[Title 46 CFR 98.25]
[Code of Federal Regulations (annual edition) - October 1, 1996 Edition]
[Title 46 - SHIPPING]
[Chapter I - COAST GUARD, DEPARTMENT OF]
[Subchapter I - CARGO AND MISCELLANEOUS VESSELS]
[Part 98 - SPECIAL CONSTRUCTION, ARRANGEMENT, AND OTHER PROVISIONS FOR CERTAIN DANGEROUS CARGOES IN BULK]
[Subpart 98.25 - Anhydrous Ammonia in Bulk]
[From the U.S. Government Publishing Office]




  46
  SHIPPING
  4
  1996-10-01
  1996-10-01
  false
  Anhydrous Ammonia in Bulk
  98.25
  Subpart 98.25
  
    SHIPPING
    COAST GUARD, DEPARTMENT OF
    CARGO AND MISCELLANEOUS VESSELS
    SPECIAL CONSTRUCTION, ARRANGEMENT, AND OTHER PROVISIONS FOR CERTAIN DANGEROUS CARGOES IN BULK
  


                Subpart 98.25--Anhydrous Ammonia in Bulk



Sec. 98.25-1  Applicability.

    (a) The regulations in this subpart apply to each self-propelled 
vessel that has anhydrous ammonia on board as a cargo, cargo residue, or 
vapor and that is not regulated under part 154 of this chapter.
    (b) Any self-propelled vessel to which this subpart applies shall be 
inspected

[[Page 92]]

and certificated under this subchapter and subchapter D of this chapter.

[CGD 74-289, 44 FR 26008, May 3, 1979]



Sec. 98.25-5  How anhydrous ammonia may be carried.

    (a) Anhydrous ammonia shall be carried in unfired pressure vessel 
type tanks independent of the structure as detailed in this part, except 
as otherwise provided in paragraph (b) of this section.
    (b) When anhydrous ammonia is to be transported at its boiling 
temperature at or near atmospheric pressure, the Commandant may permit 
the use of alternate methods of storage if it is shown to his 
satisfaction that a degree of safety is obtained consistent with the 
minimum requirements of this subpart.



Sec. 98.25-10  Design and construction of cargo tanks.

    (a) The cargo tanks shall meet the requirements for Class I, I-L, 
II, or II-L welded pressure vessels and shall be fabricated, inspected, 
and tested in accordance with the applicable requirements of part 54 of 
subchapter F (Marine Engineering) of this chapter.
    (b) Unlagged cargo tanks subject to atmospheric temperatures shall 
be designed for a pressure of not less than 250 pounds per square inch 
gage.
    (c) Where unrefrigerated cargo tanks are lagged as required by 
Secs. 98.25-30 and 98.25-60, the tanks shall be designed for a pressure 
of not less than 215 pounds per square inch gage.
    (d) Refrigerated cargo tanks, in which the temperature of the liquid 
ammonia is maintained below the normal atmospheric temperatures, shall 
be designed for a pressure of not less than the vapor pressure 
corresponding to the temperature of the liquid at which the system is to 
be maintained, plus 25 pounds per square inch gage.
    (e) Each tank shall be provided with not less than a 15'' x 18'' 
diameter manhole, fitted with a cover located above the maximum liquid 
level and as close as possible to the top of the tank. Where access 
trunks are fitted to tanks, the diameter of the trunks shall be not less 
than 30 inches.

[CGFR 65-50, 30 FR 17022, Dec. 30, 1965, as amended by CGFR 68-82, 33 FR 
18902, Dec. 18, 1968]



Sec. 98.25-15   Markings.

    (a) Cargo tanks shall be marked in accordance with the requirements 
of Sec. 54.10-20 of subchapter F (Marine Engineering) of this chapter.
    (b) In addition to the markings required to be stamped on the tank, 
the legend, ``Anhydrous Ammonia'' shall be conspicuously and legibly 
marked upon the dome or upper portion of the tank in letters at least 4 
inches high.
    (c) All tank inlet and outlet connections, except safety relief 
valves, liquid level gaging devices and pressure gages shall be labeled 
to designate whether they terminate in the vapor or liquid space. Labels 
of noncorrosive material may be attached to valves.
    (d) All tank markings shall be permanently and legibly stamped in a 
readily visible position. If the tanks are lagged, the markings attached 
to the tank proper shall be duplicated on a corrosion resistant plate 
secured to the outside jacket of the lagging.

