AN ACT
To amend title 38, United States Code, to provide for certain
requirements relating to the use of the design-build construction
method for Department of Veterans Affairs construction projects, and
for other purposes.
Be it enacted by the Senate and House of Representatives of the
United States of America in Congress assembled,
SECTION 1. SHORT TITLE.
This Act may be cited as the ``VA Design-Build Construction
Enhancement Act of 2019''.
SEC. 2. FINDINGS; SENSE OF CONGRESS REGARDING THE DESIGN-BUILD
CONSTRUCTION METHOD FOR DEPARTMENT OF VETERANS AFFAIRS
CONSTRUCTION PROJECTS.
(a) Findings.--Congress makes the following findings:
(1) The Inspector General of the Department of Veterans
Affairs found that, in the Aurora, Colorado, replacement
medical center project, the Department decided to change its
acquisition strategy from traditional design-bid-build to
integrated-design and construct in the fourth year of the
project, which was too late for the integrated design-
construction firm to provide effective input into the design.
(2) In response to deficiencies in the Department's
management of the Aurora, Colorado, replacement medical center
project and in order to prevent reoccurrence of such
deficiencies in the future, Congress enacted section 8103 of
title 38, United States Code, which mandates that an
appropriate non-Department Federal entity take over management
of future super construction projects of the Department,
including project design, acquisition, construction, and
contract changes.
(3) It has been the policy of the Federal Government since
the enactment of the Clinger-Cohen Act of 1996 (Public Law 104-
106) that design-build shall be used when appropriate
circumstances are present.
(b) Sense of Congress.--It is the sense of Congress that--
(1) the unsuccessful use of the integrated-design and
construct acquisition method in the Aurora, Colorado,
replacement medical center project should not be interpreted to
mean that design-build, as described in section 3309 of title
41, United States Code, is unsuitable for construction projects
of the Department of Veterans Affairs; and
(2) when used properly by adequately trained acquisition
and construction management personnel and in the appropriate
circumstances, design-build is an effective construction
acquisition method for the Department of Veterans Affairs,
which has been demonstrated to reduce change orders, decrease
the duration between design completion and beneficial
occupancy, and increase warranty protections.
SEC. 3. DEPARTMENT OF VETERANS AFFAIRS USE OF DESIGN-BUILD CONSTRUCTION
METHOD.
(a) Use of Design-Build Selection Procedures.--Section 8106 of
title 38, United States Code, is amended by adding at the end the
following new subsection:
``(d)(1) If the Secretary seeks to enter into a contract for the
design and construction of a building or facility, the Secretary shall
use the procedures established in section 3309 of title 41.
``(2) In the case of a super construction project for which a non-
Department Federal entity provides project management services under
section 8103(e) of this title, the Secretary shall not discourage the
entity from using the procedures established in section 3309 of title
41.''.
(b) Covered Certification Program.--Section 8103(g)(6)(A) of such
title is amended by inserting ``, including design-build construction''
before the period at the end.
Passed the House of Representatives November 12, 2019.
Attest:
Clerk.
116th CONGRESS
1st Session
H. R. 3996
_______________________________________________________________________
AN ACT
To amend title 38, United States Code, to provide for certain
requirements relating to the use of the design-build construction
method for Department of Veterans Affairs construction projects, and
for other purposes.