?
    Answer. Risk assessments supplement the joint Corps-local sponsor 
inspections. Together, the levee inspections and risk assessments 
enable the levee sponsor to understand more fully the condition of its 
levee and its effect on the overall flood risk. Levee sponsors are 
essential members of the risk assessment team and are the ultimate 
intended users of the results. The goal is to equip levee sponsors with 
the information and tools to enable them to understand and effectively 
manage their risk.
    For risk assessments, levee sponsors provide input on unique levee 
records; maintenance and emergency activities; community land use 
trends; other community participants; validation of results, and 
actionable recommendations. The Corps requires notifying levee sponsors 
at least 30 days prior to the start of any risk assessment. Levee 
sponsors can decide their level of participation in the analysis. They 
are involved in reviewing the results and developing any recommended 
actions. Following this process, the levee sponsor may decide on its 
own to reduce its flood risk through a series of steps over time, based 
on the costs and benefits of the potential actions.
    Deterministic methods and standards are part of the levee 
evaluation. A probabilistic approach, also known as risk assessments, 
supplements deterministic methods to provide a more comprehensive 
understanding of the levee. Risk assessments use probabilistic analyses 
to better understand ways a specific levee may fail and the resulting 
potential impacts. For example, one concern expressed by some levee 
owners is that there should not be a one-size fits all approach to 
levees. Risk assessments take into account the differences in flood 
loading (long duration floods versus flash floods); levee materials 
(sandy versus clay); past performance; and assets behind the levee 
(urban versus agricultural). This more textured type of analysis is 
needed to enable levee sponsors to identify options and prioritize 
their actions based on what is most cost-effective and impactful to 
address their flood risk; and to help them plan and adapt their 
operational and emergency action processes.

Post-Hearing Questions for the Record to Lieutenant General William H. 
``Butch'' Graham, Jr., Chief of Engineers and Commanding General, U.S. 
           Army Corps of Engineers, from Hon. Laura Friedman

Los Angeles River Ecosystem Restoration Project
    Question 1. Please clarify why ``federal funding is not available'' 
to support the completion of the PACR for the WRDA 2026 timeline.
    Does the Corps simply not have funds available? Has the Corps 
depleted the existing authorized funding for this purpose? Or, does the 
Corps have funds available that could be used for this project, but the 
Corps does not believe these funds are appropriately authorized to be 
used?
    Answer. The project is under review.

    Question 2. Lt. Gen. Graham addressed concerns with ``rising 
costs'' associated with completing this project. How does the Corps 
plan to address any additional costs that accrue as a result of the 
existing delay with the PACR and any further delay to the project 
resulting from Corps inaction?
    Answer. The concerns expressed with ``rising costs'' are not 
related to the timeframe for completing the PACR. Cost increases would 
be addressed in the PACR.

    Question 3. Please elaborate on the ``concerns about the viability 
of the project''. What specific aspects of the project are the Corps 
concerned about?
    Answer. Project costs have increased by $2 billion; Lands, 
Easements, Right of Ways, Relocations, and Dredged Material Disposal 
Area costs are approximately $3 billion. Construction costs have 
increased due to inflation, and contingency has increased from 37% to 
51% based on current level of design and remaining risks. An additional 
concern is the relocation of Reach 8, the LA Transit Center (LATC). 
Union Pacific Railroad continues to make significant capital 
investments in the LATC and states there is no viable relocation site. 
As the project's largest environmental benefits come from Reach 8, this 
is a significant concern to the project's environmental restoration 
outcomes.

    Question 4. In communication with my office, the Corps communicated 
that the ``area in question is important to the community'' and that 
``environmental concerns'' have resulted in delays to the PACR 
completion. I agree that this area is vital to the community, can you 
please elaborate on the specific environmental concerns that need to be 
addressed to move forward with this project?
    Answer. It is important that we get the engineering right. To 
implement this multibillion-dollar project, the Corps would look at 
dividing the project into separable elements for early actionable 
implementation. Each element must have justified restoration outputs 
(33 U.S.C. 2213(f)). Providing the most restoration output for the 
investment is an environmental concern. An additional environmental 
concern is the relocation of Reach 8, the LA Transit Center (LATC). 
This is uncertain. Union Pacific Railroad continues to make significant 
capital investments in the LATC and states there is no viable 
relocation site. As the project's largest environmental benefits come 
from Reach 8, this is a significant concern to the project's 
environmental restoration outcomes.