[CGFR 65-50, 30 FR 17022, Dec. 30, 1965, as amended by CGFR 68-82, 33 FR 
18902, Dec. 18, 1968]



Sec. 98.25-20   Installation of cargo tanks.

    (a) Independent tanks shall be arranged in the vessel so as to 
provide a minimum clearance of not less than 24 inches from the vessel's 
side and not less than 15 inches from the vessel's bottom. Where more 
than one tank is installed in a vessel, the distance between such tanks 
shall be not less than 15 inches, unless otherwise approved by the 
Commandant. Alternate provisions may be made for moving such tanks to 
provide for adequate inspection and maintenance of the vessel's 
structure and the tanks.
    (b) The design shall show the manner in which the tanks are to be 
installed, supported, and secured in the vessel and shall be approved 
prior to installation. Tanks shall be supported in steel saddles and 
securely anchored in place. If the tanks are required to be stress-
relieved no appendages shall be welded to the tanks after they have been

[[Page 93]]

stress-relieved unless authorized by the Commandant.
    (c) Tanks may be located in dry cargo holds or in liquid cargo tanks 
or may be installed ``on deck'' or ``under deck'' with the tank 
protruding above deck. On installations where a portion of the tank 
extends above the weather deck, provision shall be made to maintain the 
weathertightness of the deck, except that vessels operating on protected 
inland waters may have tanks located in the holds of hopper type barges 
without the watertightness of the deck being maintained. All tanks shall 
be installed with the manhole opening and fittings located above the 
weather deck.
    (d) The anhydrous ammonia tanks may be installed in the bulk liquid 
cargo tanks provided the liquid surrounding the enclosed anhydrous 
ammonia tanks complies with the following chemical and physical 
properties:
    (1) Boiling point above 125 deg. F. at atmospheric pressure.
    (2) Inert to ammonia at 100 deg. F. at atmospheric pressure.
    (3) Noncorrosive in the liquid and vapor phase to the ammonia tanks 
and piping.

[CGFR 65-50, 30 FR 17022, Dec. 30, 1965, as amended by CGFR 70-10, 35 FR 
3711, Feb. 25, 1970]



Sec. 98.25-30   Lagging.

    (a) Lagged tanks shall be covered with an incombustible insulation 
material of a thickness to provide a thermal conductance of not more 
than 0.075 B.t.u. per square foot per degree F. differential in 
temperature per hour. The insulating material shall be of an approved 
type complying with the requirements of subpart 164.009 of subchapter Q 
(Specifications) of this chapter, and shall be given a vapor proof 
coating with fire retardant material acceptable to the Commandant. Tanks 
exposed to the weather shall have the insulation and vapor proof coating 
covered with a removable sheet metal jacket of not less than 0.083 inch 
thickness and flashed around all openings so as to be weather tight. 
Materials other than sheet metal may be used to cover the insulation and 
vapor proof coating when specifically authorized by the Commandant.
    (b) Where unlagged tanks are installed in insulated holds or 
insulated 'tween deck spaces, such tanks shall be considered lagged 
provided the thermal conductance of the insulation is not less than that 
required by paragraph (a) of this section.



Sec. 98.25-35   Refrigerated systems.

    (a) Where refrigerated systems are installed to maintain the 
temperature of the liquid below atmospheric, at least two complete 
refrigeration plants automatically regulated by pressure variations 
within the tanks shall be provided, each to be complete with the 
necessary auxiliaries for proper operation. The capacity of each 
refrigeration compressor shall be sufficient to maintain the vapor 
pressure in the tanks during the peak atmospheric temperature conditions 
below the pressure for which the tanks are designed.
    (b) An alternate arrangement may consist of three compressors, any 
two of which shall be capable of maintaining the vapor pressure in the 
tanks during peak atmospheric temperature conditions below the pressure 
for which the tanks are designed, the third compressor acting as a 
stand-by unit.
    (c) Refrigerated tanks shall be insulated in conformance with the 
requirements of Sec. 98.25-30.



Sec. 98.25-40   Valves, fittings, and accessories.

