[Congressional Bills 104th Congress]
[From the U.S. Government Publishing Office]
[H.R. 2773 Reported in House (RH)]






                                                 Union Calendar No. 244
104th CONGRESS
  2d Session
                                H. R. 2773

                          [Report No. 104-510]

 To extend the deadline under the Federal Power Act applicable to the 
  construction of 2 hydroelectric projects in North Carolina, and for 
                            other purposes.


_______________________________________________________________________


                    IN THE HOUSE OF REPRESENTATIVES

                           December 13, 1995

 Mrs. Myrick introduced the following bill; which was referred to the 
                         Committee on Commerce

                             March 28, 1996

  Reported with an amendment, committed to the Committee of the Whole 
       House on the State of the Union, and ordered to be printed
 [Strike out all after the enacting clause and insert the part printed 
                               in italic]

_______________________________________________________________________

                                 A BILL


 
 To extend the deadline under the Federal Power Act applicable to the 
  construction of 2 hydroelectric projects in North Carolina, and for 
                            other purposes.

    Be it enacted by the Senate and House of Representatives of the 
United States of America in Congress assembled,

<DELETED>SECTION 1. EXTENSION OF DEADLINE.</DELETED>

<DELETED>    (a) Project Numbered 10812.--</DELETED>
        <DELETED>    (1) In general.--Notwithstanding the time period 
        specified in section 13 of the Federal Power Act (16 U.S.C. 
        806) that would otherwise apply to the Federal Energy 
        Regulatory Commission project numbered 10812, the Commission 
        may, at the request of the licensee for the project, and after 
        reasonable notice, in accordance with the good faith, due 
        diligence, and public interest requirements of that section and 
        the Commission's procedures under that section, extend the time 
        period during which the licensee is required to commence the 
        construction of the project, under the extension described in 
        paragraph (2), for not more than 5 consecutive 2-year 
        periods.</DELETED>
        <DELETED>    (2) Effective date.--This subsection shall take 
        effect on the date of the expiration of the extension of the 
        period required for commencement of construction of the project 
        described in paragraph (1) that the Commission issued, prior to 
        the date of enactment of this Act, under section 13 of the 
        Federal Power Act (16 U.S.C. 806).</DELETED>
<DELETED>    (b) Project Numbered 6879.--</DELETED>
        <DELETED>    (1) In general.--Notwithstanding the time period 
        specified in section 13 of the Federal Power Act (16 U.S.C. 
        806) that would otherwise apply to the Federal Energy 
        Regulatory Commission project numbered 6879, the Commission 
        may, at the request of the licensee for the project, and after 
        reasonable notice, in accordance with the good faith, due 
        diligence, and public interest requirements of that section and 
        the Commission's procedures under that section, extend the time 
        period during which the licensee is required to commence the 
        construction of the project for not more than 5 consecutive 2-
        year periods.</DELETED>
        <DELETED>    (2) Effective date.--This subsection shall take 
        effect on the date of the expiration of the period required for 
        commencement of construction of the project under the license 
        for the project.</DELETED>

SECTION 1. EXTENSION OF DEADLINE.

    (a) Project Numbered 10812.--
            (1) In general.--Notwithstanding the time period specified 
        in section 13 of the Federal Power Act (16 U.S.C. 806) that 
        would otherwise apply to the Federal Energy Regulatory 
        Commission project numbered 10812, the Commission shall, at the 
        request of the licensee for the project, and after reasonable 
        notice, in accordance with the good faith, due diligence, and 
        public interest requirements of that section and the 
        Commission's procedures under that section, extend the time 
        period during which the licensee is required to commence the 
        construction of the project, under the extension described in 
        paragraph (2), for not more than 3 consecutive 2-year periods.
            (2) Effective date.--This subsection shall take effect on 
        the date of the expiration of the extension of the period 
        required for commencement of construction of the project 
        described in paragraph (1) that the Commission issued, prior to 
        the date of enactment of this Act, under section 13 of the 
        Federal Power Act (16 U.S.C. 806).
    (b) Project Numbered 6879.--
            (1) In general.--Notwithstanding the time period specified 
        in section 13 of the Federal Power Act (16 U.S.C. 806) that 
        would otherwise apply to the Federal Energy Regulatory 
        Commission project numbered 6879, the Commission may, at the 
        request of the licensee for the project, and after reasonable 
        notice, in accordance with the good faith, due diligence, and 
        public interest requirements of that section and the 
        Commission's procedures under that section, extend the time 
        period during which the licensee is required to commence the 
        construction of the project for not more than 3 consecutive 2-
        year periods.
            (2) Effective date.--This subsection shall take effect on 
        the date of the expiration of the period required for 
        commencement of construction of the project under the license 
        for the project.




                                                 Union Calendar No. 244

104th CONGRESS

  2d Session

                               H. R. 2773

                          [Report No. 104-510]

_______________________________________________________________________

                                 A BILL

 To extend the deadline under the Federal Power Act applicable to the 
  construction of 2 hydroelectric projects in North Carolina, and for 
                            other purposes.

_______________________________________________________________________

                             March 28, 1996

  Reported with an amendment, committed to the Committee of the Whole 
       House on the State of the Union, and ordered to be printed