    Question 5. Lt. Gen. Graham also spoke of the need to balance the 
flood risk management purposes of the LA River with environmental 
concerns associated with the project. What aspects of the project does 
the Corps believe will interfere with flood risk management? How can 
the non-federal sponsor work with the Corps to ensure any concerns 
about the ability to mitigate flood risk is addressed by the project 
while also supporting the ecosystem restoration needs of the area?
    Answer. One of the biggest risks to successful completion of this 
project is the complexity of ecosystem restoration measures coupled 
with a successfully functioning flood risk management (FRM) project. 
The engineering must be right to maintain the level of FRM for the LA 
community. Currently, the project is at a 10% level of design maturity. 
Design efforts including hydrologic and hydraulic modeling and Geotech 
basis of design for the system are needed to increase confidence in the 
FRM project's continued function and the ability to design successful 
restoration features. The FRM project is complex, going from an earthen 
channel in the north to a concrete trapezoidal channel to the south 
with associated variations in flow regimes. For example, In-Channel 
work can't be accomplished on Reach 7 without Reach 8 out-of-channel 
work. The non-Federal sponsor can help by supporting the required 
system Design Maturity efforts.

    Question 6. The Corps has also highlighted the difficulty the non-
federal sponsor has had in securing required real estate. As you know, 
real estate is expensive in the Los Angeles area, and those costs will 
continue to rise the longer the Corps delays the completion of the 
PACR. How does the Corps plan to account for rising real estate costs 
associated with Corps delays while working towards PACR completion?
    Answer. Real estate costs represent the most significant financial 
risk to the project, accounting for over two-thirds of the total 
estimated cost. These costs have escalated by 175% since the 2016 
authorization. While the Corps adjusts for this by applying local 
inflation indices in Section 902 calculations, this method remains 
reactive to market changes. The primary strategy to mitigate this risk 
is for non-Federal sponsors to pursue early property acquisitions. This 
proactive measure will lock in prices and minimize the financial risk 
associated with market inflation.

    Question 7. In Corps communication with my office, the Corps stated 
that ``based on current estimates, we would need additional funding to 
complete the PACR.'' How much additional funding is necessary to 
complete the PACR? Please provide a breakdown of the costs associated 
with the work already done on the PACR as well as a detailed estimate 
on the additional funds necessary to complete the PACR.
    Answer. The project is under review.

    Question 8.a. Please elaborate on the additional costs associated 
with ``advancing the design maturity of the entire project to 35%.'' 
How much additional funding would be necessary with advancing the 
design maturity of this project?
    Answer. The project is under review.

    Question 8.b. Additionally, our office is not familiar with any 
PACRs that have been subject to the 35% design maturity requirement. As 
the LA River project is already a fully authorized project, can you 
explain why the PACR is subject to this requirement?
    Answer. The current cost estimates for the project exceed the 
authorized limit under section 902 of WRDA 1986. The requirement of a 
35% level of design includes projects subject to a PACR to deliver 
studies that are both timely and fiscally responsible, ultimately 
providing more confidence in the cost estimates and project outcomes.

    Question 9. Finally, the Oct. 15 Department of War directive 
limiting Corps communication with Congressional Offices has resulted in 
several weeks long delays in communication with my office on this 
project. At the Feb. 24, 2026, hearing before the Water Subcommittee, 
Lt. Gen. Graham stated that any ``clunkiness'' associated with this 
directive is his responsibility to iron out. Please provide a list of 
action items the Corps can commit to taking to speed up communication 
with Congressional offices.
    Answer. It is important that all communications to the Congress 
related to the Army Civil Works Program are accurate, reflect Corps 
policy, and are consistent with Administration guidance. A process has 
been established that includes having dedicated staff reviewing and 
approving congressional inquiries and other requests.

Post-Hearing Questions for the Record to Hon. Adam R. Telle, Assistant 
  Secretary of the Army for Civil Works, Department of the Army, and 
Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers 
and Commanding General, U.S. Army Corps of Engineers, from Hon. Eric A. 
                           ``Rick'' Crawford

    Question 1. Thank you for your response to my question regarding 
the removal of the Little Rock District Commander. Your answers have 
provided greater insight into the factors that led to Colonel Caukin's 
removal. In addition to the questions posed during the Subcommittee 
hearing, I have additional questions for further clarification.
    Question 1.a. My understanding is that the Southwestern Division 
had been fully briefed and engaged on the issue at Table Rock Lake for 
some time. Can you describe how oversight at the Division level was 
exercised and detail the steps your office took in relation to 
leadership at the Southwestern Division?
    Answer. The Southwestern Division (SWD) maintained continuous 
awareness of issues associated with shoreline management and real 
estate actions at Table Rock Lake. Division-level oversight is 
exercised through established supervisory channels and direct 
engagement with District leadership. Corps Headquarters engaged with 
SWD leadership through senior leader touchpoints.