    (a) All valves, flanges, fittings and accessory equipment shall be 
of a type suitable for use with anhydrous ammonia and shall be made of 
steel, or malleable or nodular iron meeting the requirements of 
Sec. 56.60-1 of subchapter F (Marine Engineering) of this chapter. 
Valves shall be fitted with noncorrosive material suitable for ammonia 
service. Valves, flanges, and pipe fittings shall be of the square or 
round tongue and groove type or raised-face, United States of America 
Standard 300-pound standard minimum, fitted with suitable soft gasket 
material. Welded fittings shall be used wherever possible and the number 
of pipe joints shall be held to a minimum. Screwed joints are not 
permitted for pipe diameters exceeding 2 inches. Nonferrous materials, 
such as copper, copper alloys and aluminum alloys, shall not be used in 
the

[[Page 94]]

construction of valves, fittings or accessory equipment. Brazed joints 
are prohibited.
    (b) Each tank shall be provided with the necessary fill and 
discharge liquid and vapor shut-off valves, safety relief valves, liquid 
level gaging devices, thermometer well and pressure gage, and shall be 
provided with suitable access for convenient operation. Connections to 
tanks installed below the weather deck shall be made to a trunk or dome 
extending above the weather deck. Connections to the tanks shall be 
protected against mechanical damage and tampering. Other openings in the 
tanks, except as specifically permitted by this part, are prohibited.
    (c) All connections to the tanks, except safety devices and liquid 
level gaging devices, shall have manually operated shut-off valves 
located as close to the tank as possible.
    (d) Excess flow valves where required by this section shall close 
automatically at the rated flow of vapor or liquid as specified by the 
manufacturer. The piping, including valves, fittings and appurtenances, 
protected by an excess flow valve, shall have a greater capacity than 
the rated flow of the excess flow valve.
    (e) Liquid level gaging devices which are so constructed that 
outward flow of tank contents shall not exceed that passed by a No. 54 
drill size opening, need not be equipped with excess flow valves.
    (f) Pressure gage connections need not be equipped with excess flow 
valves if the openings are not larger than No. 54 drill size.
    (g) Excess flow valves may be designed with a bypass, not to exceed 
a No. 60 drill size opening, to allow equalization of pressure.
    (h) Prior to disconnecting shore lines, the pressure in the liquid 
and vapor lines shall be relieved through suitable valves installed at 
the loading header.
    (i) Relief valves shall be fitted in liquid lines which may be 
subject to excessive pressure caused by liquid full condition, and the 
escape from the relief valves shall be piped to the venting system.
    (j) The pressure gage shall be located at the highest practical 
point. The thermometer well shall terminate in the liquid space and be 
attached to the shell by welding with the end of the fitting being 
provided with a gas-tight screwed plug or bolted cover.

[CGFR 65-50, 30 FR 17022, Dec. 30, 1965, as amended by CGFR 68-82, 33 FR 
18902, Dec. 18, 1968; CGFR 70-10, 35 FR 3712, Feb. 25, 1970]



Sec. 98.25-45   Liquid level gaging device.

    (a) Each tank shall be fitted with a liquid level gaging device of 
suitable design to indicate the maximum level to which the tank may be 
filled with liquid at temperatures between 20 deg. F. and 130 deg. F.
    (b) Liquid level gaging devices shall be of the following types: 
magnetic, rotary tube, slip tube, fixed tube, automatic float, or other 
types acceptable to the Commandant.
    (c) Gaging devices that require bleeding of the product to the 
atmosphere, such as rotary tube, fixed tube, and slip tube, shall be so 
designed that the bleed valve maximum opening is not larger than a No. 
54 drill size, unless provided with an excess flow valve.
    (d) Gaging devices shall have a design pressure of at least 250 
pounds per square inch.
    (e) Gage glasses of the columnar type are prohibited.



Sec. 98.25-50   Filling and discharge pipes.

    (a) Filling connections shall be provided with one of the following:
    (1) Combination back pressure check valve and excess flow valve;
    (2) One double or two single back pressure check valves; or
    (3) A positive shut-off valve in conjunction with either an internal 
back pressure check valve or an internal excess flow valve.
    (b) All other liquid and vapor connections to tanks, except filling 
connections, safety relief valves, and liquid level gaging devices and 
pressure gages described in Sec. 98.25-40(e) and (f) shall be equipped 
with automatic excess flow valves; or in lieu thereof, may be fitted 
with quick closing internal stop valves, which, except during filling 
and discharge operations, shall remain closed. The control mechanism for 
such valves shall be provided with a secondary remote control of a type 
acceptable to the Commandant.

