[Congressional Bills 104th Congress]
[From the U.S. Government Publishing Office]
[H.R. 2773 Reported in House (RH)]
Union Calendar No. 244
104th CONGRESS
2d Session
H. R. 2773
[Report No. 104-510]
To extend the deadline under the Federal Power Act applicable to the
construction of 2 hydroelectric projects in North Carolina, and for
other purposes.
_______________________________________________________________________
IN THE HOUSE OF REPRESENTATIVES
December 13, 1995
Mrs. Myrick introduced the following bill; which was referred to the
Committee on Commerce
March 28, 1996
Reported with an amendment, committed to the Committee of the Whole
House on the State of the Union, and ordered to be printed
[Strike out all after the enacting clause and insert the part printed
in italic]
_______________________________________________________________________
A BILL
To extend the deadline under the Federal Power Act applicable to the
construction of 2 hydroelectric projects in North Carolina, and for
other purposes.
Be it enacted by the Senate and House of Representatives of the
United States of America in Congress assembled,
<DELETED>SECTION 1. EXTENSION OF DEADLINE.</DELETED>
<DELETED> (a) Project Numbered 10812.--</DELETED>
<DELETED> (1) In general.--Notwithstanding the time period
specified in section 13 of the Federal Power Act (16 U.S.C.
806) that would otherwise apply to the Federal Energy
Regulatory Commission project numbered 10812, the Commission
may, at the request of the licensee for the project, and after
reasonable notice, in accordance with the good faith, due
diligence, and public interest requirements of that section and
the Commission's procedures under that section, extend the time
period during which the licensee is required to commence the
construction of the project, under the extension described in
paragraph (2), for not more than 5 consecutive 2-year
periods.</DELETED>
<DELETED> (2) Effective date.--This subsection shall take
effect on the date of the expiration of the extension of the
period required for commencement of construction of the project
described in paragraph (1) that the Commission issued, prior to
the date of enactment of this Act, under section 13 of the
Federal Power Act (16 U.S.C. 806).</DELETED>
<DELETED> (b) Project Numbered 6879.--</DELETED>
<DELETED> (1) In general.--Notwithstanding the time period
specified in section 13 of the Federal Power Act (16 U.S.C.
806) that would otherwise apply to the Federal Energy
Regulatory Commission project numbered 6879, the Commission
may, at the request of the licensee for the project, and after
reasonable notice, in accordance with the good faith, due
diligence, and public interest requirements of that section and
the Commission's procedures under that section, extend the time
period during which the licensee is required to commence the
construction of the project for not more than 5 consecutive 2-
year periods.</DELETED>
<DELETED> (2) Effective date.--This subsection shall take
effect on the date of the expiration of the period required for
commencement of construction of the project under the license
for the project.</DELETED>
SECTION 1. EXTENSION OF DEADLINE.
(a) Project Numbered 10812.--
(1) In general.--Notwithstanding the time period specified
in section 13 of the Federal Power Act (16 U.S.C. 806) that
would otherwise apply to the Federal Energy Regulatory
Commission project numbered 10812, the Commission shall, at the
request of the licensee for the project, and after reasonable
notice, in accordance with the good faith, due diligence, and
public interest requirements of that section and the
Commission's procedures under that section, extend the time
period during which the licensee is required to commence the
construction of the project, under the extension described in
paragraph (2), for not more than 3 consecutive 2-year periods.
(2) Effective date.--This subsection shall take effect on
the date of the expiration of the extension of the period
required for commencement of construction of the project
described in paragraph (1) that the Commission issued, prior to
the date of enactment of this Act, under section 13 of the
Federal Power Act (16 U.S.C. 806).
(b) Project Numbered 6879.--
(1) In general.--Notwithstanding the time period specified
in section 13 of the Federal Power Act (16 U.S.C. 806) that
would otherwise apply to the Federal Energy Regulatory
Commission project numbered 6879, the Commission may, at the
request of the licensee for the project, and after reasonable
notice, in accordance with the good faith, due diligence, and
public interest requirements of that section and the
Commission's procedures under that section, extend the time
period during which the licensee is required to commence the
construction of the project for not more than 3 consecutive 2-
year periods.
(2) Effective date.--This subsection shall take effect on
the date of the expiration of the period required for
commencement of construction of the project under the license
for the project.
Union Calendar No. 244
104th CONGRESS
2d Session
H. R. 2773
[Report No. 104-510]
_______________________________________________________________________
A BILL
To extend the deadline under the Federal Power Act applicable to the
construction of 2 hydroelectric projects in North Carolina, and for
other purposes.
_______________________________________________________________________
March 28, 1996
Reported with an amendment, committed to the Committee of the Whole
House on the State of the Union, and ordered to be printed