    Question 1.b. On what date did the Southwestern Division and/or the 
Little Rock District receive guidance from USACE Headquarters regarding 
Section 1323 of the Thomas R. Carper Water Resources Development Act of 
2024 (P.L. 118-272)?
    Question 1.b.i. Please provide my office with the full and complete 
guidance regarding WRDA 2024 that was communicated to the Southwestern 
Division and the Little Rock District.
    Answer to Questions 1.b. and 1.b.i. Corps Headquarters began 
implementation of the Water Resources Development Act of 2024 
immediately following enactment of the legislation. Section 1323 was 
identified as not needing further implementation guidance.

    Question 1.c. Secretary Telle stated during the September 2025 
Water Resources and the Environment Subcommittee Hearing that the Army 
Corps paused all enforcement actions on residents around Table Rock 
Lake. He mentioned that two months after this pause was directed, he 
contacted the Little Rock District telling them that he was still 
hearing that they had not paused this activity and again directed them 
to pause the activity in accordance with the commitment he made to 
Congressman Burlison and other Members of Congress.
    Can you provide me with documentation directing the official pause 
on enforcement and the date on which both directives were provided by 
your office to the Little Rock District?
    Answer. Communication with the Little Rock District occurred 
through the chain of command and reiterated the requirement to halt 
enforcement actions to ensure alignment with congressional intent and 
policy review.

Post-Hearing Questions for the Record to Hon. Adam R. Telle, Assistant 
  Secretary of the Army for Civil Works, Department of the Army, and 
Lieutenant General William H. ``Butch'' Graham, Jr., Chief of Engineers 
 and Commanding General, U.S. Army Corps of Engineers, from Hon. Greg 
                                Stanton