[[Page 95]]

    (c) The excess flow, internal stop or back pressure check valves 
shall be located on the inside of the tank or outside where the piping 
enters the tank. In the latter case, installation shall be made in such 
a manner that any undue strain will not cause breakage between the tank 
and the excess flow or internal stop valve.
    (d) Where the filling and discharge are made through a common nozzle 
at the tank, and the connection is fitted with a quick-closing internal 
stop valve as permitted in paragraph (b) of this section, the back 
pressure check valve or excess flow valve is not required, provided, 
however, a positive shut-off valve is installed in conjunction with the 
internal stop valve.

[CGFR 65-50, 30 FR 17022, Dec. 30, 1965, as amended by CGFR 70-10, 35 FR 
3712, Feb. 25, 1970]



Sec. 98.25-55   Cargo piping.

    (a) Piping shall be of seamless steel meeting the requirements of 
Sec. 56.60-1 of subchapter F (Marine Engineering) of this chapter. The 
piping shall be of not less than Schedule 40 thickness. In case of 
piping on the discharge side of the liquid pumps or vapor compressors, 
the design shall be for a pressure of not less than the pump or 
compressor relief valve setting; or if the piping is not fitted with 
relief valves, the design pressure shall not be less than the total 
discharge head of the pump or compressor.
    (b) Where necessary, provision shall be made for expansion and 
contraction of piping by means of seamless steel pipe expansion bends. 
Special consideration will be given for packless type expansion joints. 
Slip type expansion joints are prohibited. Piping shall be provided with 
adequate support to take the weight of the piping off the valves and 
fittings.

[CGFR 65-50, 30 FR 17022, Dec. 30, 1965, as amended by CGFR 68-82, 33 FR 
18902, Dec. 18, 1968]



Sec. 98.25-60   Safety relief valves.

    (a) Each tank shall be fitted with two or more approved safety 
relief valves, designed, constructed, and flow-tested for capacity in 
conformance with subpart 162.018 of subchapter Q (Specifications) of 
this chapter.
    (b) Each safety relief valve shall start to discharge at a pressure 
not in excess of the design pressure of the tank.
    (c) Safety relief valves shall be attached to the tank near the 
highest point of the vapor space. Shutoff valves shall not be installed 
between the tanks and the safety relief valves, except manifolds for 
mounting multiple safety relief valves may be fitted with acceptable 
interlocking three-way valves so arranged at all times as to permit at 
any position of the three-way valve, an unrestricted flow of vapors 
through at least one port. When two safety relief valves are mounted in 
parallel on both the upper outlets of the three-way valve, the 
arrangement shall be such as to permit at least one safety relief valve 
to be operative at all times.
    (d) Each safety valve shall be tested in the presence of a marine 
inspector at the site of installation before or after mounting prior to 
being placed in service. The tests shall prove that the safety relief 
valve will start to discharge at a pressure not in excess of the maximum 
allowable pressure of the tank.

[CGFR 68-82, 33 FR 18902, Dec. 18, 1968]



Sec. 98.25-65   Filling density.

    (a) The filling density, or the percent ratio of the liquefied gas 
that may be loaded in the tank to the weight of the water the tank will 
hold at 60 deg. F., shall not exceed 56 percent for unlagged tanks and 
58 percent for lagged or refrigerated tanks.



Sec. 98.25-70   Venting.

    (a) Except as provided in paragraph (b) of this section, each safety 
valve installed on a cargo tank shall be connected to a branch vent of a 
venting system which shall be constructed so that the discharge of gas 
will be directed vertically upward to a point at least 10 feet above the 
weather deck or the top of any tank or house located above the weather 
deck.
    (b) The capacity of branch vents or vent headers shall depend upon 
the number of cargo tanks connected to such branch or header as provided 
in Table 98.25-70(b).

