<?xml version="1.0"?>
<?xml-stylesheet type="text/xsl" href="cfr.xsl"?>
<CFRGRANULE xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="CFRMergedXML.xsd">
  <FDSYS>
    <CFRTITLE>46</CFRTITLE>
    <CFRTITLETEXT>Shipping</CFRTITLETEXT>
    <VOL>7</VOL>
    <DATE>2013-10-01</DATE>
    <ORIGINALDATE>2013-10-01</ORIGINALDATE>
    <COVERONLY>false</COVERONLY>
    <TITLE>Foam flotation material.</TITLE>
    <GRANULENUM>170.245</GRANULENUM>
    <HEADING>Section 170.245</HEADING>
    <ANCESTORS>
      <PARENT HEADING="Title 46" SEQ="4">Shipping</PARENT>
      <PARENT HEADING="CHAPTER I" SEQ="3">COAST GUARD, DEPARTMENT OF HOMELAND SECURITY (CONTINUED)</PARENT>
      <PARENT HEADING="SUBCHAPTER S" SEQ="2">SUBDIVISION AND STABILITY</PARENT>
      <PARENT HEADING="PART 170" SEQ="1">STABILITY REQUIREMENTS FOR ALL INSPECTED VESSELS</PARENT>
      <PARENT HEADING="Subpart G" SEQ="0">Special Installations</PARENT>
    </ANCESTORS>
  </FDSYS>
  <SECTION>
    <SECTNO>§ 170.245</SECTNO>
    <SUBJECT>Foam flotation material.</SUBJECT>
    <P>(a) Installation of foam must be approved by the OCMI.</P>
    <P>(b) If foam is used to comply with § 171.070(d), § 171.095(c), or § 173.063(e) of this subchapter, the following applies:</P>
    <P>(1) Foam may be installed only in void spaces that are free of ignition sources.</P>
    <P>(2) The foam must comply with NPFC MIL-P-21929B (incorporated by reference; see 46 CFR 170.015), including the requirements for fire resistance.</P>
    <P>(3) A submergence test must be conducted for a period of at least 7 days to demonstrate whether the foam has adequate strength to withstand a hydrostatic head equivalent to that which would be imposed if the vessel were submerged to its margin line.</P>
    <P>(4) The effective buoyancy at the end of the submergence test must be used as the buoyancy credit; however, in no case will a credit greater than 55 lbs per cubic foot (881 kilograms per cubic meter) be allowed.</P>
    <P>(5) The structure enclosing the foam must be strong enough to accommodate the buoyancy of the foam.</P>

    <P>(6) Piping and cables must not pass through foamed spaces unless they are within piping and cable trunks accessible from both ends.<PRTPAGE P="100"/>
    </P>
    <P>(7) Sample specimens must be prepared during installation and the density of the installed foam must be determined.</P>
    <P>(8) Foam may be installed adjacent to fuel tanks if the boundary between the tank and space has double continuous fillet welds.</P>
    <P>(9) MIL-P-21929B is incorporated by reference into this part.</P>
    <P>(10) The results of all tests and calculations must be submitted to the OCMI.</P>
    <P>(11) Blocked foam must—</P>
    <P>(i) Be used in each area that may be exposed to water; and</P>
    <P>(ii) Have a protective cover approved by the OCMI.</P>
    <CITA>[CGD 79-023, 48 FR 51010, Nov. 4, 1983, as amended by CGD 83-005, 51 FR 923, Jan. 9, 1986; USCG-2003-16630, 73 FR 65203, Oct. 31, 2008]</CITA>
  </SECTION>
</CFRGRANULE>