FY 2026 Arizona Environmental Infrastructure Projects:
    Question 1. The fiscal year 2026 Energy and Water Appropriations 
bill included $2.55 million I secured for the Arizona environmental 
infrastructure program. As you finalize the work plan, I ask that you 
allocate these funds to two critical projects in Arizona for the city 
of Goodyear and Santa Cruz County. The city of Goodyear would use the 
funds to increase the recharge capacity of its aquifer, allowing it to 
more effectively manage its groundwater. Santa Cruz would use the funds 
for repairs to the Nogales Wash to improve surface water drainage and 
stormwater runoff in the region.
    Lt. Gen. Graham and Assistant Secretary Telle, will you commit to 
working with me to fund these two important projects with the resources 
included in the appropriations bill?
    Answer. The $2.55 million in Community Project Funding for the 
Arizona Environmental Infrastructure program in the FY26 Energy and 
Water appropriations only specified the State of Arizona. Therefore, 
funding will be allocated in the Corps FY26 Work Plan to projects in 
the State of Arizona eligible under the Section 595 programmatic 
authority based on available technical information: capability for a 
useful increment of work that aligns with the amount of funding 
appropriated, Non-Federal Sponsor readiness, and no legal impediments. 
The technical information for the above-referenced projects will be 
considered along with other eligible projects.
Drought Resiliency and Arizona Environmental Infrastructure Projects:
    Question 2. Arizona and the rest of the West have long suffered 
historic drought, but we are operating under increasing uncertainty 
over the diminishing Colorado River. Negotiations over the River's 
future haven't led to a lasting agreement between the Colorado River 
Basin States--despite a strong offer from Arizona, Nevada and 
California. And worse, the Bureau of Reclamation's backup plan for the 
River threatens deep cuts to Arizona's water supplies.
    Arizona knows we need to do more with less water. Arizona's 
leadership in water conservation and storage, particularly in high-tech 
irrigation and water recycling, means we're already using less water 
now than we did 60 years ago, even with a growing population. But these 
looming cuts make continued support for environmental infrastructure 
(EI) assistance in the 2026 WRDA even more critical.
    But getting to groundbreaking has been beyond frustrating. Just one 
of two-dozen funded projects under the Arizona EI has started 
construction.
    What is the Corps' current assessment of the Arizona project 
backlog? What are the Corps doing to prioritize drought-resilience EI 
projects in Arizona and across the West?
    Answer. Under its Arizona EI program, the Corps has 20 project 
agreements. Subject to the availability of funds, the Corps has 
approved 5 of these projects to begin construction, with three more 
notices to proceed scheduled within the next month. The remaining 12 
projects are under environmental review, and the Corps is evaluating 
whether any categorical exclusions may apply to these projects in 
accordance with the DoD NEPA Implementing Procedures.
Tres Rios:
    Question 3. Tres Rios Ecosystem Restoration project is partially 
constructed with the most recent phase completed in 2012. WRDA 2024 
provided additional authorization to complete the Tres Rios project. 
Over $110M has been spent to date to construct levees, water treatment 
wetlands, and other engineered and natural infrastructure for Tres 
Rios.
    I secured an authorization for an increased spending limit for Tres 
Rios in WRDA 2024 to complete that project. It has been several years 
since that authorization with no substantive movement towards resuming 
Tres Rios construction.
    Will the Corps commit to prioritizing funding and staff resources 
to move Tres Rios forward?
    Answer. The Army will consider this project for funding, along with 
other programs, projects, and activities across the Nation that are 
competing for the available Federal resources.
Rio Salado Oeste:
    Question 4. Rio Salado Oeste is a Congressionally authorized 
project in WRDA 2007 that has not yet been constructed. When completed, 
it will provide important benefits to the Phoenix Metro area, including 
expected benefits for economic development. Rio Salado Oeste is 
currently in the midst of completing a feasibility study update, a 
process that started in the summer of 2023.
    The cost and timeframe for this study have already more than 
doubled from the original $3M estimated cost. As you know, last year, 
the U.S. Army Corps of Engineers instituted new requirements for 
feasibility studies--35% design maturity upon completion of the 
feasibility study (versus previous 20% design maturity requirements)--
and this has adversely impacted the progress of the Rio Salado Oeste 
Feasibility Study.
    Rio Salado Oeste is an aquatic ecosystem restoration project--not a 
levee. The increase to 35% plans is unnecessary to appropriately 
evaluate the risks of this type of project, and it makes it more 
difficult for the study to reach completion. The increase in design 
maturity is estimated to add approximately $1 million and 18 months to 
the prior budget and schedule.
    These limitations make it almost impossible to complete a 
feasibility study that would be likely to achieve an authorization in 
WRDA to move forward to design and construction.
    What is the justification for this requirement on ecosystem 
restoration project studies that don't have significant engineered 
infrastructure such as levees? Will the Corps consider refining the 
guidance to return the requirement for aquatic ecosystem restoration 
projects to 20% design stage?
    Answer. The Corps has seen an increase in costs of projects that 
have exceeded their authorized limit across all business lines, 
including aquatic ecosystem restoration. Achieving a 35% level of 
design prior to entering the Construction phase will limit delays and 
provide more confidence in the cost estimates, schedules, and project 
outcomes, while also reducing the chances of even costlier mid-
construction re-design.
Expediting Environmental Review of Environmental Infrastructure 
        Projects:
    Question 5. One of the significant delays in advancing 
environmental infrastructure projects in my state has been the lengthy 
environmental reviews. These delays have resulted in frustration for 
many communities and in some cases, they no longer want to advance the 
projects Congress has funded. I appreciate that the Corps streamlined 
its NEPA processes last June and has started to utilize more 
categorical exclusions for these projects. But our water situation 
demands we work faster, making more improvements to expedite these 
reviews.
    How are the Corps working to ensure that EI projects funded by 
Congress get out the door to communities in a timely and efficient 
manner? What additional resources or authorities, like expanded 
categorical exclusions or flexible funding reallocations, will help 
move projects forward?
    Answer. The Department of War has streamlined the NEPA process with 
the DoD NEPA Implementing Procedures issued in June 2025, which 
includes over 300 Categorical Exclusions (CATEX) that are available for 
the entire Department. The Corps is considering applying applicable 
CATEX for typical EI work like sewer repairs. The Corps is also 
considering adopting EPA's CATEX to further enhance efficiency.
Reallocation of Existing EI Funding:
    Question 6. Because of delays in approving project partnership 
agreements and environmental reviews for these environmental 
infrastructure projects, the cities of Flagstaff and Tolleson are 
seeking to have funds they were awarded for a stormwater detention 
basin and new water well reallocated to other projects. These 
communities should not be unnecessarily punished for the Corps delays 
and should be able to pursue other eligible projects with the funds 
Congress has appropriated without risk that the funds will be clawed 
back.
    What is the Corps' process for approving these reallocations, and 
can you commit to expediting the reallocations for the cities of 
Flagstaff and Tolleson?
    Answer. For Corps funds provided in an annual Energy and Water 
Development Appropriation Act (EWDAA), a proposal to change the 
allocations in a published work plan generally would be subject to 
Section 101 of the EWDAA. For example, where a reprogramming exceeds 
the amounts set forth in paragraphs (6) through (10) of subsection (a) 
of Section 101, congressional notification is required.

                           [all]