[[Page 96]]



       Table 98.25-70(b)--Capacity of Branch Vents or Vent Headers      
------------------------------------------------------------------------
                                                             Percent of 
                  Number of cargo tanks                     total valve 
                                                             discharge  
------------------------------------------------------------------------
1 or 2...................................................      100      
3........................................................       90      
4........................................................       80      
5........................................................       70      
6 or more................................................       60      
------------------------------------------------------------------------


    (c) In addition to the requirement specified in paragraph (b) of 
this section, the size of the branch vents or vent headers shall be such 
that the back pressure in relief valve discharge lines shall not be more 
than 10 percent of the safety relief valve setting.
    (d) Return bends and restrictive pipe fittings are prohibited. Vents 
and headers shall be so installed as to prevent stresses on safety 
relief valve mountings.
    (e) When vent discharge risers are installed, they shall be so 
located as to provide protection against physical damage and be fitted 
with loose raincaps.
    (f) No shut-off valve shall be fitted in the venting system between 
the safety relief valve and the vent outlets. Suitable provision shall 
be made for draining the venting system if liquid can collect therein.

[CGFR 65-50, 30 FR 17022, Dec. 30, 1965, as amended by CGFR 70-10, 35 FR 
3712, Feb. 25, 1970; 35 FR 6431, Apr. 22, 1970]



Sec. 98.25-75   Ventilation.

    (a) All enclosed spaces containing cargo tanks fitted with bottom 
outlet connections shall be provided with mechanical ventilation of 
sufficient capacity to assure a change of air every 3 minutes. Where 
cargo tanks are fitted with top outlet connections, the enclosed spaces 
containing such tanks shall be fitted with efficient natural or 
mechanical ventilation.
    (b) Enclosed compartments in which machinery such as cargo pumps or 
vapor compressors are located shall be adequately ventilated.



Sec. 98.25-80   Cargo hose.

    (a) Cargo hose fabricated of seamless steel pipe with swivel joints, 
wire braided armored rubber or other hose material acceptable to the 
Commandant, shall be fitted to the liquid or vapor lines during filling 
and discharging of the cargo tanks.
    (b) Hose subject to tank pressure shall be designed for a bursting 
pressure of not less than five times the maximum safety relief valve 
setting of the tank.
    (c) Hose subject to discharge pressure of pumps or vapor compressors 
shall be designed for a bursting pressure of not less than five times 
the pressure of setting of the pump or compressor relief valve.
    (d) Before being placed in service, each new cargo hose, with all 
necessary fittings attached, shall be hydrostatically tested by the 
manufacturer to a pressure of not less than twice the maximum pressure 
to which it may be subjected in service. The hose shall be marked with 
the maximum pressure guaranteed by the manufacturer.



Sec. 98.25-85   Electrical bonding.

    (a) Each cargo tank shall be electrically grounded to the hull. The 
cargo vessel shall be electrically connected to the shore piping prior 
to connecting the cargo hose. This electrical connection shall be 
maintained until after the cargo hose has been disconnected and any 
spillage has been removed.

[CGFR 65-50, 30 FR 17022, Dec. 30, 1965, as amended by CGFR 70-10, 35 FR 
3712, Feb. 25, 1970]



Sec. 98.25-90   Special operating requirements.

    (a) Repairs involving welding or burning shall not be undertaken on 
the cargo tanks or piping while anhydrous ammonia in either the liquid 
or vapor state is present in the system.
    (b) During the time anhydrous ammonia is laden in the tanks the 
vessel shall be under constant surveillance.
    (c) Authorization from the Commandant (G-MSO) shall be obtained to 
transport lading other than anhydrous ammonia in the cargo tanks.
    (d) Sufficient hose stations shall be installed with adequate water 
supply so that if leakage of anhydrous ammonia occurs the vapors may be 
removed by use of a stream of water.

[[Page 97]]

    (e) (1) At least two units of approved self-contained breathing 
apparatus, one stowed forward of the cargo tanks and one stowed aft of 
the cargo tanks, shall be carried on board the vessel at all times.
    (2) All approved self-contained breathing apparatus, masks and 
respiratory protective devices shall be of types suitable for starting 
and operating at the temperatures encountered, and shall be maintained 
in good operating condition.
    (3) Personnel involved in the filling or discharge operations shall 
be adequately trained in the use of the equipment.
    (4) For all self-propelled cargo vessels, during filling or 
discharge operations every person on the vessel shall carry on his 
person or have close at hand at all times a canister mask approved for 
ammonia; or each person shall carry on his person a respiratory 
protective device which will protect the wearer against ammonia vapors 
and provide respiratory protection for emergency escape from a 
contaminated area which would result from cargo leakage. This 
respiratory protective equipment shall be of such size and weight that 
the person wearing it will not be restricted in movement or in the 
wearing of lifesaving device.
    (f) While fast to a dock, a vessel during transfer of bulk cargo 
shall display a red flag by day or a red light by night, which signal 
shall be so placed that it will be visible on all sides. When at anchor, 
a vessel during transfer of bulk cargo shall display a red flag by day, 
which signal shall be so placed that it will be visible on all sides.

