[Congressional Bills 116th Congress]
[From the U.S. Government Publishing Office]
[H.R. 462 Introduced in House (IH)]
<DOC>
116th CONGRESS
1st Session
H. R. 462
To amend the Water Resources Development Act of 2000 to provide for
expedited project implementation relating to the comprehensive
Everglades restoration plan.
_______________________________________________________________________
IN THE HOUSE OF REPRESENTATIVES
January 10, 2019
Mr. Hastings (for himself, Mr. Diaz-Balart, Mr. Rooney of Florida, Ms.
Frankel, Ms. Mucarsel-Powell, Mrs. Murphy, and Mr. Crist) introduced
the following bill; which was referred to the Committee on
Transportation and Infrastructure
_______________________________________________________________________
A BILL
To amend the Water Resources Development Act of 2000 to provide for
expedited project implementation relating to the comprehensive
Everglades restoration plan.
Be it enacted by the Senate and House of Representatives of the
United States of America in Congress assembled,
SECTION 1. SHORT TITLE.
This Act may be cited as the ``Everglades for the Next Generation
Act''.
SEC. 2. COMPREHENSIVE EVERGLADES RESTORATION PLAN.
Section 601(d) of the Water Resources Development Act of 2000
(Public Law 106-541; 114 Stat. 2684) is amended--
(1) in paragraph (1), by inserting ``and subject to
paragraph (3)'' after ``subsection (b) or (c)''; and
(2) by adding at the end the following:
``(3) Expedited project implementation.--After completing a
project implementation report prepared in accordance with
subsections (f) and (h), the Secretary may carry out, without
any further congressional authorization--
``(A) any project identified in the Plan for which
a project implementation report is completed that is in
accordance with an integrated delivery schedule
approved by the Chief of Engineers and the South
Florida Water Management District, in consultation with
the South Florida Ecosystem Restoration Task Force,
subject to the condition that the report is completed
not later than 5 years after the date of enactment of
this paragraph; and
``(B) any group of projects under the Plan that the
Secretary determines will provide regional or watershed
ecosystem or water supply benefits if the group of
projects is constructed in accordance with a project
implementation report approved by the Chief of
Engineers and the South Florida Water Management
District, in consultation with the South Florida
Ecosystem Restoration Task Force, not later than 5
years after the date of enactment of this paragraph.''.
<all>