[Congressional Bills 116th Congress]
[From the U.S. Government Publishing Office]
[S. 2410 Introduced in Senate (IS)]
<DOC>
116th CONGRESS
1st Session
S. 2410
To amend the Federal Water Pollution Control Act to modify the
requirements for permits for dredged or fill material, and for other
purposes.
_______________________________________________________________________
IN THE SENATE OF THE UNITED STATES
July 31, 2019
Mrs. Hyde-Smith (for herself and Mr. Wicker) introduced the following
bill; which was read twice and referred to the Committee on Environment
and Public Works
_______________________________________________________________________
A BILL
To amend the Federal Water Pollution Control Act to modify the
requirements for permits for dredged or fill material, and for other
purposes.
Be it enacted by the Senate and House of Representatives of the
United States of America in Congress assembled,
SECTION 1. SHORT TITLE.
This Act may be cited as the ``Flood Reduction, Wildlife Habitat,
and Water Quality Improvement Act of 2019''.
SEC. 2. PERMITS FOR DREDGED OR FILL MATERIAL.
Section 404 of the Federal Water Pollution Control Act (33 U.S.C.
1344) is amended--
(1) in subsection (c)--
(A) in the third sentence, by striking ``The
Administrator'' and inserting the following:
``(5) Findings.--The Administrator'';
(B) in the second sentence, by striking ``Before
making such determination'' and inserting the
following:
``(4) Consultation.--Before making a determination under
paragraph (1)'';
(C) by striking the subsection designation and all
that follows through ``The Administrator'' in the first
sentence and inserting the following:
``(c) Prohibition of Specification of Areas as Disposal Sites.--
``(1) In general.--Subject to paragraph (2), the
Administrator'';
(D) by inserting after paragraph (1) (as so
designated) the following:
``(2) Limitations.--The Administrator may not prohibit the
specification of a defined area as a disposal site, or
otherwise deny or restrict the use of a defined area as a
disposal site--
``(A) if the area is or contains a project of the
Secretary for flood control;
``(B) before an application for a permit under this
section for the area has been filed; or
``(C) after a permit under this section for the
area has been issued by the Secretary.
``(3) Requirements.--A regional office of the Administrator
shall--
``(A) before considering a determination under
paragraph (1), obtain the approval of the
Administrator; and
``(B) before publishing notice of a proposed
determination under paragraph (1) for the area of a
project, review, consider, and adequately refute the
findings of an environmental impact statement for the
project pursuant to the National Environmental Policy
Act of 1969 (42 U.S.C. 4321 et seq.).''; and
(E) by adding at the end the following:
``(6) Immediate withdrawal of prior determinations.--
``(A) In general.--Notwithstanding any other
provision of law, a determination made by the
Administrator under paragraph (1) with respect to the
area of a project that is or contains a project of the
Secretary for flood control before the date of
enactment of the Flood Reduction, Wildlife Habitat, and
Water Quality Improvement Act of 2019 shall no longer
apply if--
``(i) a more practicable alternative to the
project has not been identified; and
``(ii) as a result of a delay in
construction of the project, severe flooding
and damage to life and property have occurred.
``(B) Judicial review.--Notwithstanding any other
provision of law, an action taken by the Secretary to
advance a project described in subparagraph (A) shall
not be subject to judicial review.''; and
(2) in subsection (r), by striking ``under section 307),''
and all that follows through the period at the end and
inserting ``under section 307).''.
<all>