[CGFR 70-10, 35 FR 3712, Feb. 25, 1970, as amended by CGD 82-063b, 48 FR 
4781, Feb. 3, 1983; CGD 95-072, 60 FR 50464, Sept. 29, 1995; CGD 96-041, 
61 FR 50730, Sept. 27, 1996]



Sec. 98.25-95   Tests and inspections.

    (a) Each tank shall be subjected to the tests and inspections 
described in this section in the presence of a marine inspector, except 
as otherwise provided in this part.
    (1) An internal inspection of the tank is conducted within--
    (i) Ten years after the last internal inspection if the tank is a 
pressure-vessel type cargo tank on an unmanned barge described under 
Sec. 151.01-25(c) of this chapter and carrying cargo at temperatures of 
-67  deg.F (-55  deg.C) or warmer; or
    (ii) Eight years after the last internal inspection if the tank is 
of a type other than that described in paragraph (a)(1)(i) of this 
section.
    (2) An external examination of unlagged tanks and the visible parts 
of lagged tanks is made at each biennial inspection. The owner shall 
ensure that the amount of insulation deemed necessary by the marine 
inspector is removed from insulated tanks during each internal 
inspection to allow spot external examination of the tanks and 
insulation, or the thickness of the tanks may be gauged by a 
nondestructive means accepted by the marine inspector without the 
removal of insulation.
    (3) If required by the Officer in Charge, Marine Inspection the 
owner shall conduct nondestructive testing of each tank in accordance 
with Sec. 98.25-97.
    (4) If the tank is a pressure vessel type cargo tank with an 
internal inspection interval of 10 years, and is 30 years old or older, 
determined from the date it was built, the owner shall conduct 
nondestructive testing of each tank in accordance with Sec. 98.25-97, 
during each internal inspection.
    (b) A hydrostatic test of 1\1/2\ times the maximum allowable 
pressure as determined by the safety relief valve setting shall be made 
at any time that the inspector considers such hydrostatic test necessary 
to determine the condition of the tank. If the jacket and lagging are 
not removed during the hydrostatic tests prescribed in this paragraph, 
the tank shall hold the hydrostatic test pressure for at least 20 
minutes without a pressure drop.
    (c) The safety relief valves shall be popped in the presence of a 
marine inspector by either liquid, gas or vapor pressure at least once 
every four years to determine the accuracy of adjustment and, if 
necessary, shall be reset.

[CGFR 65-50, 30 FR 17022, Dec. 30, 1965, as amended by CGFR 67-86, 32 FR 
17622, Dec. 9, 1967; CGD 85-061, 54 FR 50965, Dec. 11, 1989]



Sec. 98.25-97  Nondestructive testing.

    (a) Before nondestructive testing may be conducted to meet 
Sec. 98.25-95(a)

[[Page 98]]

(3) and (4), the owner shall submit a proposal to the Officer in Charge, 
Marine Inspection for approval that includes--
    (1) The test methods and procedures to be used, all of which must 
meet section V of the ASME Boiler and Pressure Vessel Code (1986);
    (2) Each location on the tank to be tested; and
    (3) The test method and procedure to be conducted at each location 
on the tank.
    (b) If the Officer in Charge, Marine Inspection rejects the 
proposal, the Officer in Charge, Marine Inspection informs the owner of 
the reasons why the proposal is rejected.
    (c) If the Officer in Charge, Marine Inspection accepts the 
proposal, then the owner shall ensure that--
    (1) The proposal is followed; and
    (2) Nondestructive testing is performed by personnel meeting ASNT 
``Recommended Practice No. SNT-TC-1A (1988), Personnel Qualifications 
and Certification in Nondestructive Testing.''
    (d) Within 30 days after completing the nondestructive test, the 
owner shall submit a written report of the results to the Officer in 
Charge, Marine Inspection.

[CGD 85-061, 54 FR 50965, Dec. 11, 1989]